SRIDEVI DATLA v. UNION OF INDIA AND ORS.

Case / Petition Number:
Civil Appeal No. 3136 of 2020
Neutral Citation:[2021] 13 SCR 282

Case Synopsis & Summary

Sridevi Datla challenged the National Green Tribunal’s environmental clearance for a Greenfield airport project at Bhogapuram, Visakhapatnam. The appeal, filed under Section 22 of the National Green Tribunal Act, contended that the NGT erred in not condoning a delay in filing the appeal and that the general principles of computation of time and limitation under Central Acts apply to NGT proceedings. The Court examined whether the Limitation Act's timeline is applicable or whether the special period in the NGT Act should govern, and whether Section 10 of the General Clauses Act can be invoked proprio vigore to extend the filing period when the last date fell on a Sunday. It held that when a special law provides its own limitation regime with a defined window for appeals, the Limitation Act does not apply, but Section 10 GC Act can be applied to provide an extension in computing time. The judgment emphasizes that “sufficient cause” is a flexible, fact-specific concept to be applied liberally, particularly in environmental matters that require expert scrutiny and documentation. The Court ultimately set aside the NGT’s order, condoned the delay, and allowed the appeal to proceed to merits, underscoring the Tribunal’s need for expert, cautious adjudication in environmental disputes.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • L. Nageswara Rao
  • S. Ravindra Bhat
Judgment Date
2021-03-02
Court Decision / Holding
Appeal allowed. The delay is condoned; the NGT order is set aside, and the matter shall proceed on its merits before the NGT in accordance with law. There shall be no order on costs.
Final Disposition
Appeal allowed.

Parties to the Case

Appellants / Petitioners

  • Sridevi Datla

Respondents

  • Union of India and Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Anitha Shenoy
  • • Mr. Atmaram Nadkarni

Counsels for Respondents

  • • K. M. Natrajan, ASG
  • • Mr. Mukul Rohatgi, Sr. Adv.

Provisions of Law Cited

Limitation Act, 1963National Green Tribunal Act, 2010General Clauses ActEnvironment (Protection) Act, 1986Environment Impact Assessment Notification, 2006Water (Prevention and Control of Pollution) Act, 1974Water (Prevention and Control of Pollution) Cess Act, 1977Forest (Conservation) Act, 1980Air (Prevention and Control of Pollution) Act, 1981Biological Diversity Act, 2002National Green Tribunal Act, 2010 – Section 16National Green Tribunal Act, 2010 – proviso to Section 16 (60 days extension)Section 10 of the General Clauses ActSection 19 of the NGT ActSection 28/29/31/33A/33 of various Acts referenced (Water/CAC/Forest/Air)Environment (Protection) Act, 1986 – EIA Notification 2006

Legal Doctrines & Maxims

  • Sufficient cause is to be construed liberally to advance substantial justice
  • Bona fides and absence of negligence are essential for condonation of delay
  • Discretion to condone delay is case-specific and not governed by a rigid formula
  • NGT combines judicial and expert elements; environmental decisions require specialized analysis
  • Public interest and sustainable development guide environmental adjudication

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that the limitation period under the NGT Act has to be interpreted in light of Section 10 of the General Clauses Act, and that condonation of delay is permissible for the purpose of advancing substantial justice, especially where the environment involves voluminous documentation and technical analysis. The appeal, though filed after a delay, falls within the extended 60-day window when the first 30 days expire; the last day fell on a Sunday, and Section 10 should apply proprio vigore to extend time. The appellant urged that the NGT’s refusal to condone delay was erroneous given the need for expert assistance and the large amount of documentation involved in environmental clearances.

Contentions of Respondents

The Union argued that the 30-day limit (with an optional 60-day extension) provides a strict regime, and the NGT’s refusal to condone delay was correct since the period ended within 90 days. It was stressed that Section 10 GC Act cannot ordinarily be read to override the NGT Act’s time limits, and the Environment Clearance process was properly communicated via official channels. The respondents cited that Section 33 of the NGT Act overrides other laws and that condonation is not a matter of right, particularly where the applicant was not diligent.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (20)

