High Court of KeralaSingle JudgeDismissed

SISUPALAN K.M and others v. THE GOVERNMENT OF KERALA, ERNAKULAM DISTRICT CO-OPERATIVE BANK LTD, ADMINISTRATOR, REGISTRAR OF CO-OPERATIVE SOCIETIES

Case / Petition Number:WP(C).No. 21018 of 2018

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • ANIL K. NARENDRAN
Judgment Date
2018-09-07
Court Decision / Holding
In the result, this writ petition fails and the same is accordingly dismissed.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • SISUPALAN K.M
  • PURUSHOTHAMAN.P.B
  • THANKAMMA.P.G
  • SHAJI.S.B
  • PRADEEP.B
  • K.R.MEENA
  • V.K.SASIDHARAN
  • E.A.VISWANATHAN
  • LUCY JACOB

Respondents

  • THE GOVERNMENT OF KERALA
  • THE ERNAKULAM DISTRICT CO-OPERATIVE BANK LTD
  • ADMINISTRATOR
  • THE REGISTRAR OF CO-OPERATIVE SOCIETIES

Legal Representation & Advocates

Counsels for Petitioners

  • • SRI.P.N.MOHANAN
  • • SRI.C.P.SABARI

Counsels for Respondents

  • • SRI.N.RAGHURAJ (SC)
  • • SPL.GOVT.PLEADER SRI.P.SANTHOSHKUMAR

Case Synopsis & Summary

This is a Kerala High Court writ petition under Article 226 by retired employees of the Ernakulam District Co-operative Bank seeking quashing of Ext.P4 (G.O. No. 96/07, dated 20.03.2007) and mandamus to pay arrears of salary for the period 01.07.2002 to 30.06.2003 with 6% interest, as extended by judgments in connected matters. The petitioners rely on Ext.P5 (15.12.2016) and Ext.P6 (25.05.2018) and Ext.P7 (11.06.2018) to contend that arrears should be payable to all similarly situated employees. The Court recounts that the Division Bench in W.A.No.1222 of 2017 and connected cases held that arrears for 01.07.2002 to 30.06.2003 were to be extended, with differences on interest depending on the petitioner’s status, and that delay or laches would not bar relief to those who acted promptly after the 2016 judgment. The petition hinges on the continuing-wrong doctrine and the principle that relief in service matters should be extended to similarly situated persons, but the Court ultimately finds delay and laches in the petition itself, noting the petitioners approached the Court only after substantial delay. The result is dismissal of the writ petition with reasons grounded in laches and delay, despite supportive Constitutional and Supreme Court authorities cited in earlier judgments.

Provisions of Law Cited

Article 226 of the Constitution of IndiaArticle 14 of the Constitution of IndiaArticle 43 of the Constitution of India

Legal Doctrines & Maxims

  • Laches
  • Delays/Acquiescence
  • Promissory estoppel
  • Continuing wrong (service-related claims)
  • In rem vs in personam

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that the period 01.07.2002 to 30.06.2003, though disallowed for arrears by Ext.P4, is payable in terms of the subsequent judgments (Ext.P5, Ext.P6, Ext.P7) granting arrears in analogous cases. They emphasise that the 2016 Division Bench decision, followed by 2018 extensions, creates a binding expectation to pay arrears to similarly situated employees, especially where the dispute concerns a continuing wrong with no third-party prejudice, and where denial would undermine the policy implications of wage revisions for retirees.

