## **IN THE HIGH COURT OF KERALA AT ERNAKULAM**
## **PRESENT**
## **THE HONOURABLE MR.JUSTICE V.G.ARUN**
**TUESDAY, THE 9[TH] DAY OF APRIL 2024 / 20TH CHAITHRA, 1946**
## **CRP NO. 374 OF 2021**
**AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.1226 OF 2014 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM**
## **REVISION PETITIONER/S:**
**SHAJI AGED 52 YEARS W/O.SHAJU, ATTUPURAM, CHERANALLOOR P.O., KOOVAPPADY VILLAGE, PERUMBAVOOR BY ADV P.T.JOSE**
## **RESPONDENT/S:**
- **1 POWER GRID CORPORATION OF INDIA CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400, 220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI 682 303, REP.BY DEPUTY MANAGER**
- **2 THE SPECIAL TAHSILDAR (L.A.) POWER GRID CORPORATION OF INDIA, CHEVARAMBALAM, KOZHIKODE, NOW NEAR CIVIL STATION, KAKKANAD, ERNAKULAM DISTRICT, PIN 682 030**
- **3 STATE OF KERALA REP.BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI 682 030**
- **4 KERALA STATE ELECTRICITY BOARD, REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB LTD., THIRUVANANTHAPURAM 695 001 BY ADV R.HARISHANKAR**
## **OTHER PRESENT:**
## **GP B.S.SYAMANTHAK;SC FOR KSEB A.ARUNKUMAR**
**THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON 18.01.2024, ALONG WITH CRP.321/2022, THE COURT ON 09.04.204 DELIVERED THE FOLLOWING:**
CRP Nos.374/21 & 321/22
-2-
## **IN THE HIGH COURT OF KERALA AT ERNAKULAM**
## **PRESENT**
**THE HONOURABLE MR.JUSTICE V.G.ARUN**
**TUESDAY, THE 9[TH] DAY OF APRIL 2024 / 20TH CHAITHRA, 1946**
**CRP NO. 321 OF 2022**
**AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.1226 OF 2014 OF**
**VI ADDITIONAL DISTRICT COURT, ERNAKULAM**
**REVISION PETITIONER/S:**
**POWER GRID CORPORATION OF INDIA CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY, KAKKANAD, COCHIN - 682 030, PRESENTLY AT CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM REPRESENTED BY ITS SENIOR GENERAL MANAGER, PIN - 683565 BY ADV MILLU DANDAPANI**
## **RESPONDENT/S:**
|**1**|**SHAJI**|
|---|---|
||**AGED 52 YEARS**|
||**W/O. SHAJU, ATTUPURAM, CHERANELLUR PO, KOOVAPADI**|
||**VILLAGE , PERUMBAVOOR, PIN - 683544**|
|**2**|**THE SPECIAL TAHSILDAR (LA)**|
||**POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,**|
||**KOZHIKODE, PIN - 673017**|
|**3**|**STATE OF KERALA**|
||**REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI,**|
||**PIN - 682030**|
|**4**|**KERALA STATE ELECTRICITY BOARD - KSEB**|
||**REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB**|
||**LTD., THIRUVANANTHAPURAM, PIN - 695001**|
||**BY ADV P.T.JOSE**|
**THIS CIVIL REVISION PETITION HAVING COME UP FOR ADMISSION**
**ON 09.04.2024, ALONG WITH CRP.321/22, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:**
CRP Nos.374/21 & 321/22
-3-
CRP Nos.374/21 & 321/22
-4-
## **ORDER**
Dated this the 09[th] day of April 2024
These revision petitions are filed
challenging the order passed by the Additional District Judge-VI, Ernakulam in O.P.(Electricity) No.1226 of 2014. The original petition was filed by the revision petitioner in CRP No.374 of 2021 (hereinafter called 'the claimant'), being dissatisfied with the compensation awarded towards the damage and loss sustained due to the drawing of 400 KV lines across her property by the Power Grid Corporation of India Ltd
(hereinafter called 'the Corporation'). The
essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 2.20 Ares in Sy.No.40/14 of Koovappady Village in
Kunnathunadu Taluk. The land was cultivated with various yielding and non-yielding trees.
CRP Nos.374/21 & 321/22
-5-
According to the claimant, to facilitate drawing of the lines and smooth transmission of power, large number of trees were cut from her property. The drawing of high tension lines rendered the land underneath and adjacent to the lines useless, resulting in diminution of the value of the property. In spite of the huge loss suffered by the claimant, only an amount of Rs.67,305/was paid as compensation towards the value of yielding and non-yielding trees cut.
