Tenetowl LogoTenetowl
Landmark CasesDivision BenchAppeal allowed; insurer directed to pay full cl...

Shri Binod Kumar Singh vs National Insurance Company Ltd.

Case Synopsis & Summary

The appellant, Binod Kumar Singh, owned a truck insured with National Insurance Company Ltd. The truck (BR-02 Q9220) caught fire on 8 June 2014 within the policy period 18.09.2013 to 17.09.2014, while the vehicle was in Bihar. The State Consumer Disputes Redressal Commission directed the insurer to settle the claim on a non-standard basis, relying on National Insurance Company vs. Nitin Khandelwal (Criminal Appeal No. 8463/2014). The National Commission reversed, holding that Nitin Khandelwal does not help since it was a theft case and the present matter concerns fire damage, and relied on Amrit Paul Singh & Anr. vs. Tata AIG General Insurance Co. Ltd. & Ors. (2018) 7 SCC 558 to deny the claim in the absence of a valid permit. The appellant asserted that a National Permit was valid from 14.10.2012 to 13.10.2017 and, since the loss occurred within Bihar, no authorization fee was required beyond 14.10.2013; the permit was issued by a competent Bihar authority and remained valid. The Supreme Court examined the permit, found it valid up to 13.10.2017, and held that repudiation was unjust. It allowed the appeal and directed the insurer to process and pay the full claim within 60 days, with interest at 9% per annum from the date of the complaint until payment, with no costs. An upshot is restoration of the State Commission’s order and affirmation of the insured’s right to the claim.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • B. V. Nagarathna
  • Satish Chandra Sharma
Judgment Date
2025-02-07
Court Decision / Holding
Appeal allowed. The National Insurance Company is directed to process and pay the full claim amount within 60 days from today, with interest at 9% per annum from the date of the complaint until payment. No costs. Pending applications, if any, are disposed of. The decision reiterates that the permit validity, not paid authorization fee beyond a specified period for intra-state use, was sufficient to uphold the insurer’s liability in Bihar.
Final Disposition
Appeal allowed; insurer directed to pay full claim with 9% interest within 60 days; no costs.

Parties to the Case

Appellants / Petitioners

  • Shri Binod Kumar Singh

Respondents

  • National Insurance Company Ltd.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that a National Permit was valid from 14.10.2012 to 13.10.2017 and remained in force in Bihar at the time of the loss on 08.06.2014. Authorization fees were payable only when the vehicle moved out of Bihar; since the loss occurred within Bihar, the permit was valid and the insurer’s repudiation lacked legal basis. The decision in Nitin Khandelwal (theft case) is distinguishable and Amrit Paul Singh was cited to emphasize permit validity as a condition for liability. The claim should be paid with interest from the date of the complaint.

Contentions of Respondents

The respondent insurer argued that the authorization fee had not been deposited beyond 14.10.2013, and under the permit terms the vehicle’s movement out of Bihar triggered the fee; hence without a valid permit the claim should be denied. It was argued that the decisions relied upon by the State Commission did not directly apply to a fire loss and that the National Commission’s reversal was appropriate.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
National Insurance Company Vs. Nitin KhandelwalCriminal Appeal No. 8463/2014DistinguishedIt involved a theft case; the court held it not applicable to a fire-damage claim under the present facts.
Amrit Paul Singh and Anr. Vs. Tata AIG General Insurance Co. Ltd. & Ors.2018) 7 SCC 558Positive relied upon to emphasize that permit validity is a prerequisite for liability; the present judgment accepts the permit validity in the instant case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•968 words•~5 min read

In The Court Record

Shri Binod Kumar Singh vs National Insurance Company Ltd.

