Tenetowl LogoTenetowl
Landmark CasesDivision BenchAppeals allowed; High Court’s status-quo order ...

State of Jharkhand v. Surendra Kumar Srivastava & Ors.

Case / Petition Number:
Civil Appeal No. 21 of 2019; Civil Appeal No. 22 of 2019 (arising out of SLP(C) Nos. 26645 of 2015 and 24684 of 2015)

Case Synopsis & Summary

These Civil Appeals challenge the Jharkhand High Court’s May 19, 2015 writ order in W.P. (C) No. 2081 of 2015 and the subsequent district-court orders in Title Suit No. 45/2015. The appellants, the State of Jharkhand and the General Manager, Jharkhand State Electricity Board, sought to permit energisation and construction of a 33/11 kV electricity sub-station on land disputed by the heirs of late Smt. Shyal Devi. The respondents claim title and possession to about 3.61 acres in Mouza Baridih, Bara, Jamshedpur, recorded in Khata Nos. 19, 21 and 33, and contend that possessory rights were established by earlier litigation (1992-1999) recognizing possession since 1958. The land records show the property as Anabad land and substantial portions were claimed to be already allocated for the sub-station by orders and communications, including a Transport Commissioner letter dated 04.03.2015. The High Court’s Single Judge granted a status-quo order while the Title Suit No. 45/2015 progressed; the District Judge affirmed the injunction denial. The Supreme Court, emphasizing the overriding public interest in supplying electricity to about one lakh people, held that the balance of convenience favours energisation, reversed the injunction stance, and vacated the status-quo order. It directed that the Title Suit be decided in due course with appropriate compensation if title is later established.Overall, the case pivots on balancing private title claims against substantial public utility interests and the propriety of interim protections during ongoing litigation.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Indu Malhotra
  • Ashok Bhushan
Judgment Date
2019-01-03
Court Decision / Holding
Civil Appeals are allowed, the impugned Jharkhand High Court judgment in W.P. No. 2081 of 2015 is set aside, and the status quo order restraining energisation is vacated. The energy sub-station construction can proceed and be energised, subject to compensation if title is ultimately established in favor of the respondents. The trial court shall decide Title Suit No. 45/2015 with due process, and the court may assess compensation under applicable law if respondents prove any loss or injury.
Final Disposition
Appeals allowed; High Court’s status-quo order vacated; energisation permitted; Title Suit No. 45/2015 to proceed with compensation as applicable.

Parties to the Case

Appellants / Petitioners

  • State of Jharkhand
  • General Manager, Jharkhand State Electricity Board

Respondents

  • Respondent Nos. 1 to 3 (heirs of late Smt. Shyal Devi)

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Ajit Kumar Sinha

Counsels for Respondents

  • • Mr. Satpal Singh

Provisions of Law Cited

CPC, Order XXXIX Rules 1 and 2CPC, Order XLIII, Rule 1(r)Electricity Act, 2003, Section 67Constitution of India, Article 226

Legal Doctrines & Maxims

  • Balance of convenience
  • Prima facie case
  • Status quo
  • Overriding public interest
  • Protection of possession of a settled possessor (Meghmala & Ors. v. G. Narasimha Reddy & Ors.)
  • Possession rights of settled possessors (Meghmala and Rame Gowda)

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellants contended that the writ petition challenging orders of civil courts under Article 226 is not maintainable. Relying on Radhey Shyam v. Chhabi Nath & Ors., they argued interference by a High Court in pending civil proceedings via writ is impermissible, and that prior findings in Title Suit No. 153/1992 and Title Appeal No. 20/1999 establishing lack of title had attained finality since respondents did not challenge them. The land reportedly belonged to the State and had been made available for the sub-station via Transport Commissioner, Ranchi (04.03.2015). Given the public utility of energisation for around one lakh residents and the lack of any demonstrated irreparable loss, the balance of convenience favours energisation. Section 67 of the Electricity Act, 2003 empowers action to be taken, with entitlement to compensation if title is established later. The petitions argued against energy project disruption and asserted the State’s ownership and possession rights over the land.

