Sharlet T.F. v. State of Kerala & Technopark, District Collector, and Others

Case / Petition Number:WP(C).No. 29890 of 2010 (I)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Antony Dominic
Judgment Date
2012-06-07
Court Decision / Holding
The court held that the invocation of Section 17(4) to dispense with Section 5A was not proven; the urgency did not appear clearly justified given the two-year delay between administrative sanction and notification. Ext.P9 (4(1)) notification was set aside. The court directed that the matter proceed with the statutory Section 5A inquiry by the appropriate authority. It also recognized alignment fixation as a technical matter for experts and disposed of the writ petitions accordingly.
Final Disposition
Writ petitions disposed of; Ext.P9 notification set aside; directs completion of Section 5A enquiry; alignment fixation acknowledged as technical and to be reviewed by appropriate authorities; the matter disposed of accordingly.

Parties to the Case

Appellants / Petitioners

  • Sharlet T.F.

Respondents

  • State of Kerala represented by Chief Secretary to Government
  • Techno Park represented by its Chief Executive Officer
  • District Collector, Thiruvananthapuram
  • Special Tahsildar, Additional Land Acquisition Unit, Kudappanakkunnu, Trivandrum

Legal Representation & Advocates

Counsels for Petitioners

  • • N. Nandakumara Menon (Senior Advocate)
  • • P.K. Manojkumar (Advocate)
  • • Hena Bahuleyan

Counsels for Respondents

  • • V.K. Rafeeq (Government Pleader) for R1, R3, R4
  • • K.A. Abdul Salam (Advocate) for R2
  • • Sunil V. Mohammed
  • • A.A. Mohammed Nazir
  • • P.A. Ahamed

Case Synopsis & Summary

These combined writ petitions challenge land acquisition proceedings for providing a road access to Technopark Phase III. The petitioner asserts that the road alignment was fixed without adequately considering alternate alignments, and that the District Collector’s Ext.P8 report, which highlighted potential displacement and rehabilitation issues, was ignored. The petitioners argue that invoking the urgency clause under Section 17(4) of the Land Acquisition Act (L.A. Act) dispensed with the statutory hearing obligations under Section 5A, which is a fundamental safeguard akin to a due process requirement. The respondents contend that the alignment is fixed in accordance with the master plan for Phase III, and that urgency exists given the substantial capital investment and the project’s timeline; they claim the 5A enquiry has effectively been conducted through a government meeting and that extending the hearing would delay the project. The court emphasizes that Section 5A protections are like fundamental rights and must be strictly observed, citing Supreme Court precedents (Maharashtra State Co-Operative Bank Ltd. v. Assistant Provident Fund Commissioner; Ramal Trading; Radhy Shyam; Darshan Lal Nagpal) and Kerala authorities’ own guidance. It notes a two-year gap between administrative sanction and the Section 4(1) notification, undermining claimed urgency. Ultimately, the courtSet as aside Ext.P9 (Section 4(1)) notification and directed that a full Section 5A inquiry be conducted, holding that alignment fixation is a technical matter for experts. Writ petitions are disposed of accordingly.

Provisions of Law Cited

Section 4 of the Land Acquisition ActSection 4(1)Section 5ASection 17(4)Section 17(1)Section 17(2)Section 6

Legal Doctrines & Maxims

  • Eminent domain
  • Audi alteram partem

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that the road alignment was fixed without considering viable alternate alignments, Ext.P8 report was ignored, and invoking Section 17(4) to dispense with Section 5A was improper and prejudicial. They point to potential rehabilitation issues and the substantial loss from the proposed acquisition.

Contentions of Respondents

The respondents contend that the alignment follows the Master Plan for Technopark Phase III and that the project’s urgency justifies invoking Section 17(4) and dispensing with 5A, arguing that an in-depth enquiry has already been conducted at high administrative levels and that any delay would frustrate the public purpose.

