State of Haryana v. Shiv Shankar Construction Co. & Anr.

Case / Petition Number:
Civil Appeal Nos. 7379-7380 of 2021

Case Synopsis & Summary

This Supreme Court Civil Appeal concerns a road maintenance contract awarded by the State of Haryana to M/s Shiv Shankar Construction Co. for strengthening, upgrading and maintenance of a 31.17 km stretch from Palwal to Hasanpur, Haryana, at a contract value of Rs 5,26,59,688. Traffic along the route surged after the Palwal–Aligarh Road was closed for a railway bridge, increasing from an intended design of 3364 PCU/day to about 24,418 PCU/day, causing accelerated road damage. The contractor claimed additional expenditure due to the heavy traffic and invoked arbitration under clauses 24–25; the High Court appointed an arbitrator in 2007. The sole arbitrator awarded Rs 1,51,95,400 for claims 1 and 8. The State challenged under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, arguing the award exceeded the claim, exceeded the scope of reference, and rewrote the contract by fixing Rs 45,000 per km per month rather than Rs 1,000 per km per month. The Supreme Court partly allowed the appeals: the award for Rs 45,000 per km per month up to January 2008 was confirmed, while the portion from February 2008 to 31.05.2010 was set aside. The Court noted that the excess beyond January 2008 was impermissible and that cited precedents relied upon by the applicant were not applicable to the facts.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2021-12-14
Court Decision / Holding
Partly Allowed. The arbitral award’s compensation at Rs.45,000 per km per month up to January 2008 is confirmed; the portion from February 2008 to 31.05.2010 is quashed and set aside. The amount due and payable has to be worked out accordingly. There shall be no order as to costs.
Final Disposition
Partly Allowed

Parties to the Case

Appellants / Petitioners

  • State of Haryana

Respondents

  • M/s Shiv Shankar Construction Co. & Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Shri Shyam Divan, Senior Advocate

Counsels for Respondents

  • • Shri Ranjit Kumar, Senior Advocate

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 11(6)Arbitration and Conciliation Act, 1996 - Section 34Arbitration and Conciliation Act, 1996 - Section 37

Legal Doctrines & Maxims

  • Award in excess of claim or beyond the scope of reference constitutes misconduct by the arbitrator
  • Arbitrator cannot rewrite the contract or alter terms beyond the scope of reference
  • Exceeding jurisdiction -> ground to set aside under Section 34/37
  • Permissible period for awards tied to the period of extra-ordinary circumstances (e.g., traffic diversion) and not beyond.
  • Judicial scrutiny can modify or set aside parts of an arbitral award while preserving valid portions

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that the arbitral award is in excess of the claimed amount (Rs 1,03,50,263) and beyond the contract’s scope; the arbitrator rewrote the contract by fixing Rs 45,000 per km per month instead of the contractual Rs 1,000 per km per month; relies on ONGC Ltd. v. Off-Shore Enterprises and other precedents to urge that excess awards constitute misconduct and exceed jurisdiction; seeks setting aside of the excess portion and restoration to the contractual framework.

Contentions of Respondents

The contractor submits that the award is not beyond the claim; the statement of claim anticipated additional expenditure beyond May 2007 and the arbitrator’s award reflects evidence-based loss due to diverted traffic; the excess is justified by sustained higher PCU/day; the period beyond January 2008 was necessary to cover continued extra maintenance; the award should be granted in full or, at least, not satisfy the appellant’s assumptions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
ONGC Ltd. v. Off-Shore Enterprises Inc.(2011) 14 SCC 147DistinguishedCited by the appellant but not adopted by the Court; the Court found the cited rationale not applicable to the facts.
Associate Builders v. Delhi Development Authority(2015) 3 SCC 49Mentioned OnlyCited to support the proposition that excess award may indicate misconduct; not applied to the facts.
J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr.(2008) 2 SCC 444Mentioned OnlyCited regarding not rewriting contract; not utilized in forming judgment.
Indian Aluminium Cables Ltd. v. Haryana State Electricity Board(1996) 5 SCALE 708Mentioned OnlyCited in context of scope of reference; not relied upon.
MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr.(2011) 10 SCC 573Mentioned OnlyCited; not relied upon in final determination.
Satyanarayana Construction Company v. Union of India and Others(2011) 15 SCC 101Mentioned OnlyCited to argue against rewriting contract; not applied in judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,971 words•~14 min read

In The Court Record

State of Haryana v. Shiv Shankar Construction Co. & Anr.