Contentions of Respondents

Respondents argued that they are legal heirs with vested title and possession under earlier adjudications; The 1999 Additional Munsif judgment and the 2005 Title Appeal judgment recognized possession and title to some extent and that the transfer of land to the Board cannot occur on mere pendency of appeals; They contended the land records show the land as Anabad, and that a Transport Commissioner letter cannot alone justify entry into possession or transfer of the property; The writ petition cannot override due process or prior judgments, and the court should not deprive them of due remedies without proper adjudication; They emphasized the need for adjudication of title and protection of possession pending trial, resisting immediate energisation to avoid prejudicial dispossession without compensation and due process.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Radhey Shyam v. Chhabi Nath & Ors.—PositiveCourt acknowledges the legal principle from Radhey Shyam regarding maintainability but proceeds to consider merits without unsettling that authority.
Meghmala & Ors. v. G. Narasimha Reddy & Ors.(2010) 8 SCC 383Mentioned OnlyCited by counsel to support possession protection; not explicitly adopted by Court in the instant facts.
Rame Gowda (dead) by LRs v. M. Varadappa Naidu (dead) by LRs & Anr.(2004) 1 SCC 769Mentioned OnlyCited by counsel on protection of possession of settled possessors; not applied as a controlling rule by the Court here.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,804 words•~18 min read

In The Court Record

State of Jharkhand v. Surendra Kumar Srivastava & Ors.