Cited Precedents (9)

Case NameCitationTreatmentExplanation
Maharashtra State Co-Operative Bank Ltd. v. Assistant Provident Fund Commissioner and Ors.2009(10)SCC 115PositiveCited to establish that Section 5A rights have a fundamental-right-like protection and must be carefully exercised before invoking Section 17(4).
Ramal Trading Private Limited v. State of West Bengal and Ors.2012(2)SCC 25PositiveCited to underline that Section 5A is a minimal safeguard against arbitrary acquisition and that urgency provisions are not to be used to bypass this requirement.
Radhy Shyam (dead) through Lr. & Ors. v. State of Uttar Pradesh & Ors.2011(5)SCC 553PositiveCited for articulating principles governing urgency under Section 17(4) and the need for proper satisfaction and demonstration of real urgency.
Darshan Lal Nagpal (dead) by LRS. v. Government of NCT of Delhi & Ors.2012(2)SCC 327PositiveCited to reinforce that records must demonstrate clear application of mind when invoking urgency under Section 17(4).
Assyst International Pvt. Ltd. v. State of Kerala2009(4)KLT 116PositiveCited to support that fixation of alignment is a technical matter for experts, not something to be decided by lay administrative enquiry.
Dwarkadas Shrinivas v. Sholapur Spg. And Wvg. Co. Ltd.—PositiveReferenced for the principle of eminent domain and the need for careful consideration of public purpose.
Charanjit Lal Chowdhury v. Union of India—PositiveCited as part of early principles on eminent domain and the impact on individual rights.
Jilubhai Nanbhai Khachar v. State of Gujarat—PositiveCited alongside other eminent domain cases to contextualize the limits of state power.
Gurdial Singh v. State of Punjab—PositiveCited to discuss the observation that property rights may not be fundamental, but Article 14 protections can still apply to Section 5A readings.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Sharlet T.F. v. State of Kerala & Technopark, District Collector, and Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT:** ## **THE HONOURABLE MR.JUSTICE ANTONY DOMINIC** ## **THURSDAY, THE 7TH DAY OF JUNE 2012/17TH JYAISHTA 1934** **WP(C).No. 29890 of 2010 (I) ---------------------------** ## **PETITIONER(S):** - **------------------------** **SHARLET T.F.,PREM VILLA, ATTINKUZHY, KAZHAKKOOTTAM P.O., TRIVANDRUM-695 582.** **BY SRI.N.NANDAKUMARA MENON,SENIOR ADVOCATE BY ADV. SRI.P.K.MANOJKUMAR SMT.HENA BAHULEYAN** ## **RESPONDENT(S):** **---------------------------** **1. THE STATE OF KERALA REPRESENTED BY THE CHIEF SECRETARY TO GOVERNMENT, SECRETARIAT, THIRUVANANTHAPURAM-695 001.** **2. THE TECHNOPARK, REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER (C.E.O.), KAZHAKKOOTTAM PO., TRIVANDRUM- 695 582.** **3. THE DISTRICT COLLECTOR, TRIVANDRUM - PIN 695 005.** **4. THE SPECIAL TAHSILDAR, ADDITIONAL LAND ACQUISITION UNIT, (L.R.) KUDAPPANAKUNNU, CIVIL STATION, TRIVANDRUM - 695 005.** **R1,R3 & R4 BY GOVERNMENT PLEADER SRI.V.K.RAFEEK R2 BY ADVS. SRI.K.A.ABDUL SALAM** **SRI.SUNIL V.MOHAMMED** **SRI.A.A.MOHAMMED NAZIR** **SRI.P.A.AHAMED** **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 07-06-2012 ALONG WITH WPC. NO,11709/2011, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **Kss** ## **WPC.NO.29890/2010 I** ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** - **P1: COPY OF THE NOTICE NO.813 DTD. 2/05/2009 PUBLISHED BY THE KERALA GAZETTE, EXTRAORDINARY PUBLISHED BY AUTHORITY.** - **P2: COPY OF THE APPEAL PETITION DTD. 15/06/2010 SUBMITTED BY THE PETITIONER BEFORE THE LAND REVENUE COMMISSIONER, TRIVANDRUM.** - **P3: COPY OF THE PLAN SHOWING THE LAY OUT OF THE APPROACH ROAD TO TECHNOPARK PHASE III.** - **P4: COPY OF THE REPRESENTATION DTD. 27/06/2009 SUBMITTED BY THE PETITIONER TO THE DISTRICT COLLECTOR, TRIVANDRUM.** - **P5: COPY OF THE REPRESENTATION DTD. NIL SUBMITTED BY THE PETITONER TO THE GRIEVANCE CELL OF HON.CHIEF MINISTER, TRIVANDRUM.** - **P6: COPY OF THE FORWARDING LETTER NO.6691/CMPGRC/2009/GAD DTD. 23/07/2009 ISSUED BY THE DISTRICT COLLECTOR, TRIVANDRUM TO THE PETITIONER.** - **P7: COPY OF THE NOTICE NO.K.13-14556/09 DTD. 27/08/2009 ISSUED BY THE DISTRICT COLLECTOR, TRIVANDRUM, TO THE PETITIONER.** - **P8: COPY OF THE REPORT NO.K.13/14556/09 DTD. OCTOBER 2009 ISSUED BY THE SPECIAL TAHSILDAR, PUBLISHED DTD. 30/07/2010.** - **P9: COPY OF THE NOTIFICATION NO.A2.534/2009 DTD. 21/07/2010 ISSUED BY THE SPECIAL TAHSILDAR, PUBLISHED DTD. 30/07/2010.** - **P10: COPY OF THE NOTICE NO.A2-534/2009 DTD. 9/09/2010 ISSUED BY THE SEPCIAL TAHSILDAR, TRIVANDRUM.** - **P11: THE ORIGINAL OF THE PLAN SHOWING THE LAY OUT OF THE PROPOSALS FOR APPROACH ROAD TO TECHNOPARK PHASE III.** ## **RESPONDENT'S EXHIBITS:** **R2(A): COPY OF THE PLAN.** **R2(B): COPY OF THE CHELAN NO.300 DTD. 14/07/2010.