State of Madhya Pradesh and Ors. v Orient Paper Mills Ltd.

Case / Petition Number:
Civil Appeal No. 498 of 1974

Case Synopsis & Summary

State of Madhya Pradesh v Orient Paper Mills concerns an industrial policy declared on 1 August 1961 that promised electricity duty exemption for five years from the date a new generating plant goes into production, applicable only to generating sets installed during the Third Plan. Orient Paper Mills, which began production on 16 February 1965, sought exemption from electricity duty for the five-year period and challenged the State's denial in a petition under Articles 226 and 227. The High Court held that the petitioner could invoke the doctrine of promissory estoppel, and quashed the State's 1973 demand notices, while directing the State to grant exemption in terms of the 1 August 1961 assurance. On appeal, the State contended there was no occasion to invoke promissory estoppel: Orient Paper Mills had not acted to its prejudice and was taking steps to install a plant even before the industrial policy, so there was no binding commitment. The Supreme Court disagreed with the exclusive reliance on whether the plant was planned at the outset; it found the High Court's inference that the respondent's indecision ended with the assurance was a permissible inference from the evidence, and ordinarily would not disturb such factual findings. It held that no statutory transgression occurred by not issuing a notification and dismissed the appeal, leaving the relief granted intact.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. M. Punchhi
  • S. Ranganathan
Judgment Date
1989-12-07
Court Decision / Holding
Appeal dismissed
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • State of Madhya Pradesh and Ors.

Respondents

  • Orient Paper Mills Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Prithvi Raj
  • • Satish K. Agnihotri
  • • Ashok Singh

Counsels for Respondents

  • • Shankar Ghosh
  • • Vivek Gambhir
  • • Parveen Kumar

Provisions of Law Cited

Constitution of India, 1950 Article 136Constitution of India, 1950 Articles 226 and 227Madhya Pradesh Electricity Duty Act, 1949 – Section 3-BMadhya Pradesh Electricity Duty (Amendment) Act, 1949 – Section 3-A(vii)

Legal Doctrines & Maxims

  • Promissory Estoppel

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellants contend that promissory estoppel cannot be invoked here. The respondent had not acted to its prejudice on the basis of the 1 August 1961 assurance; Orient Paper Mills was already negotiating to set up generation capacity before the policy announcement and had taken steps to build the plant with external finance. The State's policy did not create a binding commitment to exempt electricity duty or to issue a notification under Section 3-B; the remedy lay in following the statutory procedures. The High Court’s inference that there was a settled promise independent of the policy is not firmly established by the record, and the Court should not read a binding obligation into an assurance that failed to specify the mechanism of relief.

Contentions of Respondents

Respondents submit that the 1 August 1961 assurance was clear and unequivocal, and Orient Paper Mills relied on it to undertake construction and seek exemption for five years from 16 February 1965. The indecision ended on the assurance; the right to exemption accrued; failure to issue a Notification under 3-B did not defeat the relief granted. The High Court’s declaration of promissory estoppel was sound, and the Court normally defers to the High Court’s factual findings; the relief granted could not be considered transgression of the MP Electricity Duty Act.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,489 words•~12 min read

In The Court Record

State of Madhya Pradesh and Ors. v Orient Paper Mills Ltd.