**REPORTABLE** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **­ CIVIL APPEAL NOS.7379 7380 OF 2021** State of Haryana ..Appellant (S) ## VERSUS M/s. Shiv Shankar Construction Co. & Anr. ..Respondent (S) ## **J U D G M E N T** ## **M. R. Shah, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 03.11.2015 passed by the High Court of Punjab and Haryana at Chandigarh in FAO No. 4482 of 2011 (O&M), by which the High Court has dismissed Signature Not Verified Digitally signed by R Natarajan the appeal preferred by the appellant herein under Section Date: 2021.12.14 16:41:24 IST Reason: 1 37 of the Arbitration and Conciliation Act, 1996, the State of Haryana has preferred the present appeals. 2. At the outset it is required to be noted that while issuing notice in the present appeals, this Court has stayed the award exceeding Rs.1,03,50,263/­ insofar as claim Nos.1 and 8 are concerned. 3. The facts leading to the present appeals in a nutshell are as under:­ - 3.1 That the appellant herein awarded the contract to respondent No.1 herein – contractor for strengthening, up­gradation and maintenance of road from Palwal to Hasanpur, Haryana for a length of 31.17 kilometres on certain terms and conditions as per the contract entered into between the parties. The contract was for Rs.5,26,59,688/­. That as per the design calculation data, the specifications as prepared by the appellant department were meant for 3364 traffic intensity PCU (Passenger Car Unit)/day. The contract was up to 31.05.2010. That on 05.03.2005 due to the closing of the Palwal Aligarh Road on account of the construction of the railway bridge, the entire traffic was diverted from Palwal 2 Aligarh Road to the present road. That due to this diversion of traffic from Palwal Aligarh Road, heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day, which damaged the road. That according to the contractor – respondent No.1 herein, he was required to do heavy repair by incurring additional expenditure. Disputes arose between the parties. A legal notice was served upon the appellant making the claims. Disputes were not resolved and therefore respondent No.1 – contractor invoked the arbitration clause as clauses 24 & 25 and per approached the High Court for appointment of an arbitrator in exercise of power conferred under Section 11 (6) of the Arbitration and Conciliation Act, 1996. 3.2 Vide order dated 23.04.2007, the High Court appointed Shri R.S. Jindal, retired Chief Engineer, Delhi Development Authority as the sole Arbitrator to adjudicate upon all the disputes between the parties. That the contractor submitted various claims including claim Nos. 1 and 8. For the purpose of deciding the present appeals, claim Nos.1 and 8 are relevant. The sole Arbitrator awarded a total sum of Rs.1,51,95,400/­ with respect to claim Nos.1 and 8. 3 4. Feeling aggrieved and dissatisfied with the award declared by the learned Arbitrator, the appellant preferred an application before the Court under Section 34 of the Arbitration and Conciliation Act, 1996, which came to be dismissed against which the appellant – State preferred an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 before the High Court. By the impugned judgment and order the High Court has dismissed the said appeal. Hence, the State of Haryana has preferred the present appeals. 5. Shri Shyam Divan, learned Senior Advocate has appeared on behalf of the State – appellant and Shri Ranjit Kumar, learned Senior Advocate has appeared on behalf of the respondent No.1 – contractor. - 5.1 Shri Shyam Divan, learned Senior Advocate appearing on behalf of the appellant submitted that the appellant has already paid to respondent No.1 – contractor an amount of Rs.1,03,50,263/­ pursuant to the interim order dated 26.08.2016 passed by this Court. 