** **R2(C): COPY OF MINUTES OF THE MEETING ON 19/12/2009.** ## **/TRUE COPY/** **P.S.TO JUDGE** **Kss** ## **ANTONY DOMINIC, J** ........................................ W.P.(C)s.29890/2010 & 11709/2011 .............................................. Dated this the 7[th] day of June, 2012 ## **JUDGMENT** Issues raised in these writ petitions are connected. Therefore, these cases were heard together and are disposed of by this common judgment, treating W.P.(C). 29890/10 as the leading case. 2. Petitioners in these writ petitions challenge the land acquisition proceedings initiated at the instance of the second respondent in W.P.(C).29890/10 for the acquisition of a portion of their properties for providing a road access to the IIIrd phase of the Techno Park. 3. Ext.R2(a) is a Master Plan that was got prepared by the Techno Park for the development of its 3[rd] phase. It appears that based on Ext.R2(a), the third respondent sought sanction of the first respondent to acquire an extent of 20 Ares of land in R.S.No.251/part in Block No.17 of Attipra Village in Thiruvananthapuram Taluk by invoking the W.P.(C).29890/10 & 11709/11 2 urgency clause under Section 17(4) of the Land Acquisition Act. 4. In the counter affidavit filed by the District Collector, the third respondent in W.P.(C).29890/10, it is stated that considering the urgency of the case, as explained by the requisitioning authority, the Commissioner (Land Revenue), being satisfied that the land is urgently required, ordered in exercise of the powers under Section 17(4) of the L.A Act to dispense with the objections herein under Section 5A in this case, as per the Government Order No.GO(MS) 30/2008/ITD dated 7.8.2008. 5. Insofar as the petitioners are concerned, the petitioner in W.P.(C).29890/10 presently owns about 15 cents of land which falls within the alignment of the proposed road and the petitioner in W.P.(C).11709/11 owns 10.5 cents in the alignment and both of them are residing in the houses in their respective plots. Ext.P1 in W.P.(C).29890/10 is the notice dated 27.4.2009 issued under Section 6(1) of the Survey and Boundaries Act to the petitioner therein. It W.P.(C).29890/10 & 11709/11 3 appears that there upon, he filed Ext.P2 appeal to the Land Revenue Commissioner followed by Ext.P4 representation to the District Collector and Ext.P5 representation before the Chief Minister. Ext.P6 shows that Ext.P5 representation was forwarded to the Chief Executive of the Technopark and that acting upon the representations thus made, Ext.P7 notice was issued by the District Collector to inform the petitioner that a local inspection of the property will be made. Accordingly, a local inspection was conducted and Ext.P8 is the report made by the District Collector to the Principal Secretary to Government, Revenue (B) Department. In this report, the District Collector has stated thus:- _“The petitioner's grievance is that because of the proposal of the proposed land acquisition, her house where she is staying with husband and inlaws would go and there would be no place for them to live in there are other grievance like alternate sites open for less objections are available in the locality in the very next survey number, her in laws (husband and family) were earlier evicted in 1960's connected with the land acquisition of Thumba Rocket Station._ _All the grievances have been examined in the presence of all concerned and the finding are listed below._ _(1). There is a land acquisition in progress as indicated by the petitioner. The acquisition is for the purpose of connecting road from Bye pass to_ W.P.(C).29890/10 & 11709/11 4 _the Phase III of Technopark._ _(2). As per the alignment it is certain that almost the entire part of the petitioner's house would go due to acquisition. (It is noted that the acquisition would touch the house not only of the petitioner but also that of the neighbour who is staying adjacent of the petitioner, on the southern side.)_ _(3). With regard to the complaint, that alternate sites which are open for less objection are available it has been noted that there is substance and petitioner has substantiated her statement by pointing out an alternate site, which is very close by. In this alternate site here is nobody staying and to evade acquisition, the land holder has started construction of a house and may be 4050% of construction is done. Absolutely, there is no dwelling in this alternate site merits consideration as there would be no issue of resettlement and rehabilitation._ _(4). Regarding the eviction/displacement faced by petitioner's family at the time of land acquisition for Thumba Rocket Station, the petitioner has produced a document issued by VSSSC stating that