A B STATE OF MADHYA PRADESH AND ORS. _v._ ORIENT PAPER MILLS LTD. DECEMBER 7, 1989 [M.M. PUNCHHI AND S. RANGANATHAN, JJ.] _Administrative Law: Promissory estoppel-Industrialists_ _generat-_ _ing power through their own new generating sets-Assurance given by_ _Government-Electricity duty exemption-Effect of_ _Constitution_ _of_ _India,_ _1950:_ _Article 136-lnterference_ _.with_ C _factual findings-Only in exceptional cases._ _Madhya Pradesh Electricity Duty Act,_ _1949:_ _Section_ _3-B-_ _Electricity duty-Exemption-Notification-High Court granting relief_ _without ordering issuance_ _of notification-Whether amounts_ _to_ _trans-_ D _gression._ In its· industrial policy, the State Government declared on 1.8.1961 that . where power has to be generated by industrialists themseb<es, exemption from electricity duty would be granted for a perit>CI of five years from the date of plant goes into production, and E that the concession would be applicable only to new generating sets installed during the Third Plan_ period. The Respondent indicated to the Government on 3.5.1955 that about 5000 K. W. of electriclty Would be required by it to run its paper plant and that it would by itself make arrangements for obtaining the F necessary generating equipment. It also applied for import licence for the import of a production plant as also a power plant to run it. The import licence was granted and the Respondent started negotiation with the foreign supplier. Since the price had gone up it was rather impossible for the Respondent to import both the production plant and the power plant, and if the power plant was not purcha8ed along with the G production plant, it would make the project unsound. Hence the Respondent was in two minds whether to have the power plant or not. Meanwhile, the above said industrial policy was announced and the Respondent on installation of the power plant was able to start its production w.e.f. 16.2.1965. H Thereafter to formalise the matter, the Respondent corresponded 436 STATE OF M.P. _v._ ORIENT PAPER MILLS 437 with the appellant for the grant of the requisite exemption, which was rejected, and the Respondent approached the High Court by way of a petition under Articles 226 and 227 of the Constitution of India. The High Court held that the Petitioner was entitled to invoke the doctrine of promissory estoppel in order to claim exemption from payment of electricity duty for a periof of five years from 16.2.1965 in terms of the assurance of the State Government dated 1.8.1961. Against this order of the High Court the State has come in appeal by Special Leave. On behalf of the appellant-State it was urged that there was no occasion to invoke the doctrine of promissory estoppel, since the Respon· dent had not in any manner acted on the assurance of the Government to its own prejudice but on its own it was taking steps to set up a generating plant much before the industrial policy was announced. Dismissing the appeal, this Court, HELD: 1. Whether the respondent was ofone mind right from the beginning to set up a power plant, with or without the assurance of the State Government dated J.8.1961, as asserted by the State, is neither borne out nor is the view of the High Court arrived at from the record. On the contrary, the view taken is that the respondent's indecision in A B # c D that regard ended and it became decisive on the announcement of the E assurance dated 1.8.1961. Such view of the High Court was a possible view to be taken on the material placed before it and the inference drawn therefr(!m could be that the respondent had acted on the basis of the assurance. [441E-F] 2. This Court ordinarily d~s not interfere with factual findings F arrived at by the High Court and this case has not been shown to be an exception. The view taken by the High Court was unexceptional warranting it to be tell uninterferred with. I 44 lF] 3. Without commanding the State Government to issue such a Notification, the High Courf has granted relief to the respondent to G which there was no bar. Accordingly no provision of Madhya Pradesh Electricity Duty Act, 1949 or any other law can be said to have .been transgressed. [442A] CIVIL APPELLATE JURSIDICTION: Civil Appeal No 498 of ## ~. H 438 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R. A From the Judgment and Order dated 31.7.1974 of the Madhya Pradesh High Court in Misc. Petition No. 316 of 1973. Prithvi Raj, Satish K. Agnihotri and Ashok Singh for the Appellants. B Shankar Ghosh, Vivek Gambhir and Parveen Kumar for the Respondent. The Judgment of the Court was delivered by **PUNCHHI, J.** This is an appeal by special leave against the judgment and order of the High Court of Madhya Pradesh at J abalpur C whereby the petition under Articles 226 and 227 of the Constitution of India preferred by Orient Paper Mills Ltd., the sole respondent herein, was allowed and sequally the order dated 15.3.1973 of the State Government declining to grant the respondent exemption from payment of electricity duty for the period from 16.2.1965 to 15.2.1970 D and pursuant demand notices dated 20.3.1973 and 3.4.1973 were quashed. The aggreived State of Madhya Pradesh and its concerned Officers are the appellants challenging the same The respondent had neea to go to the High Court to have an assurance dated 1.8.1961 regarding exemption from payment of elect£ ricity duty given by the State of Madhya Pradesh in its declared industrial policy observed, which may well be reproduced here at the outset: f "Where power has to be generated by industrialists themselves, exemption from electricity duty shall be granted for a period of five years from the date of plant goes into production. The concession shall be applicable only to new generating sets installed during the Third Plan **period."** Factually it was not disputed before the High Court, that the case of the respondent squarely fall within the scope o( the assurance reproG duced above since tbe industrial plant of the respondent had gone into production w.e.f. lli.2.1965, the generating set put up was new, and had been installed during the Third Plan period. To formalise the matter, the respondent had corresponded with the Government for the grant of the requisite exemption. Since the same was rejected and demands for payment of electricity duty created, the High Court was H requested to issue suitable writs, directions and orders cancelling the STATE OF M.P. _v._ ORIENT PAPER MILLS [PUNCHHI, J.] 439 aforesaid orders and demand notices and granting exemption from payment of electricity duty in respect of electricity self-generated by A the respondent during the said period of five years, and also commanding the State to carry out the assurance and promises made in the said industrial policy dated 1.8.1961 extracted above and then, requiring the State to issue a Notification under Section 3-B of the Madhya Pradesh Electricity Duty Act, 1949 granting exemption or exception to B the respondent from payment of electricity duty and other allied consequential reliefs. Before the High Court voluminous documentary evidence was given by the parties in support of their respective pleadings. The High Court, on consideration of the entire material placed before it, spelled # c out a promissory estoppel in favour of the respondent and conclnded as follows: "To conclude, we are of opinion that the petitioner is entitled to invoke the doctrine of promissory estoppel in order to claim exemption from payment of electricity duty D for a period of five years from 16.2.1965 to 15.2.1970 in terms of the assurance of the State Government, dated 1.8.1961. Of course, as indicated earlier it is not for us to issue any writ directing the State Government to grant the petitioner exemption in terms of S. 3-A (vii) or Section 3-B of the M.P. Electricity Duty (Amendment) Act, 1949. But F **in** **view** **of** **the unambiguous** **and** **unequivocal assurance** given by the State Governmet on 1.8.1961 we can certainly quash the order of the State Government, dated 15.3.1973 as also the demand notices, dated 20.3.1973 (Petitioner's Annexure-48) and dated 3.4.1973 (Petitioner's Annexure 50) and leave the matter at that. It would be for the F Government to work out its own course of action on that **basis."