Case NameCitationTreatmentExplanation
H. H. Raja Harinder Singh v. S. Karnail Singh[1957] SCR 208PositiveFollowed as an authoritative principle on liberal construction of 'sufficient cause' and limitation in special laws.
G. Ramegowda v. Land Acquisition Officer(1988) 2 SCC 142PositiveCited for liberal, fact-specific approach to condonation of delays.
Esha Bhattacharjee v. Raghunathpur Nafar Academy(2013) 12 SCC 649PositiveUsed to illustrate that there is no universal formula for 'sufficient cause' and a flexible approach is needed.
Hanuman Laxman Aroskar v. Union of India(2019) 15 SCC 401PositiveRecognized NGT’s need to consider issues with expert/sustainable development lens.
Union of India v. Popular Construction Co.(2001) 8 SCC 470PositiveSupports position that Limitation Act may be inapplicable to certain special-law contexts.
Padmabati Mohapatra v. Union of India(2013) SCC OnLine NGT 2177Mentioned OnlyCited in discussion; not central to the decision on condonation here.
Rambir Narhargir Gosai v. Prabhakar Bhaskar GadhawayAIR 1955 Nag 300Mentioned OnlyCited as supportive precedent in related contexts.
Jitendra Singh v. Ministry of Environment & Others(2019) SCC OnLine SC 1510Mentioned OnlyCited in context of environmental-law principles but not central to the ruling.
H. Dohil Construction Company Private Limited v. Nahar Exports Limited(2015) 1 SCC 680PositiveUsed to illustrate that aggrieved parties require consideration and expert support; condonation cannot be a right.
BRS Steels Private Limited v. State of Rajasthan(2012) 6 SCC 782Mentioned OnlyCited among authorities on related principles.
Kaushalya Rani v Gopal Singh[1964] 4 SCR 982Mentioned OnlyListed in references but not central to the conclusion.
Collector of Excise & Customs v. Hongo India (P) Ltd.(2009) 5 SCC 791Mentioned OnlyCited as part of the compendium of related law.
State of Nagaland v. Lipok Ao(2005) 3 SCC 752PositiveUsed in discussing environmental-law principles and timing considerations.
New India Insurance Co. Ltd. v. Shanti Misra(1975) 2 SCC 840PositiveCited in the broader discussion of law on delays and claims.
N. Balakrishnan v. M. Krishnamurthy(1998) 7 SCC 23PositiveUsed to illustrate principles of limitation and condonation.
State of Haryana v. Chandra Mani(1996) 3 SCC 132PositiveCited in discussing the fitness of liberal condonation standards.
Tehsildar (LA) v. K.V. Ayisumma(1996) 10 SCC 634PositiveReferenced for time-computation principles.
Improvement Trust v. Ujagar Singh(2010) 6 SCC 786PositiveCited regarding flexibility in delays.
Maniben Devraj Shah v. Municipal Corpn. of Brihan Mumbai(2012) 5 SCC 157PositiveDiscussed in context of balancing delay and prejudice to opposite party.
Hanuman Laxman Aroskar v. Union of India(2019) 15 SCC 401PositiveRepeated above; clarifies NGT’s consultation with sustainability principles.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,806 words•~31 min read

In The Court Record

SRIDEVI DATLA v. UNION OF INDIA AND ORS.