Contentions of Respondents

The respondents argue delay and laches bar relief, citing the doctrine of fence-sitters and precedent that those who did not challenge the wrongful action earlier cannot claim the relief, except where the judgment is in rem giving universal benefit. They rely on the law laid down in Arvind Kumar Srivastava and Shri Hanuman Industries to deny relief based on late filing, acquiescence, and to some extent the need to protect settled rights and avoid reopening of issues.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
Union of India v. Tarsem Singh[2009 (1) KLT 101 (SC)]PositiveCited for the proposition that relief in service-related claims based on continuing wrong may be granted despite long delays, affecting the Court’s approach to extending relief in similar cases.
State of Uttar Pradesh v. Aravind Kumar Srivastava(2015) 1 SCC 347PositiveA cited principle that normally relief should extend to similarly situated persons, subject to exceptions like laches and acquiescence.
Shri Hanuman Industries—PositiveUsed to illustrate that deliberate laches and delay can disentitle claimants from earlier adjudications; helps frame the exceptions to equal-treatment doctrine.
Viswanathan v. Haripad Service Cooperative Bank Ltd.2018 (3) KLT 815PositiveSupports entitlement to pay revision arrears despite post-dated implementation; used to justify the potential extension of relief, with caveats.
Balkaran Singh v. State of Punjab(2006) 12 SCC 709PositiveCited for principles on policy decisions and Article 43-type considerations affecting implementing authorities.
Bharat Singh v. State of HaryanaAIR 1988 SC 2181PositiveAddressed pleading and evidentiary requirements in writ petitions, used to underscore procedural rigor.
K.C. Sharma and Ors. v. Union of India—PositiveCited to discuss which judgments create in rem vs in personam effects in policy-related relief (supra).

