South East Asia Marine Engineering and Constructions Ltd. (SEAMEC Ltd.) v. Oil India Limited

Case / Petition Number:
Civil Appeal No. 673 of 2012; Civil Appeal No. 900 of 2012

Case Synopsis & Summary

This Supreme Court judgment deals with Civil Appeals No. 673 of 2012 and No. 900 of 2012 arising from an arbitration award in a contract for drilling operations in Assam. SEAMEC challenged an arbitral award awarding Rs. 1.32 crore for price escalation on account of higher HSD prices, claiming Clause 23 of the contract applied to “change in law” including government orders/communications that increased costs. The Arbitral Tribunal split on interpretation; the majority held that government circulars and orders could fall within Clause 23, while the minority held such executive acts did not. The District Judge confirmed the award; the Gauhati High Court set it aside, holding the tribunal’s interpretation contrary to the contract and public policy. The issue before the Supreme Court was the scope of judicial review under Section 34 of the Arbitration Act and whether the Tribunal could rewrite the contract by broadly interpreting Clause 23. The Court examined the contract as a whole, the principle of deference to arbitral interpretation when two plausible views exist, and precedents such as Dyna Technologies and McDermott. It rejected the expansive reading of Clause 23, noting that reading the clause in isolation and equating it to force majeure would undermine the contract’s core terms. Ultimately, the appeals were dismissed, the High Court’s setting aside of the award stood, and there were no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • N. V. Ramana, J.
  • Mohan M. Shantanagoudar
  • Ajay Rastogi
Judgment Date
2020-05-11
Court Decision / Holding
Appeals dismissed; High Court’s judgment setting aside the arbitral award stands; the arbitral award is set aside; No costs.
Final Disposition
Appeals dismissed; High Court's order setting aside the arbitral award stands; arbitration award set aside; No costs.

Parties to the Case

Appellants / Petitioners

  • South East Asia Marine Engineering and Constructions Ltd. (SEAMEC Ltd.)
  • Oil India Limited

Respondents

  • Oil India Limited
  • South East Asia Marine Engineering and Constructions Ltd. (SEAMEC Ltd.)

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 — Section 34Arbitration and Conciliation Act, 1996 — Section 37Arbitration and Conciliation Act, 1996 — Section 75Arbitration and Conciliation Act, 1996 — Section 81Indian Contract Act, 1872 — Section 56Indian Contract Act, 1872 — Section 32Indian Contract Act, 1872 — Section 65

Legal Doctrines & Maxims

  • Liberal interpretation of contract clauses (Rule of Construction)
  • Habendum Clause (interpreting the clause liberally)
  • Force majeure doctrine
  • Doctrine of frustration and supervening impossibility
  • Restitution under Section 65 of the Indian Contract Act
  • Read the contract as a whole and harmonize clauses

Submissions & Arguments

Contentions of Appellants / Petitioners

SEAMEC contends Clause 23 is broad enough to cover a ‘change in law’ including government orders/resolutions that increase cost, and the Arbitral Tribunal properly interpreted the clause. It argues the High Court erred by viewing Clause 23 as akin to force majeure or frustration, and that two plausible interpretations exist; deference to the arbitrator’s reasoning is warranted. The contract’s entire framework, including force majeure payments under other clauses, supports the award. It asserts that Section 34 review should be restrained and not substitute the tribunal’s interpretative choices with the court’s own view.

