STATE OF HARYANA AND ORS. v. MAHABIR PRASAD SHARMA AND ORS concerns the recruitment process for 11 Chief Inspectors under the Subordinate Selection Committee. The State requisitioned posts for direct recruitment and categorised vacancies as general, SC, BC and Ex-serviceman, while keeping four additional candidates in a waiting list. The High Court held that the waiting list did not create any right to appointment, but if administrative exigencies required, the posts could be filled on an ad hoc basis, with waiting-list candidates considered in order of merit. The State appealed, contending that the waiting-list had elapsed by efflux of time (one year) and that the waiting-list candidates had no claim to appointment, and that ad hoc appointments must follow the rules and not confer future rights. The Court, after hearing both sides, concluded that if the appellants do not fill vacancies, the question of waiting-list claims does not arise. If, however, they choose to make ad hoc appointments, the waiting-list candidates, though their names had lapsed, must be considered de hors the Rules as an enabling direction to temporary appointments pending regular recruitment. It was further held that respondents, being general-category candidates, would be considered only against the general quota. The appeals were disposed of with no costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- K. Ramaswamy
- B. L. Hansaria
- Judgment Date
- 1994-02-07
- Court Decision / Holding
- The appeals are disposed of. No costs.
- Final Disposition
- Appeals disposed of; No costs.
Parties to the Case
Appellants / Petitioners
- State of Haryana and Others
Respondents
- Mahabir Prasad Sharma and others
Legal Representation & Advocates
Counsels for Petitioners
- • Ms. Indu Malhotra
Counsels for Respondents
- • Madhava Reddy
- • Prem Malhotra
Legal Doctrines & Maxims
- de hors the Rules
Submissions & Arguments
Contentions of Appellants / Petitioners
The State contends that the waiting list had elapsed after one year and no right to appointment accrues from a mere waiting list; admission of ad hoc appointments on the basis of a waiting list would create a potential right to future posts and is not justified unless unavoidable for administrative exigencies. It argues that ad hoc appointments, if made, must still respect the rules and not confer indefeasible future rights beyond temporary arrangements pending regular recruitment. The High Court’s direction to consider waiting-list candidates “de hors” the Rules is not a proper basis for creating rights.
Contentions of Respondents
The waiting-list candidates contend that, if vacancies arise, they should be eligible for appointment and, where ad hoc filling occurs, candidates in the waiting list should be considered in order of merit. They argue that the waiting list, though expired after a year, functions as a reservoir of qualified candidates for administrative exigencies and should be available for ad hoc appointments.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
State of Haryana v. Mahabir Prasad Sharma and Others
Related Decisions & Precedents from Supreme Court of India (1994)
BILLA JAGAN MOHAN REDDY AND ANR. v. BILLA SANJEEVA REDDY AND ORS.
This is a Supreme Court decision arising from a Land Acquisition Act reference under Section 30, where the appellants (the first party) sought to claim a 1/4 share of compensation based on pre-existing title evidenced by entries in the record of rights and other revenue records. To prove title, the appellants filed copies of family holdings, khasra Pahani, and certified copies from revenue authorities spanning 1954-70 and other documents, and moved for condonation of delay under Order XIII, Rule 1 CPC for production of these public documents. The trial court refused the application, and the High Court affirmed. The Court held that documentary evidence to be produced at or before settlement of issues must be produced in possession and, if not in possession, filed with an application to condone the delay, and the Court shall receive such documents if accompanied by an accurate list. Although there was a delay, the Court emphasized that, if the documents are relevant to decide the real issue and the interest of justice requires it, the appellate court can receive them under Order XLI, Rule 27 CPC. Consequently, the delay was condoned, and the trial court was directed to receive the documents, allow proof and rebuttal, and dispose of the reference according to law. The appeal was allowed.
M/S Pankaj Jain Agencies v. Union of India
The petitioner, M/s Pankaj Jain Agencies, challenges Notification No. 142/86-Cus., dated 13 February 1986, issued under Section 25(1) of the Customs Act, 1962, which amended the earlier exemption Notification No. 70/85-Cus. The impugned notification pertains to rates of customs duty on imports of parts and sub-assemblies of ball and roller bearings, specifically “cups” supplied from Singapore for component parts of bearings. Two consignments arrived at Bombay Port in January–February 1986; the petitioner filed two Bills of Entry for home consumption. The central issue is whether the notification reduces the exemption and thereby imposes a higher duty, or creates a fresh duty on spare parts not contemplated by the Customs Tariff Act of 1975. The petitioner argued that import was complete before the notification came into force; that the notification was ultra vires Section 25(1) and violated Section 25(3) by exceeding the statutory duty; and that the increased duty violated Article 19(1)(g) by imposing an unreasonable restriction on trade. The Respondents contended that the notification merely curtailed an exemption, the rates did not exceed the statutory duty, and publication in the Official Gazette gave operativeness. The Supreme Court held that subordinate legislation must be published to take effect, and publication sufficed for operativeness; it rejected the ultra vires and fundamental-right challenges, and dismissed the petitions with costs, underscoring the principle that delegated legislation must be published to be effective.
COMMISSIONER OF INCOME TAX, HYDERABAD v. M/s. P.J. CHEMICALS LTD. ETC.
This judgment addresses whether subsidies granted to industries on a percentage of capital cost should be deducted from the "actual cost" for computing depreciation under Section 43(1) of the Income Tax Act, 1961. Judicial opinions across Indian High Courts diverged: several held such subsidies non-deductible as they are incentives rather than payments toward asset cost, while others (including some Punjab and Haryana, Allahabad, Bombay, Calcutta, and Gauhati courts) treated the subsidy as deductible from actual cost. The matter was heard in two batches: revenue appeals challenging the Andhra Pradesh High Court’s view, and assessee appeals in the opposite camp. The Supreme Court discusses the meaning of "actual cost", urging liberal interpretation, and reinforces the majority view that government subsidies of this nature are incentives to attract investment, not amounts paid toward meeting the asset’s actual cost. It traces the legislative history, including amendments to the 1922 Act and the 1953 amendment, to explain the intended construction of the term. The Court overrules the contrary Punjab and Haryana decision in Jindal Brothers Rice Mills and sustains the rest of the High Court dissents in favor of the assessee. Consequently, Revenue appeals are dismissed and assessee appeals are allowed, with no costs."
STATE OF KERALA v. MCDOWELL CO. LTD.
The Kerala Abkari Act governs the manufacture, sale and export of Indian made Foreign Liquor (IMFL) within Kerala. Distillers could export liquor outside Kerala with permission, but were required to execute a bond to secure payment of excise duty on export. The Board of Revenue issued a circular in 1982 treating such documents as agreements rather than bonds; the Board later held the instrument was a bond, while the Kerala High Court held it to be an agreement not liable to stamp duty, prompting Kerala to appeal. The central issue was whether Form VI, executed under the Distillery and Warehouse Rules, constitutes a Bond under the Kerala Stamp Act or merely an Agreement, affecting stamp duty liability under Entry 32 (Indemnity Bond) or Entry 13 (Bond) of the Schedule. The Supreme Court majority held that the instrument in Form VI is a bond within the meaning of the Kerala Stamp Act and liable to stamp duty under Entry 32, as it creates an obligation to pay money to the State on breach of conditions, a liability arising from the instrument itself, not merely from the Abkari Act. The dissent (Sahai, J.) argued the instrument arises from the Abkari Act, making it an Agreement rather than a Bond under the Stamp Act, and that duty would not arise from the instrument itself. The appeal was allowed and the writ petition disposed accordingly, with a refund of excess duty where needed.