Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2019Division BenchAppeal dismissed.

Standard Chartered Bank v. Heavy Engineering Corporation Ltd. & Anr.

Case / Petition Number:
Civil Appeal No. 9288 of 2019
Neutral Citation:[2019] 15 S.C.R. 368

Case Synopsis & Summary

This appeal arises from two bank guarantees furnished by Standard Chartered Bank (as successor to ANZ Grindlays Bank) on behalf of M/s. SCIL (Simon Carves India Ltd.) in favour of Heavy Engineering Corporation Ltd. (HEC) in connection with a letter of intent dated 19 May 1981 for the Dankuni Coal Complex project. The guarantees, dated 16 February 1983 and 29 August 1984, were intended to secure advances made to SCIL for the supply of plant and equipment and for performance of the contract. SCIL later breached the contract by supplying defective or non-supplied equipment, causing substantial loss to HEC, which proceeded to encash the guarantees. HEC invoked the guarantees; the bank refused, prompting litigation. The High Court of Calcutta upheld the invocation and decreed Rs. 1,10,33,207.00 with 8% interest. The Supreme Court, while noting that bank guarantees are independent contracts, held that once a demand is made in terms of an unconditional guarantee, the bank is ordinarily obliged to pay, subject to fraud, irretrievable injustice, or special equities. The Court affirmed the Division Bench’s conclusion that the invocation complied with the guarantees’ terms and that the bank’s defense based on alleged misalignment with the contract did not render the invocation invalid. The appeal was dismissed with no costs, and the registry may release funds to the plaintiff-applicant to satisfy the decree.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • L. Nageswara Rao
  • Ajay Rastogi
Judgment Date
2019-12-18
Court Decision / Holding
Appeal dismissed.
Final Disposition
Appeal dismissed.

Parties to the Case

Appellants / Petitioners

  • Standard Chartered Bank

Respondents

  • Heavy Engineering Corporation Ltd.
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Amit Sibal
  • • Ajay Monga
  • • Ms. Devmani Bansal
  • • F Vikas Kumar

Counsels for Respondents

  • • Ms. Madhavi Diwan
  • • Amit Meharia
  • • Abinash Agarwal
  • • Ms. Rupali Bansal
  • • M/S. Meharia & Company
  • • Ayush Puri
  • • Sougat Sinha
  • • Dhananjay Garg

Legal Doctrines & Maxims

  • A bank guarantee is an independent contract between the bank and the beneficiary.
  • The bank must honor its guarantee if it is unconditional and irrevocable.
  • Disputes between the beneficiary and the party who furnished the guarantee are immaterial, except in cases of fraud, irretrievable injustice or special equities.
  • Exceptions to non-interference exist where fraud or irretrievable injustice or special equities are prima facie established.
  • A court should be slow to grant injunctions restraining encashment of an unconditional bank guarantee, and the guarantee should be construed strictly by its terms.
  • The objective of bank guarantees is to facilitate commerce and ensure faith in banking transactions; enforceability should not be hamstrung by underlying contract disputes.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant bank contends that invocation of the guarantees was not in accordance with the terms of the two guarantees. It argues that the invocation was inchoate, incomplete, and failed to specify the apportionment of losses between non-supply/defective supply and other contractual deficiencies. The bank asserts that the guarantee is an independent contract, but invocation must strictly adhere to its terms; hence, if the invocation deviates from the guarantee’s explicit language, the bank cannot be compelled to pay. It relies on established precedents that permit interference only in cases of fraud, irretrievable injustice, or special equities, and that the bank’s defense cannot be used to defeat a valid claim where the invocation complies with the guarantee’s conditions.

Contentions of Respondents

HEC argues that the two bank guarantees were unconditional and clearly covered advances against SCIL’s contract for plant and equipment, including losses caused by breach or non-performance. It asserts that the invocation followed subsequent correspondence aligning with the guarantees’ terms, and that the bank’s refusal to pay was improper. It maintains that the guarantees are independent of the underlying contract yet liable to honor on demand; the bank’s attempt to scrutinize the justification for losses is contrary to the guarantees’ language and the settled law on bank guarantees. The respondent also points to prior exchanges and letters invoking encashment as substantiation of timely invocation and compliance.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Ansal Engineering Projects Ltd. v. Tehri Hydro Development Corporation Ltd. and Another1996 (5) SCC 450PositiveBank guarantee is an independent contract; encashment should not be blocked absent fraud or special equity, as reiterated by Ansal.
Hindustan Construction Co. Ltd. v. State of Bihar & Others1999 (8) SCC 436PositiveUnconditional and irrevocable guarantees must be honoured; the guarantee should be paid as per its terms.
State Bank of India and Another v. Mula Sahakari Sakhar Karkhana Ltd.2006 (6) SCC 293PositiveBank guarantees must be construed on their own terms; they constitute an independent transaction.
Himadri Chemicals Industries Limited v. Coal Tar Refining Co.2007 (8) SCC 110PositiveFurther authority on bank guarantees and the independence of the guarantee contract.
Gujarat Maritime Board v. Larsen & Toubro Infrastructure Development Projects Limited and Another2016 (10) SCC 46PositivePrinciples for injunctions restraining encashment of bank guarantees; emphasis on independent contract.
Gangotri Enterprises Ltd. v. Union of India and Others2016 (11) SCC 720Mentioned OnlyCited but not relied upon for core reasoning; used as a referential doctrinal support.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,620 words•~26 min read