Contentions of Respondents

Oil India contends Clause 23 cannot extend to government orders or changes in law and would effectively rewrite the contract. The Arbitral Tribunal’s broad reading is perverse and outside the four corners of the contract, violating Section 28 and public policy. The award reads the contract in isolation, ignores the rest of the agreement, and thus misapplies contract interpretation principles. The High Court’s reversal aligns with the proper reading of Clause 23, and Section 34 should be used to prevent such overreach.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
McDermott International Inc. v. Burn Standard Co. Ltd.(2006) 11 SCC 181PositiveCited to support the principle that where two plausible views exist, deference should be given to the arbitral tribunal’s reasoning.
Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd(2019) SCC Online SC 1656PositiveSupports cautious interference under Section 34 and deference to arbitral awards unless perversity goes to the root.
Sumitomo Heavy Industries Limited v. Oil and Natural Gas Corporation Limited(2010) 11 SCC 296DistinguishedCited as persuasive but not applicable to the present facts; ratio not controlling.
Chandler v. Webster(1904) 1 KB 493Mentioned OnlyHistorical example of coronation case; used as background rather than controlling authority.
Fibrosa Spolka Akcyjna v. Fairbairn Lawson Co mb arbour Ltd.[1942] UKHL 4Mentioned OnlyUsed to illustrate evolution of frustration doctrine in English law.
Cantiare San Rocco SA v. Clyde Shipbuilding and Engineering Co. Ltd.(1924) AC 226Mentioned OnlyBackground reference to frustration and statutory reform; not a controlling precedent.
Satyabrata Ghose v Mugneeram Bangur & Co.AIR 1954 SC 44PositiveCited for the principle of supervening impossibility under Section 56 of the Contract Act.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,460 words•~21 min read

In The Court Record

South East Asia Marine Engineering and Constructions Ltd. (SEAMEC Ltd.) v. Oil India Limited