282 SUPREME COURT REPORTS[2021] 13 S.C.R.282 [2021] 13 S.C.R. A ## SRIDEVI DATLA v. ## UNION OF INDIA AND ORS. B (Civil Appeal No. 3136 of 2020) MARCH 02, 2021 ## **[L. NAGESWARA RAO AND S. RAVINDRA BHAT, JJ.]** _Limitation Act, 1963: Applicability to Special laws – Held: Where period of limitation are prescribed under special laws, appeals that exceed the period granted in the special laws can be_ C _entertained at the discretion of the tribunal and Limitation act would not apply – National Green Tribunal Act, 2010._ _General Clauses Act – Applicability of, to appeals filed under the NGT Act – Held: s.10 of General Clauses Act stipulates when the last date for doing something falls on a public holiday, the act shall be considered as done, if it is done or taken on the next day_ D _afterwards on which the Court or office is open – This provision applies to all Central Acts enacted after the said Act was brought into force – Therefore, s.10 applies proprio vigore to all appeals filed under the NGT Act – National Green Tribunal Act, 2010._ - _National Green Tribunal Act, 2010: s.16 – Approach of the_ - E _Court in considering the application for condonation of delay – The term ‘sufficient cause’ is relative, fact dependant, and has many hues, largely deriving colour from the facts of each case, and the behaviour of the litigant who seeks condonation of delay (in approaching the court) – Appellant pleaded that since the_ - F _documentation attendant to the clearance granted to the Project Applicant was voluminous, and expert as well as professional legal advice of the kind necessary to approach the NGT was not available in the State of Andhra Pradesh, the procuring of relevant documents, and correspondence with counsel in Delhi and drafting of the appeal entailed some delay – In approaching NGT, scientific or technical_ - G _support is necessary apart from expert professional legal advice – Rejection of appeal by dismissing application for condonation of delay, on the ground that no sufficient cause was shown, was erroneous discretion of NGT – An appeal to the NGT in such matters is no ordinary matter – The delay in filing the appeal before the_ - H _NGT is condoned._ 282 283 SRIDEVI DATLA v. UNION OF INDIA AND ORS. ## **Allowing the appeal, the Court** **HELD: 1. There can be no dispute that the period of limitation set out in a special law, which provides for remedies and appeals, has to be construed in its terms and without reference to the Limitation Act, if it contains specific provisions delineating the time or period within which applications or appeals can be preferred, and confines the consideration of applications for condoning the delay to a specific number of days. Undoubtedly, in such cases, the Limitation Act would be inapplicable. There are several previous judgments of this court holding that where periods of limitation are prescribed under special laws, appeals that exceed the period granted and are within the extended period of limitation in the special law, can be entertained at the discretion of the tribunal, or court concerned and the Limitation Act would not apply upon expiry of such extended period. This court held that there is merit in the contention of the Union that the provisions of the Limitation Act are inapplicable. [Para 18][293F-G; 294-A-B]** **2. The appellant argues that the appeal is to be considered as having been filed within the extended period of 60 days, since the last (of the 60 days) was a Sunday (12.07.2020). The appellant relied on Section 10 of the General Clauses Act, for this purpose. Section 10 of the General Clauses Act, 1897 stipulates that when the last date for doing something falls on a public holiday, the act** _**“shall be considered as done..”**_ **if it** _**“is done or taken on the next day afterwards on which the Court or office is open”.**_ **This provision applies to all Central Acts enacted** _**after**_ **the said Act was brought into force. It is also noticeable that there is no indication in the NGT Act that Section 10 of the General Clauses Act cannot be applied. It is therefore, held that the provision applies** _**proprio vigore**_ **to all appeals filed under the NGT Act. [Paras 19, 20, 21][294-C-E; 295-A, C-D]** _H.H Raja Harinder Singh v. S. Karnail Singh_ **[1957] SCR 208** _**–**_ **followed.** A B C D E F G **3. It is evident that the term** _**sufficient cause**_ **is relative, fact dependant, and has many hues, largely deriving colour from the facts of each case, and the behaviour of the litigant who seeks condonation of delay (in approaching the court). However, what** H 284 SUPREME COURT REPORTS [2021] 13 S.C.R. - A **can broadly be said to be universally accepted is that in principle, the applicant must display** _**bona fides,**_ **should not have been negligent, and the delay occasioned should not be such that condoning it would seriously prejudice the other party. Keeping these principles in mind, it is relevant to consider whether the NGT’s refusal to exercise discretion, in the facts and** - B **circumstances of this case, was erroneous. The court is conscious of the fact that exercise of discretion,** _**per se,**_ **is a fact dependent one, and considerable latitude should be given to the court or tribunal of the first instance, in the performance of that task. Nevertheless, as decided, cases and judgments have shown that** - C **the exercise of discretion does at times, call for appellate scrutiny by this court. This is one such. The appellant pleaded that since the documentation attendant to the clearance granted to the Project Applicant was voluminous, and expert as well as professional legal advice of the kind necessary to approach the NGT was not available in the State of Andhra Pradesh, the** - D **procuring of relevant documents, and correspondence with counsel in Delhi and drafting of the appeal entailed some delay. This court is of the opinion that there is merit in appellant argument. [Paras 27 and 28][297-F-H; 298-A-B]** _Smt. Padmabati Mohapatra v. Union of India_ **(2013)** E **SCC OnLine NGT 2177;** _Rambir Narhargir Gosai v. Prabhakar Bhaskar Gadhaway_ **AIR 1955 Nag 300;** _Save Mon Region Federation v. Union of India_ **(2013) SCC OnLine NGT 2511;** _H. Dohil Construction Company Private Limited v. Nahar Exports Limited_ F **(2015) 1 SCC 680 : [2014] 8 SCR 424;** _BRS Steels Private Limited v. State of Rajasthan_ **(2012) 6 SCC 782 : [2012] 5 SCR 583;** _Jitendra Singh v. Ministry of Environment & Others_ **(2019) SCC OnLine SC 1510;** _Hanuman Laxman Aroskar v. Union of India_ **(2019) 15 SCC 401 : [2019] 5 SCR 916;** _Kaushalya Rani v Gopal_ G _Singh_ **[1964] 4 SCR 982;** _Collector of Excise & Customs v. Hongo India (P) Ltd._ **(2009) 5 SCC 791 : [2009] 4 SCR 1197;** _Union of India v. Popular Construction Co._ **(2001) 8 SCC 470 : [2001] 3 Suppl. SCR 619;** _Patel Bros. v. State of Assam_ **(2017) 2 SCC 350 : [2017] 1** H **SCR 95;** _H.H. Raja Harinder Singh v. S. Karnail Singh_ - H 285 SRIDEVI DATLA v. UNION OF INDIA AND ORS. **[1957] SCR 208;** _Manohar Joshi v. Nitin Bhaurao Patil_ **(1996) 1 SCC 169 : [1995] 6 Suppl. SCR 421;** _Mohd. Ayub v. State of U.P._ **(2009) 17 SCC 70 : [2009] 15 SCR 1095** _**;** G. Ramegowda_ v. _Land Acquisition Officer_ **(1988) 2 SCC 142 : [1988] 3 SCR 198;** _Esha Bhattacharjee v. Raghunathpur Nafar Academy_ **(2013) 12 SCC 649 : [2013] 9 SCR 782;** _State of Nagaland_ v. _Lipok Ao_ **(2005) 3 SCC 752 : [2005] 3 SCR 108;** _New India Insurance Co. Ltd._ v. _Shanti Misra_ **(1975) 2 SCC 840 : [1976] 2 SCR 266;** _N. Balakrishnan_ v. _M. Krishnamurthy_ **(1998) 7 SCC 23 : [1998] Suppl. SCR 403;** _State of Haryana_ v. _Chandra Mani_ **(1996) 3 SCC 132 : [1996] 1 SCR 1060;** _Tehsildar (LA)_ v. _K.V. Ayisumma_ **(1996) 10 SCC 634;** _Improvement Trust_ v. _Ujagar Singh_ **(2010) 6 SCC 786: [2010] 7 SCR 376;** _Maniben Devraj Shah v. Municipal Corpn. of Brihan Mumbai_ **(2012) 5 SCC 157 – referred to.** A B C D ## **Case Law Reference** ||**Case**|**Law Reference**||| |---|---|---|---|---| |**[2014]**|**8 SCR 424**|**referred to**|**Para 11**|| |**[2012]**|**5 SCR 583**|**referred to**|**Para 11**|| |||||E| |**[2019]**|**5 SCR 916**|**referred to**|**Para 15**|| |**[1964]**|**4 SCR 982**|**referred to**|**Para 18**|| |**[2009]**|**4 SCR 1197**|**referred to**|**Para 18**|| |**[2001]**|**3 Suppl. SCR 619**|**referred to**|**Para 18**|F| |**[2017]**|**1 SCR 95**|**referred to**|**Para 18**|| |**[1957]**|**SCR 208**|**followed**|**Para 20**|| |**[1995]**|**6 Suppl. SCR 421**|**referred to**|**Para 21**|| |**[2009]**|**15 SCR 1095**|**referred to**|**Para 22**|G| |**[1988]**|**3 SCR 198**|**referred to**|**Para 22**|| |**[2013]**|**9 SCR 782**|**referred to**|**Para 24**|| |**[2005]**|**3 SCR 108**|**referred to**|**Para 24**|| |**[1976]**|**2 SCR 266**|**referred to**|**Para 24**|H| 286 SUPREME COURT REPORTS [2021] 13 S.C.R. |A|**[1998]**|**Suppl. SCR 403**|**referred to**|**Para 24**| |---|---|---|---|---| ||**[1996]**|**1 SCR 1060**|**referred to**|**Para 24**| ||**(1996)**|**10 SCC 634**|**referred to**|**Para 24**| ||**[2010]**|**7 SCR 376**|**referred to**|**Para 24**| |B|**(2012)**|**5 SCC 157**|**referred to**|**Para 26**| CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3136 of 2020. From the Judgment and Order dated 31.07.2020 of the National Green Tribunal, Southern Zone Bench at Chennai in M.A. No. 231 of C 2017 in Appeal Nos. 18 of 2020 (SZ). K. M. Natrajan, ASG, Ms. Anitha Shenoy, Atmaram Nadkarni, Mukul Rohatgi, Sr. Adv., Ms. Srishti Agnihotri, Ms. Kanika Sood, Ms. Sanjana Grace Thomas, Ms. Anmol Gupta, Gurmeet Singh Makker, Kanu Agrawal, Vatsal Joshi, Arup Banerjee, Varun Verma, Mahesh D Agarwal, M. S. Ananth, Anirudh Bhatia, E. C. Agrawala, Advs. for the appearing parties. The Judgment of the Court was delivered by ## **S. RAVINDRA BHAT, J.** E 1. The appellant is aggrieved by an order of the National Green Tribunal (hereafter referred to as “the NGT”[1] ) and has, therefore, approached this Court under Section 22 of the NGT Act. The NGT rejected her appeal, preferred to it against the environmental clearance for construction of the Greenfield International Airport, Bhogapuram, F Vishakapatnam, which had been sought for by the fifth respondent. 2. The facts are simple: the fifth respondent (hereafter called “the Project Applicant”) proposed the construction of a new Greenfield international airport. As was required by law and extant statutory notifications, it applied to the Ministry of Environment, Forests and G Climate Change (hereinafter, the “MoEF”) to seek environmental clearance. The MoEF, after following the prescribed procedure, which included ascertaining the views and objections of the concerned parties, the general public etc, indicated its approval by an order dated 14.08.2017. In terms of Section 19 of the NGT Act, the approval was posted on the - H 1 Dated 31.07.2020 287 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] website of the MoEF on 14.08.2017. Concededly, the Project Applicant A published the approval in an English daily on 13.09.2017. 3. The appellant preferred her appeal to the NGT on 13.11.2017. Along with the appeal, she preferred an application for condonation of delay in approaching the NGT, given the stipulation of Section 19 that the appeal had to be preferred within 30 days from the date of communication of the order impugned. She explained that since the clearance and related documents were voluminous and the matter required some technical expertise, requiring the papers to be forwarded to experts and lawyers in Delhi, and the _inter se_ communication delay, the NGT needed to condone the delay, in the interests of justice. After considering the submissions made by the appellant as well as the Project Applicant, which opposed the application for condonation of delay, the NGT, by its impugned order, rejected the appellant’s application and consequently the appeal as well. 4. The appellant’s arguments before this Court are mainly twofold: that the requirement of Section 16 is to _“communicate the order to the concerned parties as well as the public and that a meaningful interpretation should be given to the provision”_ . It was emphasised in this context that communication means not merely the publication on the Central Government’s website, but also dissemination of the news or the decision to the affected parties. Learned senior counsel for the appellant – Ms. Anitha Shenoy, in this context, relied upon the terms contained in the environmental clearance/approval given by the MoEF, especially those which obliged the Project Applicant to intimate the decision in dailies having local circulation in the vernacular. She also relied upon the stipulations in the environmental clearance (“EC”) which prescribed that the successful project applicant had to, in continuation to so publishing the decision or intimation in local newspapers, also ensure that the decision was forwarded to local communities through the Panchayats etc. for dissemination. 5. It was pointed out that the object of these conditions should be construed as part of a larger scheme of the Act to communicate every decision. The appellant argued that if a contrary interpretation were to be accepted, the appeal given by the statute would be meaningless as most often, large projects which involve either displacement of people or which affect habitats and have the tendency to damage or at least cause significant adverse impact upon the environment would not be B C D E F G H 288 SUPREME COURT REPORTS [2021] 13 S.C.R. - A considered on its merits by the NGT since people and neighbourhoods cannot be presumed to have knowledge of deliberations in New Delhi. 