In The Court Record

Standard Chartered Bank v. Heavy Engineering Corporation Ltd. & Anr.

368 SUPREME COURT REPORTS [2019] 15 S.C.R. 368 [2019] 15 S.C.R. A ## STANDARD CHARTERED BANK ## v. HEAVY ENGINEERING CORPORATION LTD. & ANR. (Civil Appeal No. 9288 of 2019) ## B ## DECEMBER 18, 2019 ## **[L. NAGESWARA RAO AND AJAY RASTOGI, JJ.]** _Banks/Banking – Bank guarantees – Law relating to invocation of – By letter of intent dtd. 19.05.81, 1[st] respondent placed order on the 2[nd ] respondent for the complete design, supply_ C _of both indigenous and imported equipments, erection and commissioning of requisite civil and construction works of the Dankuni Coal Complex at Rs.21.10 crores – Two bank guarantees, dtd.16.02.83 and 29.08.84 amounting to Rs.71,35,100/- and Rs. 20,32,500/- furnished on behalf of the 2[nd] respondent by the_ D _appellant-Bank in favour of the 1[st] respondent – Memorandum of Agreement executed – In due course of time, the 2[nd ] respondent failed to complete the supply of equipment and the other conditions of the letter of intent – 1[st] respondent demanded encashment of both the bank guarantees – Refused by the bank – Eventually, the 1[st] respondent filed suit before the High Court of Calcutta for_ E _Rs.1,10,33,207.07/- with interest being the aggregate sum of both the bank guarantees – Dismissed – Division Bench passed decree for Rs.1,10,33,207.00/- with interest @ 8% p.a. – Held: Bank guarantee is an independent contract between bank and the beneficiary – Bank is always obliged to honour its guarantee as_ F _long as it is an unconditional and irrevocable one – Dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence – However, exceptions to this Rule are when there is clear case of fraud, irretrievable injustice or special equities – Court ordinarily should not interfere with the invocation or encashment of the bank_ G _guarantee so long as the invocation is in terms of the bank guarantee – In the instant case, guarantees were unconditional, specific in nature and limited in amount – Guarantee documents, as a whole and clause 2 in particular cover the advance paid by the 1[st] respondent by reason of any breach or failure by 2[nd]_ H _respondent in due performance of the contracts i.e. against the_ 368 STANDARD CHARTERED BANK v. HEAVY ENGINEERING 369 CORPORATION LTD. _contract for supply of plant and equipment – On reading of letters exchanged by and between the 1[st ] respondent and the appellant pertaining to invocation of the guarantees, the condition of the guarantees had been duly complied with – Once the demand was made in due compliance of bank guarantees, it was not open for the appellant to determine as to whether the invocation of the bank guarantee was justified – Standard Chartered Bank’s predecessor in interest, ANZ Grindlay’s Bank had opened fixed deposit of Rs.91,67,600/- on 18.05.01, which was lien marked to Heavy Engineering Corporation Ltd. (HEC) and is being held under the control of the Registry of the High Court of Calcutta – Current fixed deposit is valued at Rs. 2,32,69,129.71/- and the total liability under the impugned order as on date will be Rs.2,78,03,681.64/– Registry of the High Court of Calcutta may release the money lying in the account in favour of the 1[st] respondent – It is for the appellant (judgment debtor) to settle and satisfy the decree impugned in the instant proceedings – Contract._ A B C D ## **Dismissing the appeal, the Court** **HELD: 1.1 A bank guarantee constitutes an independent contract. The bank guarantee is an independent contract between bank and the beneficiary and the bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence. There are, however, exceptions to this Rule when there is a clear case of fraud, irretrievable injustice or special equities. The Court ordinarily should not interfere with the invocation or encashment of the bank guarantee so long as the invocation is in terms of the bank guarantee. The guarantees in the instant case were unconditional, specific in nature and limited in amount. The terms of the guarantee categorically covered money which the 1[st] respondent had advanced against supply of the plant and equipment by SCIL. The said guarantees covered any loss and damage caused to or suffered by the 1[st] respondent-plaintiff in due performance of the contract for supply of plant and equipment. The guarantee documents dated 16[th] February, 1983 and 29[th] August, 1984, as a whole and clause 2 of the guarantee** E F G H 370 SUPREME COURT REPORTS [2019] 15 S.C.R. - A **document in particular cover the advance which had been paid by the 1[st] respondent-plaintiff by reason of any breach or failure by SCIL in due