**Reportable** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. 673 OF 2012** **SOUTH EAST ASIA MARINE ...APPELLANT ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.)** ## **VERSUS** **OIL INDIA LIMITED …RESPONDENT** **With** **CIVIL APPEAL NO. 900 OF 2012** **OIL INDIA LIMITED ...APPELLANT** **VERSUS** **SOUTH EAST ASIA MARINE …RESPONDENT ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.)** ## **J U D G M E N T** ## **N. V. RAMANA, J. Civil Appeal No. 673 of 2012** Signature Not Verified Digitally signed byGEETA AHUJADate: 2020.05.11 **1.** The present appeal arises out of impugned judgment and order 15:37:43 IST Reason: dated 13.12.2007 in Arbitration Appeal No. 11 of 2006 passed 1 by the Gauhati High Court, wherein the High Court allowed the appeal preferred by the Respondent under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter the _“Arbitration Act_ ”), and set aside the arbitral award dated 19.12.2003. **2.** Brief facts necessary for the disposal of this case are as follows: appellant was awarded the work order dated 20.07.1995 pursuant to a tender floated by the Respondent in 1994. The contract agreement was for the purpose of well drilling and other auxiliary operations in Assam, and the same was effectuated from 05.06.1996. Although, the contract was initially only for a period of two years, the same was extended for two successive periods of one year each by mutual agreement, and finally the contract expired on 04.10.2000. **3.** During the subsistence of the contract, the prices of High­ Speed Diesel (“HSD”), one of the essential materials for carrying out the drilling operations, increased. Appellant raised a claim that increase in the price of HSD, an essential component for carrying out the contract triggered the “change in law” clause under the contract ( _i.e._ , Clause 23) and the Respondent became liable to reimburse them for the same. 2 When the Respondent kept on rejecting the claim, the Appellant eventually invoked the arbitration clause _vide_ letter dated 01.03.1999. The dispute was referred to an Arbitral Tribunal comprising of three arbitrators. **4.** On 19.12.2003, the Arbitral Tribunal issued the award in A.P No. 8 of 1999. The majority opinion allowed the claim of the Appellant and awarded a sum of Rs. 98,89,564.33 with interest @10% per annum from the date of the award till the recovery of award money. The amount was subsequently revised to Rs. 1,32,32,126.36 on 11.03.2005. The Arbitral Tribunal held that while an increase in HSD price through a circular issued under the authority of State or Union is not a “law” in the literal sense, but has the “force of law” and thus falls within the ambit of Clause 23. On the other hand, the minority held that the executive orders do not come within the ambit of Clause 23 of the Contract. **5.** Aggrieved by the award, the Respondent challenged the same under Section 34 of the Arbitration Act before the District Judge. On 04.07.2006, the learned District Judge, upheld the award and held that the findings of the tribunal were not 3 without basis or against the public policy of India or patently illegal and did not warrant judicial interference. **6.** The Respondent challenged the order of the District Judge by filing an appeal under Section 37 of the Arbitration Act, before the High Court. By the impugned judgment, the High Court, allowed the appeal and set aside the award passed by the Arbitral Tribunal. **7.** The High Court held that the interpretation of the terms of the contract by the Arbitral Tribunal is erroneous and is against the public policy of India. On the scope of judicial review under Section 37 of the Arbitration Act, the High Court held that the Court had the power to set aside the award as it was passed overlooking the terms and conditions of the contract. Aggrieved by the same, the appellant has filed this present appeal by the way of special leave petition against the impugned judgment. **8.** Learned Counsel for the Appellant assailing the impugned order contends that - a. The High Court has imparted its own personal view as to the intent for inclusion of Clause 23 and has sat in appeal over the award of the Arbitral Tribunal. The 4 construction of Clause 23, he submitted, is a matter of interpretation and has been correctly interpreted by the Arbitral Tribunal based on the authorities cited before it. - b. If two views are possible on a question of law, the High Court cannot substitute one view and deference should be given to the plausible view of the Arbitral Tribunal. Learned counsel has relied upon a judgment of this Court in **McDermott International Inc. v. Burn Standard Co. Ltd.** [ _(2006) 11 SCC 181_ ] to support his contention. - c. The question of law decided by the Arbitral Tribunal is beyond judicial review and thus the High Court could not have interfered with a reasoned award which was neither against public policy of India nor patently illegal. **9.** In response, the learned counsel for the Respondent, supporting the findings of the High Court, submits that - a. the award passed by the Arbitral Tribunal is contrary to the terms of the contract and essentially re­writes the contract. The Arbitral Tribunal has to adjudicate the dispute within the four corners of the contract and thus awarding additional reimbursement not contemplated under Clause 23 is perverse and patently illegal. - b. Overlooking the terms and conditions of a contract is violative of Section 28 of the Arbitration Act and thus the tribunal has exceeded its jurisdiction. 5 - c. This is not a case where the Arbitral Tribunal accepted one interpretation of the terms of the contract where two interpretations were possible. Findings of the Tribunal are perverse and unreasonable as the Tribunal did not consider the contract as a whole and failed to follow the cardinal principle of interpretation of contract. - d. The Arbitral Tribunal has re­written the contract in the guise of interpretation and such interpretation being in conflict with the terms of the contract, is in conflict with the public policy of India. **10.