Sheela Sreekumar, Sheena, Sheeja and P. Natarajan v. State of Kerala, The Corporation of Kollam, Town Planner, Kollam Development Authority

Case / Petition Number:
WP(C) No. 30357 of 2006
Neutral Citation:null

Case Synopsis & Summary

This writ petition challenges Ext.P2, a letter by the Town Planning Officer of Kollam Corporation, declining occupancy certificates, and Ext.P3, the Corporation Secretary’s order reaffirming that decision, in respect of a single property where three buildings were constructed under one plan following zonal exemptions. The petitioners, legal representatives of late Smt. Mani, had obtained zonal exemption from the Government (G.O. 18.12.2003) allowing construction in a residential zone for a commercial auditorium, lodge and related facilities. Pursuant to permits issued by the Corporation, two structures already received occupancy certificates, while a third, a three-storey lodge building, was completed with Ext.P1. After delay and action by the Corporation, Ext.P2 refused occupancy until regularisation of the existing two structures, and Ext.P3 upheld that constraint. The petition argues that zoning exemptions should permit such development under Clauses of the Master Plan and Rules, and that denial would cause substantial financial loss. The court, while noting the government’s and corporation’s stand that the development violates the Town Planning Act and Master Plan, nonetheless disposed the petition by directing provisional occupancy for the lower floors de hors Ext.P2 and Ext.P3, conditional on Fire Department NOC and pending Tribunal appeal under the Local Self Government Act.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C. KuriaKose
Judgment Date
2006-12-12
Court Decision / Holding
The petition is disposed with directions: the 2nd respondent, Kollam Corporation, shall issue occupancy certificates for the ground, first and second floors of the lodge building constructed under Ext.P1 de hors Exts.P2 and P3, conditioned on the petitioners producing a no-objection certificate from the Fire Department. This relief is subject to the final outcome of the petitioners’ appeal against Ext.P3 before the Tribunal for Local Self Government Institutions, filed within three weeks of receiving this judgment. If an appeal is received, the Tribunal will treat it as timely and dispose of it in accordance with law.
Final Disposition
Writ Petition disposed of with directions to issue occupancy certificates for the lower floors de hors Ext.P2 and Ext.P3, subject to Fire Dept NOC and pending Tribunal appeal; petitioners to file appeal within three weeks; Tribunal to decide in due course.

Parties to the Case

Appellants / Petitioners

  • Sheela Sreekumar
  • Sheena
  • Sheeja
  • P. Natarajan

Respondents

  • State of Kerala
  • The Corporation of Kollam
  • The Town Planner, Kollam Development Authority

Legal Representation & Advocates

Counsels for Petitioners

  • • Smt. V.P.Seemandhini (Senior)
  • • Sri.M.S.Unnikrishnan
  • • Smt.T.B.Remani
  • • Smt.S.Karthika
  • • Sri.M.R.Anison
  • • Sri.T.R.Rajesh

Counsels for Respondents

  • • Sri Mathew G.Vadakkel (Standing Counsel)
  • • Sri M.K.Chandramohan Das (SC)

Provisions of Law Cited

Rule 12, Town Planning ActRule 16, Kerala Municipality Building Rules, 1999Rule 30(3), Kerala Municipality Building Rules, 1999Section 160, Kerala Municipality ActSection 271S, Kerala Panchayat Raj ActClauses 6.1(1), 6.2(2), 6.3(3) of Kollam Development Authority Master PlanG.O.(Rt.) 4493/2003/LSGD dated 18.12.2003

Legal Doctrines & Maxims

  • Sayeesh Kumar v. State of Kerala (Division Bench principles)
  • Nobody has a right to occupancy certificate in violation of the Town Planning Act and the Scheme

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that the three-storied lodge on the plot should be assessable for occupancy based on the extant zoning exemptions under the Master Plan and the Kerala Municipality Rules. They rely on Clauses 6.2(2), 6.1(1) and 6.3(3) of the approved Master Plan and Rule 30(3) of the Kerala Municipality Building Rules to argue that lodging, hostels and related uses fall within permissible residential uses or require only zonal exemptions rather than a blanket denial. They contend that construction was carried out with government and corporation approvals, and that denial would cause substantial financial loss, hampering the petitioners’ legitimate interests.