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against SISUPALAN K.M and others v. THE GOVERNMENT OF KERALA, ERNAKULAM DISTRICT CO-OPERATIVE BANK LTD, ADMINISTRATOR, REGISTRAR OF CO-OPERATIVE SOCIETIES and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** ## **THE HONOURABLE MR. JUSTICE ANIL K.NARENDRAN** ## **FRIDAY ,THE 07TH DAY OF SEPTEMBER 2018 / 16TH BHADRA, 1940** ## **WP(C).No. 21018 of 2018** ## **PETITIONER/S:** |**1**|**SISUPALAN K.M**| |---|---| ||**KANJIRATHINKAL HOUSE,SOUTH PARAVOOR.P.O,ERNAKULAM-**| ||**682307.**| |**2**|**PURUSHOTHAMAN.P.B**| ||**PADMALAYAM HOUSE,KUNJANBAVA**| ||**ROAD,PONNURUNNI,VYTTILA,ERNAKULAM-682019.**| |**3**|**THANKAMMA.P.G**| ||**PARACKAL HOUSE,SAHAVU DEVASSY**| ||**LANE,THYKOODAM,VYTTILLA,ERNAKULAM-682019.**| |**4**|**SHAJI.S.B**| ||**SREENILAYAM,THRIKKALATHOOR.P.O,ERNAKULAM-683541.**| |**5**|**PRADEEP.B**| ||**H.NO.8/291,MATTANCHERY,ERNAKULAM-682002.**| |**6**|**K.R.MEENA**| ||**PUTHENPURACKAL HOUSE,KUSUMAGIRI.P.O,KAKKANAD,CHN**| ||**30,ERNAKULAM.**| |**7**|**V.K.SASIDHARAN**| ||**VIRUTHIYAL HOUSE,NANDIKULANGARA,MANNAM.P.O,NORTH**| ||**PARAVOOR.**| |**8**|**E.A.VISWANATHAN**| ||**MANAKKAPARAMBIL**| ||**HOUSE,NADAKKABU.P.O,UDAYAMPERUR,ERNAKULAM-682307.**| |**9**|**LUCY JACOB**| ||**MOONJELY HOUSE,MRRA 69 C,NETHAJI ROAD,SOUTH**| ||**VAZHAKKALA,WEST KAKKANAD-682030.**| **==> picture [98 x 41] intentionally omitted <==** **BY ADVS. SRI.P.N.MOHANAN SRI.C.P.SABARI** **WP(C).No. 21018 of 2018** **2** ## **RESPONDENT/S:** |**1**|**THE GOVERNMENT OF KERALA**| |---|---| ||**REPRESENTED BY SECRETARY TO GOVERNMENT,CO-**| ||**OPERATIVE**| ||**DEPARTMENT,SECRETARIAT,THIRUVANANTHAPURAM-**| ||**695001.**| |**2**|**THE ERNAKULAM DISTRICT CO-OPERATIVE BANK LTD**| ||**REPRESENTED BY GENERAL MANAGER,KAKKANAD,KOCHI-**| ||**682030.**| |**3**|**ADMINISTRATOR**| ||**ERNAKULAM DISTRICT CO OPERATIVE BANK**| ||**LTD,KAKKAND,KOCHI-682030.**| |**4**|**THE REGISTRAR OF CO-OPERATIVE SOCIETIES**| ||**DEPARTMENT OF CO-OPERATION,OFFICE OF THE**| ||**REGISTRAR OF CO-OPERATIVE SOCIETIES,STATUE,NEAR**| ||**PRESS CLUB,THIRUVANANTHAPURAM-695001.**| ||**BY ADVS.**| ||**SRI.N.RAGHURAJ, SC, ERNAKULAM DISTRICT CO-**| ||**OPERATIVE BANK LTD.**| ||**SPL.GOVT.PLEADER SRI.P.SANTHOSHKUMAR**| **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 07.09.2018, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## **JUDGMENT** **The petitioners, who are retired employees of the 2[nd] respondent Bank, who retired from service on superannuation on various dates since 31.05.2005, have filed this writ petition under Article 226 of the Constitution of India, seeking a writ of certiorari to quash Ext.P4 Government order dated 20.03.2007 and** **WP(C).No. 21018 of 2018** **3** **seeking a writ of mandamus commanding respondents 2 and** **3 to pay arrears of salary from 01.07.2002 to 30.06.2003 with interest at the rate of 6%, within a time frame to be fixed by this Court, following the dictum laid down in Ext.P5 judgment dated 15.12.2016 in W.P.(C).No.34683 of 2009, Ext.P6 judgment dated 25.05.2018 in W.A.No.390 of 2018 and Ext.P7 judgment dated 11.06.2018 in W.P.(C).No.16806 of 2018. The petitioners have also sought for a declaration that they are entitled to get arrears of salary from 01.07.2002 to 30.06.2003 with interest within a time frame to be fixed by this Court.** **2. Heard the learned counsel for the petitioners, the learned Senior Government Pleader appearing for respondents 1 and 4 and also the learned Standing Counsel appearing for respondents 2 and 3.** **3. The entitlement of the employees of District Co-operative Banks for arrears of salary for the period from 01.07.2002 to 30.06.2003 has now been settled by Ext.P6 judgment of a Division Bench of this Court dated** **WP(C).No. 21018 of 2018** **4** ## **25.05.2018 in W.A.No.1222 of 2017 and connected cases.** ## **Paragraphs 19, 20 and the operative portion of the said** ## **judgment read thus :** _**“19. The case on hand is covered by the observations in paragraph 22.3, where the Apex Court has held that if the judgment of the court was in personam holding that benefit of the said judgment shall accrue to the parties before the court and such an intention is stated expressly in the judgment or it can be impliedly found out from the tenor and language of the judgment, those who want to get the benefit of the said judgment extended to them shall have to satisfy that their petition does not suffer from either laches and delay or acquiescence. The appellants in W.A.No.1231 of 2017 have no case that W.P. (C)No.34683 of 2009 is liable to be dismissed on the ground of delay and laches. The challenge in that writ petition is on the merits of the claim. It is in the connected cases that the ground of delay and laches is put forward. The judgment in W.P.