performance of the aforesaid contracts i.e. against the contract for supply of plant and equipment. On reading of letters exchanged by and between 1[st] respondent and the appellant Bank pertaining to invocation of the guarantees, the** - B **condition of the guarantees had been duly complied with. [Paras 20, 23-25] [379-G; 381-G-H; 382-A-C-G]** _Ansal Engineering Projects Ltd. v. Tehri Hydro Development Corporation Ltd. and Another_ **(1996) 5 SCC 450 : [1996] 4 Suppl. SCR 226 ;** _Hindustan_ C _Construction Co. Ltd. v. State of Bihar & Others_ **(1999) 8 SCC 436 : [1999] 3 Suppl. SCR 554 ;** _State Bank of India and Another v. Mula Sahakari Sakhar Karkhana Ltd._ **(2006) 6 SCC 293 : [2006] 3 Suppl. SCR 320 ;** H _imadri Chemicals Industries Limited v._ D _Coal Tar Refining Co._ **(2007) 8 SCC 110 : [2007] 8 SCR 869 ;** _Gujarat Maritime Board v. Larsen & Toubro Infrastructure Development Projects Limited and Another_ **(2016) 10 SCC 46 : [2016] 8 SCR 692** **– relied on.** - E _Gangotri Enterprises Ltd. Vs. Union of India and Others_ **(2016) 11 SCC 720 : [2016] 2 SCR 1074 – referred to.** - **1.2 Once the demand was made in due compliance of bank** - **guarantees, it was not open for the appellant Bank to determine** - F **as to whether the invocation of the bank guarantee was justified so long as the invocation was in terms of the bank guarantee. The demand once made would oblige the bank to pay under the terms of the bank guarantee and it is not the case of the appellant Bank that its defence falls in any of the exception to the rule of case of fraud, irretrievable injustice and special** - G **equities. In absence thereof, it is not even open for the Court to interfere with the invocation and encashment of the bank guarantee so long as the invocation was in terms of the bank guarantee and this what has been observed by the Division Bench of the High Court in the impugned judgment and that** - H **reflected the correct legal position. It is informed that the** STANDARD CHARTERED BANK v. HEAVY ENGINEERING 371 CORPORATION LTD. **Standard Chartered Bank’s predecessor in interest, ANZ Grindlay’s Bank had opened a fixed deposit of Rs. 91,67,600/on 18[th] May, 2001, which was lien marked to HEC (Heavy Engineering Corporation Ltd.) and is being held under the control of the Registry of the High Court of Calcutta and the current fixed deposit is valued at Rs. 2,32,69,129.71/- and the total liability under the impugned order as on date will be Rs. 2,78,03,681.64/-. The Registry of the High Court of Calcutta may release the money lying in the account in favour of the 1[st] respondent and it is for the appellant Bank(judgment debtor) to settle and satisfy the decree which is impugned in the instant proceedings. [Paras 26, 27] [382-G-H; 383-A-D]** A B C ## **Case Law Reference** |**[2016]**|**2**|**SCR 1074**|**referred to**|**Para 16**|| |---|---|---|---|---|---| |**[1996]**|**4**|**Suppl. SCR 226**|**relied on**|**Para 19**|| |**[1999]**|**3**|**Suppl. SCR 554**|**relied on**|**Para 20**|D| |**[2006]**|**3**|**Suppl. SCR 320**|**relied on**|**Para 21**|| |**[2007]**|**8**|**SCR 869**|**relied on**|**Para 22**|| |**[2016]**|**8**|**SCR 692**|**relied on**|**Para 22**|| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9288 of 2019. E From the Judgment and Order dated 08.05.2019 of the High Court of Calcutta in A.P.D. No. 198 of 2016. Amit Sibal, Sr. Adv., Ajay Monga, Ms. Devmani Bansal, F Vikas Kumar, Advs. for the Appellant. Ms. Madhavi Diwan, ASG, Amit Meharia, Abinash Agarwal, Ms. Rupali Bansal, M/S. Meharia & Company, Ayush Puri, Sougat Sinha, Dhananjay Garg, Advs. the Respondents. The Judgment of the Court was delivered by G ## **RASTOGI, J.** 1. Leave granted. 2. The instant appeal is being preferred against the judgment and order dated 8[th] May, 2019 passed by the Division Bench of the High H 372 SUPREME COURT REPORTS [2019] 15 S.C.R. - A Court of Calcutta setting aside the judgment dated 16[th] October, 2015 of the Single Bench and accepting claim of the 1[st] respondent-plaintiff holding that the bank guarantees were properly invoked in law and accordingly the decree came to be passed for Rs. 1,10,33,207.00/- as claimed in paragraph 18 of the plaint with interest at the rate of 8 per cent per annum from the date of institution of the suit until payment. - B 3. Although both the Judges of the Division Bench has delivered their separate judgment but have expressed a concurring view on the subject. 