Mr.Clement husband of the petitioner was an affected party. Accordingly, petitioner's family is facing eviction a second time in their life time._ _In the overall, it is seen that the certificate given as item no.3 regarding objection to land acquisition, furnished by the Requisition Authority at the time of giving the request for land acquisition ion form II of the rule 4(1) is not correct in the sense that when there is land open for less objection is available, the same was not considered. Instead of preferring land without any dwelling unit, when it is available now the proposal is to affect 2 houses one totally and another one partially. It would call for rehabilitation issues, which could have been avoided totally by choosing the alternative site as suggested by the petitioner._ _In this circumstances, it is decided to propose government to give a direction to the Requisition Authority to consider a change of alignment, as indicated by the petitioner. This is possible at this stage because the requisition_ W.P.(C).29890/10 & 11709/11 5 ## _authority ha not started any tangible work at the site for Phase III.”_ 6. It appears from Ext.R2(c) dated 19.12.2009 that subsequent to Ext.P8 report, a meeting was convened by the Principal Secretary, IT, in which though no inference is made to the report, it was decided that the width of the road in the area, where two houses are situated on both sides, shall be reduced so that, the residential building of the petitioner in W.P.(C).29890/10 will be saved. Still later, in the newspapers of 30.7.2010, Ext.P9 notification under Section 4(1) dated 21.7.2010 was published proposing to proceed with the acquisition, invoking the urgency clause under Section 17(4) of the Land Acquisition Act. It is at that stage these writ petitions were filed challenging the proceedings. 7. Heard the learned counsel for the petitioners, the learned counsel appearing for the Technopark and also the learned Government Pleader appearing for respondents 1, 3 and 4. W.P.(C).29890/10 & 11709/11 6 8. The main contentions raised on behalf of the petitioners are that the alignment was fixed without taking note of the alternate alignments suggested by them. They also contended that Ext.P8 report was ignored by the authorities. The second contention raised was that the respondents have acted illegally in invoking the urgency clause under Section 17(4) of the Act and dispensing with the enquiry under Section 5A thereof. 9. Insofar as the fixation of alignment is concerned, the contention raised by the requisitioning authority in its counter affidavits filed is mainly that the alignment has been fixed in terms of the Master Plan prepared by the Architect. They are also disputing the factual correctness of the assertion made by the petitioners that two other proposals were, malafidely given up by the requisitioning authority. It is therefore, stated that the alignment having been fixed in terms of the Master Plan, any change in the alignment will affect the implementation of the project for the development of the IIIrd phase of the Technopark. W.P.(C).29890/10 & 11709/11 7 10. Insofar as the invocation of the urgency clause is concerned, it is stated that the Technopark is implementing the project involving a capital investment of more than `250 Crores. It is also stated that unless the access road is laid in time, the project cannot be commissioned and that it was in view of the urgency of the matter, they sought invocation of urgency clause under Section 17(4). Further it is also contended that pursuant to the representations made by the petitioners, a meeting was convened by the Secretary to the Government and that to the extent possible, modifications have been made to the proposal. According to him, therefoare, in effect and substance, an enquiry which is similar to the one as contemplated under Section 5A has already been conducted and that too by an officer in the rank of Secretary to the Government. Therefore, he contended that no useful purpose will be achieved even if an enquiry under Section 5A was conducted and that the dispensation of the enquiry under Section 5A has not caused any prejudice to the petitioners. 11. Of the two contentions that are mainly raised, I shall W.P.