** We have heard the learned counsels for the parties and perused the materials on record. **11.** In order to answer the questions raised in this appeal we first need to delve into the ambit and scope of the court’s jurisdiction under Section 34 of the Arbitration Act. Section 34 of the Arbitration Act provides as under – **34. Application for setting aside arbitral award.** — (1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub­section (2) and sub­section (3). (2) An arbitral award may be set aside by the Court only if— (a) the party making the application furnishes proof that— (i) a party was under some incapacity, or (ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, 6 failing any indication thereon, under the law for the time being in force; or (iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or (iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or (v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or (b) the Court finds that— (i) the subject­matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or (ii) the arbitral award is in conflict with the public policy of India. Explanation. —Without prejudice to the generality of sub­clause (ii) it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the public policy of India if the making of the award was 7 induced or affected by fraud or corruption or was in violation of section 75 or section 81. (3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter. (4) On receipt of an application under sub­section (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the arbitral tribunal an opportunity to resume the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award. **12.** It is a settled position that a Court can set aside the award only on the grounds as provided in the Arbitration Act as interpreted by the Courts. Recently, this Court in **Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd** . [ _2019 SCC Online SC 1656_ ] laid down the scope of such interference. This **­** Court observed as follows **“26.** There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. **We need to be cognizant of the fact that arbitral** 8 **awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award** . Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute an alternative forum as adjudicated by provided under the law. If the Courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.” ## ( **emphasis supplied** ) **13.** It is also settled law that where two views are possible, the Court cannot interfere in the plausible view taken by the arbitrator supported by reasoning. This Court in _**Dyna Technologies**_ (supra) observed as under­ **“27.** Moreover, umpteen number of judgments of this Court have categorically held that the Courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. **The Courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays** 9 ## **perversity unpardonable under Section 34 of the Arbitration Act.”** ## ( **emphasis supplied** ) **14.** However, the question in the present case is whether the interpretation provided to the contract in the award of the Tribunal was reasonable and fair, so that the same passes the muster under Section 34 of the Arbitration Act? **15.** In the present case, respondent has argued that the view taken by the Arbitral Tribunal was not even a possible interpretation, therefore the award being unreasonable and unfair suffers from perversity. Hence, the respondent has pleaded that the award ought to be set aside. In this context, we may state that usually the Court is not required to examine the merits of the interpretation provided in the award by the arbitrator, if it comes to a conclusion that such an interpretation was reasonably possible. **16.** We begin by looking at the clause, i.e Clause 23 which is extracted below: ## ­ SUBSEQUENTLY ENACTED LAWS: Subsequent to the date of price of Bid Opening _if there is a change in or enactment of any law or interpretation of_ 10 _existing law_ , which results in additional cost/reduction in cost to Contractor on account of the operation under the Contract, the Company/Contractor shall reimburse/pay Contractor/Company for such additional/reduced cost actually incurred. **17.** The Arbitral Tribunal held that this clause must be liberally construed and any circular of the Government of India would amount to a change in law. The Arbitral Tribunal observed: “According to Rule of Construction of any document harmonious approach should be made reading or taking the document as a whole and exclusion should not be readily inferred unless it is clearly stated in the particular clause of the document. This is according to Rule of Interpretation. A consistent interpretation should be given with a view to smooth working of the system, which the document purports to regulate. The word, which makes it inconsistent or unworkable, should be avoided. This is known as beneficial construction and a construction should be made which suppress the mischief and advance the remedies. So, the increase in the operational cost due to enhanced price of the diesel is one of the subject matters of the contract as enshrined in Cl. 23. It may be said that Cl. 23 may be termed as ‘‘Habendum Clause”. In the deed of the contract containing various granting clauses and the habendum signifying the intention of, the grantor. 