## **REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. 21 OF 2019** ## **[Arising out of S.L.P. (C) No. 26645 of 2015]** The State of Jharkhand …Appellant Versus Surendra Kumar Srivastava & Ors. …Respondents ## **WITH** ## CIVIL APPEAL NO. 22 OF 2019 [Arising out of S.L.P. (C) No. 24684 of 2015] ## **J U D G M E N T** ## **INDU MALHOTRA, J.** Leave granted. Signature Not Verified 1. The present Civil Appeals arise out of S.L.P. (C) Nos. 26645 Digitally signed by JAYANT KUMAR ARORA Date: 2019.01.03 15:32:05 IST Reason: and 24684 of 2015 which have been filed to challenge the Judgment dated May 19, 2015 passed by the Jharkhand 1 High Court in W.P. (C) No. 2081 of 2015. The Writ Petition had been filed by Respondent Nos. 1 to 3 herein to challenge the Order dated 07.04.2015 refusing to grant Interim Relief in an Application filed under Order XXXIX Rules 1 and 2 of the CPC in Title Suit No. 45/2015, and Order dated 21.04.2015 passed by the District Court. 2. A brief factual background of this case is set out herein below: - 2.1. According to the Writ Petitioners/Respondent Nos. 1 to 3 herein, their mother – late Smt. Shyal Devi had purchased about 3.61 acres of land[1] (“suit property”) from Raju Gour and Shatrughan Gour by way of two unregistered Sale Deeds dated 30.04.1958. According to Respondent Nos. 1 to 3, late Smt. Shyal Devi had raised a structure over a part of the suit property, and was cultivating the rest of it. The said land was > 1 Recorded in R.S. _Khatian_ of 1937 under _Khata_ No. 19 (Plot Nos. 3737, 3733, 3710, 3741, 3749, 3751, 3752, 3753, 3754 and 3755), _Khata_ No. 21 (Plot No. 3742), _Khata_ No. 33 [Plot Nos. 3718, New Plot Nos. 2657, 2658, 2659, 2660, a portion of 2650, 2626(p), 2656(p), 2653(p), 2655(p) _Thana_ No. 1198 and 1151]. The above-described land was stated to be situated in _mouza_ agricultural and _bara_ , P.S. Sidhgora, District Singhbhum East, and was incorporated in new _Khatian_ No. 24 in the finally published record of rights of Jamshedpur Notified Area (19951996). 2 situated adjacent to the land belonging to the Bihar State Road Transport Corporation. 2.2. In 1992, Smt. Shyal Devi filed Title Suit No. 153/1992 before the Additional Munsif, Jamshedpur alleging that the officials of the Bihar State Road Transport Corporation were disturbing her possession of the suit property since 1990. The Additional Munsif _vide_ Judgment and Decree dated 18/27.02.1999 decreed the Suit in favour of the Plaintiff – late Smt. Shyal Devi, and confirmed her possession since 1958. The Bihar State Road Transport Corporation was restrained from interfering with the peaceful possession of Smt. Shyal Devi. The relevant extract of the findings of the Additional Munsif contained in the Judgment is reproduced hereinbelow: “ _11. In view of the aforesaid discussion, I found that plaintiff [Smt. Shyal Devi] has proved her possession of the suit land since 1958 and as such these issues are decided in favour of the plaintiff and against the defendant._ ” 3 2.3. The Bihar State Road Transport Corporation filed Title Appeal No. 20/1999 to challenge the Judgment and Decree dated 18/27.02.1999 before the Additional District Judge, East Singhbhum, Jamshedpur. The Title Appeal No. 20/1999 was dismissed by the Additional District Judge on the ground of possession. However, the District Judge held that the Plaintiff had failed to establish her title, and it would be open for the Bihar State Road Transport Corporation to file a suit against late Smt. Shyal Devi for declaration of title over the land, and to seek her eviction. - 2.4. The Bihar State Road Transport Corporation preferred Second Appeal No. 17509/2005 against the Judgment dated 29.08.2005 passed by the Additional District Judge before the Jharkhand High Court, which is currently pending adjudication. - 2.5. It is relevant to mention that late Smt. Shyal Devi did not challenge the finding that she had failed to 4 establish her title before the High Court. Hence, the finding of the Additional District Judge attained finality. 2.6. During the pendency of the Second Appeal, the Deputy Commissioner, East Singhbhum, Jamshedpur sought a No-Objection Certificate _vide_ letter dated 13.10.2012 from the Transport Commissioner, Jharkhand for the construction of an Electricity Sub-station on the land comprised in _Khata_ No. 24 (Plot Nos. 2650, 2652, 2656, and 2657) in Jamshedpur, recorded in the name of the Bihar State Road Transport Corporation. The Transport Commissioner _vide_ letter dated 04.03.2015 conveyed that it had no objection for transfer of the said land for the construction of an Electricity Sub-station thereupon. - 2.7. During the pendency of proceedings before the High Court, Smt. Shyal Devi expired 24.02.2014 leaving behind three sons _i.e._ Respondent Nos. 1 to 3, as her legal representatives and successors. 