State of Kerala and others v. N. Jayaprasad

Case / Petition Number:Arb. Appeal No.24/2011 (S)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • V. Chitambaresh
  • Sathish Ninan
Judgment Date
2017-08-11
Court Decision / Holding
In part allowed. The rate of interest is re-fixed at 9% per annum; the impugned award stands confirmed in all other respects. No costs.
Final Disposition
The appeal is allowed in part. The rate of interest payable is re-fixed at 9% per annum. The impugned award stands confirmed in all other respects. No costs.

Parties to the Case

Appellants / Petitioners

  • The State of Kerala represented by the Secretary, Irrigation Department, Government of Kerala; Chief Engineer, Project III, Kallada; Superintending Engineer, K.I.P. (LB) Circle, Kottarakkara (now defunct); Executive Engineer, KIP, LB - Division, No. VI, Kottarakkara (now defunct)

Respondents

  • N. Jayaprasad, S/o. Narayanan, Contractor, Pushpamangalam, Punalur, Kollam District, Pin - 691305

Legal Representation & Advocates

Counsels for Petitioners

  • • GOVERNMENT PLEADER P.M. SATHEESH

Counsels for Respondents

  • • Sri. T.S. Harikumaran; Sri. K. Jagadeesh; Sri. P.B. Sahasranaman

Case Synopsis & Summary

This arbitration appeal arises from an order of the Principal Sub Court, Thiruvananthapuram, in OP(Arb) 29/2002, challenging an arbitral award in favour of the claimant contractor for works under KI & TCDB – Formation of Melila West Distributory (Ch. 3 km to 10 km; Package II Part III; Ch. 3750 m to 5005 m) including CD works. The arbitrator allowed two heads of claim out of nine claimed sums, totaling Rs. 7,98,024, and the Sub Court declined to interfere under Section 34 of the Arbitration Act, 1940. The appellants/ respondents (State of Kerala and three government engineers) challenge the validity of the arbitration and seek to set aside the award on multiple grounds. The State contends that the appointment of the Arbitrator was beyond the time limit fixed under the Local Competitive Bidding (LCB) conditions (Clause 52), since the defects liability period ends six months after completion; the completion certificate and the certified completion date were not issued. The respondents counter that the defects liability period commences from the date of completion certificate, which was not issued, hence the time bar cannot defeat the arbitration. The High Court ultimately holds that completion certificate is essential for triggering the defects liability period and thus the time-barring argument fails; it also notes that the 1992 schedule of rates may be used, reduces the rate of interest from 18% to 9% per annum, and otherwise confirms the award. The appeal is allowed in part with no costs.

Provisions of Law Cited

Arbitration Act, 1940 – Section 30Local Competitive Bidding (LCB) conditions – Clause 52Local Competitive Bidding (LCB) conditions – Clause 18

Legal Doctrines & Maxims

  • Limited judicial review of arbitral awards: if the arbitrator's view is a possible one, the award is not liable to be interfered with.
  • The reasonableness of the arbitrator's reasons is not to be scrutinised by the court.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the arbitration could not be entertained since the Arbitrator’s appointment was sought beyond the 30-day limit after the expiry of the defects liability period under Clause 52 of the LCB conditions. They maintained that without a completion certificate, the defects liability period could not be reckoned in the ordinary course and that the contest to the arbitrator’s appointment was valid. They contended that reliance on the 1992 schedule of rates for work completed by 1994 was inappropriate, and the time-bar argument, if accepted, would vitiate the entire arbitral process.

Contentions of Respondents

The claimant urged in support of the award and its validity that the appointment of the Arbitrator was not barred and that the Court should not reweigh the arbitrator’s findings. They defended the use of the 1992 schedule of rates in determining compensation and pressed for maintaining the award, including the interest awarded by the Arbitrator.

Cited Precedents (14)