6. It was also argued on behalf of the appellant that in the circumstances of the present case, at least the appeal could not be said to be time barred. It was argued that the date for reckoning (limitation) B is from 14.08.2017, when the MoEF uploaded the decision on its website. The ninety-day period within which appeal was to be filed, expired on 12.11.2017, which was a Sunday. It was submitted that under Section 10 of the General Clauses Act, if any period prescribed ends on a Sunday or a day on which the Court or the Tribunal does not function, the next day should be considered as the _terminus quo_ in point of time. C Consequently, it was submitted that the appeal should be considered as within time and should have been entertained on merits. 7. Lastly, it was argued that the NGT’s opinion that sufficient cause was not shown while seeking condonation of delay is erroneous. Learned counsel highlighted that any proposal as well as clearances D where voluminous documentation is involved, or if any individual or entity is aggrieved, or adversely affected, the only remedy provided is by way of an appeal. To substantiate the grounds of appeal, it would be essential that in many instances, expert advice is obtained based on which the grounds of appeal can be prepared and urged. If the issue were to be E considered in this perspective, the explanation provided by the appellant in her application seeking condonation of delay could not be considered unreasonable and in fact amounts to sufficient cause. Learned counsel relied upon a previous order of the NGT in _Smt. Padmabati Mohapatra v. Union of India[2]_ . Reliance was also placed on the judgment of the Nagpur High Court, reported as _Rambir Narhargir Gosai v. Prabhakar_ F _Bhaskar Gadhaway.[3]_ 8. On behalf of the Union of India, the ASG, Mr. K.M. Natraj argued that the impugned order does not require to be disturbed. He pointed out that the impugned order had noticed that the appellant made no complaint that the MoEF had put up the decision to grant environmental G clearance on its website on 14.08.2017 or that having uploaded the decision it could not be viewed publicly in an uninterrupted manner. He further submitted that the finding that the first date when the decision was communicated by the MoEF on its website is determinative for the 2 2013 SCC OnLine NGT 2177 - H 3 AIR 1955 Nag 300 289 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] purpose of reckoning limitation rather than any other later point in time. A It was further emphasised on behalf of the UOI that the need to publish environmental clearances under the Environment Impact Notification 2006, framed under the Environment Protection Act, 1986 is now known to all. The proposal of the Project Applicant clearly fell within the sweep of the Environment Impact Notification in Item No.7(a) to the Schedule B (to the notification). 9. It was submitted on behalf of the UOI that in terms of the Environment Impact Assessment Notification, 2006, the clearance had to be published within seven days from the date of uploading. The publication of Environment Clearance dated 14.08.2017 was done on 21.08.2017. Thus, the appellant’s plea that she came to know of the environmental clearance on 24.08.2017 is baseless. The learned ASG relied upon a decision of the NGT in _Save Mon Region Federation v. Union of India[4]_ in this regard. 10. Learned ASG lastly argued that by virtue of Section 33 of the Act, the provisions of all other laws stand overridden and consequently, the question of extending the period of limitation by reference to Section 5 of the Limitation Act would not arise. He further urged that the period of limitation prescribed is actually 30 days for the filing of an appeal, and that further period of 60 days is only by way of acceptance of application for condonation of delay. Thus, no appeal is maintainable after the expiry of 90 days. It is pointed out that in the present case, the 90 day period in fact ended a day prior to the filing of the appeal; it was, therefore, clearly time-barred. C D E 11. Mr. Mukul Rohatgi, learned senior counsel appearing for the Project Applicant supported the submissions of the Union and argued F that the concerned Project Applicant, i.e. M/s Bhogapuram International Airport Corporation Ltd., has been conceived in public interest and in replacement of the existing Vishakhapatnam Airport which is primarily a defence airport. Learned counsel relied upon the decision of this Court in _H. Dohil Construction Company Private Limited v. Nahar Exports Limited[5]_ to the effect that any aggrieved litigant should be vigilant in the G exercise of his rights and that he cannot claim the exercise of discretion for condoning any delay as a matter of right. Reliance was also placed upon the decision in _BRS Steels Private Limited v. State of Rajasthan[6]_ . > 4 2013 SCC OnLine NGT 2511 5 (2015) 1SCC 680 6 (2012) 6 SCC 782 H 290 SUPREME COURT REPORTS [2021] 13 S.C.R. - A In this regard, it was submitted that the appeal before this Court which purports to be under Section 22 of the Act is confined to the grounds specified under Section 100 of the CPC, which is only if the Court is satisfied that the case involves a substantial question of law. 12. Lastly, it was submitted by learned senior counsel that the B NGT Act correctly surmised in the circumstances of the case that the appellant had adopted a casual approach and did not believe the contents of the application for condonation of delay. Learned counsel in this context argued that the appellant is an interested person in the sense that her lands had been notified for acquisition and was therefore not uninformed or incapable of receiving appropriate legal advice. - C ## _**Analysis and Findings**_ 13. The relevant provision of the Act, i.e. Section 16[7] reads as follows: - _“16. Tribunal to have appellate jurisdiction. -Any person_ - D _aggrieved by,-_ - _(a) an order or decision, made, on or after the commencement of the National Green Tribunal Act, 2010, by the appellate authority under section 28 of the Water (Prevention and Control of Pollution) Act, 1974 (6 of 1974);_ - E _(b) an order passed, on or after the commencement of the National Green Tribunal Act, 2010, by the State Government under section 29 of the Water (Prevention and Control of Pollution) Act, 1974 (6 of 1974);_ - _(c) directions issued, on or after the commencement of the_ - F _National Green Tribunal Act, 2010, by a Board, under section 33A of the Water (Prevention and Control