(C).29890/10 & 11709/11 8 first deal with the contention of the petitioners regarding the alleged illegality in invoking the urgency clause under Section 17(4) and dispensing with the enquiry under Section 5A of the Act. 12. Section 4 of the Land Acquisition Act provides publication of preliminary notification and as per this provision, when it appears to be appropriate to the Government or to the Collector the land in any locality is needed or is likely to be needed for any public purpose, a notification to that effect shall be published in the Official Gazette circulating in the locality in the manner as provided therein. Section 5A of the Act provides that any person who is interested in any land notified under Section 4(1)(a), may within 30 days of the date of publication of the notification object to the acquisition of the land or of any land in the locality as the case may be. Sub Section (2) provides that every objection under sub section (1) shall be made to the Collector in writing and the Collector shall give the objector an opportunity of being heard either in person or by any person or any person authorised by him in this behalf and W.P.(C).29890/10 & 11709/11 9 after hearing all such objections and making such further enquiry if any, as it thinks necessary, either make a report in respect of the land which has been notified under Section 4 (1) or make different reports in respect of different parcels of such land to the Government or to the Board of Revenue as provided therein. Section 17(4) of the Act provides that in case of any land to which, in the opinion of the appropriate Government or Board of Revenue, the provisions of sub sections (1) and (2) of Section 17 are applicable, the appropriate Government or the Board of Revenue as the case may be, direct that provisions of Section 5A shall not apply and if it does so direct, a declaration may be made under Section 6 in respect of the land at any time after the date of the publication of the notification under Section 4. 13. The importance and necessity to conduct the enquiry under Section 5A of the Land Acquisition Act has been dealt with by the Apex Court in various judgments and the right conferred on the land owners under Section 5A has already been equated with fundamental rights. In this context, it is relevant to refer to the judgment in **Maharashtra State Co-** W.P.(C).29890/10 & 11709/11 10 ## **operative bank Ltd., V. Assistant Provident Fund Commissioner and Ors.(2009(10)SCC 115),** where the Apex Court laid down the following principles; _“.....it has been emphasized that a right under Section 5-A is not merely statutory but also has the flavour of fundamental rights under Articles 14 and 19 of the Constitution. Such observations had been made in reference to an observation made in the earlier decision in Gurdial Singh case and keeping in mind the fact that right to property was no longer a fundamental right, an observation was made that even if the right to property was no longer a fundamental right, the observation relating to Article 14 would continue to apply in full force with regard to Section 5-A of the LA Act._ _That in the said decisions, such right was elevated to the status of a fundamental right is in itself sufficient to indicate that great care had to be taken by the authorities before resorting to Section 17(4) of the LA Act, and that they had to satisfy themselves that there was an urgency of such nature as indicated in Section 17(2) of the Act, which could brook no delay whatsoever.”_ ## 14. Subsequently, in the judgment in **Ramal Trading Private Limited V. State of West Bengal and Ors.( 2012(2)** **SCC 25** ), the Apex Court held that it must be borne in mind that the proceedings under the LA Act are based on the principle of eminent domain and that Section 5-A is the only protection available to the person whose lands are sought to W.P.(C).29890/10 & 11709/11 11 be acquired. It was further held that it is the minimal safeguard afforded to him to protect himself from arbitrary acquisition by pointing out to the authority concerned, that public purpose is absent in the proposed acquisition or that the acquisition is mala fide. The Apex Court also held that the Act being an ex-propriatory legislation, its provisions will have to be strictly construed. 15. Having thus seen the importance and the requirement of the enquiry under Section 5A , I shall now proceed to examine the circumstances in which the urgency clause provided under Section 17(4) can be invoked by the authorities. This question came up for consideration of the Apex Court in its judgment in **Radhy shyam (dead) through Lr. & Ors. V. State of Uttar Pradesh & Ors..(2011 (5) SCC 553)** , where in paragraph 77 it was held as follows; _From the analysis of the relevant statutory provisions and interpretation thereof by this Court in different cases, the following principles can be culled out:_ _(i). Eminent domain is a right inherent in every sovereign to take and appropriate property belonging to citizens for public use. To put it_ W.P.