** Mr. Prithvi Raj, learned counsel for the appellant urged that on the facts and circumstances of the case there was no occasion to invoke the doctrine of promissory estoppel. It was asserted that though the G industria.I policy was published by the State Government on 1.8.1961 containing the assurance extracted above, the respondent had not in any manner acted thereon to its own prejudice, but nad rather on its own been taking steps to set up a generating plant much before the industrial policy was announced and had factually set up the generating plant as per its earlier resolve. The facts highlighted were that the H 440 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R. A respondent Paper Mill, had been set up at Amlai in Vindhya Pradesh, when a Part-C State under the administration of the Central Government. It had in its application dated 3.5.1955 to the Government indicated that about 5000 K.W. electricity would be required by it to run its paper plant and. it would by itself make arrangements for obtaining B the necessary generating equipment. It appears that the State Government had at that time its own project in view for installing a power plant. On that basis some correspondence ensued between the respondent and the State Gdvernment with regard-to its annual requirement of electricity. That exercise was abandoned for some reasons which are not relevant here. Thereafter the respondent applied for· import licence for the import of a production plant as also a power plant to run C it. The respondent was granted an import licence on the strength of which it started negotiation with an American supplier. While negotiations were in process the American supplier increased the price. It became impossible for the respondent to import the production plant and the power plant within the funds allotted to it by the World Bank D and in these circumstances, the American suppliers advised the appellant to drop procurement of the power plant. At the same time the American supplier warned the respondent that if the power plant was not purchased along with the production plant, it would make the project unsound and it would not be able to fulfil its guarantees as desired by the respondent. The respondent in these circumstances became of two minds, whether to have the power plant or not. When it E was in that state of mind, the industrial policy was announced by the Government on 1.8.1961. Thereafter, on 21.8.1961, the respondent applied to the Government of India for sanction of permission to import 3.5 million dollar worth goods more. than the sanctioned amount. Finally, the respondent with the consent of the Government F of India and with the aid of the World Bank was able to import the production plant and the power plant and after its installation was able to go on production w .e.f. 16.2.1965. The course of the events set out earlier were not disputed as such by the appellants before the High Court but it was maintained as now before us, that the respondent would have on its own gone on to instal ,¢J the power Ijlant even without the announcement of the industrial policy dated\ 1.8.1961. Additionally, it was maintained, in the like manner, that the respondent had not acted to its prejudice on the basis of the aforesaid assurance dated 1.8.1961 and so that doctrine of promissory estoppel was not invokable. The defence of the State thus ## H raised was rejected by the High Court in the following words: STATE OF M.P. _v._ ORIENT PAPER MILLS IPUNCHHI, J.] 441 "We have already dealt with that aspect earlier and we have already held that the petitioner's action in setting up a power plant was postponed on account of certain circum. stances and ultimately on the advise of the manufacturers who refused to continue the guarantee, the petitioner decided to set up its own power plant. In the meantime, the assurance of the State Government, dated 1.8.1961 had already been given and the petitioner's action in making a final decision to set up its own power plant can be directly connected with the State Government's assurance dated 1.8.1961. No sooner the petitioner took the final decision in that behalf, it applied to the State Government for grant of an exemption, although that application was premature, because the petitioner's paper mill had not started functioning. As such, the petitioner would certainly be entitled to claim exemption in terms of the assurance of the State Government dated 1.8.1961 with effect from tile date the paper mill started functioning, namely, 16.2.1965 and the exemption would last for a period of five years upto A B # c D 15.2.1970." ' Whether the respondent was of one mind right from the beginning to set up a power plant, with or without the assurance of the State Government dated 1.8.1961, as asserted by the State, is neither borne out nor is the view of the High Court arrived at from the record. E Rather, on the contrary, the view taken is that the respondent's indecision in that regard ended and it became decisive on the announcement of the assurance dated 1.8 .1961. Such view of the High Court was a possible view to be taken on the material placed before it and the inference drawn therefrom could be that the respondent had acted on the basis of the assurance. The effort here to re-do the exercise in this F regard must inevitably fail, for this Court ordinarily does not interfere with factual findings arrived at by the High Court and this case has not been shown to us to be an exception. In this situation, the view taken by the High Court was unexceptional warranting it to be left uninterferred with. Some attempt was made by learned counsel for the appellant to contend that the doctrine of promissory estoppel could not be pressed G into service to command the State Government under Section 3cA (vii) (before its amendment) and Section 3-B of the Madhya Pradesh Electricity Duty Act, 1949 (as amended) to issue a Notification exempting the respondent from payment ·of electricity duty. The H 442 SUPREME COURT REPORTS [ 1989] Supp. 2 S.C.R. A answer to this argument is available in the conclusion arrived at by the High Court extracted above. Without commanding the State Government to issue such a Notification, it has granted relief to the respondent to which there was no bar. Accordingly, no provision of Madhya Pradesh Electricity Duty Act, 1949 or any other law can be said to B [have been transgressed. We thus reject this argument too. ] Thus for the foregoing reasons this appeal fails and is hereby dismissed. No costs. G.N. Appeal dismissed
End of Judgment Record
Browse All Supreme Court of India (1989) Decisions
1989-12-22

