State of Kerala and the Superintending Engineer, Project Circle, Chengannur v. V.G. Francis Xavier and others

Case / Petition Number:
A.S. No. 640 of 1997

Case Synopsis & Summary

This is a Kerala High Court appeal (A.S. No. 640 of 1997) arising from O.S. 571 of 1990 before the Sub‑Judge, Thiruvananthapuram, concerning a public works contract for the VIP office complex and staff quarters at Nedumangad. The State and the Superintending Engineer challenge a trial court decree awarding Rs. 20,000 to the contractor/plaintiffs for four heads of damages aggregating an alleged loss of Rs. 1,10,000, though the suit had been limited to Rs. 40,000. The contract was originally quoted at Rs. 9,32,301 above the sanctioned estimate of Rs. 7,92,123, and the contractor deposited Rs. 46,650 as security. Work commenced on 26.02.1988, but the contractor completed only Rs. 45,962 of the works and abandoned the site; Ext. A2 shows contract termination on 12.04.1989. The government deducted Rs. 17,807 from the security deposit for the shortfall in work, and paid Rs. 28,843 back to the contractor on 16.05.1989. The contractor later claimed damages under four heads; the trial court partially allowed two heads and disallowed the other two. The High Court held that the plaintiff failed to prove his loss, noting that the burden rested on the plaintiff and that marking Exhibits does not substitute for proof. The appeal was allowed; the suit was dismissed, with deposits to be refunded and without costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V. Ramkumar
Judgment Date
2009-07-06
Court Decision / Holding
The High Court set aside the trial court’s decree and dismissed the suit: the plaintiff failed to prove the four heads of damages; the burden of proof lay on the plaintiff; the plaintiff’s acceptance of the balance security deposit without protest supported the conclusion that the suit claim was misconceived; there shall be no costs; deposits, if any, paid by the defendants shall be refunded.
Final Disposition
Appeal allowed; original suit dismissed; no costs; deposits refunded to the defendants.

Parties to the Case

Appellants / Petitioners

  • State of Kerala represented by the Chief Secretary, Government of Kerala, Thiruvananthapuram
  • The Superintending Engineer, Project Circle, Chengannoor (now Project Circle, Piravom)

Respondents

  • V.G. Francis Xavier
  • Sarat Vincent
  • Gabriel
  • Gracy Francis
  • F.X. Anand Paul
  • Sheeba Halsan
  • Ashok Vincent

Legal Representation & Advocates

Counsels for Petitioners

  • • Ajay Krishnan
  • • Nagaraj Narayanan

Counsels for Respondents

  • • Benny Varghese

Legal Doctrines & Maxims

  • Burden of proof lies on the party who asserts the claim.
  • Marking of Exhibits does not dispense with proof.
  • If a party with the burden avoids the witness box, it may be presumed that the case is not true.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the plaintiff contractor abandoned the project after partial performance, resulting in a net liability to the Government of Rs. 17,807, which was recovered from the security deposit; the balance Rs. 28,843 was paid to the contractor with no protest. They argued that the plaintiff did not complete the work within the stipulated period and that the contract was validly terminated; the plaintiff failed to prove damages under the four heads; the court below erred in raising the claim beyond the substantiated facts and in misapplying the law on proof and burden of proof.

Contentions of Respondents

The respondents/plaintiffs claimed damages under four heads totaling Rs. 40,000, including prevented gains, preliminary arrangements, idle establishment, and material purchase and weather losses. They argued that the work was contracted at a higher tender, and despite finishing part of the work (Rs. 45,962), the claim for damages was legitimate; the government’s counter‑setoff from the security deposit was improper as a full discharge could not be presumed; evidence supported the claim to some extent and the court below rightly assessed damages.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
S.T. Khimchand v. Y. SatyamAIR 1971 SC 1865PositiveCited to support that marking of Exhibits does not dispense with proof.
Narbada Devi Gupta v. Birendra Kumar Jaiswal(2003) 8 SCC 745PositiveUsed to underscore the need for positive evidence when the burden rests on a party.
Vidhyadhar v. Manickrao1999 (3) SCC 573PositiveCited for the principle that a party avoiding the witness box may lead to a presumption against that party.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,868 words•~9 min read

In The Court Record

State of Kerala and the Superintending Engineer, Project Circle, Chengannur v. V.G. Francis Xavier and others

