Supreme Court of IndiaSupreme Court · 2011Division BenchAppeal allowed; writ petition dismissed.

STATE OF HARYANA & ORS. v. MALIK TRADERS

Case / Petition Number:
Civil Appeal No. 7033 of 2011
Neutral Citation:[2011] 10 S.C.R. 372

Case Synopsis & Summary

This is a Civil Appeal arising from a tender for collection of toll on the Yamuna Bridge on the Karnal–Meerut Road. The Haryana government invited bids and required a bid security of Rs. 20 lakhs, with the bid terms stipulating that the bid would remain open for acceptance for 90 days after the last date of bid receipt, and that acceptance communicated within that period would bind the bidder. The highest bidder initially failed to deposit security and instalment, resulting in forfeiture of the bid security and cancellation of its acceptance. Subsequently, Malik Traders (the second highest bidder) was issued a letter of acceptance on 26.11.2008, but also failed to deposit the security and instalment; the letter of acceptance was cancelled on 17.12.2008 and the bid security forfeited. Before the acceptance, Malik Traders had even written to state non-interest in the work and sought refund of the bid security. The matter went to the Punjab and Haryana High Court, which quashed the 26.11.2008 acceptance and directed refund of Rs. 20 lakhs. The Supreme Court, however, held that although a withdrawal before acceptance is permitted under Section 5 of the Indian Contract Act, the bid contained an express 90-day validity and an obligation to be bound by acceptance dispatched within that period; the acceptance had occurred within the 90 days, so the respondent was bound, and the forfeiture clause applied. The High Court’s order was set aside and the writ petition dismissed, with reliance on a parallel National Highways Authority of India decision to uphold forfeiture to ensure genuine bids.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • V. S. Sirpurkar
  • Cyriac Joseph
Judgment Date
2011-08-17
Court Decision / Holding
Appeal allowed. The High Court’s order dated 7.7.2009 in C.W.P. No. 2266 of 2009 is set aside and the writ petition is dismissed.
Final Disposition
Appeal allowed; writ petition dismissed.

Parties to the Case

Appellants / Petitioners

  • State of Haryana & Ors.

Respondents

  • M/S Malik Traders

Legal Representation & Advocates

Counsels for Petitioners

  • • P.N. Mishra
  • • Manjit Singh
  • • Vivekta Singh
  • • Harkesh
  • • Kamal B Mohan Gupta

Counsels for Respondents

  • • A.K. Sanghi
  • • D.K. Garg
  • • Dipak Kumar Jena
  • • Minakshi Ghosh Jena
  • • Abhishek Garg
  • • Dhananjay Garg

Provisions of Law Cited

Section 5 of the Indian Contract Act, 1872

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that the bid included an express term to keep the bid open for 90 days after the last date of receipt and to be bound by any acceptance communicated within that period. Although Malik Traders withdrew its offer on 15 November 2008, acceptance was issued within the 90-day window, thereby creating a contract upon acceptance. Paragraph 10 of the bid/offer expressly provides for forfeiture of the full Bid Security if withdrawal occurs during bid validity. The purpose of the Bid Security is to prevent withdrawal and ensure genuine bids; accordingly, applying the forfeiture clause upholds the contract and deters unserious bidders. The High Court’s quashing of acceptance undermines this protective mechanism. The decision in National Highways Authority of India v. Ganga Enterprises supports forfeiture of earnest money in government tenders to ensure only genuine bids are considered. The appeal should be allowed, the High Court order set aside, and the writ petition dismissed.

Contentions of Respondents

The respondents submit that under Section 5 of the Indian Contract Act, a proposal may be revoked before its acceptance. They withdrew the offer prior to the completion of acceptance, and the 90-day period cannot convert a non-existent contract into a binding one. They contend there was no completed contract when the acceptance date arrived and urge refund of the bid security. The High Court correctly held that withdrawal before completion of acceptance means there is no binding contract or liability to forfeit, and the writ petition should be allowed with refund of the bid security.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
National Highways Authority of India v. Ganga Enterprises & Anr.(2003) 7 SCC 410PositiveThe Court relied on this decision to uphold the principle that bid earnest money/forfeiture clauses serve to ensure genuine bids and can be enforced despite withdrawal during bid validity.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,114 words•~19 min read