4. The dispute primarily arose with regard to two bank C guarantees amounting to Rs. 71,35,100/- and Rs. 20,32,500/- in terms of the letters of intent, HEC-CS-1502-81 dated 19[th] May, 1981 and HEC-CS-1502-81 dated 19[th] May, 1981 furnished on behalf of the 2[nd] defendant by the appellant Bank(1[st] defendant) in favour of the 1[st] respondent-plaintiff “as advance against supply of plant and equipment” D by the 1[st] respondent-plaintiff to the 2[nd] respondent (defendant no. 2). The two bank guarantees are on identical terms and the only difference is the date and the amount which are reproduced as under:- ## Bank Guarantee No. 1001/03/100G dated 16th February, 1983 - “We, GRINDLAYS BANK P.L.C., 19 Netaji Subhas Road, - E Calcutta 700001 undertake the Indemnity and keep the CORPORATION indemnified to the extent of Rs. 71,35,100/(Rupees SEVENTY ONE LAKHS THIRTY FIVE THOUSAND AND ONE HUNDRED ONLY) against any loss or damage caused to or suffered by the CORPORATION by - F reason or any breach or failure by the said SUPPLIER, in due performance of the aforesaid contract, we shall forthwith on demand pay to the CORPORATION any sum or sums not exceeding Rs. 71,35,100/-(RUPEES SEVENTY ONE LAKHS THIRTY FIVE THOUSAND AND ONE HUNDRED ONLY) without making any prior reference to the said SUPPLIER with - G and exclusion of any action in Court by SUPPLIER.” ## Bank Guarantee No. G/1001/84/608 dated 29th August, 1984 - H “We, GRINDLAYS BANK P.L.C., 19 Netaji Subhas Road, Calcutta 700001 do hereby undertake the Indemnity and keep the CORPORATION indemnified to the extent of Rs. STANDARD CHARTERED BANK v. HEAVY ENGINEERING 373 CORPORATION LTD. [RASTOGI, J.] 20,32,500(Rupees TWENTY LAKHS THIRTY TWO THOUSAND FIVE HUNDRED ONLY) against any loss or damage caused to or suffered by the CORPORATION by reason or any breach or failure by the said SUPPLIER, in due performance of the aforesaid contract, we shall forthwith on demand pay to the CORPORATION any sum or sums not exceeding Rs. 20,32,500/-(RUPEES TWENTY LAKHS THIRTY TWO THOUSAND FIVE HUNDRED ONLY) without making any prior reference to the said SUPPLIER with and exclusion of any action in Court by SUPPLIER.” (emphasis supplied) 5. The said two bank guarantees were furnished for and on behalf of 2[nd] respondent towards the sum insured “against any loss or damage caused to or suffered by the Corporation by reason or any breach or failure by the said supplier, in due performance of the aforesaid contract.” A B C D ## **Brief facts of the case** : 6. By a letter of intent dated 19[th] May, 1981, 1[st] respondent placed an order on 2[nd] respondent(Simon Carves India Ltd. ‘SCIL’) for the complete design, supply of both indigenous and imported equipments, erection and commissioning of requisite civil and construction works of the Dankuni Coal Complex at a total price of Rs. 21.10 crores. The letter of intent dated 19[th] May, 1981 after describing 4 sections of the LTC plant at Dankuni stated as under:- “The above price covers the complete design, supply of both indigenous and imported equipment, erection and commissioning with requisite civil and structural works complete in all respects except land filling upto 4.00 M level, railways siding, roads & outside drawing and perphorial lighting which will only be outside your scope or work. The break up of the total price of Rs. 21.10 crores for purpose of billing is enclosed. We have noted the terms of payment proposed by you in your letter dated 18.05.81. As we have indicated about the terms of payment agreed to by us, it will not be possible to consider your proposal for relaxation of the same. However, attempts will be E F G H 374 SUPREME COURT REPORTS [2019] 15 S.C.R. - A made to consider some softening of payment terms later depending our own cash flows on this project. Kindly let us have your detailed technical specifications etc to enable us to draw up a detailed contract for the work. Kindly communicate your acceptance of this letter of intent and B furnish us a bank guarantee on approved proforma to release the initial advance of Rs. 15.64 lakhs to you. In pursuance of the letter of intent two bank guarantees have been furnished by the defendant no. 1 on behalf of the defendant C no. 2 “as advance against the supply of plant and equipment.” (emphasis supplied) 7. Pursuant to the letter of intent, a formal Memorandum of Agreement dated 8[th] August, 1985 was executed by and between SCIL. Thereafter, the 1[st] respondent (plaintiff) from time to time advanced D for the said work against several bank guarantees furnished by SCIL. It may be noticed that the instant dispute pertains to two bank guarantees dated 16[th] February, 1983 and 29[th] August, 1984, which were advanced to SCIL, the details of which have been indicated above. The said guarantees furnished by the appellant bank were extended from E time to time and revalidated. 