(C).29890/10 & 11709/11 12 _differently the sovereign is entitled to reassert its dominion over any portion of the soil of the State including private property without its owner's consent provided that such assertion is on account of public exigency and for public good - Dwarkadas Shrinivas v. Sholapur Spg. And Wvg.Co. Ltd, Charanjit Lal Chowdhury v. Union of India and Jilubhai Nanbhai Khachar v. State of Gujarat_ _(ii).The legislations which provide for compulsory acquisition of private property by the State fall in the category of expropriatory legislation and such legislation must be construed strictly - DLF Qutab Enclave Complex Educational Charitable Trust v. State of Haryana; State of Maharashtra v. B.E.Billimoria and Dev Sharan v. State of U.P._ _(iii). Though, in exercise of the power of eminent domain, the Government can acquire the private property for public purpose, it must be remembered that compulsory taking of one's property is a serious matter. If the property belongs to economically disadvantaged segment of the society or people suffering from other handicaps, then the court is not only entitled but is duty-bound to scrutinize the action/decision of the State with greater vigilance care and circumspection keeping in view the fact that the landowner is likely to become landless and deprived of the only source of his livelihood and /or shelter._ _(iv). The property of a citizen cannot be acquired by the State and/or its agencies/instrumentalities without complying with the mandate of Sections 4, 5-A and 6 of the Act. A public purpose, however, laudable it may be does not entitle the State to invoke the urgency provisions because the same have the effect of depriving the owner of his right toi property without being heard. Only in a case of real urgency, the State can invoke the urgency provisions and dispense with the requirement of hearing the landowner or other interested persons. (v). Section 17(1) read with Section 17(4) confers extraordinary power upon the State to acquire private property without complying with the mandate of Section 5-A. These provisions can be invoked only when the purpose of acquisition cannot brook_ W.P.(C).29890/10 & 11709/11 13 _the delay of even a few weeks or months. Therefore, before excluding the application of Section 5-A, the authority concerned must be fully satisfied that time of few weeks or months likely to be taken in conducting inquiry under Section 5-A will, in all probability frustrate the public purpose for which land is proposed to be acquired._ _(vi). The satisfaction of the Government on the issue of urgency is subjective but is a condition precedent to the exercise of power under Section 17(1) and the same can be challenged on the ground that the purpose for which the private property is sought to be acquired is not a public purpose at all or that the exercise of power is vitiated due to mala fides or that the authorities concerned did not apply their mind to the relevant factors and the records._ _(vii). The exercise of power by the Government under Section 17(1) does not necessarily result in exclusion of Section 5-A of the Act in terms of which any person interested in land can file objection and is entitled to be heard in support of his objection. The use of word “may” in sub section (4) of Section 17 makes it clear that it merely enables the Government to direct that the provisions of Section 5-A would not apply to the cases covered under sub-section (1) or (2) of Section 17. In other words, invoking of Section 17(4) is not a necessary concomitant of the exercise of power under Section 17(1)._ _(viii). The acquisition of land for residential commercial, industrial or institutional purposes can be treated as an acquisition for public purposes within the meaning of Section 4 but that by itself does not justify the exercise of power by the Government under Sections 17(1) and/or 17(4). The court can take judicial notice of the fact that planning, execution and implementation of the schemes relating to development of residential, commercial, industrial or institutional areas usually take few years. Therefore, the private property cannot be acquired for such purpose by invoking the urgency provision contained in Section 17(1). In any case, exclusion of the rule of audi alteram_ W.P.(C).29890/10 & 11709/11 14 _partem embodied in Section 5-A(1) and (2) is not at all warranted in such matters._ _(ix). If land is acquired for the benefit of private persons, the court should view the invoking of Sections 17(1) and/or 17(4) with suspicion and carefully scrutinize the relevant record before adjudicating upon the legality of such acquisition._ 16. The aforesaid judgment was followed by the Apex Court in its later judgment in **Darshan Lal Nagpal (dead) by LRS. V. Government of NCT of Delhi & Ors.(2012(2)SCC 327)** . **17.