Contentions of Respondents

The respondents submit that the development on the plot violates the Town Planning Act and the Master Plan; the Government’s zonal exemption was subsequently found erroneous, and hence occupancy certificates cannot be issued for the newly constructed building. They emphasize that the petitioners have a remedy by appeal under Section 160 of the Kerala Municipality Act to the Tribunal, and that the exemption issued by the Government and the earlier permits obtained on the basis of misrepresentation justify waiting for a thorough examination. They rely on Sayeesh Kumar’s case to support the position that zoning and master plan controls must be respected.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Sayeesh Kumar v. State of KeralaILR 2005 (4) Kerala 769PositiveThe judgment repeatedly cites the Sayeesh Kumar principles to justify that once an area is zoned as residential in a development plan, exemptions and permissions cannot arbitrarily alter the locus of land use; the Division Bench’s doctrine is treated as a controlling principle in upholding zoning restrictions.
Sayeesh Kumar v. State of Kerala2005 (4) KLT 1027PositiveCited to support the reasoning that development in a residential zone must align with the approved master plan; the authority cannot green-light non-residential use without proper compliance.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,502 words•~12 min read

In The Court Record

Sheela Sreekumar, Sheena, Sheeja and P. Natarajan v. State of Kerala, The Corporation of Kollam, Town Planner, Kollam Development Authority

