Court Decision / Holding
The appellants are permitted to submit a concrete proposal as to how they shall ensure compliance with the norms within two months. The proposal shall be considered, and a decision on it shall be taken within three months. The appellants may, if advised, seek an alternative site, and the authorities shall examine feasibility. Interim orders passed on 15.12.2003 shall continue for three months. The appeal is disposed of with no costs.
Final Disposition
Appeal disposed

Parties to the Case

Appellants / Petitioners

  • Sheikh Ikram Sheikh Israil
  • Others

Respondents

  • State of Maharashtra
  • Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Arun Pednekar
  • • Naresh Kumar

Counsels for Respondents

  • • M.N. Rao
  • • Ravindra Keshavrao Adsure
  • • S.S. Shinde
  • • Satyajit A. Desai
  • • Anagha S. Desai
  • • Anmol N. Suryawanshi
  • • Vikram Saluja
  • • Venkateshwara Rao Anumolu

Case Synopsis & Summary

This appeal stems from a writ petition challenging notices issued by the police to halt the appellants’ brass utensil manufacturing operations conducted from their residences in Bhandara, on the ground that the process generated noise pollution affecting nearby schools, teachers and residents. The Bombay High Court had dismissed the petition following a report from the Maharashtra Pollution Control Board, and the appellants challenged that decision in the Supreme Court. The central issue concerns the balance between livelihood concerns of small, home-based artisans and the public interest in controlling noise under environmental statutes. The Noise Pollution (Regulation and Control) Rules, 2000, framed under the Environment (Protection) Act, 1986, lay at the core of the approach as to ambient noise limits and enforcement. The appellants argued that the noise levels were marginal and that they should be afforded an opportunity to implement remedial measures and to propose concrete steps for consideration by authorities. The respondents and authorities contended the notices were justified given the nuisance, and supported enforcement of the rules. The Court did not shut down the activity; instead it permitted the appellants to submit a concrete proposal within two months for ensuring compliance with norms, to be decided within three months, and even consider an alternative site. Interim orders were extended for three months.

Provisions of Law Cited

Environment (Protection) Act, 1986Noise Pollution (Regulation and Control) Rules, 2000Environment (Protection) Rules, 1986Section 3(2)(ii) of Environment (Protection) Act, 1986Section 3(1) of Environment (Protection) Act, 1986Section 6(2) of Environment (Protection) Act, 1986Section 25 of Environment (Protection) Act, 1986Rule 5 of Environment Protection Rules, 1986

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the noise pollution level was low and there was marginal variation; therefore, the notice issued by the Superintendent is without any basis. They argued they should be given an opportunity to reduce noise and to place concrete remedial measures and suggestions for consideration of the authorities.

Contentions of Respondents

The respondents, supported by the State, the Maharashtra Pollution Control Board and intervenors, contended that the notices were justified in seeking to curb nuisance caused by noise; they urged strict enforcement of ambient noise standards under the Noise Pollution Rules and the Environment Act.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Sheikh Ikram Sheikh Israil v. State of Maharashtra and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

