STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.

Case / Petition Number:
Civil Appeal Nos. 7379-7380 of 2021
Neutral Citation:12 S.C.R. 294

Case Synopsis & Summary

This Supreme Court judgment concerns a public road maintenance contract awarded by the State of Haryana to Shiv Shankar Construction Co. for strengthening, upgrading and maintaining a 31.17-km stretch from Palwal to Hasanpur. The contract, valued at Rs 5.26 crore, anticipated traffic of 3364 PCU/day and was to endure until July 2010. After the Palwal–Aligarh Road was closed for railway works, traffic was diverted to the present road, causing a dramatic increase in traffic to 24,418 PCU/day and thereby escalating maintenance costs. The contractor claimed compensation for the added expenditure through claims 1 and 8; the sole arbitrator awarded Rs 1,51,95,400. The State challenged this award under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, arguing the award exceeded the claim amount, exceeded the scope of reference, and effectively rewrote contract terms by fixing Rs 45,000 per km per month instead of Rs 1,000 per km per month. The High Court dismissed the appeal. The Supreme Court stayed payment beyond Rs 1,03,50,263 and eventually partly allowed the appeals: it held that the amount up to May 2007, as stated in the claimant’s materials, was not in excess of the claim; however, it found the Rs 45,000/km/month rate impermissible beyond January 2008. Consequently, the Court confirmed the Rs 45,000/km/month rate up to January 2008 and quashed it from February 2008 to 31.05.2010, directing the remainder to be worked out. Appeals partly allowed; no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. SHAH
  • B. V. NAGARATHNA
Judgment Date
2021-12-14
Court Decision / Holding
Appeals partly allowed. The arbitrator’s award of Rs.45,000 per km per month up to January 2008 is confirmed; the portion from February 2008 to 31.05.2010 is quashed; the amount due and payable to be worked out accordingly. No order as to costs.
Final Disposition
Appeals partly allowed

Parties to the Case

Appellants / Petitioners

  • STATE OF HARYANA

Respondents

  • M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.

Legal Representation & Advocates

Counsels for Petitioners

  • • Alok Sangwan, AAG
  • • Shyam Divan, Sr. Adv.
  • • Sumit Kumar Sharma
  • • Anurag Kulharia
  • • Ms. Diksha Sharma
  • • Adith Deshmukh
  • • Dr. Monika Gusain

Counsels for Respondents

  • • Ranjit Kumar, Sr. Adv.
  • • Mohit Paul
  • • Vikrant Singh Bloria
  • • Bikram Dwivedi

Provisions of Law Cited

Arbitration and Conciliation Act, 1996: Section 34Arbitration and Conciliation Act, 1996: Section 37Arbitration and Conciliation Act, 1996: Section 11(6)

Legal Doctrines & Maxims

  • Award in excess of claim constitutes misconduct of the Arbitrator
  • Arbitrator cannot exceed the scope of reference
  • Arbitrator cannot rewrite the terms of the contract

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that the arbitral award is largely outside the claims (excess of claim), exceeds the scope of reference and rewrites the contract by specifying Rs.45,000 per km per month instead of Rs.1,000 per km per month. It relies on decisions such as ONGC Ltd. v. Off-Shore Enterprises Inc., Associate Builders v. Delhi Development Authority, J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr., Indian Aluminium Cables Ltd. v. Haryana State Electricity Board and MSK Projects India (JV) Ltd. to argue misconduct by the arbitrator. The time-bound nature of the post-diversion damages and the date of entering reference (mid-2007) raise issues about permissible scope.

Contentions of Respondents

The contractor asserts that the claim Nos. 1 and 8 involve Rs. 1,03,50,263 up to May 2007 with subsequent expenditure to be proved; the award is not beyond the claim. The increased traffic caused additional expenditure, which the arbitrator could award within the broad reference. The Rs. 45,000/km/month rate is justified given traffic diversion and the contract's overall framework. The challenge is to be resolved by confirming reasonable portions of the award.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
ONGC Ltd. v. Off-Shore Enterprises Inc.(2011) 14 SCC 147Mentioned OnlyCited by appellant; court found it not applicable to the facts.
Associate Builders v. Delhi Development Authority(2015) 3 SCC 49Mentioned OnlyCited by appellant; not controlling on the facts.
J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr.(2008) 2 SCC 444Mentioned OnlyCited by appellant; not applied to the facts.
Indian Aluminium Cables Ltd. v. Haryana State Electricity Board1996 (5) SCALE 708Mentioned OnlyCited; not applicable to the facts.
MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr.(2011) 10 SCC 573Mentioned OnlyCited; relied on in argument but not controlling.
Satyanarayana Construction Company v. Union of India and Others(2011) 15 SCC 101Mentioned OnlyCited in argument on contract rewriting; not applicable to the facts.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,133 words•~19 min read

In The Court Record

STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.