5 2.8. Respondent Nos. 1 to 3 filed Title Suit No. 45/2015 before the Civil Judge (Junior Division – I), Jamshedpur seeking permanent injunction to restrain the Appellant –The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] from interfering with their alleged possession of the suit property, along with an Application for Temporary Injunction. 2.9. The Civil Judge (Junior Division – I) _vide_ Order dated 07.04.2015 dismissed the Application for Temporary Injunction filed by Respondent Nos. 1 to 3. It was held that Respondent Nos. 1 to 3 failed to describe the specific area/portion of the suit property which was in their alleged possession, over which the construction of the Electricity Sub-station was being carried out by the Jharkhand State Electricity Board. The Civil Judge (Junior Division – I) concluded that Respondent Nos. 1 to 3 had failed to make out a _prima facie_ case, and held that no irreparable loss would be caused, which could not be compensated in terms of money. 6 2.10. Aggrieved by the Order dated 07.04.2015, Respondent Nos. 1 to 3 filed an Appeal under Order XLIII, Rule 1(r) of the CPC before the District Judge III-cum-MACT, East Singhbhum, Jamshedpur. The Appeal was dismissed _vide_ Order dated 21.04.2015 whereby the District Judge affirmed the Order passed by the Civil Judge (Junior Division – I) dated 07.04.2015. It was held that Respondent Nos. 1 to 3 had failed to demarcate the suit property in the Plaint to show that the construction activity was taking place on their land. The Plaintiffs had not placed on record the old _Khatian_ , or the new _Khatian_ . Respondent Nos. 1 to 3 were making a claim of possession with respect to 3.61 acres of land recorded in R.S. _Khatian_ of 1937 under _Khata_ No. 19 (Plot Nos. 3737, 3733, 3710, 3741, 3749, 3751, 3752, 3753, 3754 and 3755), _Khata_ No. 21 (Plot No. 3742), _Khata_ No. 33 [Plot Nos. 3718, New Plot Nos. 2657, 2658, 2659, 2660, a portion of 2650, 2626(p), 7 2656(p), 2653(p), 2655(p) _Thana_ No. 1198 and 1151]. The said land stated to be situated in _Mouza_ Baridih and Bara, P.S. Sidhgora, District Singhbhum East, in new _Khatian_ No. 24 in the finally published record of rights of Jamshedpur Notified Area (19951996). On the other hand, the Counsel for the State Electricity Board stated that 1.47 acres of land recorded as _Khata_ No. 24 (Plot Nos. 2650, 2652, 2656 and 2657) was registered in the name of the Bihar State Road Transport Corporation, as _Anabad_ land. The Board placed reliance on trace map, and a letter dated March 4, 2015 addressed by the Transport Commissioner, Ranchi, Jharkhand to the Deputy Commissioner, East Singhbhum, Jamshedpur making the land available for the Jharkhand State Electricity Board. The District Court held that the Plaintiffs had produced no rent receipts, or municipal receipts to corroborate their plea of alleged possession over the disputed suit property. 8 The District Court found that Respondent No. 3 – Narendra Kumar Srivastava had concealed a material fact that he had filed a Writ Petition before the High Court seeking an injunction from construction of a boundary wall and digging on the suit property by the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015]. The Writ Petition came to be withdrawn on 24.04.2015. The suppression of a material fact warranted the drawing of an adverse inference against the Respondents. The grant of injunction being a discretionary relief, Respondent Nos. 1 to 3 were found to not be entitled to the same. 2.11. Aggrieved by the judgment of the District Judge, Respondent Nos. 1 to 3 filed W.P. (C) No. 2081 of 2015 before the Jharkhand High Court seeking a writ of _certiorari_ to quash the Order dated 07.04.2015 passed by the Civil Judge (Junior Division – I) in Title Suit No. 45/2015, and Order dated 21.04.2015 passed by the District Court in Misc. Appeal No. 5/2015. 