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE V.RAMKUMAR MONDAY, THE 6TH JULY 2009 / 15TH ASHADHA 1931 AS.No. 640 of 1997(C) --------------------OS.571/1990 of I ADDL. SUB COURT, THIRUVANANTHAPURAM .................... ## APPELLANTS/DEFENDANTS:- ------------------------------- 1. STATE OF KERALA REPRESENTED BY THE CHIEF SECRETARY, GOVERNMENT OF KERALA, THIRUVANANTHAPURAM. 2. THE SUPERINTENDING ENGINEER, PROJECT CIRCLE, CHENGANNOOR (NOW PROJECT CIRCLE, PIRAVOM) BY ADV. MR. BENNY VARGHESE, GOVERNMENT PLEADER RESPONDENTS/PLAINTIFFS:- -------------------------------- 1. SRI. V.G. FRANCIS XAVIER, SARAT VINCENT, GABRIEL, CONTRACTOR, RESIDING AT ANAND BHAVAN, KULANGARA, MAYYANAD P.O., QUILON DISTRICT. (DIED) - ADDL. 2. GRACY FRANCIS, ANAND BHAVAN, KULANGARA, MAYYANAD, QUILON DISTRICT. 3. F.X. ANAND PAUL, ANAND BHAVAN, KULANGARA, MAYYANAD, QUILON DISTRICT. 4. SHEEBA HALSAN, - DO - -DO - 5. ASHOK VINCENT, - DO- - DO - ADV. MR. AJAY KRISHNAN - MR. NAGARAJ NARAYANAN THIS APPEAL SUITS HAVING BEEN FINALLY HEARD ON 06/07/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: A.S. NO. 640/1997 : 2 : ORDER ON C.M.P. NO. 4705/1997 IN A.S. NO. 640/1997 ## DISMISSED 06.07.2009 sd/- **V. RAMKUMAR, JUDGE.** ## V. RAMKUMAR , J. ========================== A.S. No. 640 of 1997 ========================== Dated this the 6[th] day of July, 2009. ## **JUDGMENT** Defendants 1 and 2, namely, State of Kerala and the Superintending Engineer, Project Circle, Chengannur in O.S. No. 571 of 1990 on the file of the Subordinate Judge's Court, Thiruvananthapuram are the appellants in this appeal. 2. The said suit originally instituted by one V.G. Francis Xavier (who died pending suit resulting in his legal representatives being impleaded as additional plaintiffs 2 to 5) was one for realisation of a sum of Rs.40,000/- claimed under four different heads being the damages allegedly sustained by the plaintiff in connection with the contract undertaken by him under the 2[nd] defendant. Even though the plaintiff estimated the total amount of damages due to him at Rs.1,10,000/-, he limited the claim to Rs.40,000/-. 3. The suit was resisted by the defendant contending A.S. No. 640/1997 : 2 : inter alia that as against the sum of Rs.9,32,301/- quoted by the plaintiff for doing the work, he had done the work only for a sum of Rs.45,962/- and that deducting the said amount from Rs.64,999/- which was the cost of materials supplied to him by the defendants, the net liability due to the Government was Rs.17,807/- which was recovered from his security deposit and he was paid the balance amount of Rs.28,843/- which he received by him without any demur. According to the defendants, the plaintiff who did not complete the work before the stipulated period, was not entitled to any of the amounts claimed by him and that the contract was validly terminated. 4. The court below framed nine issues for trial. Except producing Exts.A1 to A21, the plaintiff did not adduce any oral evidence. The defendant also did not adduce any oral evidence but got marked Exts.B1, B2 series and B3 series. 5. The learned Subordinate Judge, after trial, as per A.S. No. 640/1997 : 3 : judgment dated 26.03.1996 decreed the suit in part for a sum of Rs.20,000/-. Hence, this appeal by the defendants. 6. The only point which arises for consideration in this appeal is as to whether the judgment and decree passed by the court below are sustainable or not. 7. The facts leading to the impugned judgment and decree are the following:- The work relating to the construction of the office complex and staff quarters for the Vamanapuram Irrigation Project (VIP) at Nedumangad was auctioned by the State through the Superintending Engineer, Pamba Irrigation Project Circle, Chengannur (2[nd] defendant). The value of the work as per the sanctioned estimate was Rs.7,92,123/including the cost of materials which were valued at Rs.3,08,750/-. The plaintiff had quoted Rs.9,32,301/- which was 29% above the estimate amount. He remitted a sum of Rs.46,650/- by way of security deposit which was 5% of the Probable Amount of Contract (PAC). The work was to A.S. No. 640/1997 : 4 : commence from the date of handing over of the site to the plaintiff. The date of completion of the work was 12 months from the date of handing over of the site. The plaintiff had deposited a sum of Rs.46,650/- by way of security in the District Treasury, Kollam. A selection notice was issued to the plaintiff on 19.12.1987. On 29.01.1988, the plaintiff executed Ext.B1 agreement. The site was handed over to him on 26.02.1988. Hence, as per the terms of the contract, the work was to be completed on or before 26.02.1989. But after executing a part of the work for Rs.45,962/- as evidenced by Ext.B3 series, the plaintiff abandoned the work. As per Ext.A2 order dated 12.04.1989, the contract in favour of the plaintiff was terminated without risk and cost. Since the total cost of materials supplied by the 2[nd] defendant to the plaintiff was Rs.64,999/- and the plaintiff had executed the work only for Rs.45,962/-, the net liability of the plaintiff towards the Government was worked out at Rs.17,807/-. The said amount was recovered from the A.S. No. 640/1997 : 5 : security deposit of the plaintiff and the balance amount of Rs.28,843/- was offered to the plaintiff who received the same without any protest on 16.05.1989. It was thereafter that the plaintiff instituted the present suit alleging that he incurred a loss of Rs.1,10,000/- which was limited to Rs.40,000/- shown under four different heads. A sum of Rs.20,000/- was claimed towards prevented gains. Another sum of Rs.10,000/- was claimed under the head 'expenses for preliminary arrangements made for the work'. A sum of Rs.5000/- was claimed towards the idling of establishment, watch and ward etc. Another sum of Rs.5000/- was claimed towards the expenses incurred for purchasing materials and the loss due to weather conditions etc. As against the above four different heads of claim totalling to Rs.40,000/-, the court below awarded a sum of Rs.15,000/- towards the prevented gains and Rs.5000/- towards the expenses for preliminary arrangements for the work. The other two claims were disallowed. It is against the award of A.S. No. 640/1997 : 6 : Rs.20,000/- as damages that the defendants have come up in appeal. The plaintiff has not preferred any cross objection with regard to the disallowed portion of the suit claim. 