294 SUPREME COURT REPORTS[2021] 12 S.C.R. 294 [2021] 12 S.C.R. A ## STATE OF HARYANA v. ## M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. (Civil Appeal Nos.7379-7380 Of 2021) B DECEMBER 14, 2021 ## **[M. R. SHAH AND B. V. NAGARATHNA, JJ.]** - _Arbitration and Conciliation Act, 1996: ss.34 and 37 –_ - _Contract awarded for maintenance of road for Rs.5.26 crores – The rate of maintenance of the road was accepted at Rs.1,000 per_ - C _km p.m. – Maintenance contract was valid up to 31.07.2010 – Contract was meant for only 3364 PCUS per day – Dispute arose when contractor was required to incur additional expenditure on maintenance due to diversion of traffic from Palwal Aligarh Road to the present road and heavy traffic of 24418 PCUS per day started_ - D _plying on the road which damaged the road – Contractor claimed the amount towards additional expenditure for maintenance – Arbitrator awarded Rs.1.51 crores taking loss at Rs.45,000 per km per month (claim Nos.1 and 8) – Case on behalf of the State-appellant was that in the statement of claim, the claimant claimed an amount of Rs.1.03 crores under claim Nos. 1 and 8 and, therefore award_ - E _was in excess of amount claimed – Held: No substance in this contention – The statement of claim submitted by contractor specifically stated thatamount of Rs.1.03 crores was worked out up to May, 2007 and details of expenditure beyond May,2007 will be submitted during the course of hearing – Therefore,amount awarded_ - F _by the arbitrator cannot be said to be in excess of the claim – So far as the submission on behalf of the appellant that the arbitrator exceeded the scope of reference while awarding an amount beyond 19.05.2007-the date on which the High Court appointed the sole arbitrator is concerned, same has no substance – Case of appellant that Arbitrator ought to have restricted the claim either up to_ - G _06.03.2006-the date on which the contractor invoked the arbitration clause or 23.04.2007, the date on which the High Court appointed the sole arbitrator or at least up to 19.05.2007-the date on which the arbitrator entered into reference cannot be accepted since the award made by the arbitrator was till the traffic was diverted which_ - H _was up to January, 2008 – Therefore, the arbitrator was justified in_ 294 295 STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. _awarding the amount beyond the said periods and till the additional traffic was diverted – Third submission on behalf of the appellant was that by awarding Rs.45,000 per km per month, the arbitrator has rewritten the contract with respect to the amount payable than what was specified in the contract – At the time when contract was entered into the mutually agreed, the rate fixed was Rs.1,000 per km per month and the estimated traffic was 3364 PCUS per day – Cause of action arose subsequently due to diversion of traffic from Palwal Aligarh Road and plying of more heavy vehicles due to which the contractor was required to incur additional expenditure for maintenance of the road – Therefore, the contractor was entitled to the loss on account of the additional expenditure incurred for maintenance of the road – By no stretch of imagination, it can be said that there was rewriting the terms of the contract as submitted on behalf ofthe appellant – However, arbitrator ought not to have awarded an amount of Rs.45,000 per km p.m. beyond the time period of additional traffic – Arbitrator has awarded the loss/amount at Rs.45,000 per km per month up to 31.05.2010 i.e. till the end of the contract which is wholly impermissible diversion of the additional traffic ceasedto exist w.e.f. January, 2008 – Therefore, the arbitrator ought not to have awarded any amount beyond the above time periodbeyond January, 2008 – To that extent the award passed by the arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed._ A B C D E ## **Partly allowing the appeals, the Court** **HELD: 1.1 When the statement of claim submitted by the contractor is seen, it is specifically stated by the claimant that the amount of Rs.1,03,50,263/- has been worked out up to May, 2007 and the details of expenditure beyond May, 2007 will be submitted during the course of hearing. It is specifically stated that expenditure incurred up to May, 2007 works out to Rs.1,03,50,263/-. Therefore, the amount awarded by the Arbitrator cannot be said to be in excess of the claim. [Para 9.1][302-B-C]** **1.2 The Arbitrator has awarded the loss/amount at Rs.45,000/- per km per month up to 31.05.2010 i.e. till the end of the contract which is wholly impermissible diversion of the additional traffic ceased to exist w.e.f. January, 2008. Therefore,** F G H 296 SUPREME COURT REPORTS [2021] 12 S.C.R. - A **the Arbitrator ought not to