11 That Cl. 23 requires liberal interpretation for interpreting the expression ‘law’ or change in law etc. will also be evident from the facts that the respondents Oil India Ltd. through its witness Mr. Pasrija has clearly stated that the change in diesel price or any other oil price was never done and by way of any statutory enactment either by Parliament or by State Legislature So, it is clear that at the time when the Cl. 23 was incorporated in the agreement the Oil India Ltd. was very much aware that change in oil price was never made by any Statutory Legislation but only by virtue of Government Order, Resolution, Instruction, as the case may be, on accepting that a condition of the appropriate committee namely O.P.C. it is also clear to apply when there is change in oil price, here HSD, by the Government and its statutory authority as enacted in the above without resorting any statutory enactment. Therefore that the interpretation of expression ‘law’ or change in law etc. requires this extended meaning to include the statutory law, or any order, instruction and resolution issued by the Central Government in its Ministry of Petroleum and Natural Gas.” The majority award utilizes ‘liberal interpretation rule’ to construe the contract, so that the price escalation of HSD could be brought under the Clause 23 of the contract. Further the Arbitral Tribunal identifies the aforesaid clause to be a 12 ‘Habendum Clause’, wherein the rights granted to the appellant are required to be construed broadly. **18.** On the other hand, the High Court in the impugned order, interpreted the same clause as follows: “ **27** …I am of the firm view that clause 23 was inserted in the agreement to meet such uncertain and unforeseen eventualities and certainly not for revising a fixed rate of contract. I also find that both parties had agreed to keep “force majeure” clause in the agreement. Under this doctrine of commercial law, a contract agreement can be rescinded for acts of God, etc. Under clause 44.3 of the agreement, ‘force majeure” has been clearly defined, which includes acts and regulations of the Government to rescind a contract. In this way, clause 23 is very close and akin to the “force majeure clause”. Besides this, I may also declare that clause 23 is pari materia to the “doctrine of frustration and supervening impossibility”. In other words, under clause 23 rights and obligations of both the parties have been saved due to any change in the existing law or enactment of a new law or on the ground of new interpretation of the existing law. In my opinion, clause 23 must have been made a part of the agreement keeping in mind section 56 of the Indian Contract Act, 1872 sans any other intention.” 13 **19.** The High Court, in its reasoning, suggests that Clause 23 is akin to a force majeure clause. We need to understand the utility and implications of a _force majeure_ clause. Under Indian contract law, the consequences of a _force majeure_ event are provided for under Section 56 of the Contract Act, which states that on the occurrence of an event which renders the performance impossible, the contract becomes void thereafter. Section 56 of the Contract Act stands as follows: .—An **56. Agreement to do impossible act** agreement to do an act impossible in itself is void. **Contract to do act afterwards becoming impossible or unlawful** —A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful. **20.** When the parties have not provided for what would take place when an event which renders the performance of the contract impossible, then Section 56 of the Contract Act applies. When the act contracted for becomes impossible, then under Section 56, the parties are exempted from further performance and the 14 contract becomes void. As held by this Court in _**Satyabrata**_ ## _**Ghose v. Mugneeram Bangur & Co.**_ **,** AIR 1954 SC 44: **“15.** These differences in the of way formulating legal theories really do not concern us so long as we have a statutory provision in the Indian Contract Act. In deciding cases in India the only doctrine that we have to go by is that of supervening impossibility or illegality as laid down in Section 56 of the Contract Act, taking the word “impossible” in its practical and not literal sense. **It must be borne in mind, however, that Section 56 lays down a rule of positive law and does not leave the matter to be determined according to the intention of the parties.”** ## **(emphasis supplied)** However, there is no doubt that the parties may instead choose the consequences that would flow on the happening of an uncertain future event, under Section 32 of the Contract Act. **21.** On the other hand, the common law at one point interpreted the consequence of such frustration to fall on the party who sustained loss before the frustrating event. The best example of such an interpretation can be seen in the line of cases which came to be known as ‘coronation cases’. In _**Chandler v.**_ _**Webster**_ , [1904] 1 KB 493, Mr. Chandler rented space from 15 Mr. Webster for viewing the coronation procession of King Edward VII to be held on 26[th] June 1902. Mr. Chandler had paid part consideration for the same. However, due to the King falling ill, the coronation was postponed. As Mr. Webster insisted on payment of his consideration, the case was brought to the Court. The Court of Appeals rejected the claims of both Mr. Chandler as well as Mr. Webster. The essence of the ruling was that once frustration of contract happens, there cannot be any enforcement and the loss falls on the person who sustained it before the _force majeure_ took place. **22.** This formulation was over­ruled by the House of Lords in the historic decision of _**Fibrosa Spolka Akcyjna v. Fairbairn Lawson Combe Barbour Ltd.**_ , [1942] UKHL 4, wherein the harsh consequences of frustration as per the old doctrine was moderated by the introduction of the law of restitution. Interestingly, Lord Shaw in _**Cantiare San Rocco SA (Shipbuilding Company) v. Clyde Shipbuilding and**_ _**Engineering Co. Ltd.**_ , [1924] AC 226, had observed that English law of leaving the loss to where it fell unless the contract provided otherwise was, he said, appropriate only 16 ‘among tricksters, gamblers and thieves’. The UK Parliament took notice of the aforesaid judgment and legislated Law Reform (Frustrated Contracts) Act, 1943. **23.