(C)No.34683 of 2009 was delivered on 15.12.2016. The other writ petitions were filed immediately thereafter namely in March and April, 2017. It is no doubt true that none of the petitioners had challenged Ext.P5 Government order dated 20.3.2007 as soon as it was passed. They accepted it and retired from service. It was only after the petitioners in W.P.(C)No.34683 of 2009 succeeded in getting relief that the other writ**_ **WP(C).No. 21018 of 2018** **5** _**petitions were filed. As the dispute is about denial of arrears of salary and allowances, which stood revised with effect from 1.7.2002, for a period of 12 months commencing from 1.7.2002 and ending with 30.6.2003 and as the petitioners had moved this court within three months after W.P. (C)No.34683 of 2009 was allowed by a learned single Judge of this court, we find no reason or justification to deny relief to the petitioners on the ground that there was delay and laches and acquiescence on their part.**_ _**20. We however notice that the learned single Judge has directed disbursement of arrears of salary and allowances during the period from 1.7.2002 to 30.6.2003 with 6% interest. Except the petitioners in W.P.(C)No.34683 of 2009, the others had not moved the Government or this court in time. The petitioners in the connected writ petitions moved this court only in the year 2017. The Apex Court has in Union of India v. Tarsem Singh [2009 (1) KLT 101 (SC)] held that where a service related claim is based on a continuing wrong, relief can be granted even if there is a long delay as it does not affect the rights of third parties. It was also held that in such cases interest on arrears should be declined. In the instant case, if the claim made by the petitioners is granted it would not affect the settled rights of third parties. It will also not result in the reopening of issues already concluded. It would not also affect the seniority**_ **WP(C).No. 21018 of 2018** **6** _**of employees in service or their promotions. In the light of these facts, we find no reason or justification to deny relief to the petitioners on the ground of delay and laches. However, as the petitioners in W.P.(C)Nos.7146, 11337, 11344, 20741, 22430, 26955 and 27455 of 2017 moved this court only after W.P.(C)No.34683 of 2009 was heard and allowed, in the light of the principles laid down by the Apex Court in Union of India v. Tarsem Singh (supra) we are of the opinion that they are not entitled to interest. The petitioners in W.P. (C)No.34683 of 2009, from which W.A.No.1231 of 2017 arises, stand on a different footing. They had moved the Government claiming arrears of salary and allowances in the year 2008. They had thereafter moved this court on two occasions and it was in the last occasion that relief was granted to them. Merely for the reason that they were granted interest the petitioners in the other cases be granted that benefit. We are therefore of the opinion that except the petitioners in W.P. (C)No.34683 of 2009, the petitioners in the other writ petitions are not entitled to interest on the arrears of salary and allowances during the period from 1.7.2002 to 30.6.2003.**_ _**For the reasons stated above, we dismiss W.A.No.1231 of 2017, allow W.A.Nos.1222, 1247 and 1538 of 2017 and W.A.Nos.162, 163, 380 and 390 of 2018 in part to the extent it relates to the award of interest and vacate the direction issued by the learned single Judge in the respective writ petitions to pay**_ **WP(C).No. 21018 of 2018** **7** _**interest on the amounts due and payable to the petitioners therein towards arrears of salary and allowances during the period from 1.7.2002 to 30.6.2003. The judgments impugned in W.A.Nos.1222, 1247 and 1538 of 2017 and W.A.Nos.162, 163, 380 and 390 of 2018 shall stand affirmed in all other respects. No costs.” (underline supplied)**_ **4. In the judgment dated 25.05.2018 in W.A.No.1222 of 2017 and connected cases the Division Bench held that, as the dispute is about denial of arrears of salary and allowances, which stood revised with effect from 1.7.2002, for a period of 12 months commencing from 1.7.2002 and ending with 30.6.2003 and as the petitioners had moved this court within three months after W.P.(C)No.34683 of 2009 was allowed by the learned single Judge by the judgment dated 15.12.2016, there is no reason or justification to deny relief to the petitioners on the ground that there was delay and laches and acquiescence on their part. It was also held that if the claim made by the petitioners is granted it would not affect the settled rights of third parties. It will also not result in the reopening of issues** **WP(C).No. 21018 of 2018** **8** **already concluded. It would not also affect the seniority of employees in service or their promotions. In such circumstances, the Division Bench found no reason or justification to deny relief to the petitioners on the ground of delay and laches. However, as the petitioners in W.P.