STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.
Case Synopsis & Summary
This Supreme Court judgment concerns a public road maintenance contract awarded by the State of Haryana to Shiv Shankar Construction Co. for strengthening, upgrading and maintaining a 31.17-km stretch from Palwal to Hasanpur. The contract, valued at Rs 5.26 crore, anticipated traffic of 3364 PCU/day and was to endure until July 2010. After the Palwal–Aligarh Road was closed for railway works, traffic was diverted to the present road, causing a dramatic increase in traffic to 24,418 PCU/day and thereby escalating maintenance costs. The contractor claimed compensation for the added expenditure through claims 1 and 8; the sole arbitrator awarded Rs 1,51,95,400. The State challenged this award under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, arguing the award exceeded the claim amount, exceeded the scope of reference, and effectively rewrote contract terms by fixing Rs 45,000 per km per month instead of Rs 1,000 per km per month. The High Court dismissed the appeal. The Supreme Court stayed payment beyond Rs 1,03,50,263 and eventually partly allowed the appeals: it held that the amount up to May 2007, as stated in the claimant’s materials, was not in excess of the claim; however, it found the Rs 45,000/km/month rate impermissible beyond January 2008. Consequently, the Court confirmed the Rs 45,000/km/month rate up to January 2008 and quashed it from February 2008 to 31.05.2010, directing the remainder to be worked out. Appeals partly allowed; no costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- M. R. SHAH
- B. V. NAGARATHNA
- Judgment Date
- 2021-12-14
- Court Decision / Holding
- Appeals partly allowed. The arbitrator’s award of Rs.45,000 per km per month up to January 2008 is confirmed; the portion from February 2008 to 31.05.2010 is quashed; the amount due and payable to be worked out accordingly. No order as to costs.
- Final Disposition
- Appeals partly allowed
Parties to the Case
Appellants / Petitioners
- STATE OF HARYANA
Respondents
- M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.
Legal Representation & Advocates
Counsels for Petitioners
- • Alok Sangwan, AAG
- • Shyam Divan, Sr. Adv.
- • Sumit Kumar Sharma
- • Anurag Kulharia
- • Ms. Diksha Sharma
- • Adith Deshmukh
- • Dr. Monika Gusain
Counsels for Respondents
- • Ranjit Kumar, Sr. Adv.
- • Mohit Paul
- • Vikrant Singh Bloria
- • Bikram Dwivedi
Provisions of Law Cited
Legal Doctrines & Maxims
- Award in excess of claim constitutes misconduct of the Arbitrator
- Arbitrator cannot exceed the scope of reference
- Arbitrator cannot rewrite the terms of the contract
Submissions & Arguments
Contentions of Appellants / Petitioners
The State contends that the arbitral award is largely outside the claims (excess of claim), exceeds the scope of reference and rewrites the contract by specifying Rs.45,000 per km per month instead of Rs.1,000 per km per month. It relies on decisions such as ONGC Ltd. v. Off-Shore Enterprises Inc., Associate Builders v. Delhi Development Authority, J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr., Indian Aluminium Cables Ltd. v. Haryana State Electricity Board and MSK Projects India (JV) Ltd. to argue misconduct by the arbitrator. The time-bound nature of the post-diversion damages and the date of entering reference (mid-2007) raise issues about permissible scope.
Contentions of Respondents
The contractor asserts that the claim Nos. 1 and 8 involve Rs. 1,03,50,263 up to May 2007 with subsequent expenditure to be proved; the award is not beyond the claim. The increased traffic caused additional expenditure, which the arbitrator could award within the broad reference. The Rs. 45,000/km/month rate is justified given traffic diversion and the contract's overall framework. The challenge is to be resolved by confirming reasonable portions of the award.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (6)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| ONGC Ltd. v. Off-Shore Enterprises Inc. | (2011) 14 SCC 147 | Mentioned Only | Cited by appellant; court found it not applicable to the facts. |
| Associate Builders v. Delhi Development Authority | (2015) 3 SCC 49 | Mentioned Only | Cited by appellant; not controlling on the facts. |
| J.C. Budhraja v. Chairman, Orissa Mining Corpn. Ltd. & Anr. | (2008) 2 SCC 444 | Mentioned Only | Cited by appellant; not applied to the facts. |
| Indian Aluminium Cables Ltd. v. Haryana State Electricity Board | 1996 (5) SCALE 708 | Mentioned Only | Cited; not applicable to the facts. |
| MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr. | (2011) 10 SCC 573 | Mentioned Only | Cited; relied on in argument but not controlling. |
| Satyanarayana Construction Company v. Union of India and Others | (2011) 15 SCC 101 | Mentioned Only | Cited in argument on contract rewriting; not applicable to the facts. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
STATE OF HARYANA v. M/S. SHIV SHANKAR CONSTRUCTION CO. & ANR.
Related Decisions & Precedents from Supreme Court of India (2021)
HARI OM @ HERO v. STATE OF U.P.
This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.
INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL
This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.
Hasmat Ali v. Amina Bibi & ORS.
This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.
Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.
This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.