In The Court Record

STATE OF HARYANA & ORS. v. MALIK TRADERS

(2011] 10 S.C.R 372 A ## STATE OF HARYANA & ORS. _v._ M/S MALIK TRADERS (Civil Appeal No. 7033 of 2011) B AUGUST 17, 2011 **[V.S. SIRPURKAR AND CYRIAC JOSEPH, JJ.]** _Contract:_ c _Tender_ - _Inviting of bids for collection of toll_ - _Terms of bid requiring to keep the offer/bid open for acceptance upto_ - _90 days after the last date of receipt of bid Letter of_ - _acceptance issued to bidder within the bid validity period Bidder failed to deposit security amount and the first_ - _instalment within the stipulated period Letter of acceptance_ 0 _issued to bidder cancelled and bid security forfeited_ - _HELD: A person may have_ a _right to withdraw his offer, but if he has made his offer on_ a _condition that the Bid Security amount can be forfeited in case he withdraws the offer during the_ E _period of bid validity, he has no right to claim that the Bid Security should not be forfeited and it should be returned to him_ - _In the instant case, the bidder had agreed to keep the bid open for 90 days after the last date of receipt of the bid and that he would be bound by the communication of_ - _acceptance of the bid within the said period of 90 days_ F _Therefore, the bidder could not have withdrawn the bid within_ - _the said 90 days Besides, since the bidder withdrew his offer during the period of bid validity in violation of the agreement,_ - _the full value of Bid Security was liable to be forfeited The purpose of bid security is to ensure that the offer is not_ G _withdrawn during the bid validity period of 90 days and a_ - _contract comes into existence Such conditions are included_ - _to ensure that only genuine parties make the bids The very purpose of such a condition in the offer/bid will be defeated, if forfeiture is not permitted when the offer is withdrawn in_ **H** 372 STATE OF HARYANA & ORS. _v._ MALIK TRADERS 373 _violation of the agreement_ - _High Court_ was _not justified in_ A _quashing the letters accepting the bid of the respondent and the letter cancelling the acceptance of the bid and forfeiting_ - - _the Bid Security Order of High Court set aside Contract Act, 1872_ - s. 5. B The respondent was the second highest bidder for the bid of collection of toll. In terms of the written offer/ bid, the respondent agreed to ke,ep the bid open for acceptance upto 90 days after the last date of receipt of bid. As the highest bidder failed to deposit the security C amount and the first instalment within the stipulated period, the letter of acceptance issued to that bidder was cancelled and a letter of acceptance dated 26.11.2008 was issued to the respondent within the stipulated period of 90 days. Since the respondent also failed to deposit the security amount and the first instalment within the D stipulated period, the letter of acceptance issued to the respondent was cancelled by Memo dated 17.12.2008, and the Bid Security of Rs. 20 lakhs was forfeited. Bids were re-invited for collection of toll and this time the respondent being the highest bidder, its bid was accepted E and it deposited the security amount a.nd the first instalment in terms of the letter of acceptance. Thereafter the respondent filed a writ petition before the High Court for refund of the forfeited amount of the Bid Security of Rs. 20 lakhs in respect of the earlier bid contending that F before the receipt of the letter of acceptance, it, by letter dated 15.11.2008, had informed the authority concerned that it was not interested in the work and the amount of Bid Security be refunded to it. The writ petition was allowed by the High Court holding that since the offer was withdrawn before it was accepted, there could be no acceptance of the offer and, as such, there could not be any consequence of the writ petitioner not honouring the commitment. Aggrieved, the State Government filed the appeal. · · F G . , · ..: H ·\ 374 SUPREME COURT REPORTS [2011] 10 S.C.R. ## A Allowing the appeal, the Court HELD: 1. It is true that as per s. 5 of the Contract Act, 1872, a proposal may be revoked at any time before the communication of its acceptance is complete as against 8[the proposer. It is also true that before receipt ][of ][the letter ] of acceptance dated 26.11.2008, the respondent had sent a letter dated 15.11.2008 withdrawing its offer. H·owever, admittedly, in paragraph 8 of the written offer/bid, the respondent had agreed to keep the bid open for C acceptance upto 90 days after the last date of receipt of bid. The respondent had also agreed that it shall be bound by the communication of acceptance of the bid dispatched within the said period of 90 days. Therefore, respondent could not have withdrawn the bid before the expiry of the period of 90 days. It is not disputed that the D acceptance of the respondent's bid was communicated to the respondent within the said period of 90 days. Therefore, the respondent was bound by the said acceptance of the bid, despite its withdrawal by the respondent in the meanwhile. (para 10) [379-D-H] E 1.2 In paragraph 10 of the offer/bid, the respondent had also agreed that the full value of the Bid Security would be forfeited without prejudice to any other right or remedy available to the Executive Engineer or his F successor in office or his representative, should the respondent withdraw or modify its offer/bid during the period of bid validity (90 days) or extended validity period. Since the respondent withdrew its offer during the period of bid validity in violation of the agreement in paragraph G 8 of the offer/bid, the full value of Bid Security was liable to be forfeited in terms of the agreement contained in paragraph 10 of the offer/bid. Under the cover of the provisions contained in s. 5 of the Act, the respondent cannot escape from the obligations and liabilities under the