(C)Nos.7146, 11337, 11344, 20741, 22430, 26955 and 27455 of 2017 moved this Court only after W.P.(C)No.34683 of 2009 was heard and allowed, in the light of the principles laid down by the Apex Court in Union of India v. Tarsem Singh (supra), the Division Bench held that they are not entitled to interest.** **5. One of the main contentions raised by the learned Standing Counsel for the District Co-operative Bank is that the petitioners, who have waited till the disposal of W.A.No.1222 of 2017 and connected cases in approaching this Court, are not entitled for any relief on account of the delay and laches. The principle of denial of relief to fence-sitters has application in the facts of the case on hand and as such, they are not** **WP(C).No. 21018 of 2018** **9** **entitled for the relief sought for in this writ petition. The learned Standing Counsel would place reliance on the judgments of the Apex Court in State of Uttar Pradesh v. Aravind Kumar Srivastava [(2015) 1 SCC 347] and Union of India v. Shri Hanuman Industries [(2015) 6 SCC 600].** **6. Per contra, the learned counsel for the petitioners would point out that the judgment of the Division Bench of this Court in W.A.No.1222 of 2017 and connected cases is one rendered after taking note of the law laid down by the Apex Court in Arvind Kumar Srivastava's case (supra). The learned counsel would also place reliance on the judgment of a Division Bench of this Court in Viswanathan v. Haripad Service Cooperative Bank Ltd. [2018 (3) KLT 815].** **7. In Arvind Kumar Srivastava's case (supra), the Apex Court has stated in categorical terms that the normal rule is that when a particular set of employees are given relief by court, all other identically situated persons should be treated alike by extending** **WP(C).No. 21018 of 2018** **10** **the same benefit. In the said decision, the Apex Court has also held that the said principle will be subject to well recognized exceptions in the form of laches and delays as well as acquiescence. Those persons who did not challenge the wrongful action in their cases and acquiesced into the same and woke up after long delay only because of the reason that their counterparts who had approached the court earlier in time succeeded in their efforts, then such employees cannot claim that the benefit of the said judgment rendered in the case of similarly situated persons be extended to them. They** **would be treated as fence-sitters and laches and delays, and/or the acquiescence, would be a valid ground to dismiss their claim. Paragraphs 22 of the said decision reads thus :** _**“22. The legal principles which emerge from the reading of the aforesaid judgments, cited both by the appellants as well as the respondents, can be summed up as under:**_ _**22.1. Normal rule is that when a particular set of employees is given relief by the Court, all other identically situated persons need to be treated alike**_ **WP(C).No. 21018 of 2018** **11** _**by extending that benefit. Not doing so would amount to discrimination and would be violative of Article 14 of the Constitution of India. This principle needs to be applied in service matters more emphatically as the service jurisprudence evolved by this Court from time to time postulates that all similarly situated persons should be treated similarly. Therefore, the normal rule would be that merely because other similarly situated persons did not approach the Court earlier, they are not to be treated differently.**_ _**22.2. However, this principle is subject to well recognized exceptions in the form of laches and delays as well as acquiescence. Those persons who did not challenge the wrongful action in their cases and acquiesced into the same and woke up after long delay only because of the reason that their counterparts who had approached the Court earlier in time succeeded in their efforts, then such employees cannot claim that the benefit of the judgment rendered in the case of similarly situated persons be extended to them. They would be treated as fence-sitters and laches and delays, and/or the acquiescence, would be a valid ground to dismiss their claim.