4 5.2 Shri Shyam Divan, learned Senior Advocate appearing on behalf of the appellant has submitted that the arbitral award is liable to be set aside on the following grounds:­ - (i) The award is in excess of claim; - (ii) The Arbitrator exceeded the scope of reference; - (iii) The Arbitrator has rewritten the contract with respect to the amount payable which was specified in the contract. - 5.3 Now, so far as ground No.1 that the award is in excess of claim, it is vehemently submitted by Shri Shyam Divan, learned Senior Advocate appearing on behalf of the appellant that the contractor in its statement of claim had claimed an amount of Rs. 1,03,50,263/­ only under the claim Nos.1 and 8. It is submitted that despite the above the Arbitrator has awarded a total sum of Rs.1,51,95,400/­, which is in far excess of amount claimed. It is submitted that the statement of claim was never modified by the contractor and therefore, the Arbitrator ought not to have awarded the sum/amount in excess of the amount claimed. 5 - 5.3.1 It is submitted that the differential amount of Rs.48,45,137/­ is in excess of claim and to that extent the arbitral award is invalid and liable to be set aside. Reliance is placed on the decision of this Court in the case of **ONGC Ltd. v. Off­Shore Enterprises Inc.,** (2011) 14 SCC 147 (para 16). 5.3.2 It is submitted that as held by this Court in the cases of **Associate Builders v. Delhi Development Authority** , (2015) 3 SCC 49 (para 36) and **J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr.,** (2008) 2 SCC 444 (para 31­32), making an award in excess of claim is clear cut an act exceeding the jurisdiction and amounts to a misconduct of the Arbitrator. - 5.4 Now, so far as ground No.2 namely, that the Arbitrator exceeded the scope of reference, it is contended that the Arbitrator cannot exceed the scope of reference. - 5.4.1 It is submitted that the contractor invoked the arbitration clause on 06.03.2006. The High Court appointed the sole 6 Arbitrator on 23.04.2007 and the Arbitrator entered upon reference on 19.05.2007. It is urged that by allowing the claims for a period beyond 19.05.2007, the Arbitrator exceeded the scope of reference. 5.4.2 It is submitted that an amount of Rs.57,96,000/­ (approx.) has been awarded for claims arising between 19.05.2007 to 31.07.2008 (calculated as amount for maintenance of road @ Rs. 45,000/­ per kilometre (km) per month). It is submitted that it was not permissible for the Arbitrator to exceed the scope of the reference beyond the date upon entering reference and as a consequence the award is liable to be set aside. 5.4.3 Learned senior counsel appearing on behalf of the appellant has relied upon the decisions of this Court in the cases of **Indian Aluminium Cables Ltd. v. Haryana State Electricity Board,** 1996 (5) SCALE 708 (para 2) and **MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr.** (2011) 10 SCC 573 (para 15), in support of his above submissions that as the Arbitrator exceeded the scope of reference and hence the award is liable to be set aside. 7 - 5.5 In so far as the ground No.3 is concerned namely, the Arbitrator has rewritten the contract with respect to the amount payable which was specified in the contract, it is submitted that the Arbitrator has rewritten the terms of the contract by directing the appellant to pay the compensation to respondent No.1 – contractor at the rate of Rs.45,000/­ per km per month instead of mutually agreed contractual rate of Rs.1,000/­ per km per month. It is contended that it was not open to the Arbitrator to rewrite the terms of the contract and award the contractor a higher rate for the work than the rate which was already fixed in the contract. It is submitted that such an exercise is beyond the competence and authority of the Arbitrator. Reliance is placed on the decision of this Court in the case of **Satyanarayana Construction Company v. Union of India and Others** (2011) 15 SCC 101 (para 11). - 5.6 It is further contended by Shri Divan, learned Senior Advocate appearing on behalf of the appellant that even otherwise, the amount awarded by the Arbitrator at 8 Rs.45,000/­ per km per month beyond the time period of additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. till the end of contract is wholly impermissible. It is submitted that diversion of traffic on 9.2 km stretch of the road which gave rise to the cause of action ceased to exist w.e.f. January 2008. It is submitted that however, the Arbitrator has directed the appellant to make payment at Rs. 45,000/­ per km per month even beyond the time period of additional traffic. It is contended that the aforesaid is wholly impermissible. 6. Making the above submissions, it is prayed to allow the present appeals. 