agreements contained in its offer/bid. The right to H STATE OF HARYANA & ORS. _v._ MA~IK TRADERS 375 withdraw an offer before its acceptance cannot nullify the agreement to suffer any penalty for the withdrawal of the offer against the terms of agreement. [para 10) [379-G-H; 380-A-F] A 1.3 A person may have a right to withdraw his offer, 8 but if he has made his offer on a condition that the Bid Security amount can be forfeited in case he withdraws the offer during the period of bid validity, he has, no right to claim that the Bid Security should not be forfeited and it should be returned to him. Forfeiture of such Bid Security amount does not, in any way, affect any statutory C right u/s 5 of the Act. The Bid Security was given by the respondent and taken by the appellants to ensure that the offer is not withdrawn during the bid validity period of 90 days and a contract comes into existence. Such conditions are included to ensure that only genuine D parties make the bids. The very purpose of such a condition in the offer/bid will be defeated, if forfeiture is not permitted when the offer is withdrawn in violation of the agreement. [para 1 OJ [380-E~H; 381-A] D E _National. Highways Authority of India_ v. _Ganga Enterprises_ & _Anr._ 2003 (3) Suppl. SCR 114 = (2003) 7 SCC - 410 relied on. 2. The High Court was not justified in quashing the letter dated 26.11.2008 accepting the bid of the respondent and the letter dated 17 .12.2008 forfeiting the Bid Secur~ty amount of Rs. 20 lakhs. The order of the High Court is set aside. Consequently, the writ petition stands dismissed. [para 12) [383-C] F G ## Case Law Reference: 2003 (3) Suppl. SCR 114 relied on para 11 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7033 of 2011. . . H [2011] 10 S.C.R. 376 SUPREME COURT REPORTS A From the Judgment & Order dated 07.07.2009 of the High Court of Punjab & Haryana at Chandigarh in Civil Writ Petition No. 2266 of 2009. P.N. Mishra, Manjit Singh, Vivekta Singh, Harkesh, Kamal B Mohan Gupta for tt:ie Appellants. A.K. Sanghi, D.K. Garg, Dipak Kumar Jena, Minakshi Ghosh Jena, Abhishek Garg, Dhananjay Garg for the Respondent. c The Judgment of the Court was delivered by **CYRIAC JOSEPH, J.** 1. Leave granted. 2. This appeal is filed against the judgment dated 7.7.2009 rendered by a Division Bench of the High Court of Punjab & D Haryana in C.W.P. No. 2266 of 2009, allowing the said writ petition. The appellants were the respondents in the writ petition and the sole respondent herein was the petitioner therein. 3. Facts in brief are stated hereunder: E On 18.9.2008, the appellant State of Haryana invited tenders from interested persons for appointment as Entrepreneur/Agent for collection of toll at Toll Bridge over river Yamuna on Karnal-Meerut Road, near U.P. Border. The respondent M/s. Malik Traders was one of the 13 bidders who F submitted tenders. As required by the terms and conditions of the Bid, all the bidders, including the respondent, deposited the Bid Security of Rs. 20 lakhs in the form of bank guarantee or FDR in favour of the Executive Engineer. M/s. Gaurav Traders who quoted Rs. 8,83,30,000/- was the highest bidder and the G respondent Mis. Malik Traders who quoted Rs. 7,97,66,180/was the second highest bidder. 4. As required under the terms and conditions of the bid, the respondent in paragraph 8 of its written offer/bid agreed to H keep the bid open for acceptance upto 90 days after the last STATE OF HARYANA & ORS. _v._ MALIK TRADERS 377 [CYRIAC JOSEPH, J.) date of receipt of bid. The respondent also agreed that it shall be bound by the communication of acceptance of the bid dispatched within the aforesaid period of 90 days. In paragraph 10 of the offer/bid, the respondent also agreed that the full value of Bid Security would be forfeited without prejudice to any other right or remedy available to the Executive Engineer or his successor in office or his representative, should the respondent withdraw or modify its bid/offer after the last date and time for the receipt of bids, during the period of bid validity (90 days) or extended validity period. 5. Since Mis. Gaurav Traders was found to be the highest bidder, a letter of acceptance was issued to it on 25.9.2008. However, it failed to deposit the security amount and the first instalment as per the letter of acceptance. Therefore, as per conditior:i No. 9.3(8) of the Detailed Notice Inviting Tender (DNIT) and condition No. 6 of the acceptance letter, the Bid Security of Rs. 20 lakhs deposited by M/s. Gaurav Traders was forfeited and the letter of acceptance was cancelled and withdrawn vide letter dated 16.10.2008 of the competent authority. Thereafter, a letter of acceptance dated 26.11.2008 was issued to the respondent M/s. Malik Traders who was the second highest bidder. As per condition No. 6 of the said letter of acceptance, the respondent was required to deposit the security amount and the first instalment within 21 days from the receipt of the letter of acceptance. However, the respondent failed to deposit the security amount and the first instalment as - required by the letter of acceptance. Hence, vide Memo No. 5029 dated 17.12.2008 issued by the Executive Engineer, Provincial Division No. Ill, PWD, B&R Branch, Kamal, the letter of acceptance was cancelled and withdrawn and the Bid Security of Rs. 20 lakhs was forfeited. 