Case NameCitationTreatmentExplanation
Arosan Enterprises Ltd. v. Union of India and Another[1999] 9 SCC 449PositiveCited to emphasise the limited scope of judicial review; if a possible view of the arbitrator is adopted, interference is unwarranted.
Ispat Engineering & Foundry Works, B.S.City, Bokaro v. Steel Authority of India Ltd., B.S.City, Bokaro[2001] 6 SCC 347PositiveSupports the proposition on limited review and deferential approach to arbitral awards.
Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.[2003] 5 SCC 705PositiveAffirms non-interference where arbitral conclusions are plausible.
Kwality Manufacturing Corporation v. Central Warehousing Corporation[2009] 5 SCC 142PositiveUsed to underline the principle of limited judicial review.
Madhya Pradesh Housing Board v. Progressive Writers and Publishers[2009] 5 SCC 678PositiveSupport for restrained interference with arbitral awards.
O.P.Pathrose v. State of Kerala and Another[2010] 12 SCC 100PositiveReinforces limits on review of arbitral awards.
Ravindra Kumar Gupta and Company v. Union of India[2010] 1 SCC 409PositiveAffirms deference to arbitrator’s findings where possible.
State of Rajasthan v. Puri Construction Co.Ltd.[1994] 6 SCC 485PositiveCited for principles on arbitral review and efficiency of arbitral process.
G.Ramachandra Reddy and Company v. Union of India and Another[2009] 6 SCC 414PositiveSupport for limited judicial interference in arbitration.
Continental Construction Ltd. v. State of U.P.[2003] 8 SCC 4PositiveAuthorities on arbitration review standards.
State of U.P. v. Allied Constructions[2003] 7 SCC 396PositiveUsed to reinforce limited judicial scrutiny of awards.
Bhagavati Oxygen Ltd. v. Hindustan Copper Ltd.[2005] 6 SCC 462PositiveCited for principles on arbitral awards and review.
Municipal Corporation of Delhi v. M/s.Jagan Nath Ashok Kumar and Another[1987] 4 SCC 497PositiveReferenced in context of arbitration review philosophy.
State of Rajasthan v. Ferro Concrete Construction Private Limited[2009] 12 SCC 1PositiveUsed to justify reduction of interest rate in arbitral awards.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against State of Kerala and others v. N. Jayaprasad and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT:** **THE HONOURABLE MR.JUSTICE V.CHITAMBARESH & THE HONOURABLE MR. JUSTICE SATHISH NINAN** **FRIDAY, THE 11TH DAY OF AUGUST 2017/20TH SRAVANA, 1939** **Arb.A.No. 24 of 2011 (S) -------------------------** **AGAINST THE ORDER IN OP(ARB.)29/2002 OF PRL.SUB COURT,TRIVANDRUM DATED 09.11.2009** **APPELLANTS/RESPONDENTS:** **------------------------** **1. THE STATE OF KERALA, REPRESENTED BY THE SECRETARY, IRRIGATION DEPARTMENT GOVERNMENT OF KERALA, SECRETARIAT, THIRUVANANTHAPURAM.** **2. THE CHIEF ENGINEER, PROJECT III, KALLADA, PULAMON P.O., KOTTARAKKARA.** **3. THE SUPERINTENDING ENGINEER, K.I.P.(LB) CIRCLE, KOTTARAKKARA (NOW DEFUNCT) CHARGE HELD BY THE SUPERINTENDING ENGINEER, KIP, RB CIECLE, PULAMON P.O., KOTTARAKKARA.** **4. THE EXECUTIVE ENGINEER, KIP, LB - DIVSION, NO.VI KOTTARAKKARA, (NOW DEFUNCT) CHARGE HELD BY THE EXECUTIVE, ENGINEER, KIP, RB DIVISION, NO.II, PULAMON P.O. KOTTARAKKARA.** **BY ADV. GOVERNMENT PLEADER P.M.SATHEESH** **RESPONDENT/CLAIMANT:** **---------------------** **N.JAYAPRASAD, S/O. NARAYANAN, CONTRACTOR, PUSHPAMANGALAM, PUNALUR KOLLAM DISTRIT, PIN - 691 305.** **BY ADV. SRI.T.S.HARIKUMAR ADV. SRI.K.JAGADEESH ADV. SRI.P.B.SAHASRANAMAN** **THIS ARBITRATION APPEALS HAVING BEEN FINALLY HEARD ON 11-08-2017, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **vdv** **V.Chitambaresh & Sathish Ninan, JJ. ============================== Arb. Appeal No.24 of 2001 ========================== Dated this the 11[th] day of August, 2017** ## **JUDGMENT** ## **Sathish Ninan, J** 1. The order dated 09.11.2009 in O.P (Arb) No.29/2002 of Principal Sub Court, Thiruvananthapuram is under challenge by the respondents in the arbitration proceedings. As per the impugned order the court below refused to interfere with the award passed by Arbitrator in favour of the claimant to recover an amount of Rs.7,98,024/- from the appellants herein. 2. On 29.10.1984 an agreement was entered into by the claimant with the appellants for the work of “KI & TCDB – Formation of Melila West Distributory from Ch:3KM to 10KM Package II Part III from Ch:3750M to 5005M including CD works”. The work was to be completed on or before 14.01.1986. However, the work was completed only on 31.08.1994. The dispute that arose between the parties lead to the appointment of Arbitrator. Before the Arbitrator, as many as 9 Arb. Appeal No.24/2011 2 claims were raised for a total amount of Rs.93,61,59/-. However, the Arbitrator upheld the claims only under two heads namely claim for rock blasting and the claim for earth work. Though the appellants approached the subordinate Judge's Court in an application under Section 30 of the Arbitration act 1940, they were not successful and hence the appeal. 3. Heard the learned Govt. Pleader on behalf of the appellants and Advocate Sri. P.B.Sahasrabaman on behalf of the claimant/respondent. 