Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeRevision disposed of; directions issued as above.

Special Tahsildar, L.A. (G) II, Palakkad v. Parvathy Ammal and others

Case / Petition Number:
CRP.No.404 of 2009 (E)

Case Synopsis & Summary

This is a Kerala High Court Civil Revision Petition (CRP 404 of 2009) filed by the State challenging an order in Execution Proceedings (EP 266/98) arising from Land Acquisition Award/LAR 69/1986 in Palakkad. The Sub Court determined a due amount of Rs. 7,73,201 on the decree holder and ordered attachment and sale of movables for realisation. During pendency, some movables were attached and later released on bond. The State contended that, after reconciling accounts, the balance as on 12.9.2001 (Rs. 3,24,639) should be treated as interest on enhanced compensation rather than as principal, and that no further liability existed beyond the enhanced sum, citing the need for proper appropriation. The decree holder and others responded with detailed calculations, showing enhancements and deposits under prior awards, solatium, and interest. The court undertook a thorough inquiry, considering statements and the guiding principle of appropriation from a Constitutional Bench decision and the apex court’s rulings, including Gurpreet Singh v. Union of India (2006 KHC 1608). It held that the claimant could claim interest on the principal amount of Rs.1,97,730 from 12.9.2001 until the entire interest on the amount is exhausted, rejecting the State’s narrow interpretation. The court directed the State to deposit Rs.3,00,280 within one month and permitted release of Rs.2,66,826 deposited earlier to the decree holders, subject to charges. The revision is disposed of accordingly.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S.S.Satheesachandran
Judgment Date
2009-11-26
Court Decision / Holding
Revision disposed of; State directed to deposit Rs.3,00,280 before the execution court within one month; the amount deposited Rs.2,66,826 on 2.7.2008 to be released to the decree holders, subject to any charge; case disposed with directions as stated.
Final Disposition
Revision disposed of; directions issued as above.

Parties to the Case

Appellants / Petitioners

  • Special Tahsildar, L.A.(G) No.II, Palakkad

Respondents

  • Parvathy Ammal
  • Kanakaraj
  • Nataraj
  • Varadaraj
  • Thandavariyil
  • Danabhagyam
  • Jayalakshmi
  • Pasupathy

Legal Representation & Advocates

Counsels for Petitioners

  • • P.K. Ravikrishnan, Government Pleader

Counsels for Respondents

  • • G. Shrikumar (for R2 to 8)
  • • Sreejith S. Nair (for R2 to 8)

Provisions of Law Cited

Land Acquisition Act, Section 3(1) notificationLand Acquisition Act, Section 11 read with Section 31Land Acquisition Act, Section 23(1A)Land Acquisition Act, Section 28Land Acquisition Act, Section 34

Legal Doctrines & Maxims

  • Principle of appropriation of deposited amounts towards interest, costs, and principal (as elaborated by the apex court and subsequent rulings)
  • Appropriation of enhanced compensation deposits to the enhanced amount only (Gurpreet Singh v. Union of India, 2006 KHC 1608)

Submissions & Arguments

Contentions of Appellants / Petitioners

The State submitted that once the balance due as on 12.9.2001 (Rs.3,24,639) is set, the decretal liability could only be treated as interest on the enhanced compensation, and no further liability should be admitted beyond this balance. It urged that the appropriation mechanism in law dictated by settled precedents would prevent further payment beyond the stated balance, and that the claimant should not receive further interest beyond the enhancement already deposited or payable. The State relied on the apex court’s guidance on appropriation and on the principle that interest should not accrue beyond the deposit until notices of deposit are given.