8. In due course of time, in breach of contract with the 1[st] respondent-plaintiff, SCIL failed to duly complete the supply of equipment and the other conditions of the letter of intent and further defective equipments. It is alleged that the work had to be abandoned F due to which 1[st] respondent suffered huge losses and damages. Ultimately, a sum of Rs. 139.90 lakhs, was deducted by the 1[st] respondent from final bill which pertained to the apportioned work handed over to SCIL. 9. In view of the letter dated 6[th] November, 1998, 1[st] respondent- G plaintiff demanded encashment of both the said guarantees which were refused by the bank to honour and diverse correspondence was exchanged by and between the 1[st] respondent -plaintiff and the appellant-defendant bank. 1[st] respondent in continuation made subsequent demands for encashment of the guarantees by letter dated H 19[th] December, 1998 which is reproduced hereunder:- STANDARD CHARTERED BANK v. HEAVY ENGINEERING 375 CORPORATION LTD. [RASTOGI, J.] “No.HDC/Proj/Fin/98-343 A Dated the 19[th] December, 1998 ## To The Chief Manager Corporate Banking ANZ Grindlays Bank 19, Netaji Subhas Road Post Box No.2645 Calcutta – 700001 Dear Sir, With reference to your St. Relationship Manager’s letter dtd. 7.12.98 regarding encashment of B.Gs issued by you on behalf of M/s. SCIL for a total value of Rs.91.68 lakhs you are very much aware that M/s. SCIL owes to H.E.C. Rs.139.90 lakhs - due to defective supply of Plant & Equipment as well as non supply of Plant & Equipment and also other contractual deficiencies which has caused loss as reflected in the handing over/taking over report of the DCC Project by CIL. You are also aware that HEC has gone out of the way in supporting SCIL and getting the Plant completed with minimum damage. It is within HEC’s full rights to invoke the BG as per Clause No.2 of the BG’s which is reproduced below; (BG No.G1001/83/1084 dt. 16.8.83 for Rs. 71,35,100.00 and BG No.G1001/84/608 dt. 29.8.84 for Rs. 20,32,500.00). WE GRINDLAYS BANK PLC 19, Netaji Subhas Road, Calcutta – 700001 do hereby undertake the Indemnity of Rs. (Rupees _______________________) against any loss or damage caused to or suffered by the CORPORATION by reason or any breach or failure by the said SUPPLIER, in due performance of the aforesaid contract, we shall forthwith on demand pay to the CORPORATION any sum or sums not exceeding Rs. (RUPEES without making any prior reference to the said SUPPLIER with an exclusion of any action in court by SUPPLIER. The failure of M/s. SCIL in fulfilling the contractual obligation which includes performance Guarantees of Plant & Equipment B C D E F G H 376 SUPREME COURT REPORTS [2019] 15 S.C.R. - A are very well documented by HEC & CIL. In fact, the unadjusted advance of SCIL on account of Plant & Equipment is far in excess of the loss suffered by HEC. The same has been brought down to Rs.139.90 lakhs after allowing credit for contractual settlement. - B Although as per terms of BG we are not bound to explain you all these things but the above details are furnished so that good sense will prevail and we expect you to live up to your reputation and honour the beneficiaries claim for encashment. Thanking you, C Yours faithfully, T.L.N. SOURI GENERAL MANAGER (PROJECTS & MNTG) (emphasis supplied)” D 10. This was followed by the letter dated 28[th] December, 1998 which is also reproduced hereunder:- “No.GGM(CM)/ /98 28[th] December, 1998 E To The Chief Manager ANZ Grindlays Bank CALCUTTA. (Atten: Shri Vasudeo Kundu) F ## Fax No.033-2211196 Sub: Encashment of two Bank Guarantees Nos. G 1) G/1001/83/108G for Rs.71,35,100/2) G/1001/88/608 for Rs.20,32,500/- Ref: Our letter dated 19.11.1998. Dear Sir, H We have intimated vide our above letter to encash the above two Bank Guarantees issued by you on behalf of SCIL India Ltd., to HEC. STANDARD CHARTERED BANK v. HEAVY ENGINEERING 377 CORPORATION LTD. [RASTOGI, J.] You are requested to encash the above Bank Guarantees and A send the proceeds amounting to Rs.91,67,600/- within 3 days time. Kindly treat this as most urgent and failing on the part of the Bank to honour the beneficiaries demand will be viewed seriously. Thanking you, B Yours faithfully, **==> picture [71 x 11] intentionally omitted <==** 11. A further complaint was made by way of a letter dated 22[nd] February, 1999 to the Banking Ombudsman, Calcutta. Ultimately, 1[st] respondent-plaintiff was constrained to institute a suit before the High Court of Calcutta for decree of Rs. 1,10,33,207.07/- along with interest being the aggregate sum of both the said guarantees. C 12. The appellant Bank filed its written statement and primarily took objection that the invocation of the bank guarantees was not in D accordance with either of the said guarantees and contrary to the terms thereof and accordingly the appellant Bank was not liable to make payment to the 1[st] respondent-plaintiff under either of the said guarantees. In support of its defence, the appellant Bank referred to the diverse correspondence exchanged between the appellant and 1[st] E respondent. In brief, the defence of the appellant Bank was that the invocation of the said bank guarantees was contrary to the terms or not in terms thereof. 