Shri Mallikarjun Devasthan, Shelgi v. Subhash Mallikarjun Birajdar & Ors.
Case Synopsis & Summary
This matter concerns the acceptance of Change Reports under the Bombay Public Trusts Act, 1950 (Maharashtra Public Trusts Act, 1950) affecting the Vahiwatdar (Administrator) and trustees of Shri Mallikarjun Devasthan, Shelgi. Registered under Section 18, the trust followed a mode of succession where the eldest male of Mallikarjun Patil’s family would be Vahiwatdar, with power to co-opt others. After the death of the original Vahiwatdar, Jagdishchandra Mallikarjun Patil (the third son) assumed office and subsequently co-opted four trustees. Change Report No. 899 of 2015 recorded his name in the Section 17 register and was accepted, and later Change Report No. 1177 of 2017 recorded the four co-opted trustees; both were upheld by the Deputy/Assistant Charity Commissioner. Five devotees challenged these changes under Section 70A, and the Bombay High Court quashed the acceptance on the ground that there was no separate order condoning the delay beyond 90 days as required by Section 22. The Supreme Court held that amendments in 2017 added a proviso to Section 22(1) enabling condonation for sufficient cause, which need not be accompanied by a written application; delay is curable, and non-automatic invalidation of the Vahiwatdar’s office can occur. Accordingly, the appeals were allowed and the Change Reports confirmed, with the High Court judgment set aside.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- A.S. Bopanna
- Sanjay Kumar
- Judgment Date
- 2024-04-25
- Court Decision / Holding
- Appeals allowed; acceptance of Change Reports Nos. 899 of 2015 and 1177 of 2017 confirmed; High Court judgment set aside; writ petitions disposed; parties to bear their own costs.
- Final Disposition
- Appeals allowed
Parties to the Case
Appellants / Petitioners
- Shri Mallikarjun Devasthan Shelgi
Respondents
- Subhash Mallikarjun Birajdar
- Abhijeet Prakash Birajdar
- Kalyani Mallappa Birajdar
- Sachin Shivanand Birajdar
- Kedar Shivanna Birajdar
Legal Representation & Advocates
Counsels for Petitioners
- • Shyam Divan
- • Abhay Anil Anturkar
- • Dhruv Tank
- • Nitin Habib
- • Aniruddha Awalgaonkar
- • Bhagwant Deshpande
- • M/S Dr. R.R. Deshpande and Associates
Counsels for Respondents
- • Sudhanshu S. Choudhari
- • A. Selvin Raja
Provisions of Law Cited
Legal Doctrines & Maxims
- Delay condonation should be liberal and justice-oriented; not mandatory that a written application be filed for condonation of delay; relief can be granted on oral request if sufficient cause is shown
- Condonation of delay is curable and does not automatically invalidate changes in the Trust once the proper statutory remedies are available
- 2017 amendments clarificatory in nature and do not alter substantive rights; reliance on Limitation Act provisions remains applicable
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants submitted that the delay in filing the Change Reports is curable under the 2017 proviso to Section 22(1) of the Bombay Public Trusts Act, which allows extension for sufficient cause and does not mandatorily require a written application for condonation; relief can be granted on oral request if sufficient cause is shown. The proviso is clarificatory and does not negate applicability of Limitation Act protections; delay cannot automatically invalidate the Vahiwatdar’s office; records must be kept updated and remedies exist under the Act.
Contentions of Respondents
The devotees argued that there was no separate order condoning the long delay in filing Change Report No. 899 of 2015, and that the High Court correctly held the absence of such an order invalidated the Change Reports; they contended that delay beyond 90 days cannot be condoned absent a formal order and that the revision machinery should fix accountability for the delay; they asserted that the challenge to the validity of the Vahiwatdar’s appointment should not be bypassed by surmised condonation.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Bhagmal & Ors. v. Kunwar Lal & Ors. | [2010] 8 SCR 1104 : [2010] 12 SCC 159 | Positive | Cited to support liberal condonation of delay and that relief can be granted for sufficient cause; written application not mandatory. |
| Sesh Nath Singh & Anr. v. Baidyabati Sheoraphuli Co-operative Bank Ltd. & Anr | [2021] 3 SCR 806 : [2021] 7 SCC 313 | Positive | Cited as authority for delay condonation under Limitation Act and doctrine of sufficient cause. |
| Esha Bhattacharjee v. Managing Committee of Raghunathpur Nafar Academy & Ors. | [2013] 9 SCR 782 : [2013] 12 SCC 649 | Positive | Relied on for liberal, pragmatic approach to condonation of delay. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Shri Mallikarjun Devasthan, Shelgi v. Subhash Mallikarjun Birajdar & Ors.
Related Decisions & Precedents from Supreme Court of India (2024)
Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors
This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.
Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others
Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.
Union of India v. M/s Indian Oil Corporation Ltd.
This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.
Gene Campaign & Anr. v. Union of India & Ors.
This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.