**_ _**22.3. However, this exception may not apply in those cases where the judgment pronounced by the Court was judgment in rem with intention to give benefit to all similarly situated persons, whether they approached the Court or not. With such a pronouncement the obligation is cast upon the authorities to itself extend the benefit thereof to all similarly situated persons. Such a situation can occur when the subject-**_ **WP(C).No. 21018 of 2018** **12** _**matter of the decision touches upon the policy matters, like scheme of regularisation and the like (see K.C. Sharma and Ors. v. Union of India, (supra). On the other hand, if the judgment of the Court was in personam holding that benefit of the said judgment shall accrue to the parties before the Court and such an intention is stated expressly in the judgment or it can be impliedly found out from the tenor and language of the judgment, those who want to get the benefit of the said judgment extended to them shall have to satisfy that their petition does not suffer from either laches and delays or acquiescence.”**_ **8. In Shri Hanuman Industries's case (supra), another decision relied on by the learned Standing Counsel for the District Co-operative Bank, the Apex Court was dealing with a case in which the coapplicants in the earlier round of litigation immediately approached the court and obtained relief. However, the respondent applicants before the Apex Court waited till the said relief was affirmed by the Apex Court on 01.05.2009 and only thereafter, on 27.08.2009, approached the High Court for similar relief. The Apex Court held that, the respondent applicants, in view of their deliberate laches,** **WP(C).No. 21018 of 2018** **13** ## **negligence and inaction have disentitled themselves to** **the benefit of adjudication in the earlier lis. Paragraphs 18 and 22 of the said decision read thus:** _**“18. The pleaded facts and the competing arguments have received our due attention. To start with, it is not disputed that the writ petitioners in the earlier round of adjudication were applicants under SPINE alike the respondents herein. They being appalled by the delay in the grant of their receivables thereunder and being faced with the letter dated 05-02-2007 whereby pending receipt and scrutiny of the reports as called for, further sanction/disbursement of Grants-in-Aid under the said scheme was stopped, did promptly approach the Guwahati High Court with a batch of writ petitions in the year 2007 itself and as narrated hereinabove were favoured with a direction to the implementing authorities for consideration of their application for the investment subsidy in accordance with law without being influenced by the said letter. Admittedly, the respondents herein elected not to join them and instead, soon thereafter this Court affirmed the above verdict on 01-05-2009, staked their claim on 27-08-2009. There is evidently thus a time lag of more than two years by which the respondents’ challenge was delayed.**_ _**18.1. It is a matter of record, that by letter/notification dated 04-05-2010 issued by the Secretary, Ministry of DONER, NEC, Shillong,**_ **WP(C).No. 21018 of 2018** **14** _**confirmation of the decision of withdrawal and closure of SPINE with effect from 23-02-2007, was notified. A plain perusal of the contents of this document would reveal in no uncertain terms that the withdrawal and closure of SPINE had been effected by an Order of Government of India vide NEC/PLAN/ii-23-2-2007. Thus the letter/notification dated 04-05-2010, did relate back to 23-02-2007 for all intents and purposes. Therefore the scheme, SPINE stood withdrawn and/or closed on and from 2302-2007. As a corollary, on a cumulative reading of the letters dated 05-02-2007, 23-02-2007 and 04-052010 as well as the resolution dated 21-02-2007 it is indubitable that SPINE stood withdrawn and/or closed with effect from 23-02-2007. As adverted to hereinabove, by letter dated 01-10.2007, as a consequential step, the proposal which had remained unprocessed as per the standard procedures of the scheme were returned to the State Governments. The list of proposals remitted back admittedly included those amongst others of the respondents herein. It is thus patent that on such date i.e. 01-10-2007, the claims of the respondents had not been accepted and in view of the closure of the scheme, were returned to the respective State Governments. In this pronounced backdrop, the plea of the respondents that at the institution of the writ petitions in 2009, no decision had been taken rejecting their applications fades into insignificance, as those by implication had not been entertained under the scheme.**_ **WP(C).No. 21018 of 2018** **15** _**18.2 The letters dated 04-08-2006, 04-09-2007 and 12-09-2007 to which our attention has been drawn in course of the arguments, suffice it to mention, do not contain any assurance on the part of the implementing authorities promising grant of the subsidy allowance under the scheme or any other incentive to the respondent. No reference has been made before us of any other document qua the other respondents. We are thus constrained to hold that there was no promise on the part of the public functionaries in charge of implementation of SPINE to the respondents to extend benefits thereunder, inspite of the decision to withdraw or close the same with effect from 23-02-2007.