~ ~' _.,) # SHEIKH IKRAM SHEIKH ISRAIL AND ORS. v. # STA TE OF MAHARASHTRA AND ORS. ## APRIL 12, 2007 "). \ [DR. ARIJIT PASA YAT AND LOKESHWAR SINGH PANT A, JJ.] _Environmental law-Noise Pollution-Manufacturing of brass utensils by residents of locality in their houses-Resulting in noise pollution-Issuance of notice to stop the activities-Writ petition by manufacturers, dismissal of-_ c _On appeal held: In view of the opportunity sought by residents to reduce noise level, residents to give concrete proposal regarding control of noise pollution-Noise Pollution (Regulation and Control) Rules, 2000._ Appellants are engaged in manufacturing of brass utensils in their respective houses at place B. Respondent No. 3-Superintendent of Police issued D notices to the appellants directing them to stop their business since noise pollution was created in the process of preparing brass utensils which affected the neighbours, teachers and students around and nearby the houses of the appellants. Appellants filed writ petition challenging off the order of respondent no. 3. High Court dismissed the Writ petition in view of the report of the State Pollution Control Board. Hence the present appeal E E Appellants contended that the noise pollution level was low and thus, the notice was without any basis; and that they should be given an opportunity to take remedial measures to reduce the noise level and also be permitted to place suggestions for consideration of the Authorities. F ## Disposing the appeal, the Court HELD: Appellants are permitted to give a concrete proposal as to how they would ensure sticking of the norms within two months. The proposal would be dealt with; a decision to be taken within three months. Further, the G appellants may move the authorities for making available alternative site and the Authorities would consider the feasibility. [Paras 12 and 13) (59-F-G) CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4533 of2004. _55_ H _56_ SUPREME COURT REPORTS (2007] _5_ S.C.R. _f_ A From the Judgment and Order dated 07 .10.2003 of the High Court of Judicature at Bombay, Nagpur Bench, Nagpur in Writ Petition No. 2898 of 2003. Arun Pednekar and Naresh Kumar for the Appellants. B c M.N. Rao, Ravindra Keshavrao Adsure, S.S. Shinde, Satyajit A. Desai, Anagha S. Desai, Anmol N. Suryawanshi, Vikram Saluja and Venkateshwara Rao Anumolu for the Respondents. Tue Judgment of the Court was delivered by **DR.** ARIJIT **P** ASAY AT, J. 1. Challenge in this appeal is to the order passed by a Division Bench of the Bombay High Court, / Background facts in a nutshell are as follows: 2. Appellants are residents of Bhandara since the time of their forefathers. **D**[They are engaged ][in ][the business ][of ][manufacturing brass utensils. ] Undisputedly they carry on the same business in their respective houses. 3. On 18.7.2003 the Superintendent of Police, Bhandara issued notices to the appellants directing them to stop their business within two days from the date of receipt of the order, failing which suitable legal action would be E taken. Tue reasons disclosed in the notice were that in the process of preparing brass utensils, noise pollution is created which affects the neighbours, teachers and students around and nearby the houses of the appellants. Tue appellants took the stand that they were in business before the opening of the school in the vicinity of their houses and there cannot be any complaint of noise F[pollution against ][them. ][On ][that ][basis ][the ][writ ][petition ][was ][filed ][impugning ] order of the Superintendent of Police. Reply affidavit was filed by the said Superintendent of Police as respondent No. 3 in the writ petition indicating that the mechanical power is used in the production of brass utensils as it facilitates pressing, embossing, spinning, cutting and buff polishing. It was stated that because of the aforesaid activities noise pollution in the vicinity G is caused and the area being thickly and densely populated area, it. was causing annoyance in addition to noise pollution. The Superintendent of Police had called for a report from the Maharashtra Pollution Control Board, Nagpur (in short the 'Board') who had also suggested that the noise level in the area is very high and amounted to nuisance. H 4. In view of the above position, the writ petition was di!;missed. f. i... SHEIKHIKRAMSHEIKH ISRAIL v. STATE OF MAHARASHTRA [PASAYAT,J.] 57 ~ 5. In support of the appeal learned counsel for the appellanis submitted that the noise pollution level was low and there was marginal variation and, therefore, the notice issued by the Superintendent is without any basis. 