S.M. Abdul Majeed v. Assistant Engineer, Kerala State Electricity Board, Electrical Section, Wadakkancherry & Others
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- C. K. Abdul Rehim
- Judgment Date
- 2013-10-18
- Court Decision / Holding
- The Court does not interfere with the penalty; Ext.P4 and Ext.P6 penalties are sustained. However, the petitioner is exempted from paying interest if the balance demanded in Ext.P7 is remitted within two months, and is allowed to pay in two instalments (on or before 15.11.2013 and 15.12.2013). If not paid, interest will accrue from today.
- Final Disposition
- Writ petition disposed; penalty upheld; interest waived if balance paid within two months; instalment facility granted.
Parties to the Case
Appellants / Petitioners
- S.M. Abdul Majeed, Proprietor, M/S S.M. Steel Re-Rolling Mills, Enkekkadu P.O., Wadakkancherry, Thrissur District
Respondents
- Assistant Engineer, Kerala State Electricity Board, Electrical Section, Wadakkancherry, Thrissur District-680 582
- Deputy Chief Engineer, Kerala State Electricity Board, Electrical Circle, Irinjalakuda, Thrissur District-680 121
- Special Officer Revenue, Kerala State Electricity Board, Office of Special Officer (Revenue), Vaidyuthi Bhavanam, Pattom, Thiruvananthapuram 695 004
- Kerala State Electricity Board, Office of Special Officer (Revenue), Vaidyuthi Bhavanam, Pattom, Thiruvananthapuram - 695 001, represented by its Secretary
Legal Representation & Advocates
Counsels for Petitioners
- • Sri. Harisankar V. Menon
- • Smt. Meera V. Menon
- • Sri. Mahesh V. Menon
Counsels for Respondents
- • Smt. Nazeeba O.H., SC, K.S.E. Board
- • Sri. Jaice Jacob, SC, K.S.E. Board
Case Synopsis & Summary
This Kerala High Court writ petition challenges a penalty under Section 126 of the Electricity Act, 2003 imposed on HT industrial consumer S.M. Abdul Majeed for unauthorised additional load detected during a 9 October 2012 inspection. The Site Mahazar (Ext.P3) counted all installations and determined a total connected load of 259.672 KW (288.524 KVA) against an authorised load of 188.954 KW (209.949 KVA), leading to a penalty for unauthorised use of energy, and consequent twofold charge on the unauthorised load plus proportional energy charges for the preceding 12 months (Ext.P4). The Appellate Authority (Ext.P6) confirmed the penalty. The petitioner argues multiple grounds: (i) he had applied for and partly obtained approval to enhance contract demand, (ii) mere submission of an enhancement request cannot justify unauthorised loading, (iii) a scheme approved by the Electrical Inspectorate cannot override supply contracts, (iv) Regulation 51(5) cannot immunise him from liability, and (v) the excess demand charges were contractual, not penal. The respondents maintain the penalty is valid for unauthorised use. The Court upholds the penalty but grants relief: the petitioner is exonerated from interest if the balance is paid within two months and allowed to pay in two instalments, otherwise interest accrues.
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner contends that since he sought enhancement of the contract demand and the scheme was approved by the Electrical Inspectorate, penalisation for unauthorised loading is unsustainable. Mere submission of an application cannot justify unauthorised use; terms of supply require prior permission to connect additional load. Regulation 51(5) does not absolve liability, but cannot be used to impose double penalties. The excess demand charges in Ext.P2 relate to contract terms (Clause 15 Ext.P1) and are not penalties under Section 126. After inspection, there was an attempt to regularise; the subsequent enhancement should not exonerate the petitioner. He seeks waiver of interest and relaxation in payment.
Contentions of Respondents
The respondents submit that the penalty under Section 126 is warranted for unauthorised use of electricity; even with an application for enhancement, the consumer cannot connect additional load without approval. Regulation 51(5) empowers disconnection but does not relieve liability for unauthorised use; the excess demand is payable under the contract terms and penalties are distinct; the appellate confirmation of the penalty was proper. The writ petition should be dismissed or penalty upheld.
Cited Precedents (1)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Executive Engineer and Others v Seetaram Rice Mill | 2011 KHC 4978 | Positive | Cited to support that unauthorised usage constitutes penal action under Section 126; disconnection under Regulation 51(5) does not exempt liability. |
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against S.M. Abdul Majeed v. Assistant Engineer, Kerala State Electricity Board, Electrical Section, Wadakkancherry & Others and instantly map out authorities that support, challenge, or govern your position.
Extracted Judgment Text
Exact text extracted from official judgment records.