** A reading of these two judgments show that in cases where the powers under Section 17(4) is invoked, records produced should demonstrate a clear application of mind by the competent authority on the question of necessity and desirability of invoking the urgency provision. Further , these provisions can be invoked only if competent authority is satisfied that even a small delay of even few weeks or months may frustrate the public purpose. Therefore before excluding the enquiry under Section 5A, the authorities concerned should be fully satisfied that delay of few weeks W.P.(C).29890/10 & 11709/11 15 or months which is likely to be taken for enquiry under Section 5A will have the possibility of frustrating the public purpose, for which the land is proposed to be acquired. Further, though the satisfaction of the appropriate Government in this behalf is subjective, but such satisfaction is a condition precedent to exercise of power under Section 17(4) and that when challenged, it is up to the appropriate Government to produce materials before the Court and satisfy the Court that the subjective satisfaction arrived at by it was on the basis of the materials available before it. 18. Having thus seen the principles laid down by the Apex Court, the question to be considered is whether the respondents have made out a case justifying the invocation of urgency clause under Section 17(4) of the Act. As already seen, the facts pleaded in the counter affidvit of the District Collector show that by order dated 7.8.2008, prior sanction was granted by the Government for the acquisition of 20 ares of land. Despite the administrative sanction so granted, notification under Sections 4(1) and 17(4) was issued only on 21.7.2010. This itself show that between the W.P.(C).29890/10 & 11709/11 16 date of granting administrative sanction and the date of Section 4(1) notification, respondents themselves wasted more than 2 years which itself will belie the claim of urgency to invoke Section 17(4) of the Act. In regard to the issue regarding the satisfaction of the appropriate Government, on the question of urgency, the only material available before this court is the bald averment in the counter affidavit filed by the District Collect, the 3[rd] respondent in writ petition(c). No.29890/2010 that the Commissioner of Land Revenue was satisfied of the urgency, based on the urgency of the case as explained by the requisitioning authority. This therefore means that the Commissioner of Land Revenue has mainly gone only by the claim made by the requisitioning authority and there was no independent application of mind in this respect. In other words, before invoking the urgency clause under Section 17(4), the Commissioner did not make any endeavour for a subjective satisfaction of the urgency justifying the invocation of section 17(4). 19. For the aforesaid reasons I am not satisfied that the respondents have made out a case to invoke Section 17(4) W.P.(C).29890/10 & 11709/11 17 and dispense with the enquiry under Section 5A of the Act. In that view of the matter, I set aside Ext.P9 notification in writ petition(c).No.29890/2010 and direct that the respondents will proceed further to conduct the enquiry as contemplated under Section 5A of the Land Acquisition Act. 20. Although, it is true that the respondents contended that since a meeting has been convened by the Principal Secretary to the Government and Ext.R2(c) decision was taken, in effect the enquiry as contemplated under Section 5A has been conducted by the Principal Secretary to the Government himself. On this basis, it was argued that no prejudice has been caused to the petitioners. However, I am unable to accept this contention because the enquiry under Section 5A is a statutory enquiry and that enquiry is to be conducted by the authority authorized by the statute itself. An informal enquiry conducted by a Government official cannot be a substitute for such a statutory enquiriy under Section 5A of the Act. 21. In so far as the contention of the petitioners regarding W.P.(C).29890/10 & 11709/11 18 the alignment is concerned, fixation of an alignment in a land acquisition proceedings is a matter for the experts and this principle has been laid down by this court in **Assyst International Pvt. Ltd v. State of Kerala (2009(4) KLT 116).** In this case, there is no material for this court to take a view that fixation of alignment is vitiated for any arbitrariness and mala fides. On the other hand, if the petitioners have any grievance, it is up to them to canvass it before the appropriate authority while the enquiry under Section 5A is conducted. The Writ Petitions are disposed of as above. ## **Sd/- ANTONY DOMINIC, JUDGE** mrcs /true copy/ PA To Judge