Surprisingly, no compensation was granted for diminution in land value. Hence, the original petition was filed, seeking enhanced compensation towards the value of trees cut and diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut since no evidence in support of the claim was produced. As far as the claim for enhanced
compensation towards diminution in land value is
CRP Nos.374/21 & 321/22
-6-
concerned, the court below relied on Ext.A7 document as well as Exts.C20 and C20(a) commission report and plan. Relying on Ext.C20(a) plan, the extent of central corridor was held to be 2.350 cents and that of the outer corridor was held to be 3.090 cents. For the central corridor, 40% of the land value was granted as compensation and for the outer corridor, 20% of the land value. The court below also took note of the fact that the major portion of the house is situated within the extent covered by the outer corridor and granted Rs.2,00,000/- as compensation on that account. Since the entire property was found to be affected by the drawing of electric lines, Rs.1,00,000/- was also awarded as compensation to the claimant. Accordingly, the claimant was found entitled to compensation of Rs.5,64,765/-. Dissatisfied with the quantum of enhancement, the claimant has filed CRP No.374 of 2021, whereas the Corporation has filed CRP No.321 of 2022
CRP Nos.374/21 & 321/22
-7-
contending that the enhancement ordered is far in
excess of the actual damage sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross illegality in refusing to grant enhanced compensation for the loss sustained due to the cutting of valuable trees, in spite of the Advocate Commissioner assessing and reporting the loss. The findings in the Commissioner's report were not relied on by the court below for the reason that the property was inspected much after the trees were cut. The said reasoning is flawed since the trees were cut much after issuance of notification by the Corporation and the cause of action for filing the original petition arose only on payment of the initial compensation, even later.
5. It is submitted that the court below
CRP Nos.374/21 & 321/22
-8-
grossly erred in granting only 40% of the land value for the central corridor and only 20% for the outer corridor. It is further submitted that the court below is not justified in granting only Rs.2,00,000/- towards injurious affection on the house situated under the corridors and only Rs.1,00,000/- as compensation even after finding the entire property is affected due to the drawing of electric lines. Considering the extent of damage sustained and the diminution in land value consequent to the drawing of lines, the court below ought to have granted compensation as claimed.
6. Learned Counsel for the Corporation contended that, compensation towards diminution in land value granted is exorbitant and there is no rationale in granting 9% interest on that amount. The court below also erred in relying on Ext.A7 document for fixing the land value of the claimant's property. As the drawing of electric
CRP Nos.374/21 & 321/22
-9-
lines does not prohibit the landowner from conducting agricultural activities and putting up small structures, 40% of the land value granted for the central corridor and 20% for the outer corridor are exorbitant. The court below grossly erred in granting additional compensation of Rs.2,00,000/- towards injurious affection on the house and Rs.1,00,000/- for the property which is in no way affected.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was rightly rejected since no supporting material, other than the findings in the Advocate
Commissioner's report, was made available. As found by the court below, apart from the
interested testimony of a solitary witness, who is the claimant in two of the connected cases, no other independent witnesses were examined to prove the claim. It is also not in dispute that
CRP Nos.374/21 & 321/22
-10-
the trees were cut in the year 2011 and the
commissioner inspected the property after a long period and had assessed the value of the trees by considering the trees standing in the remaining petition schedule property and neighbouring property. Such assessment, having no scientific basis, is not sufficient to discard the contemporaneous valuation statement prepared by the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in _**KSEB v. Livisha**_
## _**[(2007) 6 SCC 792]**_ are as under;
“ _10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The_
CRP Nos.374/21 & 321/22
-11-
_owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used.”_
On careful scrutiny of the impugned order, it is seen that the compensation was enhanced after taking all the above factors into consideration. The nature of the land, the cultivation therein, and the manner in which the land was affected by drawing of the lines are all seen considered for fixing the land value as well as the percentage of diminution. For the central corridor, 40% of the land value is granted as compensation and for the outer corridor, 20% is granted, which I find to be just and proper. The discretion was
properly exercised in granting Rs.2,00,000/towards injurious affection on the house situated
under the corridors and Rs.1,00,000/-, finding the entire property is affected due to the
drawing of electric lines.
9. The contention of the Corporation that
CRP Nos.374/21 & 321/22
-12-
the Government having fixed the fair value, the court below could not have fixed a higher value is liable to be rejected since, while assessing the damage sustained and fixing the compensation, the court is not bound by the guidelines/orders issued by the Government. The contention that the court below committed an illegality in awarding 9% interest cannot also be sustained in the light of the decision of this Court in _**V.V.**_
## _**Jayaram v Kerala State Electricity Board [2015**_
_**(3) KHC 453].**_ As such, there is no illegality or material irregularity in the impugned order, warranting intervention by this Court in exercise of the revisional power under Section 115 of the Code of Civil Procedure.
For the aforementioned reasons, the civil revision petitions filed by the claimant as well as the Corporation are dismissed.
If any amount is deposited pursuant to the
order of this Court or otherwise, the same shall
CRP Nos.374/21 & 321/22
-13-
forthwith be released to the claimant on her filing appropriate application. The entire enhanced compensation shall be paid to the claimant within three months of receipt of a copy
of this order.
Sd/-
**V.G.ARUN JUDGE**
Scl/