Siji Jacob and AISLE Isac alias AISLE Jacob v. Ultima Builders and Developers Pvt. Ltd.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- T. R. Ravi
- Judgment Date
- 2023-08-10
- Court Decision / Holding
- The second appeal is dismissed.
- Final Disposition
- Second appeal dismissed.
Parties to the Case
Appellants / Petitioners
- Siji Jacob
- AISLE Isac alias AISLE Jacob
Respondents
- Ultima Builders and Developers Pvt. Ltd., represented by its Director M.C.M. NajeeB
- M.C.M. NajeeB, Director, Ultima Builders & Developers, Nilampathinjamugal, MLA Road, Nilampathinjamugal, Rajagiri Valley, Kakkanad, Ernakulam, PIN-682 039.
Legal Representation & Advocates
Counsels for Petitioners
- • P. Haridas
- • Biju Hariharan
- • Shijimol M.Mathew
- • P.C. Shijin
- • Rishikesh Haridas
Counsels for Respondents
- • Sunil Shanker
- • SANDHRA.S
Case Synopsis & Summary
This Kerala High Court judgment (MSA No. 3 of 2022) concerns whether a housing project falls within the Real Estate (Regulation and Development) Act, 2016 (the 2016 Act) as an “ongoing project” on the appointed day and whether the appellants are entitled to a promised covered car park. The appellants, Siji Jacob and AISLE Isac alias AISLE Jacob, had contracted to purchase unit 12G from Ultima Builders and Developers Pvt. Ltd. with a promise of a covered car park; multiple letters between 2011 and 2018 failed to secure the parking space, and the sale deed did not record the parking. The core issue is whether the project qualifies as ongoing under the 2016 Act, which came into force in 2017. The respondents contend the project was completed prior to the sale and the occupancy certificate was issued in 2010, with the sale deed executed in 2011, and therefore the Act does not apply. The appellants rely on decisions including M/s Newtech Promoters and Developers Pvt. Ltd. v. State of UP (2021 KHC 6692) and Alfa Ventures (P) Ltd. v. State of Kerala (2022 (5) KHC 157) to argue for a broad interpretation. The court examines the distinction between completion and occupancy certificates, as addressed in Alfa Ventures, and notes that occupancy certificates issued before 2017 do not render a project an ongoing one under the 2016 Act. Ultimately, the court upholds the appellate authority’s finding that the project is not ongoing and dismisses the second appeal.
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants contend that their project should be treated as an ongoing project under the 2016 Act on the grounds that completion/occupancy certificates issued before 2017 indicate continued regulatory relevance, and that the decision in Alfa Ventures (P) Ltd. v. State of Kerala supports distinguishing completion certificates from occupancy certificates. They argue that the project, though completed in the early2010s, was still subject to regulatory oversight because the 2016 Act targets ongoing projects, and the absence of a car park is a breach of the sale agreement. They rely on Newtech Promoters and Developers Pvt. Ltd. v. State of UP & Others to stress that the relevant factor is the completion/occupancy status under the 2016 Act, with emphasis on the provider’s assurances and the lack of car parking as a continuing grievance.
Contentions of Respondents
The respondents submit that the project was completed before the sale deed; occupancy certificate was issued in 2010 and the building was numbered in 2010; the sale deed occurred in 2011, with no explicit car parking provision; the 2016 Act came into force only on 01.05.2017, and the twin requirements for ongoing projects are not satisfied; thus the project cannot fall under the 2016 Act. They argue there is no basis to treat pre-2017 occupancy as converting the project into an ongoing one for applicability of the Act, and contend that the appellate authority correctly found the project not ongoing.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| M/s. Newtech Promoters and Developers Pvt.Ltd. v. State of UP & Others | 2021 KHC 6692 | Mentioned Only | Cited by the appellants as persuasive authority; the court refers to it in passing within the argument but does not adopt or distinguish it as a controlling basis for its decision. |
| Alfa Ventures (P) Ltd. v. State of Kerala and Others | 2022 (5) KHC 157 | Positive | The court explicitly relies on Alfa Ventures to distinguish completion certificates under the 2016 Act from those under building rules and to discuss the concept of an 'ongoing project,' thereby treating Alfa Ventures as supportive and binding authority on the issue. |
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Siji Jacob and AISLE Isac alias AISLE Jacob v. Ultima Builders and Developers Pvt. Ltd. and instantly map out authorities that support, challenge, or govern your position.
Extracted Judgment Text
Exact text extracted from official judgment records.