13. On the pleadings of the parties, the suit in the first instance came to the dismissed vide judgment & decree dated 16[th] October, 2015 F which came to be challenged by the 1[st] respondent in appeal before the Division Bench of the High Court of Calcutta. In a concurring judgment while setting aside the judgment of the Single Judge of the High Court, it was finally held that the bank guarantees were properly invoked in law by the 1[st] respondent-plaintiff and accordingly passed a decree of Rs. 1,10,33,207.00/- together with interest at the rate of 8% G per annum on and from the date of institution of the suit until payment. 14. Learned senior counsel for the appellant Bank, Shri Amit Sibal submits that the said bank guarantees only covered losses arising out of supply of plant & equipment and according to the pleadings on record, the plant stood installed in October, 1990 and this is the case H 378 SUPREME COURT REPORTS [2019] 15 S.C.R. - A where the appellant Bank in its independent capacity, refused the claim for it being clearly false to its knowledge and also not in accordance with the terms of the guarantee, i.e. beyond the purview of the bank guarantees and failing to apportion those losses suffered on account of claims which would be within the terms of the bank guarantees. B 15. Learned counsel further submits that the bank guarantees are in reference to two category of losses (i) non-supply/defective supply of plant & equipment (ii) “other contractual deficiencies” and by the invocation vide letter dated 19[th ] December, 1998 claims caused by “nonsupply/defective supply of plant & equipment **and other contractual deficiencies** ” is outside the purview of the bank guarantee. Further, C assuming the correctness of the claim, the 1[st] respondent if suffered loss for both (i) non-supply/defective supply of plant and equipment (ii) “other contractual deficiencies”, it is difficult to determine the apportionment between the two categories, because the invocation does not state how they are apportioned. The invocation is thus inchoate D and incomplete and this according to the appellant does not constitute a valid invocation at all and it has not been properly appreciated by the Division Bench of the High Court in the impugned judgment and has to be interfered by this Court. 16. In support of his submission, learned counsel has placed reliance on the judgment of this Court in _**Hindustan Construction Co.**_ E _**Ltd. Vs. State of Bihar & Others1**_ and _**Gangotri Enterprises Ltd. 2 Vs. Union of India and Others**_ ~~.~~ 17. Per contra, Ms. Madhavi Diwan, learned ASG appearing on behalf of the 1[st] respondent, while supporting the finding recorded by the High Court in the impugned judgment submits that as per precedents F laid down by this Court, the question of law is no more res integra and is well settled that the bank guarantee is an independent contract between the bank and the beneficiary and the bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. At the same time, the dispute between the beneficiary and the G party at whose instance the bank has given the guarantee is immaterial and is of no consequence and two exceptions to the rule have been carved out. The first is when there is a fraud of which the Bank has notice and a fraud of the beneficiary from which it seeks to benefit. 1 1999(8) SCC 436 H 2 2016(11) SCC 720 STANDARD CHARTERED BANK v. HEAVY ENGINEERING 379 CORPORATION LTD. [RASTOGI, J.] The second exception to the general rule of non-intervention is such A when there is a ‘irretrievable injury’ or ‘irretrievable injustice’ that would occur to the Bank. 18. We have heard learned counsel for the parties and with their assistance perused the material available on record. 19. The law relating to invocation of bank guarantees with the consistent line of precedents of this Court is well settled and a threeJudge Bench of this Court in _**Ansal Engineering Projects Ltd. Vs. Tehri Hydro Development Corporation Ltd. and Another3**_ held thus:- **“4.