7. Shri Ranjit Kumar, learned Senior Advocate appearing on behalf of respondent No.1 – contractor, has vehemently contended that the award passed by the Arbitrator cannot be said to be (i) in excess of claim; (ii) exceeding the scope of reference and (iii) rewriting the contract with respect to the amount payable which was specified in the contract, as submitted on behalf of the appellant. It is submitted that in the statement of claim the contractor specifically stated that 9 the amount has been worked out up to the month of May, 2007 and the details of expenditure beyond May, 2007 will be submitted during the course of hearing. It is therefore submitted that it cannot be said that claim Nos.1 and 8 were restricted to Rs. 1,03,50,263/­ only. It is urged that on appreciation of the evidence on record the Arbitrator has awarded Rs. 1,51,95,400/­ for claim Nos.1 and 8, which in any case cannot be said to be beyond the amount claimed in the statement of claim. 7.1 It is next contended that it also cannot be said that the award passed by the Arbitrator was beyond the scope of reference. It is submitted that as such cause of action to claim the additional amount arose due to over­expenditure owing to maintenance of road due to diversion of traffic from Palwal Aligarh Road to the present road which continued even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007. It is submitted that the amount awarded by the Arbitrator under claim Nos.1 and 8 cannot be said to be exceeding the scope of reference. 10 - 7.2 It is further submitted that even the award passed by the Arbitrator to make payment at Rs.45,000/­ per km per month cannot be said to be rewriting of the contract with respect to the amount payable which was specified in the contract. It is urged that at the time when the contract was written/entered into between the parties the contract rate of Rs.1,000/­ per km per month was agreed against the design of 3364 PCUS per day. However, after the contract was entered into and the contractor acted as per the contract there was diversion of traffic from Palwal Aligarh Road to the present road and the heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day and therefore the contractor was required to incur additional expenditure at Rs.45,000/­ per km per month. It is submitted that the amount awarded by the Arbitrator at Rs.45,000/­ per km per month cannot be said to be rewriting the contract with respect to the amount payable than what was specified in the contract i.e. Rs.1,000/­ per km per month. - 7.3 However, Shri Ranjit Kumar, learned Senior Advocate appearing on behalf of the contractor is not in a position to 11 justify the award by which the Arbitrator has awarded the payment at Rs.45,000/­ per km per month even beyond the time period of additional traffic i.e. up to 31.05.2010 i.e. till the end of the contract. 8. We have heard the learned senior counsel appearing on behalf of the respective parties at length and given our thoughtful consideration. 9. That the contractor was awarded the contract for maintenance, etc. The contract amount was for Rs.5,26,59,688/­. The rate of maintenance of the road as accepted was Rs.12,000/­ per km per annum or Rs.1,000/­ per km per month. The maintenance contract was valid up to 31.07.2010. When the contract was entered into, the contract was meant for only 3364 PCUS per day. However, due to diversion of traffic from Palwal Aligarh Road to the present road, the contractor was required to incur additional expenditure on the maintenance due to increase in the traffic and plying the additional commercial vehicles. Therefore the contractor claimed the amount towards additional expenditure for maintenance which was due to increase in 12 the traffic and plying more commercial vehicles. On appreciation of evidence the Arbitrator has determined the loss at Rs.45,000/­ per km per month (claim Nos.1 and 8). - 9.1 The case on behalf of the appellant that as in the statement of claim, the claimant claimed an amount of Rs.1,03,50,263/­ under the claim Nos. 1 and 8 and the Arbitrator has awarded Rs.1,51,95,400/­, the same is in far excess of amount claimed and therefore the award is in excess of amount claimed has no substance. When the statement of claim submitted by the contractor is seen, it is specifically stated by the claimant that the amount of Rs.1,03,50,263/­ has been worked out up to May, 2007 and the details of expenditure beyond May, 2007 will be submitted during the course of hearing. It is specifically stated that expenditure incurred up to May, 2007 works out to Rs.1,03,50,263/­. Therefore, the amount awarded by the Arbitrator cannot be said to be in excess of the claim. 