6. Learned counsel for the State of Maharashtra, the Board and the applicants for intervention supported the order. B 7. It appears that earlier a writ petition was filed in the Nagpur Bench of the High Court. In that case applications for interventions were filed on behalf of the school and some local residents. The writ petition was disposed of granting liberty to the parties to place the materials in support of their respective stands before the concerned authorities. The Noise Pollution C (Regulation and Control) Rules, 2000 (in short the 'Rules") have been framed in exercise of powers conferred by clause (ii) of sub-section (2) of Section 3, sub section (1) and clause (b) and sub Section (2) of Section 6 and Section 25 of the Environment (Protection) Act, 1986 (in short the 'Environment Act') read with Rule _5_ of the Environment Protection Rules, 1986 (in short the 'Environment Rules'). D D 8. Rules 3, 4 and 6 of the Rules read as follows: "(3) Ambient air Quality standards in respect of noise for different areas/zones E I) The ambient air quality standards in respect of noise for different areas/zones shall be such as specified in the schedule annexed to these rules. 2) The State Government may categorize the areas into industrial, commercial, residential or silence areas/zones for the pw-pose of implementation of noise standards for different areas. F 3) The State Government shall take measures for abatement of noise including noise emanating from vehicular movements and ensure that the existing noise levels do not exceed the ambient air quality standards specified under these rules. G 4) All development authorities, local bodies and other concerned authorities while planning developmental activity or carrying out functions relating to town and country planning shall take into consideration all aspects of noise pollution as a parameter of quality of life to avoid noise menace and to achieve the objective of maintaining the ambient air quality standards in H 58 [2007) 5 S.C.R. SUPREME COURT REPORTS _(_ A A respect of noise. 5) An area comprising not less than I 00 metres around hospitals, educational institutions and courts may be declared as silence area/zone for the purpose of these rules. B 4) Responsibility as to enforcement of noise pollution control measures:- 1) The noise levels in any area/zone shall not exceed the ambient air quality standards in respect of noise as specified in the schedule / 2) The authority shall be responsible for the enforcement of noise C pollution control measures and the due compliance of the ambient air quality standards in respect of noise. 6) Consequences of any violation in silence zone/area :- Whoever, in any place covered under zone/area commits any of the D following offence, liable for penalty under the provisions of the Act :- (i) Whoever, plays any music or used any sound amplifiers, (ii) Whoever, beats a drum or tom-tom or blows a horn either musical or pressure, or trumpet or beats or sounds any instrument, or E (iii) Whoever, exhibits any mimetic, musical or other performances of a nature to attract crowds." 9. In the Gazette ofindia : Extraordinary (Part II) it has been notified as under: F Ambient Air Quality Standards in respect of Noise. |Area<br>Categoryof<br>Code<br>area/zone|Area<br>Categoryof<br>Code<br>area/zone|Limitindb(A)leq*<br>Day Time<br>NightTim~| |---|---|---| |A|IndustrialArea|75<br>'Xl| |B|CommercialArea|65<br>55| |c|ResidentialArea|55<br>45| |D|SilenceZone|50<br>40| _)_ H Note:- I. Day time shall mean from 600 a.m. to IO p.m 59 SHEIKH !KRAM SHEIKH IS RAIL _v._ STA TE OF MAHARASHTRA (PASAYA T, J.] A -' 4. 2. Night time shall mean from 10.00 p.m. to 6.00 a.m. 3. Silence zone is defined as an area comprising not less than JOO metres around hospitals, educational institutions and courts. The silence zones are declared as such by the competent authority. 4. Mixed categories of areas may be declared as one of the four above mentioned categories by the competent authority. B *. dB(A) Leq denotes the time weighed average of the level of sound in decibels on scale A which is relatable to human hearing. A "decibel" is a unit in which noise is measured. "A" in dB(A) Leq. Denotes the frequency weighting in the measurement C of noise and corresponds to frequency response characteristics of the human hearing. Leq: It is an energy mean of the noise level over a specified period. IO. The Government of Maharashtra also has empowered the concerned authority for prohibiting the continuance of music or noise and the power D includes prevention, prohibition, control or regulation of the carrying on in/ or upon any premises of trade, avocation or operation or process. resulting in/or attended with noise. 11. Learned counsel for the appellant submitted that they should be given an opportunity to reduce the noise level and remedial measures can be E taken and suggestions in this regard shall be placed for consideration of the authorities. 12. In the circumstances we direct that the appellants are permitted to give a concrete proposal as to how they shall ensure sticking of the norms within two months. The proposal shall be dealt with; a decision to be taken F within three months. 13. The appellants may, if so advised, and as contended move the authorities for making available alternative site. The feasibility by such a request shall be duly considered by the authorities. 14. For a period of three months the interim orders, passed by this Court G on 15.12.2003, shall be continued. By giving this interim protection it shall not be considered as if we have expressed any opinion on the merits of the case. 15. The appeal is accordingly disposed of. No costs. Appeal disposed. H NJ.