** In India, the Contract Act had already recognized the harsh consequences of such frustration to some extent and had provided for a limited mechanism to ameliorate the same under Section 65 of the Contract Act. Section 65 provides as under: ## **65. Obligation of person who has received advantage under void agreement, or contract that becomes void** When an agreement is discovered to be void, or when a contract becomes void, any person who has received under such any advantage agreement or contract is bound to restore it, or to make compensation for it to the person from whom he received it. The aforesaid clause provides the basis of restitution for ‘failure of basis’. We are cognizant that the aforesaid provision addresses limited circumstances wherein an agreement is _void ab initio_ or the contract becomes subsequently void. **24.** Coming back to the case, the contract has explicitly recognized _force majeure_ events in Clause 44.3 in the following manner: 17 For purpose of this clause “Force Majeure” means an act of God, war, revolt, riots, strikes, bandh, fire, flood, sabotage, failure or destruction of roads, **systems and acts and regulations of the Government of India and other clauses** (but not due to employment problem of the contractor) beyond the reasonable control of the parties. Further, under Clause 22.23, the parties had agreed for a payment of _force majeure_ rate to tide over any _force majeure_ event, which is temporary in nature. **25.** Having regards to the law discussed herein, we do not subscribe to either the reasons provided by the Arbitral Tribunal or the High Court. Although, the Arbitral Tribunal correctly held that a contract needs to be interpreted taking into consideration all the clauses of the contract, it failed to apply the same standard while interpreting Clause 23 of the Contract. **26.** We also do not completely subscribe to the reasoning of the High Court holding that Clause 23 was inserted in furtherance of the doctrine of frustration. Rather, under Indian contract law, the effect of the doctrine of frustration is that it discharges all the parties from future obligations. In order to mitigate the 18 harsh consequences of frustration and to uphold the sanctity of the contract, the parties with their commercial wisdom, chose to mitigate the risk under Clause 23 of the contract. **27.** Our attention was drawn to _**Sumitomo Heavy Industries**_ ## _**Limited v. Oil and Natural Gas Corporation Limited**_ , (2010) 11 SCC 296, where this Court interpreted an indemnity clause and found that an additional tax burden could be recovered under such clause. Based on an appreciation of the evidence, the Court ruled that additional tax burden could be recovered under the clause as such an interpretation was a plausible view that a reasonable person could take and accordingly sustained the award. However, we are of the opinion that the aforesaid case and ratio may not be applicable herein as the evidence on record does not suggest that the parties had agreed to a broad interpretation to the clause in question. **28.** In this context, the interpretation of Clause 23 of the Contract by the Arbitral Tribunal, to provide a wide interpretation cannot be accepted, as the thumb rule of interpretation is that the document forming a written contract should be read as a whole and so far as possible as mutually explanatory. In the 19 case at hand, this basic rule was ignored by the Tribunal while interpreting the clause. **29.** The contract was entered into between the parties in furtherance of a tender issued by the Respondent herein. After considering the tender bids, the Appellant issued a Letter of Intent. In furtherance of the Letter of Intent, the contract (Contract No. CCO/FC/0040/95) was for drilling oil wells and auxiliary operations. It is important to note that the contract price was payable to the ‘contractor’ for full and proper performance of its contractual obligations. Further, Clauses 14.7 and 14.11 of the Contract states that the rates, terms and conditions were to be in force until the completion or abandonment of the last well being drilled. **30.** From the aforesaid discussion, it can be said that the contract was based on a fixed rate. The party, before entering the tender process, entered the contract after mitigating the risk of such an increase. If the purpose of the tender was to limit the risks of price variations, then the interpretation placed by the Arbitral Tribunal cannot be said to be possible one, as it would completely defeat the explicit wordings and purpose of the contract. There is no gainsaying that there will be price 20 fluctuations which a prudent contractor would have taken into margin, while bidding in the tender. Such price fluctuations cannot be brought under Clause 23 unless specific language points to the inclusion. **31.** The interpretation of the Arbitral Tribunal to expand the meaning of Clause 23 to include change in rate of HSD is not a possible interpretation of this contract, as the appellant did not introduce any evidence which proves the same. **32.** The other contractual terms also suggest that the interpretation of the clause, as suggested by the Arbitral Tribunal, is perverse. For instance, Item 1 of List II (Consumables) of Exhibit C (Consolidated Statement of Equipment and Services Furnished by Contractor or Operator for the Onshore Rig Operation), indicates that fuel would be supplied by the contactor, at his expense. The existence of such a clause shows that the interpretation of the contract by the Arbitral Tribunal is not a possible interpretation of the contract. **33.** For the aforesaid reasons, we are not inclined to interfere with the impugned judgment and order of the High Court setting 21 aside the award. The appeal is accordingly dismissed. There shall be no order as to costs. ## **CIVIL APPEAL NO. 900 OF 2012** **34.** In view of the judgment pronounced in C.A. No. 673 of 2012, the aforesaid matter is disposed of in the aforesaid terms. **..............................................J. (N.V. RAMANA) ..............................................J. (MOHAN M. SHANTANAGOUDAR) ..............................................J. (AJAY RASTOGI)** **NEW DELHI; MAY 11, 2020.** 22
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.