6. It has to be mentioned that before receipt of the letter of acceptance, the respondent had sent a letter dated 15.11.2008 informing the Executive Engineer that the respondent was not interested in the work and, therefore, the A B C D E F G H [2011] 10 S.C.R. 378 SUPREME COURT REPORTS - A amount of Bid Security deposited on 19.9.2008 may be refunded. However, the appellants did not consider or act upon the said letter dated 15.11.2008 of the respondent, as the respondent had agreed to keep its bid open for acceptance upto 90 days after the last date of receipt of bid and the said - B period of 90 days had not expired. In this connection, it has also to be mentioned that the letter of acceptance dated 26.11.2008 was issued to the respondent before the expiry of the above-mentioned period of 90 days. 7. After cancellation of the letter of acceptance issued to C the respondent and after expiry of the above-mentioned period of 90 days on 17.12.2008, the Executive Engineer vide Bid Notice No. 5160 dated 31.12.2008 re-invited bids for the collection of toll at toll point on the Bridge over river Yamuna on Karnal-Meerut Road. The respondent again participated in - D the bid, offering an amount of Rs. 4,94,91,810/-. It may be noted that the amount offered by the re~pondent in the subsequent bid was less than its offer in the first bid with a difference of Rs. 3.03 crores. Since the respondent's bid was the highest bid among the bids submitted pursuant to the Bid Notice dated - E 31.12.2008, a _letter of acceptance was issued to the respondent on 6.2.2009. The respondent deposited the security amount and the first instalment in terms of the said letter of acceptance. 8. After the second letter of acceptance dated 6.2.2009 F was issued to the respondent, the respondent on 7.2.2009 filed C.W.P. No. 2266 of 2009 in the Punjab & Haryana High Court praying for quashing the first letter of acceptance dated 26.11.2008 of the Executive Engineer and the Memo No. 5029 dated 17.12.2008 cancelling the said letter of acceptance and G forfeiting the Bid Security of Rs. 20 lakhs. Even though the appellants opposed the grant of prayers in the writ petition, a Division Bench of the High Court vide order dated 7.7.2009 allowed the writ petition quashing the letter of acceptance dated 26.11.2008 and the Memo dated 17.12.2008 and also directed H # STATE OF HARYANA & ORS. _v._ MALIK TRADERS 379 [CYRIAC JOSEPH, J.] the Executive Engineer (appellant No. 5) to refund the Bid A Security amount of Rs. 20 lakhs to the respondent within two months from the date of receipt of a copy of the order. A"ggrieved by the said order dated 7.7.2009 passed by the High Court in C.W.P. No. 2266 of 2009, the respondents in the writ petition have filed this appeal. B B ·s. We have considered the pleadings in the case, the submissions made by the learned senior counsel for the parties and the materials placed on record. C 10. For allowing the writ petition, the only reason stated C by the High Court is that, since the writ petitioner (respondent herein) had withdrawn its offer before it was accepted, there could be no acceptance of the offer and there could not be any consequence of the petitioner not honouring the commitment. However, we cannot agree with the view taken by the High court. D It is true that as per Section 5 of the Indian Contract Act, 1872 {hereinafter referred to as "the Act"), a proposal may be revoked at any time before the communication of its acceptance is complete as against the proposer. It is also true that before receipt of the letter of acceptance dated E 26.11.2008, the respondent had sent a letter dated 15, 11.2008 withdrawing its offer. However, admittedly, in paragraph 8 of the written offer/bid, the respondent had agreed to keep the bid open for acceptance upto 90 days after the last date of receipt of bid. The respondent had also agreed that it sh.all be bound F by the communication of acceptance of the bid dispatched within the aforesaid period of 90 days. Hence, the respondent could not have withdrawn the bid before the expiry of the period of 90 days. It is not disputed that the acceptance of the respondent's bid was communicated to the respondent within G the said period of 90 days. Therefore, the respondent was bound by the said acceptance of the bid, despite its withdrawal by the respondent in the meanwhile. In paragraph 10 of the offer/bid, the respondent had also agreed that the full value of the Bid Security would be forfeited without prejudice to any H [2011) 10 S.C.R. ## 380 SUPREME COURT REPORTS A other right or remedy ava_ilable to the Executive Engineer or his successor in office or his representative, should the respondent withdraw or modify its offer/bid during the period of bid validity (90 days) or extended validity period. Since the respondent withdrew its offer during the period of bid validity in violation of B the above-mentioned agreement in paragraph 8 of the offer/ bid, the full value of Bid Security was liable to be forfeited in terms of the agreement contained in paragraph 10 of the offer/ bid. Thus, even though under Section 5 of the Act a proposal may be revoked at any time before the communication of its c acceptance is complete as against the proposer, the respondent was bound by the agreement contained in its offer/ bid to keep the bid open for acceptance upto 90 days after the last date of receipt of bid and if the respondent withdrew its bid before the expiry of the said period of 90 days the respondent was liable to suffer the consequence (i.e. forfeiture 0 of the full value of Bid Security) as agreed to by the respondent in paragraph 10 of the offer/bici. Under the cover of the provisions contained in Section 5 of the Act, the respondent cannot escape from the obligations and liabilities under the E agreements contained in its offer/bid. The right to withdraw an offer before its acceptance cannot nullify the agreement to suffer any penalty for the withdrawal of the offer against the· terms of agreement. A person may have a right to withdraw his offer, but if he has made his offer on a condition that the Bid Security amount can be forfeited in case he withdraws the offer F during the period of bid validity, he has no right to claim that the Bid Security should not be forfeited and it should be returned to him. Forfeiture of such Bid