9 2.12. The Electricity Board filed a Counter Affidavit along with photographs of the construction of the Electricity Sub-station. It was submitted that almost 90% of the construction work of the Electricity Sub-station had already been completed. It was further stated that the grant of an injunction would seriously affect public interest, and the welfare scheme for providing electricity to the local populace at subsidised rates. - 2.13. The learned Single Judge of the High Court _vide_ the impugned Judgment dated 19.05.2015 allowed W.P. (C) No. 2081 of 2015 filed by Respondent Nos. 1 to 3, and directed the parties to maintain _status quo_ with respect to the suit property. It was clarified, that the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] was, however, at liberty to raise construction on any other land, except the disputed suit property. The learned Single Judge held that the findings of the courts below with respect to there being no _prima facie_ case in favour of Respondents No. 1 to 3 was erroneous in view of the judicial 10 findings in their favour in the previous round of litigation in Title Suit No. 153/1992, and Title Appeal No. 20/1999. The Single Judge held that the courts below dismissed the Application for Temporary Injunction filed by Respondent Nos 1 to 3 on the ground that Respondent Nos. 1 to 3 (Plaintiffs) had failed to specifically describe the disputed suit property, even though the description of the disputed suit property was not objected by the Jharkhand State Electricity Board. On balance of convenience, the Single Judge held that in case the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] completes the construction of the Electricity Sub-station, Respondent Nos. 1 to 3 would be under a compulsion to accept compensation, even if the Title Suit No. 45/2015 was decreed in their favour. 11 The Single Judge held that the photographs produced by the Appellant Electricity Board only indicated the raising of electricity poles, and no other construction had been raised on the disputed Suit Land. 3. Aggrieved by the impugned Judgment dated 19.05.2015 passed by the learned Single Judge of the High Court, the State of Jharkhand filed the present S.L.P. (C) No. 26645 of 2015, and the General Manager, Jharkhand State Electricity Board filed S.L.P. (C) No. 24684 of 2015. - 3.1. This Court _vide_ Interim Order dated 14.12.2015, granted liberty to the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] to draw the supply lines. - 3.2. The Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] in I.A. Nos. 91857 & 91859/2018, sought permission to energise the Electricity Sub-station, after depositing the costs of the suit property as 12 assessed by the Circle Officer, Jamshedpur before the Deputy Commissioner, Jamshedpur. 3.3. During the pendency of the proceedings, the Electricity Sub-station has been fully constructed having a capacity of 33/11 K.V. As per the Executive Engineer, Electricity Supply Division, Jamshedpur approximately 1 lakh people residing in the nearby areas would be benefitted by the supply of electricity, and it would result in reduction of loss of load on other Electricity Sub-stations situated in the vicinity. 4. The Appellants and Respondent No. 4 in both the Special Leave Petitions were represented by Mr. Ajit Kumar Sinha, Senior Advocate, while Respondent Nos. 1 to 3 were represented by Mr. Satpal Singh, Advocate. - 4.1. The learned Senior Counsel appearing for the Appellants, _inter alia_ submitted that Writ Petition No. 2081 of 2015, seeking a writ of _certiorari_ , was not maintainable, as it was filed to challenge judicial orders passed by civil courts. Learned Counsel placed 13 reliance on the decision of a three-judge bench in _Radhey Shyam_ v. _Chhabi Nath & Ors._[2] . 4.2. On merits, it was submitted that Respondent Nos. 1 to 3 did not have title to the disputed suit property. The Counsel relied on the findings in the Judgment dated 29.09.2005 passed in Title Appeal No. 20/1999 wherein the Additional District Judge had clearly held that the mother of Respondent Nos. 1 to 3 had failed to prove her title with respect to the disputed suit property. The said finding attained finality, since late Smt. Shyal Devi, or her legal heirs and successors _i.e._ Respondent Nos. 1 to 3 had not challenged the finding any further. 4.3. It was further submitted that the State of Jharkhand was the owner of the suit property, which was evidenced from the revenue records of the suit property recorded in the name of the Bihar State Road Transport Corporation. > 2 (2015) 5 SCC 423. 