This Supreme Court decision concerns a contract dispute over price adjustment for a four-lane bypass project on National Highway 26 in Madhya Pradesh. Ssangyong’s bid incorporated price adjustment for cement, steel, plant & machinery, and other local materials using a formula under sub-clause 70.3 of the contract, with base indices anchored to the all-India WPI (old series, 1993-94=100). After the Ministry stopped publishing the old series in 2010, a new WPI (2004-05=100) was published, and Ssangyong raised bills using the New Series. In 2013, the respondent NHAI issued a Circular proposing a “linking factor” to connect Old to New Series, conditioned on the contractor’s undertaking. Ssangyong rejected the Circular; disputes were referred to the Dispute Adjudicating Board, which endorsed the linking factor, despite a dissent. The arbitral tribunal’s majority award then applied the Circular and relied on guidelines not on record, prompting Ssangyong to challenge under Section 34(2)(a)(iii), (iv), and (b)(ii). The Delhi High Court and the Division Bench set aside the majority award; the Supreme Court partly allowed the appeal, preserving the minority award under Article 142 to do complete justice. The Court also clarified the post-2015 amendments narrowing “public policy” and introduced a patent illegality ground for domestic awards, applying prospectively to petitions after 23.10.2015.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- R. F. Nariman
- Vineet Saran
- Judgment Date
- 2019-05-08
- Court Decision / Holding
- The appeal is allowed in the aforesaid terms. The Delhi High Court’s and Division Bench’s judgments setting aside the majority award are reversed. The minority award, along with interest, is upheld and to be executed between the parties. The Tribunal’s formula under the minority award is accepted, with the principal sum of INR 2,01,42,827 for price adjustment from Sep 2010 to May 2014, interest at 10% per annum compounded monthly, and further interest at 12% per annum simple thereafter until payment. Costs: none. The decision also clarifies the applicability of the Arbitration and Conciliation (Amendment) Act, 2015, and narrows the scope of “public policy of India.”
- Final Disposition
- Appeal allowed; minority award upheld; majority award and High Court orders set aside; complete justice via Article 142; payment of price adjustment with interest as specified.
Parties to the Case
Appellants / Petitioners
- Ssangyong Engineering & Construction Co. Ltd.
Respondents
- National Highways Authority of India (NHAI)
Legal Representation & Advocates
Counsels for Petitioners
- • Mukul Rohatgi
- • Navin Kumar
- • Rashmeet Kaur
- • Arpana Majumdar
- • Ashwani Kumar
Counsels for Respondents
- • S. Nandakumar
- • Deepika Nandakumar
- • P. Palanivelu
- • M. S. Saran Kumar
- • Naresh Kumar
Provisions of Law Cited
Legal Doctrines & Maxims
- Judicial approach
- Audi alteram partem
- Wednesbury principle of reasonableness
- Most basic notions of morality or justice
- Fundamental policy of Indian law
- Severability of awards under Article V(1)(c) for partial recognition
- Patently illegal ground (patent illegality)
- Perverse or irrational findings as a ground for patent illegality
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant ( Ssangyong ) argued that the majority award’s reliance on a unilateral Circular dated 15.02.2013 to introduce a linking factor between the Old and New WPI series was not anchored in the contract and was therefore an excess of jurisdiction under s.34(2)(a)(iv). It violated natural justice since necessary guidelines were not on record, and Ssangyong had offered only a conditional undertaking that could not bind without Ssangyong’s consent, contradicting the contract’s terms. The Circular’s adoption amounted to a novation by the arbitrators, breaching the “most basic notions of justice” and fundamental policy of Indian law. The 2015 amendments (notably s.34(2A) patent illegality and narrowing of “public policy”) apply to petitions filed after 23.10.2015, limiting court intervention. The appellant urged upholding the minority award (which followed the contract terms) and invoking Art. 142 to achieve complete justice. The appellant also highlighted that the linking factor should be de hors the contract and argued against retrospective application of clarifications; natural justice and reasonableness require that evidence relied on must be disclosed and that the tribunal’s decision be within the terms of reference.