2025 INSC 154 **==> picture [72 x 72] intentionally omitted <==** ## **REPORTABLE** **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. OF 2025** **[Arising out of SLP (Civil) No. 13060 of 2020]** **Shri Binod Kumar Singh Appellant Versus National Insurance Company Ltd. Respondent** ## **J U D G M E N T** ## **SATISH CHANDRA SHARMA, J.** 1. Leave Granted. 2. The present appeal is arising out of order dated 19.08.2020 passed by National Consumer Disputes Redressal Commission, New Delhi, (for short, “the National Commission”) in First Appeal No. 1778 of 2017 . **==> picture [46 x 5] intentionally omitted <==** **----- Start of picture text -----**<br> Signature Not Verified<br>**----- End of picture text -----**<br> Digitally signed by RADHA SHARMA Date: 2025.02.07 15:40:44 IST Reason: 3. The facts of the case reveal that the appellant before this Court is the owner of Truck bearing registration No. BR-02Q9220 make TATA-251625.0LPKTC. The truck was insured with the respondent National Insurance Company for a period of one year i.e. from 18.09.2013 to the midnight of 17.09.2014 and unfortunately, the truck caught fire on account of short-circuit on SLP (Civil) No. 13060 of 2020 Page 1 of 5 08.06.2014 meaning thereby during the validity of insurance cover. 4. The appellant preferred a complaint before the State Consumer Disputes Redressal Commission, Bihar, Patna (for short, “the State Commission”) and the State Commission placing reliance on the judgment delivered in the case of _**National Insurance Company Vs. Nitin Khandelwal**_ (Criminal Appeal No. 8463/2014) directed the respondent insurance company to settle the claim on non-standard basis within a period of three months if other requirements were fulfilled by the appellant. 5. The respondent National Insurance Company being aggrieved by the order passed by the State Commission dated 07.07.2017 preferred an appeal before the National Commission and the National Commission has allowed the appeal holding that the judgment delivered by this Court in the case of _**Nitin Khandelwal**_ (supra) does not help the appellant as it was a theft case whereas the present case relates to damage by fire. The National Commission after placing reliance upon the judgment delivered in the case of _**Amrit Paul Singh and Anr. Vs. TATA AIG General Insurance Co. Ltd. & Ors.**_ (2018) 7 SCC 558 has allowed the appeal and held that the insurance claim cannot be SLP (Civil) No. 13060 of 2020 Page 2 of 5 allowed in the absence of any valid permit thereby setting aside the order passed by the State Commission. 6. Learned counsel for the appellant has vehemently argued before this Court that the All India Permit (National Permit) was issued having validity period with effect from 14.10.2012 to 13.10.2017 and for State of Bihar, the permit was in force from 13.10.2012 to 13.10.2013 meaning thereby, on the date the truck caught fire on 08.06.2014, there was a valid National Permit in existence. 7. Learned counsel for the respondent National Insurance Company has vehemently argued before this Court that as per the terms and conditions of the permit, the fee was deposited for a period with effect from 13.10.2012 to 13.10.2017 and the authorization fee was not deposited beyond 14.10.2013 and, therefore, and in the absence of non-depositing of authorization fee, National Permit cannot be said to be a valid permit. 8. This Court has carefully gone through the permit which is on record and the National Permit is certainly valid up to 13.10.2017. The authorization fee was required to be paid only when the truck was moving out of State of Bihar as it was registered in the State of Bihar and the truck caught fire on account of short-circuit on 08.06.2014 in the State of Bihar itself and, therefore, the respondent company could not have SLP (Civil) No. 13060 of 2020 Page 3 of 5 repudiated the claim on such a frivolous ground. The permit in question was issued by the competent authority in Bihar and, therefore, there was no requirement of paying authorization fee when the truck was being used in the State of Bihar and as per the terms and conditions of the National Permit, authorization fee was required to be paid only when the truck was moving out of State of Bihar. Thus, in the considered opinion of this Court, the appellant was certainly entitled for the insurance claim as held by the State Commission and, therefore, the order passed by the National Commission, dated 19.08.2020, deserves to be set aside and is accordingly set aside. The respondent National Insurance Company is directed to process the claim of the appellant and to pay the amount to the appellant within a period of 60 days from today. It is needless to mention that the claim became due in the year 2014 and it was repudiated by the respondent National Insurance Company in the year 2014 itself. The order of the State Commission allowing the claim was passed in the year 2017 which was reversed by the National Commission in the year 2020. Therefore, in the considered opinion of this Court, the appellant was not only entitled for the entire claim amount right from the date it became due but he is also entitled for interest from the date of the complaint made before State Commission till the date, the amount is actually paid to him. The appellant shall SLP (Civil) No. 13060 of 2020 Page 4 of 5 be entitled to interest @ 9% per annum and the same with the proposed amount be paid positively within 60 days from today. 9. With the aforesaid, the appeal stands allowed. No orders as to costs. Pending applications, if any, shall stand disposed of. **……………………………………J. [B. V. NAGARATHNA]** **……………………………………J. [SATISH CHANDRA SHARMA]** NEW DELHI February 7[th] , 2025. SLP (Civil) No. 13060 of 2020 Page 5 of 5
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.