** It is settled law that bank guarantee is an independent and distinct contract between the bank and the beneficiary and is not qualified by the underlying transaction and the validity of the primary contract between the person at whose instance the bank guarantee was given and the beneficiary. Unless fraud or special equity exists, is pleaded and prima facie established by strong evidence as a triable issue, the beneficiary cannot be restrained from encashing the bank guarantee even if dispute between the beneficiary and the person at whose instance the bank guarantee was given by the bank, had arisen in performance of the contract or execution of the works undertaken in furtherance thereof. The bank unconditionally and irrevocably promised to pay, on demand, the amount of liability undertaken in the guarantee without any demur or dispute in terms of the bank guarantee. The object behind is to inculcate respect for free flow of commerce and trade and faith in the commercial banking transactions unhedged by pending disputes between the beneficiary and the contractor. 5.…..The court exercising its power cannot interfere with enforcement of bank guarantee/letters of credit except only in cases where fraud or special equity is prima facie made out in the case as triable issue by strong evidence so as to prevent irretrievable injustice to the parties.” B C D E F (emphasis supplied) G 20. A bank guarantee constitutes an independent contract. In _**Hindustan Construction Co. Ltd. Vs. State of Bihar and Others**_ (supra), a two Judge Bench of this Court formulated the condition > 3 1996(5) SCC 450 H 380 SUPREME COURT REPORTS [2019] 15 S.C.R. - A upon which the invocation of the bank guarantee depends in the following terms:- **“9.** What is important, therefore, is that the bank guarantee should be in unequivocal terms, unconditional and recite that the amount would be paid without demur or objection and irrespective of any B dispute that might have cropped up or might have been pending between the beneficiary under the bank guarantee or the person on whose behalf the guarantee was furnished. The terms of the bank guarantee are, therefore, extremely material. Since the bank guarantee represents an independent contract between the bank and the beneficiary, both the parties would be bound by the terms C thereof. The invocation, therefore, will have to be in accordance with the terms of the bank guarantee, or else, the invocation itself would be bad.” ## 21. The same principle was followed in _**State Bank of India and Another Vs. Mula Sahakari Sakhar Karkhana Ltd.4**_ wherein a D two-Judge Bench held thus:- **“33.** It is beyond any cavil that a bank guarantee must be construed on its own terms. It is considered to be a separate transaction. E **34.** If a construction, as was suggested by Mr Naphade, is to be accepted, it would also be open to a banker to put forward a case that absolute and unequivocal bank guarantee should be read as a conditional one having regard to circumstances attending thereto. It is, to our mind, impermissible in law.” F 22. Taking note of the exposition of law on the subject in _**Himadri Chemicals Industries Limited Vs. Coal Tar Refining Co.5**_ ~~,~~ a twoJudge Bench of this Court in _**Gujarat Maritime Board Vs. Larsen & Toubro Infrastructure Development Projects Limited and Another6**_ has laid down the principles for grant or refusal for invocation of bank guarantee or a letter of credit. The relevant paragraph is as under:- G **“** From the discussions made hereinabove relating to the principles for grant or refusal to grant of injunction to restrain enforcement 4 2006(6) SCC 293 5 2007(8) SCC 110 H 6 2016(10) SCC 46 ## STANDARD CHARTERED BANK v. HEAVY ENGINEERING 381 CORPORATION LTD. [RASTOGI, J.] of a bank guarantee or a letter of credit, we find that the A following principles should be noted in the matter of injunction to restrain the encashment of a bank guarantee or a letter of credit: - ( _i_ ) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional bank B guarantee or letter of credit is given or accepted, the beneficiary is entitled to realise such a bank guarantee or a letter of credit in terms thereof irrespective of any pending disputes relating to the terms of the contract. - ( _ii_ ) The bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. - C - ( _iii_ ) The courts should be slow in granting an order of injunction to restrain the realisation of a bank guarantee or a letter of credit. - D - ( _iv_ ) Since a bank guarantee or a letter of credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of bank guarantees or letters of credit. - E - ( _v_ ) Fraud of an egregious nature which would vitiate the very foundation of such a bank guarantee or letter of credit and the beneficiary seeks to take advantage of the situation. - F - ( _vi_ ) Allowing encashment of an unconditional bank guarantee or a letter of credit would result in irretrievable harm or injustice to one of the parties concerned.” 