Contentions of Respondents
NHAI argued that the linking factor was a contractual necessity to ensure comparability between indices after the old-series base year ceased, and that the arbitration tribunal’s interpretation was within the scope of the contract. The majority award applied a reasonable construction of the contract’s price-adjustment clause and used government guidelines that supported linking the indices; the court’s role is not to re-weigh evidence but to test for arbitral excess of jurisdiction or violation of natural justice. The respondents contended that the 2015 Amendment Act applies to petitions after 23.10.2015 and narrows the public-policy ground, but natural justice safeguards (ss.18, 24(3), 26) remain intact while s.34(2)(a)(iii) and (ii) confirm the tribunal’s jurisdiction. They sought dismissal of the appeal and upholding the majority award.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (16)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Board of Control for Cricket in India v. Kochi Cricket (P.) Ltd. and Ors. | (2018) 6 SCC 287; [2018] 2 SCR 829 | Positive | Held that Amendment Act, 2015 applies to Section 34 petitions filed after 23.10.2015; supports narrowing test for public policy in domestic awards. |
| Sedco Forex International Drill, Inc. v. Commissioner of Income Tax, Dehradun and Anr. | (2005) 12 SCC 717 | Positive | Explained that clarifications of amendments cannot be retrospective if substantive changes are made. |
| Renusagar Power Co. Ltd. v. General Electric Co. | (1994) Supp (1) SCC 644 | Positive | Established the traditional public policy grounds for setting aside foreign awards. |
| Associate Builders v. Delhi Development Authority | (2015) 3 SCC 49 | Positive | Described fundamental policy of Indian law and most basic notions of justice; informs narrowing of public-policy scope. |
| ONGC Ltd. v. Western Geco International Ltd. | (2014) 9 SCC 263 | Overruled | Expansion of public policy scope reversed by 2015 amendments; Western Geco’s broader test is done away with. |
| ONGC Ltd. v. Saw Pipes Ltd. | (2003) 5 SCC 705 | Overruled | Earlier expansion of public policy broadened test now curtailed by amendment. |
| Parsons & Whittemore Overseas Co., Inc. v. Societe Generale De L’industrie Du Papier (RAKTA) | 508 F.2d 969 (2d Cir. 1974) | Positive | Support for narrow review of merits; limits on review of arbitral decisions in enforcement. |
| P. R. Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd. | (2012) 1 SCC 594 | Positive | Illustrates limitations on reappreciation of evidence when challenging awards. |
| CRW Joint Operation v. PT Perusahaan Gas Negara (Persero) TBK | [2011] SGCA 33 | Positive | Cited to illustrate limits on public-policy defenses in cross-border enforcement. |
| Pilliod v. Econosto | (2006) Rev arb 687 | Positive | Used to discuss ultra petita/overreach concerns and the arbitral tribunal’s mandate. |
| Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd | [2007] 3 SLR(R) 86 | Positive | Illustrates Singaporean perspective on inquiry into whether proceedings comply with due process. |
| Dexia Bank v PT Asuransi Jasa Indonesia (Persero) | (2007) 1 SLR(R) 597 | Positive | Used to discuss the role of due process and public policy in international arbitration. |
| Delargy v Hickey | [2015] IEHC 436 | Positive | Irish precedent on challenge to arbitration awards for excess of jurisdiction and due process. |
| Snoddy v. Mavroudis | [2013] IEHC 285 | Positive | Established presumption that tribunal acts within its mandate; grounds to challenge must be shown. |
| O’Leary Lissarda v. Ryan | [2015] IEHC 820 | Positive | Reinforces that set-aside is not an appeal on merits. |
| State of Goa v. Praveen Enterprises | (2012) 12 SCC 581 | Positive | Defines the concept of reference to arbitration and scope of submissions. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India (NHAI)
Related Decisions & Precedents from Supreme Court of India (2019)
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.
STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.
This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.
PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.
Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).
RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.
Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.