9.2 Now so far as the submission on behalf of the appellant that the Arbitrator exceeded the scope of reference while awarding an amount beyond 19.05.2007 – the date on which the High 13 Court appointed the sole Arbitrator is concerned, the same has no substance. The case on behalf of the appellant that the Arbitrator ought to have restricted the claim either up to 06.03.2006 – the date on which the contractor invoked the arbitration clause or 23.04.2007, the date on which the High Court appointed the sole Arbitrator or at least up to 19.05.2007 – the date on which the Arbitrator entered into reference, is concerned, it is required to be noted that the claim made by the Arbitrator was till the traffic was diverted which was up to January, 2008. Therefore, the Arbitrator was justified in awarding the amount beyond the aforesaid periods and till the additional traffic was diverted due to the closure of Palwal Aligarh Road. - 9.3 Now the submission on behalf of the appellant is that by awarding Rs.45,000/­ per km per month the Arbitrator has rewritten the contract with respect to the amount payable than what was specified in the contract. It is urged that under the contract mutually agreed contractual rate was Rs.1,000/­ per km per month and therefore any amount higher than Rs.1,000/­ per km per month is beyond the terms and conditions of the contract, is also without 14 substance. It is noted that at the time when the contract was entered into the the rate fixed was mutually agreed, Rs.1,000/­ per km per month and the estimated traffic was 3364 PCUS per day. The cause of action arose subsequently due to diversion of traffic from Palwal Aligarh Road and plying of more heavy vehicles due to which the contractor was required to incur additional expenditure for maintenance of the road. Therefore, the contractor was entitled to the loss on account of the additional expenditure incurred for maintenance of the road due to increase in the traffic because of the closure of the Palwal Aligarh Road and diversion of the traffic to the present road. Therefore, by no stretch of imagination it can be said that there was rewriting the terms of the contract as submitted on behalf of the appellant. 9.4 In view of the above findings, none of the decisions of this Court relied upon by the learned senior counsel appearing on behalf of the appellant are applicable to the facts of the case on hand as the same are not of any assistance to the appellant. 15 - 9.5 However, at the same time Shri Divan, learned Senior Advocate, appearing on behalf of the appellant is justified in submitting that the Arbitrator ought not to have awarded an amount of Rs.45,000/­ per km per month beyond the time period of additional traffic. The Arbitrator has awarded the loss/amount at Rs.45,000/­ per km per month up to 31.05.2010 i.e. till the end of the contract which is wholly impermissible diversion of the additional traffic ceased to exist w.e.f. January, 2008. Therefore, the Arbitrator ought not to have awarded any amount beyond the above time period beyond January, 2008. To that extent the award passed by the Arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed. 10. In view of the above and for the reasons stated above, the present appeals are allowed in part. The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/­ per km per month up to January, 2008 under claim Nos.1 and 8 is hereby confirmed. The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/­ per km per month from February, 2008 to 31.05.2010 i.e. till the end of the contract is hereby quashed 16 and set aside. The amount due and payable has to be worked out accordingly. The present appeals are partly allowed to the aforesaid extent. In the facts and circumstances of the case there shall be no order as to costs. …………………………………J. **(M. R. SHAH)** …………………………………J. **(B.V. NAGARATHNA)** New Delhi, December 14, 2021. 17
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.