of Pollution) Act, 1974 (6 of 1974);_ - _(d) an order or decision made, on or after the commencement of the National Green Tribunal Act, 2010, by the appellate_ - G _authority under section 13 of the Water (Prevention and Control of Pollution) Cess Act, 1977 (36 of 1977);_ - _(e) an order or decision made, on or after the commencement of the National Green Tribunal Act, 2010, by the State_ - H 7 Of the NGT Act 291 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] _Government or other authority under section 2 of the Forest_ A _(Conservation) Act, 1980 (69 of 1980);_ _(f) an order or decision, made, on or after the commencement of the National Green Tribunal Act, 2010, by the Appellate Authority under section 31 of the Air (Prevention and Control of Pollution) Act, 1981 (14 of 1981);_ B _(g) any direction issued, on or after the commencement of the National Green Tribunal Act, 2010, under section 5 of the Environment (Protection) Act, 1986 (29 of 1986);_ _(h) an order made, on or after the commencement of the National Green Tribunal Act, 2010, granting environmental clearance in the area in which any industries, operations or processes or class of industries, operations and processes shall not be carried out or shall be carried out subject to certain safeguards under the Environment (Protection) Act, 1986 (29 of 1986);_ _(i) an order made, on or after the commencement of the National Green Tribunal Act, 2010, refusing to grant environmental clearance for carrying out any activity or operation or process under the Environment (Protection) Act, 1986 (29 of 1986);_ _(j) any determination of benefit sharing or order made, on or after the commencement of the National Green Tribunal Act, 2010, by the National Biodiversity Authority or a State Biodiversity Board under the provisions of the Biological Diversity Act, 2002 (18 of 2003), may, within a period of thirty days from the date on which the order or decision or direction or determination is communicated to him, prefer an appeal to the Tribunal;_ _Provided that the Tribunal may, if it is satisfied that the appellant was prevented by sufficient cause from filing the appeal within the said period, allow it to be filed under this section within a further period not exceeding sixty days.”_ C D E F G 14. Environmental disputes are complicated and entail expertise in diverse fields (such as ecology, chemistry, biology, economics, administration, management, law etc.) for their determination in an H 292 SUPREME COURT REPORTS [2021] 13 S.C.R. - A effective and speedy fashion, that is not possible within the regular judicial and administrative set up in India. In other words, environmental disputes relating to forests, biodiversity, air and water are complicated in nature; resolving and expeditiously disposing of these cases is not possible without a separate special court. Environmental courts or tribunals have been a long-standing demand for other reasons too. For effective prevention - B and control of environmental protection, there was an urgent need for a separate environmental court or tribunal to adjudicate without much delay. India is a party to the United Nations Conference on the Human Environment (known as the Stockholm Conference), 1972 where it made commitments relating to safeguarding of natural resources and developing - C international law, and to provide compensation to victims of pollution and other environmental degradation. India is also a signatory to the Rio Declaration adopted at the United Nations Conference on Environment and Development at Rio de Janeiro in 1992. The Rio Declaration states that participating states must make suitable environmental legislation regarding effective access to the people, to judicial and administrative - D proceedings, including remedies. The Law Commission’s 186[th] report recommended that the Union government should establish and constitute separate Environmental Courts in each state, to deal with complex, specialised issues concerning the environment. It was in this background that Parliament enacted the NGT Act. The Act amends various other - E enactments and adds provisions to them, for appeal before the NGT. These are incorporated in Section 33-B of The Water (Prevention and Control of Pollution) Act, 1974; Section 13-A of The Water (Prevention and Control of Pollution) Cess Act, 1977; Section 2-A of The Forest (Conservation) Act, 1980; Section 31-B of The Air (Prevention and Control of Pollution) Act, 1981; Section 5-A in the Environment - F (Protection) Act, 1986 and Section 52-A in the Biological Diversity Act, 2002. 15. In _Jitendra Singh v. Ministry of Environment & Others[8]_ the narrow, but important question considered was whether a state could alienate publicly available resources like ponds. This court held that that G such transfer or alienation was impermissible. In _Hanuman Laxman Aroskar v. Union of India[9]_ this court held that the NGT is under an obligation to consider issues as an expert body, and apply the principle of sustainable development, in adjudicating environmental issues, especially - 8 2019 SCC OnLine SC 1510 - H 9 (2019) 15 SCC 401 293 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] while considering the validity of grant of clearance to large projects A under the Environment Protection Act. It was held that the NGT Act: _“provides for the constitution of a tribunal consisting both of judicial and expert members. The mix of judicial and technical members envisaged by the statute is for the reason that the Tribunal is called upon to consider questions which involve_ B _the application and assessment of science and its interface with the environment.”_ 16. The court noted that to be a member of the NGT, the individual had to possess specified academic qualifications, including a master’s degree in science with a doctorate in engineering or technology, with prescribed experience in certain domains. To be an administrative member, the individual should possess fifteen years’ administrative experience including experience of five years in dealing with environmental matters in the Central or State Government or in a reputed national or state level institution. The court proceeded to hold in _Hanuman Laxman Aroskar (supra),_ that the grant of environmental clearance to a greenfield airport in Goa did not receive proper merits review by the NGT. 17. Having regard to these decisions, and given the nature of jurisdiction which the NGT has been invested with, the substantial questions of law that arise in the present case, are whether the approach to the issue of limitation by the NGT was correct, and whether on a correct interpretation of law, the appeal under Section 16 was filed within the 90 days period, in the facts of this case. C D E ## _**Applicability of General Clauses Act**_ F 18. There can be no dispute that the period of limitation set out in a special law, which provides for remedies and appeals, has to be construed in its terms and without reference to the Limitation Act, if it contains specific provisions delineating the time or period within which applications or appeals can be preferred, and confines the consideration of applications for condoning the delay to a specific number of days. Undoubtedly, in such cases, the Limitation Act would be inapplicable.