Supreme Court of IndiaSupreme Court · 1997Division BenchAppeal allowed; No costs.

STATE OF GUJARAT v. DAHYABHAIZAVERBHAI

Case / Petition Number:
Civil Appeal No. 1821 of 1997
Neutral Citation:[1997] 2 S.C.R. 469

Case Synopsis & Summary

This appeal concerns the rescision of a government contract for protective works on a road bridge and the forfeiture of the contractor's security deposit. The respondent contractor had entered into agreement No. B-1/17 of 1981-82 to complete protective measures for the Ambica river bridge. Although there was delay in handing over worksheets and specifications, the trial court found that the government land was public and the contractor alone abandoned the work after being given reasonable time and opportunity to complete it. Clause-3 of the contract empowered the Executive Engineer to rescind the contract and forfeit the security deposit if the contractor was liable for termination or abandonment. The High Court held that the state was not entitled to forfeit the deposit; The Supreme Court allowed the appeal, holding the forfeiture valid under Clause-3. It rejected the applicability of Mis Hind Construction Contractors v. State of Maharashtra (AIR 1979) SC 720, which concerned a different scenario where time was not considered essential. The Court concluded that because the contractor abandoned the work, the contract could be rescinded, and the deposit forfeited, with the state entitled to retain the security deposit. The appeal is allowed and costs are withheld.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G. T. Nanavati
Judgment Date
1997-02-24
Court Decision / Holding
Appeal allowed. The High Court’s direction to refund the security deposit is set aside. The contract was rescinded under Clause-3 due to abandonment, and the security deposit was rightly forfeited to the Government. No costs.
Final Disposition
Appeal allowed; No costs.

Parties to the Case

Appellants / Petitioners

  • State of Gujarat

Respondents

  • Dahyabhai Zaverbhai

Legal Representation & Advocates

Counsels for Petitioners

  • • Adhyaru Yashank Pravin
  • • H. Wahi
  • • N. Mukherjee

Counsels for Respondents

  • • K. L. Janjani

Provisions of Law Cited

Clause-3 of the contract

Legal Doctrines & Maxims

  • Time is not the essence of the contract
  • Rescission of contract on abandonment leads to forfeiture of security deposit

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that Clause-3 of the contract expressly authorizes rescission and forfeiture of the security deposit upon abandonment. It argues the High Court erred in directing refund of the deposit and relies on the contract provision empowering the Government to rescind and forfeit. The land being public, no private title obstacle existed, and the contractor’s abandonment justifies forfeiture under the contract terms. The decision in Mis Hind Construction Contractors v. State of Maharashtra (AIR 1979 SC 720) is distinguished as inapplicable to this case since the present dispute concerns abandonment and forfeiture under a valid rescission clause rather than non-completion within an extended time frame.

Contentions of Respondents

The contractor contends that time was not the essence of the contract, and the work was prolonged due to delays; it had been given reasonable time to complete but ultimately abandoned the site. It argues that the cited Mis Hind Construction Contractors case is relevant to issues of time extension and awards, and that the court should not treat the contract as rescinded merely on abandonment without proper justification. The respondent maintains that the High Court’s emphasis on refunding the deposit was correct absent a clear breach entitling forfeiture.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Mis Hind Construction Contractors v. State of MaharashtraAIR (1979) SC 720DistinguishedThe judgment states that the ratio of this case has no relevance to the present case and distinguished it on facts involving abandonment and a rescission clause rather than non-completion after extended time.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•919 words•~5 min read