**_ ## _**xxx xxx**_ _**22. On a consideration of the totality of the aspects involved, we are thus of the unhesitant view that the respondents herein in view of their deliberate laches, negligence and inaction have disentitled themselves to the benefit of the adjudication in the earlier lis. In the accompanying facts and circumstances in our comprehension, it would be iniquitous and repugnant as well to the public exchequer to entertain the belated claim of the respondents on the basis of the doctrine of promissory estoppel which is even otherwise inapplicable to the case in hand.”**_ ## **9. In the instant case, a reading of judgment of** **the Division Bench of this Court dated 25.05.2018 in** **WP(C).No. 21018 of 2018** **16** **W.A.No.1222 of 2017 and connected cases would show that, after referring to the law laid down by the Apex Court in Arvind Kumar Srivastava's case (supra), the Division Bench held in paragraph 19 that, the case before it is covered by the observations in paragraph 22.3 wherein the Apex Court held that, if the judgment of the court was in personam holding that benefit of the said judgment shall accrue to the parties before the court and such an intention is stated expressly in the judgment or it can be impliedly found out from the tenor and language of the judgment, those who want to get the benefit of the said judgment extended to them shall have to satisfy that their petition does not suffer from either laches and delay or acquiescence. The Division Bench noticed that the appellants in W.A.No.1231 of 2017 have no case that W.P.(C).No.34683 of 2009 is liable to be dismissed on the ground of delay and laches. The challenge in that writ petition is on the merits of the claim. It is in the connected cases that the ground of delay and laches is put** **WP(C).No. 21018 of 2018** **17** **forward. The judgment in W.P.(C).No.34683 of 2009 was delivered on 15.05.2016. The other writ petitions were filed immediately thereafter, namely in March and April, 2017. None of the petitioners had challenged Ext.P5 Government Order dated 20.03.2007 as soon as it was passed. They accepted it and retired from service. It was only after the petitioners in W.P.(C).No.34683 of 2009 succeeded in getting relief that the other writ petitions were filed. As the dispute is about denial of arrears of salary and allowances, which stood revised with effect from 01.07.2002, for a period of 12 months commencing from 01.07.2002 and ending with 30.06.2003 and as the petitioners had moved this Court within three months after W.P.(C).No.34683 of 2009 was allowed by a learned Single Judge of this Court, the Division Bench found no reason or justification to deny relief to the petitioners on the ground that there was delay and laches and acquiescence on their part. However, the Division Bench found that the petitioners are not entitled for interest.** **WP(C).No. 21018 of 2018** **18** **10. In Viswanathan's case (supra), a decision relied on by the learned counsel for the petitioners, a Division Bench of this Court held that, the mere fact that the Co-operative Bank thought it fit to postpone the disbursement of the pay revision arrears in implementation does not affect the entitlement thereof. In the said decision, the Division Bench was dealing with a belated claim for pay revision arrears for the period from 01.07.1991 to 17.07.1998. After referring to the law laid down by the Apex Court in State of Punjab v. Balkaran Singh [(2006) 12 SCC 709] and also the provisions under Article 43 of the Constitution of India, the Division Bench held that the entitlement of the employees for the revised pay is not seriously in dispute and the main contention of the Co-operative Bank is that it was implemented much later. Therefore, the Division Bench held that, the mere fact that the Co-operative Bank thought it fit to postpone the disbursement of pay revision arrears in implementation does not affect the entitlement thereof. The pay** **WP(C).No. 21018 of 2018** **19** **revision orders issued by the Government itself enables the Registrar to grant time for effecting payment depending on the financial position of the Co-operative Bank. The obligation is on the Co-operative Bank (which is the employer) to disburse the salary promptly even without waiting for the employee to make a demand. The total salary included the pre-revised and revised pay and the admitted disbursement of a portion to the appellant during the period in question saves limitation even if there is any. Accordingly, the Division Bench directed the competent among the respondents to disburse the pay revision arrears due to the appellant within a period of three months from that judgment.