have awarded any amount beyond the above time period beyond January, 2008. To that extent the award passed by the Arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed. [Para 9.5][303-D-E]** - B _ONGC Ltd. v. Off-Shore Enterprises Inc.,_ **(2011) 14 SCC 147;** _Associate Builders v. Delhi Development Authority,_ **(2015) 3 SCC 49 : [2014] 13 SCR 895;** _J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr._ **(2008) 2 SCC 444 : [2008] 1 SCR 821;** _Indian Aluminium Cables Ltd. v. Haryana State Electricity_ - C _Board,_ **1996 (5) SCALE 708;** _MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr._ **(2011) 10 SCC 573 : [2011] 9 SCR 402;** _Satyanarayana Construction Company v. Union of India and Others_ **(2011) 15 SCC 101 – referred to.** |D||**Case Law Reference**|| |---|---|---|---| ||**(2011) 14 SCC 147**|**referred to**|**Para 5.3.1**| ||**[2014] 13 SCR 895**|**referred to**|**Para 5.3.2**| ||**[2008] 1 SCR 821**|**referred to**|**Para 5.3.2**| |E|**1996 (5) SCALE 708**|**referred to**|**Para 5.4.3**| ||**[2011] 9 SCR 402**|**referred to**|**Para 5.4.3**| ||**(2011) 15 SCC 101**|**referred to**|**Para 5.5**| - CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 7379- - F 7380 of 2021. From the Judgment and Order dated 03.11.2015 of the High Court of Punjab and Haryana at Chandigarh in FAO No.4482 of 2011 (O&M) and Order dated 18.03.2016 in RA-CR No.63 CII of 2016 in FAO No.4482 of 2011 (O&M). G Alok Sangwan, AAG, Shyam Divan, Sr. Adv., Sumit Kumar Sharma, Anurag Kulharia, Ms. Diksha Sharma, Adith Deshmukh, Dr. Monika Gusain, Advs. for the Appellant. Ranjit Kumar, Sr. Adv., Mohit Paul, Vikrant Singh Bloria, Bikram Dwivedi, Advs. for the Respondents. H 297 STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. The Judgment of the Court was delivered by A ## **M. R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 03.11.2015 passed by the High Court of Punjab and Haryana at Chandigarh in FAO No. 4482 of 2011 (O&M), by which the High Court has dismissed the appeal preferred by the appellant herein under Section 37 of the Arbitration and Conciliation Act, 1996, the State of Haryana has preferred the present appeals. 2. At the outset it is required to be noted that while issuing notice in the present appeals, this Court has stayed the award exceeding Rs.1,03,50,263/- insofar as claim Nos.1 and 8 are concerned. B C 3. The facts leading to the present appeals in a nutshell are as under:- 3.1 That the appellant herein awarded the contract to respondent No.1 herein – contractor for strengthening, up-gradation and maintenance of road from Palwal to Hasanpur, Haryana for a length of 31.17 kilometres on certain terms and conditions as per the contract entered into between the parties. The contract was for Rs.5,26,59,688/-. That as per the design calculation data, the specifications as prepared by the appellant department were meant for 3364 traffic intensity PCU (Passenger Car Unit)/day. The contract was up to 31.05.2010. That on 05.03.2005 due to the closing of the Palwal Aligarh Road on account of the construction of the railway bridge, the entire traffic was diverted from Palwal Aligarh Road to the present road. That due to this diversion of traffic from Palwal Aligarh Road, heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day, which damaged the road. That according to the contractor – respondent No.1 herein, he was required to do heavy repair by incurring additional expenditure. Disputes arose between the parties. A legal notice was served upon the appellant making the claims. Disputes were not resolved and therefore respondent No.1 – contractor invoked the arbitration clause as per clauses 24 & 25 and approached the High Court for appointment of an arbitrator in exercise of power conferred under Section 11 (6) of the Arbitration and Conciliation Act, 1996. D E F G 3.2 Vide order dated 23.04.2007, the High Court appointed Shri R.S. Jindal, retired Chief Engineer, Delhi Development Authority as the sole Arbitrator to adjudicate upon all the disputes between the parties. H 298 SUPREME COURT REPORTS [2021] 12 S.C.R. - A That the contractor submitted various claims including claim Nos. 1 and 8. For the purpose of deciding the present appeals, claim Nos.1 and 8 are relevant. The sole Arbitrator awarded a total sum of Rs.1,51,95,400/ - with respect to claim Nos.1 and 8. 4. Feeling aggrieved and dissatisfied with the award declared by B the learned Arbitrator, the appellant preferred an application before the Court under Section 34 of the Arbitration and Conciliation Act, 1996, which came to be dismissed against which the appellant – State preferred an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 before the High Court. By the impugned judgment and order the High Court has dismissed the said appeal. Hence, the State of Haryana has C preferred the present appeals. 