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE TUESDAY, THE 12TH DECEMBER 2006 / 21ST AGRAHAYANA 1928 WP(C).No. 30357 of 2006(L) -------------------------- PETITIONERS: - ------------ 1. SHEELA SREEKUMAR, KAILAS BHAVAN, MARANADU P.O., KOLLAM. 2. SHEENA, KAILAS BHAVAN, MARANADU P.O., KOLLAM. 3. SHEEJA, KAILAS BHAVAN, MARANADU P.O., KOLLAM. 4. P. NATARAJAN, KAILAS BHAVAN, MARANADU P.O., KOLLAM. BY ADV. SMT.V.P.SEEMANDINI (SR.) SRI.M.S.UNNIKRISHNAN SMT.T.B.REMANI SMT.S.KARTHIKA SRI.M.R.ANISON SRI.T.R.RAJESH RESPONDENTS: ------------- 1. STATE OF KERALA, REP. BY ITS SECRETARY TO GOVT., LOCAL SELF GOVERNMENT DEPARTMENT, TRIVANDRUM. 2. THE CORPORATION OF KOLLAM, REPRESENTED BY ITS SECRETARY, KOLLAM. 3. THE TOWN PLANNER, KOLLAM DEVELOPMENT AUTHORITY, KOLLAM. R1 BY SR.GOVT.PLEADER SRI.MATHEW G.VADAKKEL R2 BY ADV.SRI.M.K.CHANDRAMOHAN DAS, SC THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 12/12/2006, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **PIUS C. KURIAKOSE, J.** .......................................................... W.P.(C) No.30357 OF 2006 ........................................................... DATED THIS THE 12TH DECEMBER, 2006 ## **JUDGMENT** Ext.P2 letter issued by the Town Planning Officer of the 2[nd] respondent-Corporation declining the application submitted by the petitioners for occupancy certificate and Ext.P3 order passed by the Secretary of the Corporation reiterating Ext.P2 are under challenge in this Writ Petition. 2. Being convinced that the petitioners have made out a case for examination, I directed that copies of the Writ Petition be served on the Standing Counsel for 2[nd] respondent-Corporation of Kollam and also on the Government Pleader. Sri.M.K.Chandramohan Das, Standing Counsel accordingly took notice on behalf of the 2[nd] respondent and Sri.Mathew G.Vadakkel, Government Pleader took notice on behalf of the 1[st] respondent-State. Sri.Chandramohan Das filed a statement answering the grounds raised in the Writ Petition and resisting the interim relief sought for. The Government Pleader would place before me, the written instructions given to the Advocate General in the matter by the Government. 3. The petitioners being legal representatives of Smt.K.Mani are the co-owners in joint possession of 1 acre 11 cents of land in WP(C)N0.30357 OF 2006 -2- Vadakkevila Village, Kollam. This land is situated in residential zone notified by the Kollam Development Authority, the 3[rd] respondent. Zonal exemption was given by the 1[st] respondent-Government as per G.O.(Rt.) 4493/2003/LSGD dated 18.12.2003 to late Smt.Mani for construction of a commercial auditorium building and lodge on the property. Based on that order, the 2[nd] respondent-Corporation issued building permit on 28.1.2004 for the construction of a four-storied commercial building and two storied lodge building. On the basis of the above permit and sanctioned plan, the two buildings were constructed and occupancy certificates were issued for the lodge building on 22.4.2005 and for commercial building on 13.7.2006. On the very same property the petitioners applied again for permit for construction of a separate three storied lodge building. Ext.P1 permit was issued to the petitioners. They claim to have spent more than Rs.75 lakhs for completing the construction of the three-storied building on the strength of Ext.P1 plan and permit. The property, it is submitted, is situated within a distance of only 1 KM. from the office of the Kollam Corporation and the Building Inspectors and Town Planners attached to the Corporation used to visit the construction site regularly till construction of all the three floors of this new building was WP(C)N0.30357 OF 2006 -3- completed. It is pointed out that at no point of time any objection was raised by any of the officials of the Corporation regarding the construction. After construction, occupancy certificate was applied for and on noticing the delay on the part of the Corporation, the petitioner filed W.P.(C) No.26879 of 2006 before this Court. During the pendency of that Writ Petition, Ext.P2 letter was issued by the 2[nd] respondent on 10.10.2006 informing that occupancy certificate can be issued only on regularising the two constructions already effected by the petitioners in the same compound. Later, on the basis of the interim order passed by this Court in the Writ Petition, the 2[nd] respondent-Corporation issued Ext.P3 order dated 10.11.2006. In the light of Ext.P3 order, W.P.(C)No.26879 of 2006 filed by the petitioners was closed by this Court, reserving the petitioners' right to challenge the validity of Ext.P3 order. Ext.P4 dated 18.12.2003 is the order of the Government granting zonal exemption to the petitioners for effecting construction of the other two buildings on the property, i.e., the two storied lodge building and the commercial building. It was thereafter that on 20.9.2005 the 1[st] respondent issued Ext.P5 letter to the petitioners informing them that they will have to seek regularisation of the two buildings (two storied lodge building and the WP(C)N0.30357 OF 2006 -4- commercial building) either by making the buildings conform to zonal regulations or by obtaining zoning exemption from the Government. Exts.P6 and P7 are the occupancy certificates issued by the 2[nd] respondent for these two buildings which are actually covered by Ext.P4 exemption order. Petitioners have produced Ext.P8 which is copy of letter dated 6.4.2005 issued by the Government to the Corporation seeking explanation from the Corporation for granting permit for the construction of a commercial-cum-auditorium building in a residential zone. The petitioner could notice Ext.P8 only when the same was produced by the Corporation in W.P.(C)No.26879 of 2006. The petitioner has also produced Ext.P9 dated 29.6.2005, which is copy of explanation submitted by the Secretary of the Corporation to Ext.P8. The petitioners contend that in the peculiar facts and circumstances of this case, the Corporation has no jurisdiction to deny occupancy certificates and even if there is any violation of zonal restrictions, the same can be set at right by giving concurrence to the petitioners as stipulated in Clause 6.2 (2) of the Master Plan. The petitioners also refer to Rule 30(3) of the Kerala Municipality Building Rules, 1999 to contend that lodge building will also come under the category of residential buildings and therefore there is no necessity for WP(C)N0.30357 OF 2006 -5- zonal exemption for constructing a lodge building in a residential zone. Impugning Ext.P3 on various grounds, the petitioners pray that Exts.P2 and P3 be quashed and that a mandamus be issued directing the Corporation to issue occupancy certificate for the buildings constructed by the petitioners on the basis of Ext.P1 de hors Exts.P2 and P3. By way of interim relief, the petitioners pray that occupancy certificate be issued provisionally de hors Exts.P2 and P3. 