[10] G > 10 That provision is as follows: > _**29. Savings** .—(1) Nothing in this Act shall affect Section 25 of the Indian Contract Act, 1872 (9 of 1872)._ > _(2) Where any special or local law prescribes for any suit, appeal or application a period of limitation different from the period prescribed by the Schedule, the provisions_ H 294 SUPREME COURT REPORTS [2021] 13 S.C.R. - A There are several previous judgments of this court holding that where periods of limitation are prescribed under special laws, appeals that exceed the period granted and are within the extended period of limitation in the special law, can be entertained at the discretion of the tribunal, or court concerned and the Limitation Act would not apply upon expiry of such extended period.[11] This court holds that there is merit in the - B contention of the Union that the provisions of the Limitation Act are inapplicable. This is, however, not dispositive of the issue; the next question is whether there is merit in the appellant’s argument that the NGT should have considered the issue of whether the appeal was filed within the extended period prescribed under the proviso to Section 16, i.e. within - C sixty days after the expiration of the initial 30 day period, required in the main provision. 19. The appellant argues that since there is no indication to the contrary; the appeal is to be considered as having been filed within the extended period of 60 days, since the last (of the 60 days) was a Sunday D (12.07.2020). The appellant relied on Section 10 of the General Clauses Act, for this purpose. The respondents, notably the Union, opposed this argument. 20. Section 10 of the General Clauses Act, 1897[12] stipulates that when the last date for doing something falls on a public holiday, the act E _“shall be considered as done..”_ if it _“is done or taken on the next day afterwards on which the Court or office is open”._ This provision _of Section 3 shall apply as if such period were the period prescribed by the Schedule and for the purpose of determining any period of limitation prescribed for any suit, appeal or application by any special or local law, the provisions contained in Sections 4 to 24 (inclusive) shall apply only insofar as, and to the extent to which, they are not expressly_ F _excluded by such special or local law.”_ > 11 _Kaushalya Rani v Gopal Singh_ 1964 (4) SCR 982; _Collector of Excise & Customs v. Hongo India (P) Ltd._ (2009) 5 SCC 791; _Union of India v. Popular Construction Co._ (2001) 8 SCC 470; _Patel Bros. v. State of Assam_ (2017) 2 SCC 350 - _12 “_ _**10. Computation of time** .— (1) Where, by any Central Act or Regulation made after the commencement of this Act, any act or proceeding is directed or allowed to be done_ - G _or taken in any Court or office on a certain day or within a prescribed period, then, if the Court or office is closed on that day or the last day of the prescribed period, the act or proceeding shall be considered as done or taken in due time if it is done or taken on the next day afterwards on which the Court or office is open:_ - _Provided that nothing in this section shall apply to any act or proceeding to_ - _which the Indian Limitation Act, 1877, applies._ - _(2) This section applies also to all Central Acts and Regulations made on or_ - H _after the fourteenth day of January, 1887.”_ 295 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] applies to all Central Acts enacted _after_ the said Act was brought into A force. The scope of this provision was considered by this Court in _H.H. Raja Harinder Singh v. S. Karnail Singh[13]_ by a four judge Bench, which explained the object of Section 10 and held as under: _“5. … Where, therefore, a period is prescribed for the performance of an act in a court or office, and that period_ B _expires on a holiday, then according to the section the act should be considered to have been done within that period, if it is done on the next day on which the court or office is open. For that section to apply, therefore, all that is requisite is that there should be a period prescribed, and that period_ C _should expire on a holiday.”_ 21. Other decisions[14 ] have followed the same reasoning. It is also noticeable that there is no indication in the NGT Act that Section 10 of the General Clauses Act cannot be applied. It is therefore, held that the provision applies _proprio vigore_ to all appeals filed under the NGT Act. D ## _**Approach of the court in considering the application for condonation of delay**_ 22. What constitutes _“sufficient cause”_ in terms of Section 16 of the NGT Act? While it is unexceptionable for the Project Applicant to argue that the Limitation Act is _per se_ inapplicable to proceedings under the NGT Act, given that the basic, and outer period of limitation for filing an appeal have been enacted, nevertheless, what constitutes _sufficient cause,_ is left to the discretion of the tribunal. Here, the court discerns a surfeit of authority on what the term denotes, and the general approach of the court, in dealing with delay. E F 23. In _G. Ramegowda_ v. _Land Acquisition Officer[15]_ , speaking for this court, Venkatachaliah, J summarized the position in the following terms: _“14. The contours of the area of discretion of the courts in the matter of condonation of delays in filing appeals are set out in a number of pronouncements of this Court._ G 13 1957 SCR 208. > 14 _Manohar Joshi v. Nitin Bhaurao Patil_ (1996) 1 SCC 169; _Mohd. Ayub v. State of U.P._ , (2009) 17 SCC 70. 15 (1988) 2 SCC 142 H 296 SUPREME COURT REPORTS [2021] 13 S.C.R. A _See Ramlal v. Rewa Coalfields Ltd. [AIR 1962 SC 361 : (1962) 2 SCR 762] , Shakuntala Devi Jain v. Kuntal Kumari [AIR 1969 SC 575 : (1969) 1 SCR 1006], Concord of India Insurance Co. Ltd. v. Nirmala Devi [(1979) 4 SCC 365 : 1979 SCC (Cri) 996 : (1979) 3 SCR 694], Mata Din v. A. Narayanan [(1969) 2 SCC 770 : (1970) 2 SCR 90]_ B _and Collector (LA) v. Katiji [(1987) 2 SCC 107 : 1989 SCC (Tax) 172], etc. There is, it is true, no general principle saving the party from all mistakes of its counsel. If there is negligence, deliberate or gross inaction or lack of bona fides on the part of the party or its counsel there is no reason why the opposite_ C _side should be exposed to a time-barred appeal. Each case will have to be considered on the particularities of its own special facts. However, the expression ‘sufficient cause’ in Section 5 must receive a liberal construction so as to advance substantial justice and generally delays in preferring appeals are required to be condoned in the interest of justice where_ D _no gross negligence or deliberate inaction or lack of bona fides is imputable to the party seeking condonation of the delay.”