5. Shri Shyam Divan, learned Senior Advocate has appeared on behalf of the State – appellant and Shri Ranjit Kumar, learned Senior Advocate has appeared on behalf of the respondent No.1 – contractor. 5.1 Shri Shyam Divan, learned Senior Advocate appearing on behalf D of the appellant submitted that the appellant has already paid to respondent No.1 – contractor an amount of Rs.1,03,50,263/- pursuant to the interim order dated 26.08.2016 passed by this Court. 5.2 Shri Shyam Divan, learned Senior Advocate appearing on behalf of the appellant has submitted that the arbitral award is liable to be set E aside on the following grounds:- - (i) The award is in excess of claim; - (ii) The Arbitrator exceeded the scope of reference; F - (iii) The Arbitrator has rewritten the contract with respect to the amount payable which was specified in the contract. 5.3 Now, so far as ground No.1 that the award is in excess of claim, it is vehemently submitted by Shri Shyam Divan, learned Senior Advocate appearing on behalf of the appellant that the contractor in its statement of claim had claimed an amount of Rs. 1,03,50,263/- only under the claim Nos.1 and 8. It is submitted that despite the above the G Arbitrator has awarded a total sum of Rs.1,51,95,400/-, which is in far excess of amount claimed. It is submitted that the statement of claim was never modified by the contractor and therefore, the Arbitrator ought not to have awarded the sum/amount in excess of the amount claimed. - 5.3.1 It is submitted that the differential amount of Rs.48,45,137/ - H - is in excess of claim and to that extent the arbitral award is invalid and 299 STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. [M. R. SHAH, J.] liable to be set aside. Reliance is placed on the decision of this Court in A the case of **ONGC Ltd. v. Off-Shore Enterprises Inc.,** (2011) 14 SCC 147 (para 16). 5.3.2 It is submitted that as held by this Court in the cases of **Associate Builders v. Delhi Development Authority** , (2015) 3 SCC 49 (para 36) and **J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr.,** (2008) 2 SCC 444 (para 31-32), making an award in excess of claim is clear cut an act exceeding the jurisdiction and amounts to a misconduct of the Arbitrator. 5.4 Now, so far as ground No.2 namely, that the Arbitrator exceeded the scope of reference, it is contended that the Arbitrator cannot exceed the scope of reference. 5.4.1 It is submitted that the contractor invoked the arbitration clause on 06.03.2006. The High Court appointed the sole Arbitrator on 23.04.2007 and the Arbitrator entered upon reference on 19.05.2007. It is urged that by allowing the claims for a period beyond 19.05.2007, the Arbitrator exceeded the scope of reference. 5.4.2 It is submitted that an amount of Rs.57,96,000/- (approx.) has been awarded for claims arising between 19.05.2007 to 31.07.2008 (calculated as amount for maintenance of road @ Rs. 45,000/- per kilometre (km) per month). It is submitted that it was not permissible for the Arbitrator to exceed the scope of the reference beyond the date upon entering reference and as a consequence the award is liable to be set aside. 5.4.3 Learned senior counsel appearing on behalf of the appellant has relied upon the decisions of this Court in the cases of **Indian Aluminium Cables Ltd. v. Haryana State Electricity Board,** 1996 (5) SCALE 708 (para 2) and **MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr.** (2011) 10 SCC 573 (para 15), in support of his above submissions that as the Arbitrator exceeded the scope of reference and hence the award is liable to be set aside. 5.5 In so far as the ground No.3 is concerned namely, the Arbitrator has rewritten the contract with respect to the amount payable which was specified in the contract, it is submitted that the Arbitrator has rewritten the terms of the contract by directing the appellant to pay the compensation to respondent No.1 – contractor at the rate of Rs.45,000/ - per km per month instead of mutually agreed contractual rate of B C D E F G H 300 SUPREME COURT REPORTS [2021] 12 S.C.R. - A Rs.1,000/- per km per month. It is contended that it was not open to the Arbitrator to rewrite the terms of the contract and award the contractor a higher rate for the work than the rate which was already fixed in the contract. It is submitted that such an exercise is beyond the competence and authority of the Arbitrator. Reliance is placed on the decision of this Court in the case of **Satyanarayana Construction Company v. Union** - B **of India and Others** (2011) 15 SCC 101 (para 11). 