LAXMI NARAYAN NAYAK v. RAMRATAN CHATURVEDI AND ORS.

This appeal concerns an election petition challenging the Madhya Pradesh Vidhan Sabha election from Niwadi constituency (No. 34) held in early 1985. The appellant, Laxmi Narayan Nayak, alleged that the first respondent, Ramratan Chaturvedi, engaged in corrupt practices under Sections 123(2), 123(3) and 123(3A) of the Representation of the People Act, 1951. The Madhya Pradesh High Court dismissed the petition for lack of substantiation, and Nayak challenged that decision in this Supreme Court appeal. The Court concentrates on three issues: (i) whether the nomination paper of Pratap Singh (11th respondent) was improperly rejected; (ii) whether the respondent held a meeting on 28 February 1985 at Niwadi and promised a silver shield to electors, constituting corrupt practice under Section 123(1); and (iii) whether government servants and a police officer accompanied the respondent to persuade electors and whether money was distributed. The Court reiterates that election petitions are quasi-criminal and require strict proof, including a clear element of bargaining in bribery, with reliability and corroboration of oral evidence. It critically analyzes the evidence: the nomination issue is resolved in the petitioner's favour by the High Court’s reasoning, while the alleged bribery and use of government officers fail due to inconsistencies and lack of corroboration. Ultimately, the Supreme Court upholds the High Court’s decision and dismisses the appeal with costs.