4. In the detailed statement filed on behalf of the 2[nd] respondent-Corporation, it is stated that from the very beginning itself the stand of the Corporation was that construction of buildings by the petitioners on the plot in question is against the Town Planning Act and also against the approved and notified Master Plan. The Corporation denied permission to the petitioners for construction of the buildings. They approached the Government and obtained zonal exemption. It was on the basis of the zonal exemption issued by Government that the Corporation issued permits to the petitioners for construction of the buildings. Later, the Government found that permission earlier granted is legally bad and issued strict direction by its order dated 6.4.2005 (Ext.P8) to the Corporation to take further action. On 20.9.2005, the Government issued a further letter reminding of Ext.P8 WP(C)N0.30357 OF 2006 -6- and directing appropriate action against the petitioners for noncompliance with the Town Planning Act and the Scheme. Referring to the judgment in **Sayeesh Kumar v. State of Kerala** (2005 (4) KLT 1027 = ILR 2005 (4) Kerala 769), it is stated that once the development scheme is approved and published in the Gazette stating that a particular area is ear-marked as residential zone, even the Government cannot tinker with the same and grant permission for construction of a non-residential building in a residential zone. The area being ear-marked as residential zone, no construction as made by the petitioners presently is permissible. Individual exemptions would upset the entire scheme and would also adversely affect the health, environment, sanitation, ecology etc. of the locality. The present Writ Petition challenging Exts.P2 and P3 is not maintainable firstly because the petitioners have a remedy by way of appeal under Section 160 of the Kerala Municipality Act to the Tribunal which has been constituted under Section 271S of the Kerala Panchayat Raj Act and secondly because the petitioners have obtained exemption from the Government by ingenious methods. The veracity of the orders passed by the Government and the connected records can be approved only on a thorough examination of witnesses by a competent civil court. WP(C)N0.30357 OF 2006 -7- The challenge against Ext.P3 is not sustainable on merits also since Ext.P3 has been passed in the light of ruling Government Orders, the Town Planning Act, the Master Plan of the Kollam Development Authority and also the principles of law laid down by the Division Bench in **Sayeesh Kumar's** case (supra). The statement answers the contention that the Corporation having already issued occupancy certificate in respect of the earlier construction is not entitled to deny occupancy certificate for the present construction by contending that the petitioners are not entitled to demand perpetration of an illegality which has now been recognised by the Government itself. The earlier permit happened to be issued due to mis-representation of fact and law. The statement also refers to Rule 16 of the Kerala Municipality Building Rules which enables the Secretary to cancel, suspend or revoke permits, if it is noticed that permit was issued erroneously or due to mis-representation of fact or law. Occupancy certificate can be issued only on regularising the earlier two constructions. Nobody has a right to claim that he is entitled for occupancy certificate in violation of the Town Planning Act and the Scheme. A conjoint reading of Rule 30 of the Kerala Municipality Building Rules as well as Rule 12 of the Town Planning Act will reveal this aspect. WP(C)N0.30357 OF 2006 -8- 5. Smt.V.P.Seemanthini, Senior Counsel for the petitioners, Sri.M.K.Chandramohan Das, Standing Counsel for the 2[nd] respondent and Sri.Mathew G.Vadakkel, Government Pleader for the 1[st] respondent have addressed me on the question of granting the interim relief sought for by the petitioners. While Smt.Seemanthini would refer to Clauses 6.2 (2) of the Master Plan, the provisions of the approved and notified plan of the Kollam Development Authority such as clauses 6.1.(1), 6.2 (2) and 6.3 (3) and the provisions such as Rule 30(3) of the Kerala Municipality Building Rules. Mr.Chandramohan Das, Standing Counsel for 2[nd] respondent and Mr.Mathew G.Vadakkel, Government Pleader would rely on Section 12 of the Town Planning Act and the Zoning Regulations set out by the Development Plan and more on the principles laid down by the Division Bench of this Court in **Sayeesh Kumar's** case. 6. I find force in the submissions of Mr.Chandramohan Das as well as Mr.Mathew G.Vadakkel that since contentious issues necessitating an enquiry into the circumstances under which the Government came to pass exemption orders in respect of Smt.K.Mani, the predecessor-in-interest of the petitioners in the matter of construction of the earlier two buildings have arisen, the petitioners WP(C)N0.30357 OF 2006 -9- ought to be relegated to their remedies by way of appeal. At the same time, the following circumstances cannot go unnoticed: 1. The building in respect of which occupancy certificate is sought for by the petitioners is a lodge building. The claim that more than Rs.75 lakhs was expended by the petitioners for completing the construction of the building and that all arrangements have been made by purchasing the necessary utensils and equipments for conducting a lodge in the building by incurring huge expenditure was not seriously disputed before me. 2. The construction of the building was on the basis of permit issued by the 2[nd] respondent. The ground presently raised by the Government as well as the 2[nd] respondent is that the building is constructed in violation of zoning regulations and in that way offends the law as declared by this Court in **Sayeesh Kumar's** case. Rule 30(3) of the Kerala Municipality Building Rules will show that all lodging and rooming houses, dormitories and hostels will come within the description of Group A2, Special Residential Buildings. 3. The provisions in the approved and notified WP(C)N0.30357 OF 2006 -10- development plan will also show that a lodge building will not in any event come within the prohibited uses. Hostels, Boarding houses, commercial offices etc, come within the category of “uses restricted” only. It may therefore be possible for the 3[rd] respondent to permit a lodge on the plot in question even without zonal exemption from the Government. 4. Refusing to number the building and to issue occupancy certificate will result in a situation wherein the petitioners are compelled to keep the building unused. This situation will result in considerable financial loss to the petitioners who claim to have raised funds for constructing the building and for purchasing the necessary equipments by raising loans from financial institutions. Even in the statement filed by the Corporation, what is contended is that the veracity of the exemption order issued by the Government to the petitioners is an aspect which can be proved only by taking evidence. That the constructions were made on the strength of the exemption order and a permit issued by the Corporation cannot be in question. To what extent the “ingeniousness” of the petitioners or their predecessor is responsible for the exemption order is a WP(C)N0.30357 OF 2006 -11- matter yet to be established. 5. The interpolation of one sentence in the last paragraph of Ext.P3 that the building has been constructed in variation from the approved plan, in the handwriting of the Secretary of the Corporation may indicate that the said reason has been stated only on afterthoughts. But what I find from Ext.P1 is that permit is given for a building having three floors. The building which is now constructed has four floors. To that extent, the interpolation of that one sentence in the last paragraph of Ext.P3 was justified. 7. Noticing the above points, I am of the view that even as the petitioners are relegated to their remedies by way of appeal, there is justification for passing the following directions:- The 2[nd] respondent-Corporation shall issue occupancy certificate to the petitioners in respect of the ground floor, first floor and second floor of the building constructed by them pursuant to Ext.P1 permit de hors Exts.P2 and P3 on condition that no-objection certificate from the Fire Department will also be produced by the petitioners before the 2[nd] respondent. It is however made clear that such issuance will be subject to the WP(C)N0.30357 OF 2006 -12- final outcome of the appeal which the petitioners prefer against Ext.P3 before the Tribunal. The Writ Petition is disposed of directing the petitioners to prefer appeal against Ext.P3 before the Tribunal for Local Self Government Institutions within three weeks of receiving a copy of this judgment. If such an appeal is received by the Tribunal for Local Self Government Institutions, the Tribunal will entertain that appeal as one filed on time and dispose of the same in accordance with law. ## **(PIUS C. KURIAKOSE, JUDGE)** tgl WP(C)N0.30357 OF 2006 -13-
End of Judgment Record
Browse All High Court of Kerala (2006) Decisions
2006-11-30