Contentions of Respondents

The decree holders argued that, despite the enhanced compensation and deposits, the balance outstanding on 12.9.2001 must be handled via proper appropriation: first toward interest on enhanced sums, then costs, and finally the principal subject to the awarding of further enhancements. They asserted that deposits and awards from subsequent proceedings (reference court, High Court, Supreme Court) must be considered in computing the realisable amount and that interest on the principal sum should be safeguarded through appropriate appropriation, ensuring recompense as per the statutory framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Gurpreet Singh v. Union of India2006 KHC 1608PositiveCited for the principle of appropriation of deposited compensation amounts toward interest, costs, and principal, and for guiding the manner of applying deposits against enhanced compensation amounts.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,758 words•~8 min read

In The Court Record

Special Tahsildar, L.A. (G) II, Palakkad v. Parvathy Ammal and others

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE S.S.SATHEESACHANDRAN THURSDAY, THE 26TH NOVEMBER 2009 / 5TH AGRAHAYANA 1931 CRP.No. 404 of 2009 (E) --------------------AGAINST THE ORDER DATED 6.7.2009 IN EP 266/98 IN LAR.69/1986 of PRINCIPAL SUB COURT, PALAKKAD .................... REVN. PETITIONER/JUDGMENT DEBTOR/RESPONDENT: ----------------------------------------------THE SPECIAL TAHSILDAR, L.A.(G) NO.II, PALAKKAD. BY GOVERNMENT PLEADER MR.P.K.RAVIKRISHNAN RESPONDENTS/DECREE HOLDERS/CLAIMANTS: --------------------------------------- 1. PARVATHY AMMAL, W/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR (DIED) 2. KANAKARAJ, S/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 3. NATARAJ, S/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 4. VARADARAJ, S/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 5. THANDAVARIYIL, S/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 6. DANABHAGYAM, D/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 7. JAYALAKSHMI, D/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR 8. PASUPATHY, S/O.KANTHASWAMY PILLAI, NELLIMEDU, CHITTUR ADV. MR.G.SHRIKUMAR FOR R2 TO 8 MR.SREEJITH S.NAIR FOR R2 TO 8 THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON 26/11/2009, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: ## CRP.No. 404 of 2009 (E) ## ORDER ON I.A.NO.1998/2009 IN C.R.P.NO.404/2009 DISMISSED. 26.11.2009 SD/- S.S.SATHEESACHANDRAN, JUDGE. // TRUE COPY // P.A. TO JUDGE. ## **S.S.SATHEESACHANDRAN, J. ----------------------------------C.R.P.No.404 of 2009 - E --------------------------------Dated this the 26[th] day of November, 2009** ## **O R D E R** Revision is filed by the State against the order dated 6.7.2009 in E.P.No.266 of 1998 in L.A.R.No.69 of 1986 passed by the learned Sub Judge, Palakkad. On the basis of the statements filed by both sides as to what exactly is the amount due under the decree, after enquiry, the execution court passed an order that a sum of Rs.7,73,201/- is due to the decree holder. During the pendency of the execution proceedings some of the movables belonging to the State had been attached and produced before the court, but, later they were released on bond. Under the impugned order the court has further ordered that the movables so attached are liable to be sold for realisation of the decree debt. Questioning the correctness of the conclusion made and the amount ordered to be realised under the decree and also impeaching the propriety of the order as vitiated by jurisdictional infirmity the State has preferred this revision. **C.R.P.No.404 of 2009 - E** 2 2. After hearing the counsel on both sides at length, I directed them to file statement to determine as to what exactly is the amount due under the decree to the decree holder. The concerned officer from the Revenue Department was also summoned to appear before the Court to finalise what is the amount due to the decree holder under the decree so that a quietus can be given to the whole controversy. After the statements were filed by both sides and scrutinising them the learned Government Pleader submitted that the statement filed by the decree holder on 16.11.2009 to a large extent can be accepted