** **11. In the instant case, the claim of the petitioners is for disbursement of pay arrears for the period from 01.07.2002 to 30.06.2003, which was sanctioned vide Ext.P4 G.O.(MS)No.96/07 dated 20.03.2007, with a restriction that the disbursement of monetary benefits on account of pay revision will be** **WP(C).No. 21018 of 2018** **20** **given only to the employees who have retired prior to 31.05.2005. The fact that the petitioners have also enjoyed the benefit of pay revision is not in dispute. However, they were denied arrears for the period from 01.07.2002 to 30.06.2003, in view of the restriction imposed in Ext.P4. By Ext.P5 judgment dated 15.12.2016 the said benefit was extended to the petitioners in W.P.(C).No.34683 of 2009. Ext.P5 judgment and the judgments in W.P.(C).Nos.7146 of 2017, 11344 of 2017, 11337 of 2017, etc. were under challenge before the Division Bench in W.A.No.1222 of 2017 and connected cases, which were filed in the year 2017 and 2018 respectively. Those writ appeals were disposed of by Ext.P6 judgment dated 25.05.2018. Now the petitioners have filed this writ petition on 25.06.2018 seeking extension of the benefit of Ext.P5 judgment dated 15.12.2016, which was affirmed by the Division Bench in Ext.P6 judgment dated 25.05.2018 in W.A.No.1222 of 2017 and connected cases. The petitioners would also place reliance on in Ext.P7 judgment of this Court dated** **WP(C).No. 21018 of 2018** **21** **11.06.2018 in W.P.(C).No.16806 of 2017, whereby, the benefit of Ext.P6 judgment of the Division Bench in W.A.No.1222 of 2017 was extended to the petitioner therein, who filed that writ petition in May, 2017, during the pendendcy of writ appeals challenging Ext.P5 judgment and connected matters.** **12. In the instant case, admittedly, the petitioners have not chosen to approach this Court either immediately after Ext.P5 judgment of the learned Single Judge or during the pendency of W.A.No.1222 of 2017 and connected cases. No reason whatsoever has been stated in the writ petition for the delay in approaching this Court.** **13. In Bharat Singh v. State of Haryana (AIR 1988 SC 2181), the Apex Court held that, when a point which is ostensibly a point of law is required to be substantiated by facts, the party raising the point, if he is the writ petitioner, must plead and prove such facts by evidence which must appear from the writ petition and if he is the respondent, from the counter-** **WP(C).No. 21018 of 2018** **22** **affidavit. If the facts are not pleaded or the evidence in support of such facts is not annexed to the writ petition or to the counter-affidavit, as the case may be, the Court will not entertain the point. The Apex Court held further that there is a distinction between a pleading under the Code of Civil Procedure Code, 1908 and a writ petition or a counter-affidavit. While in a pleading, i.e., a plaint or a written statement, the facts and not evidence are required to be pleaded, in a writ petition or in the counter-affidavit not only the facts but also the evidence in proof of such facts have to be pleaded and annexed to it.** **14. Having considered the averments in the writ petition and also the arguments advanced by the learned counsel on both sides, conclusion is irresistible that the petitioners who have waited till Ext.P5 judgment dated 15.12.2016 is affirmed by the Division Bench by Ext.P6 judgment dated 25.05.2018 and thereafter filed this writ petition on 25.06.2018, offering no explanation whatsoever for the delay in approaching** **WP(C).No. 21018 of 2018** **23** **this Court, going by the averments in the writ petition are not entitled for any relief in this writ petition, in exercise of the extraordinary jurisdiction under Article 226 of the Constitution of India.** **In the result, this writ petition fails and the** **same is accordingly dismissed.** **Sd/ANIL K.NARENDRAN, JUDGE** ## **APPENDIX** ## **PETITIONER'S/S EXHIBITS:** |**EXHIBIT P1**|**A TRUE COPY OF THE G.O.**<br>**(MS)NO.145/2005.CO.DATED 21.06.2005**| |---|---| ||| |**EXHIBIT P2**|**A TRUE COPY OF THE G.O(MS)NO.251/05 DATED**<br>**05.10.2005**| ||| |**EXHIBIT P3**|**A TRUE COPY OF THE G.O(MS)NO.21/2007**<br>**CO.DATED 06.01.2007**| ||| |**EXHIBIT P4**|**A TRUE COPY OF THE G.O.(MS()NO.96/07 DATED**<br>**20.03.2007**| ||| |**EXHIBIT P5**|**A TRUE COPY OF THE JUDGMENT DATED 15.12.2016**<br>**IN W.P.(C)NO.34683/09**| ||| |**EXHIBIT P6**|**A TRUE COPY OF THE JUDGMENT DATED 25.05.2018**<br>**IN W.A.NO.390/2018**| ||| |**EXHIBIT P7**|**A TRUE COPY OF THE JUDGMENT DATED 11.06.2018**<br>**IN W.P.(C)NO.16806/2018.**| AV/29/9