Baburaj v. State of Kerala

Baburaj, the appellant, was convicted under Section 302 IPC for intentionally causing the death of his wife Geetha by constrictive neck compression. The Thrissur Sessions Court had sentenced him to life imprisonment on a conviction based on circumstantial evidence. The Kerala High Court heard Crl.A. No. 794 of 2004, challenging that conviction. The occurrence occurred in the early hours of 1 February 2002, approximately at 1:30 A.M., at Engandiyoor, where Geetha was found dead in her home after prior quarrels between husband and wife. The FIR was lodged on 1 February 2002 by Geetha’s brother. Dr. Cyriac Job conducted the post-mortem on 1 February 2002 and found signs of asphyxia with constrictive force on the neck, as well as multiple ante-mortem injuries suggesting a struggle. The prosecution relied on motive—frequent quarrels between the spouses—and the accused’s presence in the house that night to connect him to the crime. The defense contended that timing of death could be earlier than alleged and that the chain of circumstantial evidence was not complete, possibly pointing to accidental death. The High Court evaluated the medical testimony, ocular and accepted witnesses, and found the circumstantial chain sufficient to prove guilt beyond reasonable doubt, applying the principle of last-seen-together, and upholding the Sessions Court’s verdict. The appeal was dismissed, and the conviction affirmed.