8. The only point which arises for consideration in this appeal is as to whether the judgment and decree passed by the court below is sustainable or not. ## 9. The point. ## In paragraph 16 of the written statement what is specifically pleaded is as follows:- “ As per contractor's certificate an amount of Rs.17,807/- had to be recovered from the plaintiff and the same was therefore adjusted while releasing the security deposit. So no amount is pending due to the plaintiff and the balance portion of the security deposit was released to him and the same was accepted by him without any protest. So there is full accord and satisfaction and the plaintiff is therefore, not entitled for getting any interest”. 10. There is no dispute that the total cost of materials supplied to the plaintiff by the defendants was Rs.64,999/-. Going by Ext.B3 series of Measurement Books, the actual work executed by the plaintiff was for Rs.45,962/-. The plaintiff was found to be a defaulter, since he did not A.S. No. 640/1997 : 7 : complete the work on or before 26.02.1989. The contract was terminated as per Ext.A2 order two months thereafter without risk and cost. Thus, deducting the quantum of work actually done by the plaintiff from the cost of materials supplied to him, a sum of Rs.17,807/- was found due to the Government which was recovered from his security deposit of Rs.46,650/-. The balance amount of Rs.28,843/- was, according to the defendants, accepted by the plaintiffs without any protest on 16.05.1989. In the face of such a plea, it was for the plaintiff to adduce evidence to show that the said contention in the written statement was not true. If as contended by the defendants, the plaintiff had accepted the balance amount of Rs.28,843/- without any protest, then the plaintiff was precluded from bringing the present suit for damages. 11. The court below was not justified in culling out a portion of Ext.A2 order dated 12.04.1989 to hold that there was an admission that the work could not be proceeded A.S. No. 640/1997 : 8 : with due to the lack of departmental materials and paucity of funds. There was no doubt an admission as aforesaid by the defendants in Ext.A2 order. But that was not enough to entitle the plaintiff to allege that the work could not be completed due to the fault of the defendants. At any rate, in the light of the pleadings, the burden was definitely on the plaintiff to prove his case. The defendants had specifically denied the plaintiff's allegation that he had sustained loss under the four heads of claim made by him. They had further pleaded that the plaintiff had accepted without any demur, the balance security deposit after adjusting a sum of Rs.17,807/- found due to the Government. So, the burden was on the plaintiff to substantiate the claim by adducing satisfactory evidence. Except producing Exts.A1 to A21, the plaintiff did not care to prove any of those documents. It is well settled that the marking of Exhibits does not dispense with proof. (See **S.T. Khimchand v. Y. Satyam** - AIR 1971 SC 1865 and A.S. No. 640/1997 : 9 : **Narbada Devi Gupta v. Birendra Kumar Jaiswal** - (2003) 8 SCC 745). When the burden was squarely on the plaintiff, it was for him to adduce positive evidence and thereby discharge the burden on him. Strangely enough, the plaintiff did not even mount the witness box and speak in terms of his case. When the party on whom the burden lies avoids the witness box and does not depose in terms of his case and does not offer himself for cross examination by the opposite party, it could be legitimately presumed that the case of the party who avoids the witness box is not true. - (See **Vidhyadhar v. Manickrao** 1999 (3) SCC 573). Moreover, there is an added fact that the plaintiff received the balance amount of security deposit without any demur. He had no case at the time of receiving the balance amount that he had sustained loss on account of the termination of the contract. Hence the suit was misconceived apart from the fact that the suit claim has not been proved as required by law. Such being the position, the court below was not A.S. No. 640/1997 : 10 : justified in granting a decree as it did. The judgment and decree passed by the court below are accordingly, set aside and the suit will stand dismissed. The amounts, if any, deposited by the defendants shall be refunded to the defendants. This appeal is allowed as above. There shall be no costs. Dated this the 6[th] day of July, 2009. ## **V. RAMKUMAR, JUDGE.** Rv A.S. No. 640/1997 : 11 : ## V. RAMKUMAR, J **------------------------------------** A.S. No.640 of 1997 ---------------------------------------- 6[th ] day of July, 2009. JUDGMENT A.S. No. 640/1997 : 12 :
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.