23. The settled position in law that emerges from the precedents of this Court is that the bank guarantee is an independent contract between bank and the beneficiary and the bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence. There are, however, exceptions to this Rule when there is a clear case of fraud, irretrievable injustice or special equities. The G H 382 SUPREME COURT REPORTS [2019] 15 S.C.R. - A Court ordinarily should not interfere with the invocation or encashment of the bank guarantee so long as the invocation is in terms of the bank guarantee. 24. The guarantees in the instant case were unconditional, specific in nature and limited in amount. The terms of the guarantee B categorically covered money which the 1[st] respondent had advanced against supply of the plant and equipment by SCIL. The said guarantees covered any loss and damage caused to or suffered by the 1[st] respondent-plaintiff in due performance of the contract for supply of plant and equipment. The guarantee documents dated 16[th] February, 1983 and 29[th] August, 1984, as a whole and clause 2 of the guarantee C document in particular cover the advance which had been paid by the 1[st] respondent-plaintiff by reason of any breach or failure by SCIL in due performance of the aforesaid contracts i.e. against the contract for supply of plant and equipment. 25. From the correspondence that has been exchanged by and D between them pertaining to invocation of the said guarantees, it clearly manifests that the initial letter of invocation written by the 1[st] respondentplaintiff dated 6[th] November, 1998 indeed was per se inadequate and did not enumerate any condition for invocation of said guarantees save and except a reference to “a substantial amount to be recovered from E SCIL”. However, in the later correspondence exchanged between the parties dated 19[th] December, 1998 followed by a letter dated 28[th] December, 1998, 1[st] respondent informed the appellant Bank that due to defective supply of plant and equipment as well as non-supply of plant and equipment and also other contractual deficiencies of SCIL, losses had been suffered by the 1[st] respondent and it was duly informed F to the appellant Bank that the losses had been incurred both on account of supply of plant and equipment and on account of performance of the supply of plant and equipment. On reading of letters exchanged by and between 1[st] respondent and the appellant Bank pertaining to invocation of the guarantees, the condition of the guarantees had been G duly complied with. 26. In our considered view, once the demand was made in due compliance of bank guarantees, it was not open for the appellant Bank to determine as to whether the invocation of the bank guarantee was justified so long as the invocation was in terms of the bank guarantee. H The demand once made would oblige the bank to pay under the terms STANDARD CHARTERED BANK v. HEAVY ENGINEERING 383 CORPORATION LTD. [RASTOGI, J.] of the bank guarantee and it is not the case of the appellant Bank that A its defence falls in any of the exception to the rule of case of fraud, irretrievable injustice and special equities. In absence thereof, it is not even open for the Court to interfere with the invocation and encashment of the bank guarantee so long as the invocation was in terms of the bank guarantee and this what has been observed by the Division Bench B of the High Court in the impugned judgment and that reflected the correct legal position. 27. It is informed by the learned counsel for the appellant that the Standard Chartered Bank’s predecessor in interest, ANZ Grindlay’s Bank had opened a fixed deposit of Rs. 91,67,600/- on 18[th] May, 2001, C which was lien marked to HEC(Heavy Engineering Corporation Ltd.) and is being held under the control of the Registry of the High Court of Calcutta and the current fixed deposit is valued at Rs. 2,32,69,129.71/ - and the total liability under the impugned order as on date will be Rs. 2,78,03,681.64/-. The Registry of the High Court of Calcutta may release the money lying in the account in favour of the 1[st] respondent D and it is for the appellant Bank(judgment debtor) to settle and satisfy the decree which is impugned in the instant proceedings. 28. We do not find any merit in the appeal which is hereby dismissed. No costs. 29. Pending application(s), if any, stands disposed of. E Divya Pandey Appeal dismissed. F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.