Security amount does not, in any way, affect any statutory right under Section 5 of the Act. The Bid Security was given by the respondent and taken G by the appellants to ensure that the offer is not withdrawn during the bid validity period of 90 days and a contract comes into existence. Such conditions are included to ensure that only genuine parties make the bids. In the absence of such conditions, persons who do not have the capacity or have no H intention of entering into the contract will make bids. The very ## STATE OF HARYANA & ORS. _v._ MALIK TRADERS 381 [CYRIAC JOSEPH, J.] purpose of such a condition in the offer/bid will be defeated, if forfeiture is not permitted when the offer is withdrawn in violation of the agreement. A 11. In taking the above view, we are supported by the decision of this Court in _National Highways Authority of India_ 8 _v. Ganga Enterprises_ & _Anr._ [(2003) 7 SCC 41 OJ which was rendered in a similar case. In the said case, the appellant, National Highways Authority of India, by a notice, called for tenders by 31. 7 .1997 for collection of toll on a portion of a particular highway. The notice provided that toll plazas would C be got completed by the appellant and handed over to the selected enterprise. The notice required the bidders to furnish: (i) a bid security in a sum of Rs. 50 lakhs in the form of a bank draft or bank guarantee, and (ii) a performance security in the form of a bank guarantee of Rs. 2 crores. The bid security was liable to forfeiture in case the bidder withdrew his bid during D the validity period of the bid or failed within the specified period to furnish the performance security and sign the agreement. The bid .was to remain valid for a period of 120- days after the last date of bid submission. In terms of the tender document, the respondent firm gave its bid or offer and furnished a bank E guarantee in a sum of Rs. 50 lakhs. It was an "on-demand bank guarantee" stating that it could be enforced on demand if the bidder withdrew his bid during the period of bid validity or failed to furnish the performance security or failed to sign the agreement. While the validity period of the bid was to end on F 28.11.1997, the respondent withdrew its bid on 20.11.1997 and did not furnish the performance guarantee. Therefore, the ai:;pellant although found the respondent to be the highest bidder and accepted its offer on 21.11.1997, encashed the bani' guarantee for Rs. 50 lakhs. The respondent then filed a G writ petition in the High Court for refund of the amount. The High Court formulated two questions viz.: (a) whether the forfeiture of security deposit was without authority of la~ and without any binding contract between the parties and also contrary to _ Section 5 of the Contract Act; and (b) whether the writ petition H 382 SUPREME COURT REPORTS [2011) 10 S.C.R. A was maintainable in a claim arising out of a breach of contract. Without considering Question {b), the High Court allowed the writ petition on the ground that the offer was withdrawn before it was accepted and thus no completed contract had come into existence. The High Court observed that in law a party could B always withdraw its offer before acceptance. Therefore, it held that the invocation and encashnient of the bank guarantee was illegal and void and was liable to be set aside. The appellant then approached the Supreme Court. Allowing the appeal, this Court held as follows: c D E F G H "In our view, the High Court fell in error in so holding. By invoking the bank guarantee and/or enforcing the bid security, there is no statutory right, exercise of which was being fettered. There is no term in the contract which is contrary to the provisions of the Indian Contract Act. The Indian Contract Act merely provides that a person can withdraw his offer before its acceptance. But withdrawal of an offer, before it is accepted, is a completely different aspect from forfeiture of earnest/security money which has been given for a particular purpose. A person may have a right to withdraw his offer but if he has made his offer on a condition that some earnest money will be forfeited for not entering into contract or if some act is not performed, then even though he may have a right to withdraw his offer, he has no right to claim that the earnest/ security be returned to him. Forfeiture of such earnest/ security, in no way, affects. any statutory right under the Indian Contract Act. Such earnest/security is given and taken to ensure that a contract comes into existence. It would be an anomalous situation that a person who, by his own conduct, precludes the coming into existence of the contract is then given advantage or benefit of his own. wrong by not allowing forfeiture. It must be remembered that, particularly in government contracts, such a term is always included in order to ensure that only a genuine party makes a bid. If such a term was not there even a # STATE OF HARYANA & ORS. _v._ MALIK TRADERS 383 [CYRIAC JOSEPH, J.] person who does not have the capacity or a person who A has no intention of entering into the contract will make a bid. The whole purpose of such a clause i.e. to see that only genuine bids are received would be lost if forfeiture was not permitted." B We respectfully agree with the above view of this Court. 12. Hence, the High Court was not justified in quashing the letter dated 26.11.2008 accepting the bid of the respondent and the letter dated 17 .12.2008 forfeiting the Bid Security amount of Rs. 20 lakhs. The appeal is allowed and the order dated C 7.7.2009 passed by the High Court of Punjab & Haryana in C.W.P. No. 2266 of 2009 is set aside. Consequently, the writ petition stands dismissed. There will be no order as to costs. R.P. Appeal allowed. D
End of Judgment Record
Browse All Supreme Court of India (2011) Decisions
2011-10-13