and the limited dispute which the State would like to canvass is only with respect to the claim for interest made by the decree holder on the balance amount due from 12.9.2001. To have an effective appreciation as to the calculation shown in the statement arrived at in the statement referred to above it would be profitable to reproduce the statement: ## General Information Section 3(1) notification : 29.05.1984 Date of Award No.12/86 by LAO : 30.05.1986 Date of dispossession : 29.05.1986 3 ## **C.R.P.No.404 of 2009 - E** Date of judgment in L.A.R.No.69/86, Sub Court, Palakkad : 11.04.1990 Enhanced value as per judgment in L.A.R.No.69/86 : Rs.4,86,720.00 Amount already paid by LAO : Rs.2,86,486.00 Quantum of enhancement given by LAR Court : Rs.2,00,234.00 30% Solatium on Rs.2,00,234 : Rs.60,070.00 12% Additional compensation for enhanced amount (i.e.Rs.200234) from 29.05.1984 (date of notification) to 29.05.86 (date of award)(731 days): Rs.48,122.00 9% interest on Rs.200234/- from 30.05.86 to 30.05.87 (one year) : Rs.18,021.00 15% interest 30.05.87 to 3.10.90 (1223 days) : Rs.1,00,638.00 **Total as on 3.10.1990** : **Rs.4,27,085.00 Amount deposited on 4.10.1990 : Rs.4,62,294.00 Excess deposit : Rs.35,209.00** Enhancement awarded by Hon'ble High Court in L.A.A.No.137/91 dated 3.4.1998 : Rs.6,84,450.00 LAR Award Amount : Rs.4,86,720.00 ## **C.R.P.No.404 of 2009 - E** |4|||||| |---|---|---|---|---|---| |Quantum of Enhancement by|||||| |High Court|:|Rs.1,97,730.00|||| |30% solatium on Rs.1,97,730/-|:|Rs.59,319.00|||| |12% Additional compensation on|||||| |Rs.1,97,730/- (enhanced compensation)|||||| |from 29.5.1984 (date of notification)|||||| |to 29.5.1986 (date of award)|:|Rs.47,520.00|||| |9% interest on Rs.1,97,730/- from|||||| |30.05.86 to 29.05.87 (one year)|:|Rs.17,796.00|||| |15% interest on Rs.1,97,730/- from|||||| |30.05.87 to 11.09.2001 (5218 days)|:|Rs.4,24,009.00|||| |**Total due as on 12.09.2001**|**:**|**Rs.7,46,374.00**|||| |**Deposit on 12.09.2001**|**:**|**Rs.3,86,534.00**|||| |**Balance outstanding as on 12.09.01:**||**Rs.3,59,840.00**|||| |**Reduce excess deposit**|**:**|**Rs.35,209.00**|||| |**New Balance as on 12.09.2001**|**:**|**Rs.3,24,639.00**|||| |15% interest on Rs.1,97,730/- from|||||| |12.09.2001 to 2.7.08 (2483 days)|:|Rs.2,01,765.00|||| |Total as on 2.07.08|:|Rs.5,26,396.00|||| |Amount deposited on 2.7.08|:|Rs.2,66,826.00|||| |**Balance as on 2.7.08**|**:**|**Rs.2,59,570.00**|||| |15% interest on Rs.1,97,730/- from|||||| |3.7.08 to 16.11.09 (501 days)|:|Rs.40,710.00|||| |**Total outstanding as on 16.11.2009:**||**Rs.3,00,280.00**|||| |||==========|||| **C.R.P.No.404 of 2009 - E** 5 Up to the calculation made arriving the balance as on 12.9.2001 it is stated that there is no dispute. The learned Government Pleader submitted that on the balance amount found due on 12.9.2001, that is a sum of Rs.Rs.3,24,639.00, the decree holder is not entitled to claim any further interest. Whatever amount given by way of enhanced compensation by virtue of the decree passed in the LA Appeal had already been deposited even before that date and the outstanding amount arrived on 12.9.2001, according to the learned Government Pleader, can only be treated as interest. 3. The enhanced compensation awarded in appeal by this Court is Rs.1,97,730/-. The argument canvassed by the learned Government that the principal amount awarded as enhanced compensation stood exhausted on 12.9.2001 cannot be accepted since the balance amount as on that date is more than the enhanced compensation awarded by the court. How appropriation has to be made in respect of compensation awarded under the Land Acquisition proceedings has been considered by the apex Court in _**Gurpreet Singh v. Union of India**_ (2006 KHC 1608). A Constitutional Bench of the Apex **C.R.P.No.404 of 2009 - E** 6 Court was constituted to resolve the controversy then prevailing over conflicting decisions decided earlier as regard the entitlement of the claimants for interest on the solatium awarded as compensation. The Apex Court resolving that issue also considered the mode of appropriation to be followed in respect of the compensation deposited before the court from time to time. The Apex Court has laid down the principle of appropriation applicable stating that the decree