5.6 It is further contended by Shri Divan, learned Senior Advocate appearing on behalf of the appellant that even otherwise, the amount awarded by the Arbitrator at Rs.45,000/- per km per month beyond the time period of additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. C till the end of contract is wholly impermissible. It is submitted that diversion of traffic on 9.2 km stretch of the road which gave rise to the cause of action ceased to exist w.e.f. January 2008. It is submitted that however, the Arbitrator has directed the appellant to make payment at Rs. 45,000/- per km per month even beyond the time period of additional D traffic. It is contended that the aforesaid is wholly impermissible. 6. Making the above submissions, it is prayed to allow the present appeals. 7. Shri Ranjit Kumar, learned Senior Advocate appearing on behalf of respondent No.1 – contractor, has vehemently contended that the E award passed by the Arbitrator cannot be said to be (i) in excess of claim; (ii) exceeding the scope of reference and (iii) rewriting the contract with respect to the amount payable which was specified in the contract, as submitted on behalf of the appellant. It is submitted that in the statement of claim the contractor specifically stated that the amount has been worked F out up to the month of May, 2007 and the details of expenditure beyond May, 2007 will be submitted during the course of hearing. It is therefore submitted that it cannot be said that claim Nos.1 and 8 were restricted to Rs. 1,03,50,263/- only. It is urged that on appreciation of the evidence on record the Arbitrator has awarded Rs. 1,51,95,400/- for claim Nos.1 and 8, which in any case cannot be said to be beyond the amount claimed G in the statement of claim. 7.1 It is next contended that it also cannot be said that the award passed by the Arbitrator was beyond the scope of reference. It is submitted that as such cause of action to claim the additional amount arose due to over-expenditure owing to maintenance of road due to H diversion of traffic from Palwal Aligarh Road to the present road which 301 STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. [M. R. SHAH, J.] continued even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007. A It is submitted that the amount awarded by the Arbitrator under claim Nos.1 and 8 cannot be said to be exceeding the scope of reference. 7.2 It is further submitted that even the award passed by the Arbitrator to make payment at Rs.45,000/- per km per month cannot be said to be rewriting of the contract with respect to the amount payable which was specified in the contract. It is urged that at the time when the contract was written/entered into between the parties the contract rate of Rs.1,000/- per km per month was agreed against the design of 3364 PCUS per day. However, after the contract was entered into and the contractor acted as per the contract there was diversion of traffic from Palwal Aligarh Road to the present road and the heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day and therefore the contractor was required to incur additional expenditure at Rs.45,000/- per km per month. It is submitted that the amount awarded by the Arbitrator at Rs.45,000/- per km per month cannot be said to be rewriting the contract with respect to the amount payable than what was specified in the contract i.e. Rs.1,000/per km per month. 7.3 However, Shri Ranjit Kumar, learned Senior Advocate appearing on behalf of the contractor is not in a position to justify the award by which the Arbitrator has awarded the payment at Rs.45,000/ - per km per month even beyond the time period of additional traffic i.e. up to 31.05.2010 i.e. till the end of the contract. B C D E 8. We have heard the learned senior counsel appearing on behalf of the respective parties at length and given our thoughtful consideration. 9. That the contractor was awarded the contract for maintenance, etc. The contract amount was for Rs.5,26,59,688/-. The rate of maintenance of the road as accepted was Rs.12,000/- per km per annum or Rs.1,000/- per km per month. The maintenance contract was valid up to 31.07.2010. When the contract was entered into, the contract was meant for only 3364 PCUS per day. However, due to diversion of traffic from Palwal Aligarh Road to the present road, the contractor was required to incur additional expenditure on the maintenance due to increase in the traffic and plying the additional commercial vehicles. Therefore the contractor claimed the amount towards additional expenditure for maintenance which was due to increase in the traffic and plying more commercial vehicles. On appreciation of evidence the Arbitrator has F G H 302 SUPREME COURT REPORTS [2021] 12 S.C.R. - A determined the loss at Rs.45,000/- per km per month (claim Nos.1 and 8). 