14 The learned Senior Counsel submitted that TISCO Ltd. had transferred 16.529 acres of land to the Bihar State Road Transport Corporation. The suit property was recorded in the name of the Bihar State Road Transport Corporation in the recent survey ( _khatiyal_ ). The Electricity Sub-station has been constructed on 1.47 acres of land registered as _Khata_ No. 24 (Plot Nos. 2650, 2652, 2656 and 2657) made available to the Jharkhand State Electricity Board by the Transport Department, Ranchi, Jharkhand _vide_ letter dated 04.03.2015. 4.4. Pursuant to the interim Order dated 14.12.2015, the Electricity Sub-station had been completely constructed, and would provide electricity to over 1 lakh people residing in the vicinity. 4.5. It was further submitted that the learned Single Judge erred in allowing W.P. (C) No. 2081 of 2015 since Respondent Nos. 1 to 3 had failed to make out a _prima facie_ case in their favour. They had also failed to demarcate the area in their alleged possession, in 15 the Plaint, on which the electricity Sub-station was being constructed. The balance of convenience was in favour of the Appellant-Electricity Board, in view of the overriding public interest in providing electricity to over 1 lakh people. Further, no irreparable loss or injury would be caused to Respondent Nos. 1 to 3 as they could always be adequately compensated under Section 67 of the Electricity Act, 2003, if found entitled. 4.6. On the other hand, Advocate Mr. Satpal Singh supported the findings of the learned Single Judge of the High Court. It was submitted that the title to the disputed suit property vested in Respondent Nos. 1 to 3 since the issue pertaining to title was decided by the Additional Munsif in favour of the mother of Respondent Nos. 1 to 3, _vide_ Judgment dated 18.02.1999. Title Appeal No. 20/1999 filed by the Bihar State Road Transport Corporation against the 16 Judgment of the Additional Munsif was dismissed by the Additional District Judge, _vide_ Judgment dated 29.08.2005. Although, Second Appeal No. 17509/2005 had been filed by the Bihar State Transport Corporation against the Judgment dated 29.08.2005 passed by the Additional District Judge, it was pending final determination before the High Court. The learned Advocate contended that the mere pendency of the Second Appeal No. 17059/2005 would not entitle the Bihar State Road Transport Corporation to transfer the disputed suit property to the Appellant – General Manager, Jharkhand State Electricity Board [in SLP (Civil) No. 24684 of 2015]. The Appellant–State Electricity Board failed to establish its title or possession over the disputed Suit property, since it had not produced any material except the letter of the Transport Commissioner dated 04.03.2015 and a map. 17 The learned Counsel relied on the decisions of this Court in _Meghmala & Ors._ v. _G. Narasimha Reddy & Ors._[3] and _Rame Gowda (dead) by LRs_ v. _M. Varadappa Naidu (dead) by LRs & Anr._[4] to submit that a person who is in settled possession, even in case he is a trespasser, has the right to be protected against forcible eviction, and can be evicted only after following the procedure prescribed by law. 5. The limited issue which arises for consideration in the present Civil Appeals is whether the learned Single Judge of the High Court was justified in directing the parties to maintain _status quo_ during the pendency of the Title Suit No. 45/2015 before the Court of Civil Judge (Junior Division – I), Jamshedpur. ## 6. **DISCUSSION AND ANALYSIS** We have heard the Counsel for both parties at length, perused the pleadings, and the written submissions filed in the present Civil Appeals. > 3 (2010) 8 SCC 383, paragraphs 46-48. > 4 (2004) 1 SCC 769. 18 6.1. With respect to the first submission of the learned counsel for the Appellants that the Writ Petition filed by Respondent Nos. 1 to 3/Plaintiffs for a writ of _certiorari_ to quash the Order dated 07.04.2015 passed by the Civil Judge (Junior Division) and the Order dated 21.04.2015 passed by the District Judge was not maintainable in view of the judgment of the three-judge bench in _Radhey Shyam_ v. _Chhabi Nath & Ors._[5] , there cannot be any dispute to the law laid down by this Court in _Radhey Shyam_ v. _Chhabi Nath & Ors._ (supra), but in the facts of the present case, we do not propose to unsettle the judgment of the High Court on the above ground due to two reasons, _firstly_ , in the High Court, the Appellants, who were Respondents in the Writ Petition, did not challenge the maintainability of the Writ Petition under Article 226 of the Constitution of India, and _secondly_ , had the Appellants raised the above objection regarding maintainability of the Writ Petition, the course open for Plaintiffs/Respondent Nos. 1 to 3 was to amend 5 (2015) 5 SCC 423. 