holder may be entitled to apply the rule of appropriation by appropriating the amount first towards the interest, then towards the costs and then towards the principal amount due under the decree. In paragraph 28 of the judgment dilating those aspects further the apex court has observed as follows: _“28. Going by this principle and for the moment keeping out the scheme of the Land Acquisition Act, it appears to us that on payment or deposit of the amount awarded by the Collector in terms of S.11 read with S.31 of the Act, the claimant cannot thereafter claim any interest on that part of the compensation paid to him or deposited for the payment to him once notice of deposit is given to him. Thereafter, when the Reference Court enhances_ 7 ## **C.R.P.No.404 of 2009 - E** _the compensation with consequential enhancement in solatium and interest under S.23(1A) of the Act and further awards interest on the enhanced compensation in terms of S.28 of the Act, the claimant/decree holder can seek an appropriation of the amounts deposited pursuant to that award - decree, only towards the enhanced amount so awarded by the Reference Court. While making the appropriation, he can apply the amount deposited, first towards the satisfaction of his claim towards interest on the enhanced amount, the costs, if any, awarded and the balance towards the land value, solatium and the payment under S.23(1A) of the Act and if there is a shortfall, claim that part of the compensation with interest thereon as provided in S.28 of the Act and as covered by the award - decree. Once the sum enhanced by the Reference Court, along with the interest is deposited by the State, there will be no occasion for the claimant/awardee to seek a reopening of the amount awarded by the Collector, substituted by the amount awarded by the Reference Court and seek to have a reappropriation of the amount towards what is due. Same would be the position in a case where the amount awarded by the Reference Court, including the interest is deposited, but the amount is further enhanced in appeal by the High Court. Again, the same principle_ **C.R.P.No.404 of 2009 - E** 8 _would apply. The principle would continue to apply when the Supreme Court awards further enhancement in a further appeal to that Court. But if after the award by the Reference Court, the amount is not deposited by the State, interest would run on the compensation in terms of S.28 of the Act on that amount as provided in S.28. The same would be the position regarding the enhancement given in appeal by the High Court and in the enhancement given in appeal by the Supreme Court. The mandate of S.34 and S.28 that interest would run from the date the Collector takes possession till the particular amount is deposited as provided in those sections, ensures that the claimant is recompensed adequately. S.28 ensures such recompense at each stage of enhancement of compensation.”_ So much so as on 12.9.2001 the balance amount due to the decree holder being Rs.3,24,639/- which was in excess of the principal amount due as enhanced compensation i.e., Rs.1,97,730/-, and no point of time earlier that principal amount had been reduced by payment or deposit the decree holder is entitled to claim interest on the principal amount of Rs.1,97,730/- from the above date as well till the entire interest on the amount is exhausted. Learned Government Pleader **C.R.P.No.404 of 2009 - E** 9 submitted that if the appropriation is made in the light of the decision rendered above there cannot be any further quarrel with respect to the statement filed by the decree holder. So much so, it follows that the outstanding amount due from the State as on 16.11.2009 recognising the deposit of Rs.2,66,826/- State had deposited on 2.7.2008 will be Rs.3,00,280/-. So there will be a direction to the State to deposit Rs.3,00,280/- before the execution court within one month from the date of this order. The execution court shall also release the amount of Rs.2,66,826/- which had been deposited by the State on 2.7.2008 to the respondents/decree holder provided there is no charge, attachment or other liability interdicting such release. Revision is disposed of as above. **S.S.SATHEESACHANDRAN, JUDGE.** bkn/-
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.