GRASIM INDUSTRIES LTD. v. UNION OF INDIA

Grasim Industries Ltd. v. Union of India deals with whether metal scrap or waste generated during repair of worn-out machinery used in a cement manufacturing plant constitutes manufacture and thus obligations to pay Central excise duty. The core dispute arose after Grasim repaired plant components and generated scrap, which was cleared without duty; the Tribunal later held that such scrap did not arise from any manufacturing activity and was not excisable. The Rajasthan High Court initially upheld the duty demand and penalties, while the Tribunal had dropped them. The Supreme Court reversed the High Court, restoring the Tribunal’s order and allowing the appeal. The Court held that although repair work produces metal scrap, this scrap does not participate in the manufacture of cement and cannot be treated as a by-product of the final product. It emphasized that excise duty is on manufacture of goods, requiring that the goods be produced or manufactured in India, and the charging Section 3 applies only when the goods are excisable under Section 2(d) and are manufactured under Section 2(f). Section 2(f) defines manufacture as including any process incidental or ancillary to the completion of the manufactured product, involving transformation of raw material into a new or distinct excisable product. The process of repair, using non-raw materials, does not satisfy this test. The Court also cautioned against deeming provisions in tariff notes as creating manufacture unless expressly stated, relying on various precedents such as Shyam Oil Cake, Ujagar Prints, Hindustan Polymers, and Union of India v. Delhi Cloth and General Mills, among others, to delineate the law of manufacture.