19 the cause title of the writ petition under Article 227 of the Constitution, and such a Writ Petition under Article 227 would have been clearly maintainable. - 6.2. The Writ Petition under Article 227 challenging the orders passed by Civil Courts refusing to grant interim injunction under Order XXXIX, Rules 1 and 2 of the CPC could very well be maintainable, and the opportunity to amend the cause title by Respondent Nos. 1 to 3 by raising any objection to that effect having been denied to them, we, instead of setting aside the judgment of the High Court on the above ground, proceed to examine the contentions on merits. - 6.3. The Learned Single Judge granted an order of _status quo_ with respect to the construction of the Electricity Sub-station even though the Plaintiffs/Respondent Nos. 1 to 3 herein had failed to produce any documentary evidence whatsoever to establish their title to the suit property. 20 The Additional District Judge in the earlier round of litigation, in Title Appeal No. 20/1999 _vide_ Judgment dated 29.08.2005 had categorically held that late Smt. Shyal Devi, the mother of Respondents No. 1 to 3 and the predecessor in title, had failed to establish her title to the suit property. The said finding has admittedly not been challenged by Respondent Nos. 1 to 3. The said finding has attained finality. In this view of the matter, the Respondents failed to make out a _prima facie_ case, which would have justified the grant of an interim injunction. 6.4. Furthermore, the Plaintiffs/Respondent Nos. 1 to 3 also failed to establish that the Electricity Sub-station was being constructed on their land. The Respondents No. 1 to 3 failed to describe the specific area which was in their alleged possession over which the Electricity Sub-station was being constructed. 6.5. The balance of convenience lies entirely in favour of the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 21 2015] since the entire Electricity Sub-station has been fully constructed, and is now at the stage of being energised for supply of electricity _inter alia_ to four feeders _viz_ . Bhuiyadih (BHU), Baridih (BRD), Vidyapatinagar (VPN). It is estimated to provide electricity to approximately 1 lakh people. The Board is statutorily empowered under Section 67 of the Electricity Act, 2003 to undertake all actions necessary for transmission or supply of electricity, subject to the procedure under the Electricity Act, 2003. - 6.6. Respondent Nos. 1 to 3 have failed to produce any evidence of their possession over the vacant land, no undue hardship or prejudice would be caused to them, in the event the Appellant – The General Manager, Jharkhand State Electricity Board [in S.L.P. (C) No. 24684 of 2015] is permitted to proceed with the energisation of the Electricity sub-station. - 6.7. In the event that Respondents No. 1 to 3 are able to establish their title and possession to any part of the property utilised for the Electricity Sub-station, they 22 would be entitled to compensation for any damage, detriment or inconvenience caused, in accordance with S. 67(3) of the Electricity Act, 2003, and/or any other law for the time being in force. - 6.8. The Electricity Sub-station is complete in all respects and ready to be energised, as per the documentary evidence placed before the Court. The overriding public interest of providing electricity to the local populace would far outweigh the alleged interest of Respondent Nos.1 to 3. In view of the aforesaid facts and circumstances, the decision of the Civil Judge (Junior Division – I) and the District Judge in refusing to grant a Temporary Injunction in Title Suit No. 45/2015, was justified, and is restored. 7. In view of the aforesaid reasons, the Civil Appeals are allowed, and the impugned Judgment dated May 19, 2005 passed by the Learned Single Judge of the Jharkhand High Court in Writ Petition No. 2081 of 2015 is hereby set aside. The impugned Judgment ordering the maintenance of 23 _status quo_ with respect to the Suit property till the final disposal of the Title Suit No. 45/2015 stands vacated. The findings given in this judgment are _prima facie_ in nature given at the interim stage, and will not influence the trial of the case. The pending applications be disposed of accordingly. Ordered accordingly. **…..……...........................J.** **(ASHOK BHUSHAN)** **..….……..........................J. (INDU MALHOTRA)** **New Delhi; January 03, 2019** 24
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.