In The Court Record

STATE OF GUJARAT v. DAHYABHAIZAVERBHAI

STATE OF GUJARAT A _v._ ## DAHYABHAIZAVERBHAI ## FEBRUARY 24, 1997 [K. RAMASWAMY AND G.T. NANAVATI, J.1.J B _Contract :_ _Rescission of Contract-Forfeiture of secwity deposit-Held, was per! ectly valid as the Contractor had abandoned execution of contract work in_ C _spite of opportunity having been given to him to complete the work._ _Mis. Hind Construction Contractors_ v. _State of Maharashtra,_ A.l.R. (1979) SC 720, held inapplicable. > CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1821 of D 1997. From the Judgment and Order dated 21.8.95 of the Gujarat High Court in F.A. No. 3875 of 1995. Adhyaru Yashank Pravin, H. Wahi and N. Mukherjee for the Appel- E I ant KL. Janjani for the Respondent. The following Order of the Court was delivered : Delay condoned. F Leave granted. We have heard learned counsel on both sides. This appeal by special leave arises from the judgment of the Gujarat High Court, dated August 21, 1995 passed in First Appeal No. 3875/95. Admittedly, the respondent-contractor had entered into an agreement No. B-1/17 of 1981-82 to complete the work of protective measures for the road bridge across river Ambica. The appellant had issued the work order on June 3, 1981. It is true that there was a delay in handing over the work sheet and the specifications. But the trial Court after considering the H 469 470 SUPREME COURT REPORTS [1997] 2 S.C.R. A entire evidence had noted its finding thus : B c "In the present ease the land on which the construction work was required to be made was a land of the Government and not of private party or private owner, so there was no hurdle in the construction work of the plaintiff but the plaintiff himself has left the construction and hence, in the present case, only the plaintiff can be held a person who has· revoked the contract. Before revoking the contract, the plaintiff was given sufficient time and reasonable opportunity to complete the work but the plaintiff has not done anything to complete the work and left the work and the site so we have no option, the deft/Department to take the decision for revocation of the contract." In view of the above finding, the inevitable conclusion is that the respondent had abandoned the execution of the work in spi'4i of the opportunity having been given to him to complete the work. ci~use 3 of D the Contract reads as under : E "Clause-3 : In any case, in which under any clause or clauses of this contract, the contractor shall have rendered himself liable to pay compensation amounting to the whole of his security deposit (whether paid in the sum or deducted by instalments) or in the case of abandonment of the work owing to serious illness or death of the contractor or any othe·r cause, the Executive Engineer, on behalf of the Government of Gujarat shall have power :- F (a) to rescind the contract (of which recession notice in writing to the Contractor under the hand of the Executive Engineer shall be conclusive evidence) and in that case the security deposit of the Contractor shall stand forfeited and be absolutely at the disposal of Government. G That in view of this express provision the Hon'ble High Court erred in holding that the petitioner/State is not entitled to forfeiture the deposit." A reading thereof would clearly indicate that in any case, under any clause or clauses of the contract, the contractor would. have rendered H himself liable to pay compensation amounting to the whole of his security 471 STATE _v._ DAHYABHAI whether paid in the sum or deducted by instalments; in the case of A abandonment of the work owning to serious illness or death of the contractor or _a11y other cause,_ the Executive Engineer is empowered to have the contract rescinded; in that case the security deposit of the contractor shall stand forfeited and be absolutely at the disposal of the Government.· In consequence, forfeiture of the security deposit, on account of abandonment B of the work by the appellant, was perfectly valid. The High Court, therefore, was not right in directing the appellant to refund the security deposit. Learned counsel for the respondents contends that time was not the essence of the contract, and therefore, the recession of the contract was not for valid reason. We are, however, not on the validity of the recession of the contract on the ground of time being the essence of contract but on C · the question whether the respondent had abandoned the contract or not. The question in that backdrop arises : whether the recession of the contract was correct in law? In view of the above facts, the action was legal. In that perspective, the ratio in _Mis. Hind Construction Contractors_ v. _State of Maharashtra,A.I.R._ (1979) SC 720 has no relevance. Therein, the contract D was not rescinded. Work was executed after the extended time and the claims were made before the Arbitrator for the work done during the extended time. Therein, the contention was raised that time was essence of the contract. Respondent and the contractor having not completed the work within the schedule time, he was not entitled to the amount under the award. In that contract, this Court had held that time was not essence E of the contract. That question, however, does not arise in this case for the reason that the respondent had abandoned the contract. The appeal is accordingly allowed. No costs. R.P. Appeal allowed. F
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.