2006-11-22

K. Gopi (D/o Late Ex.GS-142996 PNR) v Union of India and others

Petitioner K. Gopi, daughter of late Ex.GS-142996 PNR, sought compassionate appointment in the Border Roads Organisation after her father’s death on 03.03.2002. The petition, filed in 2004, contends that the family, comprising the petitioner, her brother and mother, was very poor and dependent on government employment. An application for compassionate appointment was made on 16.12.2003 but Ext.P4 rejected it, noting a revised policy that the dependent must be a major at the time of death. Subsequently, the government issued policy extensions (Ext.P7 and Ext.P8) allowing a three-year window, and the mother was advised to submit fresh documents. The petitioner argued that completion of 18 years by a dependent at death is not a precondition for eligibility. The respondents asserted that under the revised policy only those who were minor at death qualify; if the son attains 18 later, he may be advised to apply as per rules then in force. The court referred to a Kerala case (O.P.3338/2002) allowing merits-based consideration where there is no laches and noting that policy changes cannot retroactively defeat rights fixed as of death. It also cited Umesh Kumar Nagpal (1994) 4 SCC 138 to acknowledge the need for a reasonable period. Ultimately, the writ petition was allowed, directing the respondents to consider the claim on merits and dispose of it within four months.

2006-11-29

V. Bahuleyan v. State of Kerala and The Secretary to Government, Transport (C) Department, Government Secretariat, Thiruvananthapuram

V. Bahuleyan, a retired Regional Transport Officer, challenged Ext.P5 denying notional promotion to Deputy Transport Commissioner based on a pre-existing select list (Ext.P1) in which he was ranked No.4 as of 15 June 2002. A vacancy for the post arose on 1 December 2002 in the retirement vacancy of Sri Kunhambu, but Bahuleyan, though still in service, was bypassed and superseded by the immediate junior through Ext.P2 dated 6 January 2003. Disciplinary proceedings against him were initiated but later dropped as per Ext.P3 dated 23 August 2003, with his representation Ext.P4 dated 11 February 2004 seeking placement as Deputy Transport Commissioner with effect from 6 January 2003 and arrears. Ext.P5 dated 1 April 2004 rejected the claim. Bahuleyan contends that Note iii to Rule 28(b)(i)(7) of the Kerala State and Subordinate Services Rules provides that an officer included in a select list who is exonerated from major penalties must be promoted on the basis of his position in the list; if fully exonerated, retrospective promotion should be granted. Delhi Jal Board v. Mahinder Singh (JT 2000 (10) SC 158) is cited to support the right to be considered for promotion under Article 16. The High Court holds that Ext.P5 is unsustainable, and Bahuleyan is entitled to notional promotion from 1 December 2002, but no monetary benefits; salary and pension are to be fixed accordingly, and arrears, if any, to be settled within four months. The petition is allowed as above.

2006-12-11

The Correspondent and Chairman Standing Committee, MES, Central College Committee, MES Office, Kozhikode - Rep. by the General Secretary, Muslim Education Society, Kozhikode v. M. Syed Mohammed

This writ petition challenges execution of an order of the University Appellate Tribunal directing re-posting and monetary benefits to the respondent, an employee of a private MES college. The respondent had been moved from M.E.S. College, Kodungallur to M.E.S. College, Mampad, and claimed salary for the period he was kept out of duty. The University Appellate Tribunal held in his favour, and the High Court later directed payment of monetary benefits and posting, but the matter escalated to execution proceedings in which the petitioner (the MES management) contends that Sub Court Kozhikode lacks jurisdiction to execute the order under Calicut University Act, section 60(8). The petition traces the chain of litigation since the Tribunal’s order and a prior High Court order in CRP Nos.895/79 etc. The core issue is where an execution petition under the Tribunal’s order should be heard and executed: should it be the Sub Court with jurisdiction over the private college’s location, or the court where MES’s main office or the employee’s work was situated at the time of the appeal. The court ultimately held that Sub Court Kozhikode has no jurisdiction under section 60(8) and transferred the execution to Sub Court Manjeri, directing expeditious disposal within six months, while disposing of the writ petition.