_ 24. Much later, in _Esha Bhattacharjee v. Raghunathpur Nafar_ _Academy[16]_ this court referred to a large number of previous judgments[17] , E and observed that adoption of a strict standard of proof sometimes fails to protect public justice and it may result in public mischief. Other decisions have highlighted that there cannot be a universal formula to judge whether sufficient cause has, or has not been shown and the exercise is necessarily fact specific; in _Improvement Trust_ v. _Ujagar_ F _Singh[18]_ , the court held: - _“16. While considering [an] application for condonation of delay no straitjacket formula is prescribed to come to the conclusion if sufficient and good grounds have been made out or not.”_ G ## 16 (2013) 12 SCC 649 > 17 _State of Nagaland_ v. _Lipok Ao_ (2005) 3 SCC 752; _New India Insurance Co. Ltd._ v. _Shanti Misra_ (1975) 2 SCC 840; _N. Balakrishnan_ v. _M. Krishnamurthy_ (1998) 7 SCC 123; _State of Haryana_ v. _Chandra Mani_ (1996) 3 SCC 132; and _Tehsildar (LA)_ v. _K.V. Ayisumma_ (1996) 10 SCC 634. - H 18 (2010) 6 SCC 786 297 SRIDEVI DATLA v. UNION OF INDIA AND ORS. [S. RAVINDRA BHAT, J.] 25. The court also emphasized that each case has to be balanced A on the basis of its facts and the surrounding circumstances in which the parties act and behave. 26. Yet another dimension to the issue was highlighted in _Maniben Devraj Shah v. Municipal Corpn. of Brihan Mumbai[19]_ , where the court underlined a distinction between a case where the delay is inordinate, and a case where the delay is of few days and that in the former case the consideration of prejudice to the other side will be a relevant factor; in the latter case, no such consideration arises. After noticing that a liberal and justice-oriented approach needs to be taken, it was stated that the court, equally should be sensitive to the fact that _“the successful litigant has acquired certain rights on the basis of the judgment under challenge and a lot of time is consumed at various stages of litigation apart from the cost.”_ The court then held that: _“24. What colour the expression ‘sufficient cause’ would get in the factual matrix of a given case would largely depend on bona fide nature of the explanation. If the court finds that there has been no negligence on the part of the applicant and the cause shown for the delay does not lack bona fides, then it may condone the delay. If, on the other hand, the explanation given by the applicant is found to be concocted or he is thoroughly negligent in prosecuting his cause, then it would be a legitimate exercise of discretion not to condone the delay.”_ 27. It is evident that the term _sufficient cause_ is relative, fact dependant, and has many hues, largely deriving colour from the facts of each case, and the behaviour of the litigant who seeks condonation of delay (in approaching the court). However, what can broadly be said to be universally accepted is that in principle, the applicant must display _bona fides,_ should not have been negligent, and the delay occasioned should not be such that condoning it would seriously prejudice the other party. 28. Keeping these principles in mind, it is relevant to consider whether the NGT’s refusal to exercise discretion, in the facts and circumstances of this case, was erroneous. The court is conscious of the fact that exercise of discretion, _per se,_ is a fact dependent one, and B C D E F G 19 (2012) 5 SCC 157 H 298 SUPREME COURT REPORTS [2021] 13 S.C.R. - A considerable latitude should be given to the court or tribunal of the first instance, in the performance of that task. Nevertheless, as decided, cases and judgments have shown that the exercise of discretion does at times, call for appellate scrutiny by this court. This is one such. The appellant pleaded that since the documentation attendant to the clearance granted to the Project Applicant was voluminous, and expert as well as - B professional legal advice of the kind necessary to approach the NGT was not available in the State of Andhra Pradesh, the procuring of relevant documents, and correspondence with counsel in Delhi and drafting of the appeal entailed some delay. 29. This court is of the opinion that there is merit in the appellant’s C argument. The respondents, especially, the project applicant, had urged that the appellant is an interested party, and cannot be called a publicspirited citizen, because she had opposed acquisition of land for the airport and therefore, was able to access legal advice at the High Court stage. There is, in our opinion, nothing in the NGT Act which excludes parties _who would be directly affected by a project,_ that has D environmental repercussions, from accessing the tribunal (NGT). Likewise, characterizing the nature of legal advice that can be accessed for challenging land acquisition, as similar to a challenge to environmental clearance which involves application of mind to technical issues in a detailed manner, would be unfair and simplistic. Scientific or technical E support – apart from expert professional legal advice is necessary, if the NGT were to be approached. In these circumstances, this court is of the opinion that given the mandate of the NGT Act, the exercise of discretion, as was done in this case, to reject the appeal by dismissing the application for condonation of delay, on the ground that no sufficient cause was shown, was erroneous and based on a narrow reading of the F law. An appeal to the NGT in such matters is no ordinary matter; it has the potential of irrevocably changing the environment with the possibility of likely injury. Application of judicial mind by an independent tribunal in such cases, at the first appellate stage, is almost a necessity. 30. In view of the foregoing findings, this court is of the opinion that the impugned order of NGT has to be and is, therefore set aside. G The delay in filing the appeal before the NGT is hereby condoned; the parties shall now appear and proceed to argue the appeal on its merit, which shall then be disposed in accordance with law. The appeal is allowed. There shall be no order on costs. - H Devika Gujral Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.