1989-09-19

Aphali Pharmaceuticals Ltd. v. State of Maharashtra & Ors.

Aphali Pharmaceuticals Ltd., an Ayurvedic medicine manufacturer, challenged excise-duty liability on the product Ashvagandharist, which contains self-generated alcohol but is not a beverage. Initially treated as exempt under item 2(i) of the 1955 Act’s Schedule (renumbered as item 3(i) after the 1961 Amendment) because it was an Ayurvedic preparation containing self-generated alcohol not capable of being consumed as an ordinary alcoholic beverage. The 1962 Finance Act introduced Explanation I to the Schedule, defining “patent and proprietary” medicines by reference to the Drugs Act, 1940, with retrospective effect. A Maharashtra circular (31 May 1962) directed treating such preparations as falling under item 1 (patent or proprietary medicines) rather than item 3, and excise duties were subsequently levied and paid under protest. The appellant filed suit; the Civil Judge decreed in its favor, the High Court reversed, and this Court allowed the appeal. The Court held that Explanation I did not amend or override the Schedule’s categories, and the circular could not override the enactment; the Schedule and the Act, read with the Rules (Rules 64-66) and the Drugs Act, determine taxability. The Supreme Court restored the Civil Judge’s decree, holding the appellant was not liable under the amended schedule as interpreted. The parties were to bear their own costs.

1989-07-13

Sundarjas Kanyalal BhatiJa & Ors. v. Collector, Thane, Maharashtra & Ors.

This matter concerns judicial review of Government action under Section 3 of the Bombay Provincial Municipal Corporations Act, 1949, in the context of proposing the formation of the Kalyan Municipal Corporation by merging Kalyan, Ambarnath, Domoivali, and Ulhasnagar. Objections poured in, including from Ulhasnagar’s Sindhi community which sought to preserve its identity via the All India Sindhi Panchayat Federation. The Government undertook a draft notification under Section 3(3) and later issued a final notification excluding Ulhasnagar under Section 3(2). The Bombay High Court held that excluding Ulhasnagar while keeping contiguous areas in the proposed Corporation was arbitrary and irrational, and it directed the Government to reconsider the proposal under Section 3(3), inviting hearing for petitioners and Federation. The appellants contended that the formation of a corporation is a legislative function, thus subject to no general rules of natural justice, and that the State had complied with statutory requirements. The Supreme Court, in a Division Bench, reversed the High Court, emphasizing that judicial review aims at predictability and certainty of law, and that the procedure for forming a Corporation under Section 3 is a legislative act not bound by ordinary hearing requirements unless expressly prescribed. It criticized the High Court’s approach and held that the Government’s action was within the scheme of law, while affirming the need for proper procedure and respecting the decorum of judicial process.

1989-08-08

ATUL MATHUR v. ATUL KALRA

This appeal from the Bombay criminal proceedings concerns Section 630 of the Companies Act, where a company sought to recover possession of a flat occupied by a former employee after resignation. The leave-and-licence agreement for the flat was executed on behalf of Jenson and Nicholson (India) Ltd by the first respondent, who served as Divisional Sales Manager, under a power of attorney. The first respondent filed a civil suit asserting he was the licencee, while the company paid deposits and continued to pay licence fees. After resignation, the respondent did not vacate, was convicted under Section 630 by the Additional Chief Metropolitan Magistrate, and the conviction was upheld by the Sessions Court. The Bombay High Court, via Article 227 converted to Section 482 Cr.P.C., reversed the judgments, holding that two letters by a junior employee, Exs. 3 and 4, and the existence of a civil suit created a bona fide dispute that should be resolved in civil court rather than a criminal proceeding. The Supreme Court allowed the appeal, holding that Section 630 aims to provide speedy relief to the company, that the complaint was properly filed, and that the two letters did not establish a bona fide dispute. The Court restored the lower court judgments and granted the respondent time to vacate.