2011-03-02

Bharat Petroleum Corporation Ltd. v. Chembur Service Station

This Supreme Court appeal concerns BPCL’s licence-based relationship with a dealer at a Retail Petroleum Outlet (RPO) in Chembur, Mumbai. BPCL (then Burmah Shell) leased the land and services premises to operate the RPO; in 1972 a DPSL (Dispensing Pump and Selling Licence) granted the respondent the right to sell BPCL’s petroleum products from the outlet. A 1995 renewal extended the arrangement. In 2007, a show-cause notice alleged tampering with dispensing equipment, prompting BPCL to terminate the dealership. The respondent filed suits in the Court of Small Causes claiming tenancy or deemed tenancy under rent-control laws and sought an injunction to continue supply, while BPCL argued the arrangement was a revocable licence, not a tenancy, and the remedy lay in due process and contract law, not eviction under rent-control statutes. The lower courts issued status-quo orders preserving possession and continuing supplies, with various challenges under Public Premises Act and rent-control regimes. The Supreme Court clarified that the DPSL licence creates a limited, revocable right to enter and use the premises to sell BPCL’s products, not a tenancy; the licence terminates with revocation and the licensee has no independent right to possession. The Court ultimately referred the matter to a larger Bench due to divergent views and, in the order, dismissed the appeal with directions to proceed under due process of law.

2011-07-04

Sudam @ Rahul Kaniram Jadhav v. State of Maharashtra

Sudam alias Rahul Kaniram Jadhav challenged a conviction for the murder of a woman with whom he lived as husband and wife and her four children. The victims were found in a village pond in August 2007. The trial court convicted the appellant under IPC Sections 302 and 201 and sentenced him to death; the Bombay High Court affirmed. The State relied on circumstantial evidence: the victims were last seen alive with the appellant; he had posed as single, later marrying another woman (PW-6); the deceased had agreed to pay Rs. 15,000 to PW-6 to settle the dispute; extra-judicial confessions were made by the appellant to PW-6 and PW-9; he absconded and could not explain the deaths. The defense argued that the circumstantial chain was not complete and could admit alternate explanations; there were no direct eyewitnesses. The Supreme Court reiterated the standard for circumstantial evidence: the evidence must be cogently and firmly established, form a complete chain, point to guilt beyond reasonable probability, and be inconsistent with innocence. It concluded all five deaths were homicidal and, applying the rarest-of-the-rare doctrine, upheld the conviction and the death sentence, while dismissing the appeals.

2011-04-18

J.S. Yadav v. State of U.P. & ANR.

This case concerns a challenge to a May 28, 2008 notification declaring the appellant, a member of the Uttar Pradesh State Human Rights Commission, ceased to hold office after amendments to the Protection of Human Rights Act, 1993 were introduced by the Protection of Human Rights (Amendment) Act, 2006. The appellant joined the Commission on 29 June 2006 for a five-year tenure and argued that the amendment, which requires seven years of experience as a District Judge for eligibility, could not curtail an incumbent’s tenure and could not be applied retrospectively. He also contended that Section 26 of the Act guarantees that terms and conditions of service shall not be varied to his disadvantage after appointment, and that the proposed reconstitution would deprive accrued rights. The State argued that fresh appointments to the Commission had to be made, that the amendment could alter service conditions, and that public funds cannot pay two persons for one post; non-joinder of relatives and the lack of a suitable remedy rendered the petition academic. The Supreme Court held that tenure posts must be allowed to endure to the end of the fixed term and that accrued rights cannot be taken away by a repealing or amended statute without express or necessary implication. It held the 2006 Amendment prospective and the impugned notification illegal, allowed the appeal to the extent discussed, and awarded Rs. 1 lakh as costs to the appellant.