4. The learned Govt. Pleader would contend that the arbitration proceedings could not have been entertained since the appointment of Arbitrator was sought for beyond the time limit fixed under the Local Competitive Bidding (LCB) specifications. Clause 52 of LCB conditions provides that the Arbitrator is to be appointed within 30 days after expiry of 'defects liability period'. The 'defects liability period' is six months from the date of completion of the work. Arb. Appeal No.24/2011 3 The work in question was completed on 31.08.1994 and the defect liability period expired on 28.02.1995. The request for arbitration was not made within 30 days from 28.02.1995 in terms of clause 52 of the LCB conditions. Therefore, according to the learned Govt. Pleader, the very appointment of the Arbitrator was illegal and consequently the award was vitiated and needs to be interfered with. According to the learned Govt. Pleader, the fact that a completion certificate was not issued is of no consequence since the determining factor is the certified date of completion and not the date of issue of the certificate of completion. Therefore, appointment of Arbitrator should have been sought for within 30 days from 28.02.1995 when the 'defects liability period' expired. 5. However, we are unable to agree with the said contention. Clause 18 of the LCB conditions provides that the defects liability period commences from the 4 Arb. Appeal No.24/2011 date of certificate of completion. It is only when the authority certifies that the work has been completed could it be reckoned that the work is completed. Therefore, the contention of the learned Govt. Pleader that the issuance of completion certificate is insignificant, cannot be accepted. Admittedly, certificate of completion has not been issued. We turn down the contention that the claim is not brought before the Arbitrator within the time stipulated. 5. Next contention of the learned Govt. Pleader is that though the work was executed before 1986, the Arbitrator has adopted the 1992 schedule of rates. As noted supra, it is the case of the appellants that the work was completed only on 31.08.1994 though the same was to be completed before 14.01.1986. The Aarbitrator considered the evidence and has passed an award adopting the 1992 schedule of rates. The Arbitrator has taken into consideration the period during which the work was carried on and completed. Though claims 5 Arb. Appeal No.24/2011 were made under several heads, most of the claims were rejected by the Arbitrator. The Arbitrator has looked into the measurement book to ascertain regarding the quantity of work done. The court below has in the application under section 34 found that "the rates allowed by the Arbitrator were very reasonable which does not call for any interference from the court." The Apex Court has repeatedly cautioned the scope of interference with an award of the Arbitrator. If the view taken by the Arbitrator is a possible one, the award is not liable to be interfered with. The reasonableness of the reasons given by the Arbitrator is not to be gone into by the court (See **Arosan Enterprises Ltd. v. Union of India and Another** ([1999] 9 SCC 449) **, Ispat Engineering & Foundry Works, B.S.City, Bokaro v. Steel Authority of India Ltd., B.S.City, Bokaro** ([2001] 6 SCC 347) **, Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd.** ([2003] 5 SCC 705) **, Kwality Manufacturing Corporation v. Central** 6 Arb. Appeal No.24/2011 **Warehousing Corporation** ([2009] 5 SCC 142] **, Madhya Pradesh Housing Board v. Progressive Writers and Publishers** ([2009] 5 SCC 678) **, O.P.Pathrose v. State of Kerala and Another** ([2010] 12 SCC 100), **Ravindra Kumar Gupta and Company v. Union of India** ([2010] 1 SCC 409) **, State of Rajasthan v. Puri Construction Co.Ltd.** ([1994] 6 SCC 485) **, G.Ramachandra Reddy and Company v. Union of India and Another** ([2009] 6 SCC 414) **, Continental Construction Ltd. v. State of U.P.** ([2003] 8 SCC 4) **, State of U.P. v. Allied Constructions** ([2003) 7 SCC 396) **, Bhagavati Oxygen Ltd., v. Hindustan Copper Ltd.** ([2005] 6 SCC 462) and **Municipal Corporation of Delhi v. M/s.Jagan Nath Ashok Kumar and Another ([1987] 4 SCC 497)** . The court below has found the award to be reasonable. 6. It is seen that the Arbitrator has granted interest at the rate of 18% per annum which we feel is excessive considering the prevalent Bank rate of interest. In tune with the law laid down by the Apex 7 Arb. Appeal No.24/2011 Court in **State of Rajasthan and Another v. Ferro Concrete Construction Private Limited** ([2009] 12 SCC 1), we re-fix the interest at the rate of 9% per annum. We do not find any grounds to interfere with the award except regarding the rate of interest. 7. In the result the appeal is allowed in part. The rate of interest payable is re-fixed at 9% per annum. The impugned award stands confirmed in all other respects. No costs. ## **V.Chitambaresh, Judge** **Sathish Ninan, Judge** vdv //True copy// P.A to Judge