9.1 The case on behalf of the appellant that as in the statement of claim, the claimant claimed an amount of Rs.1,03,50,263/- under the claim Nos. 1 and 8 and the Arbitrator has awarded Rs.1,51,95,400/-, the B same is in far excess of amount claimed and therefore the award is in excess of amount claimed has no substance. When the statement of claim submitted by the contractor is seen, it is specifically stated by the claimant that the amount of Rs.1,03,50,263/- has been worked out up to May, 2007 and the details of expenditure beyond May, 2007 will be submitted during the course of hearing. It is specifically stated that C expenditure incurred up to May, 2007 works out to Rs.1,03,50,263/-. Therefore, the amount awarded by the Arbitrator cannot be said to be in excess of the claim. - 9.2 Now so far as the submission on behalf of the appellant that - the Arbitrator exceeded the scope of reference while awarding an amount - D beyond 19.05.2007 – the date on which the High Court appointed the sole Arbitrator is concerned, the same has no substance. The case on behalf of the appellant that the Arbitrator ought to have restricted the claim either up to 06.03.2006 – the date on which the contractor invoked the arbitration clause or 23.04.2007, the date on which the High Court - E appointed the sole Arbitrator or at least up to 19.05.2007 – the date on which the Arbitrator entered into reference, is concerned, it is required to be noted that the claim made by the Arbitrator was till the traffic was diverted which was up to January, 2008. Therefore, the Arbitrator was justified in awarding the amount beyond the aforesaid periods and till the additional traffic was diverted due to the closure of Palwal Aligarh Road. - F 9.3 Now the submission on behalf of the appellant is that by awarding Rs.45,000/- per km per month the Arbitrator has rewritten the contract with respect to the amount payable than what was specified in the contract. It is urged that under the contract mutually agreed contractual rate was Rs.1,000/- per km per month and therefore any amount higher G than Rs.1,000/- per km per month is beyond the terms and conditions of the contract, is also without substance. It is noted that at the time when the contract was entered into the mutually agreed, the rate fixed was Rs.1,000/- per km per month and the estimated traffic was 3364 PCUS per day. The cause of action arose subsequently due to diversion of traffic from Palwal Aligarh Road and plying of more heavy vehicles due - H 303 STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR. [M. R. SHAH, J.] to which the contractor was required to incur additional expenditure for A maintenance of the road. Therefore, the contractor was entitled to the loss on account of the additional expenditure incurred for maintenance of the road due to increase in the traffic because of the closure of the Palwal Aligarh Road and diversion of the traffic to the present road. Therefore, by no stretch of imagination it can be said that there was B rewriting the terms of the contract as submitted on behalf of the appellant. 9.4 In view of the above findings, none of the decisions of this Court relied upon by the learned senior counsel appearing on behalf of the appellant are applicable to the facts of the case on hand as the same are not of any assistance to the appellant. 9.5 However, at the same time Shri Divan, learned Senior Advocate, appearing on behalf of the appellant is justified in submitting that the Arbitrator ought not to have awarded an amount of Rs.45,000/per km per month beyond the time period of additional traffic. The Arbitrator has awarded the loss/amount at Rs.45,000/- per km per month up to 31.05.2010 i.e. till the end of the contract which is wholly impermissible diversion of the additional traffic ceased to exist w.e.f. January, 2008. Therefore, the Arbitrator ought not to have awarded any amount beyond the above time period beyond January, 2008. To that extent the award passed by the Arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed. 10. In view of the above and for the reasons stated above, the present appeals are allowed in part. The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/- per km per month up to January, 2008 under claim Nos.1 and 8 is hereby confirmed. The award passed by the Arbitrator awarding the amount/compensation at Rs.45,000/- per km per month from February, 2008 to 31.05.2010 i.e. till the end of the contract is hereby quashed and set aside. The amount due and payable has to be worked out accordingly. The present appeals are partly allowed to the aforesaid extent. In the facts and circumstances of the case there shall be no order as to costs. C D E F G H Devika Gujral Appeals partly allowed.
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.