Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1992Division BenchAppeal dismissed with costs.

Sewaram v. Sobaran Singh

Case / Petition Number:
Civil Appeal No. 4390 of 1991

Case Synopsis & Summary

The case concerns an Election Petition under Sections 80, 84 read with 100 of the Representation of the People Act, 1951, challenging the Morena Assembly election of Sewaram on the ground that he had subsisting contracts with the Madhya Pradesh Government, rendering him disqualified under Section 9-A. Sewaram admitted contracts with the PWD and MP AKVN but contended that no subsisting contract with the State existed on 1 February 1990 (date of nomination) or 28 February 1990 (date of declaration). He argued that his business was in his individual capacity until 31 December 1989 and that, upon dissolution of his partnership in 1989, a fresh partnership was formed; he further claimed that he withdrew from the contracts by a letter dated 30 January 1990, and that any continuing engagement after that date was via his brother Patiram Gupta as agent. The Madhya Pradesh High Court held MP AKVN to be an “appropriate Government” under Section 9-A and concluded that the contracts remained subsisting on the relevant dates, disqualifying Sewaram. The Supreme Court affirmed the High Court on the single question argued here: whether the PWD contract remained subsisting on 1 February 1990. It held that, on the evidence, the contract with the PWD continued in Sewaram’s individual capacity up to the nomination date, and that the 30 January 1990 letter did not establish a definitive end to the contract; therefore, the disqualification stood. The Court dismissed the appeal with costs, while leaving other issues open for consideration. The decision underscores that subsistence of a contract is a factual inquiry, and that transfers or assignments require clear, written approvals.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Kuldip Singh
  • N. M. Kasliwal
Judgment Date
1992-09-15
Court Decision / Holding
Appeal dismissed. The Supreme Court affirmed the High Court, holding that the contract with the PWD remained subsisting on 1 February 1990 (the nomination date). It concluded that the appellant did not conclusively sever the contract and that continuing arrangements through his proxy did not negate subsistence under Section 9-A. The Court directed steps under Section 103 and noted that the question of MP AKVN being an appropriate government need not be decided for this appeal. Interim orders were vacated.
Final Disposition
Appeal dismissed with costs.

Parties to the Case

Appellants / Petitioners

  • Sewaram

Respondents

  • Sobaran Singh

Legal Representation & Advocates

Counsels for Petitioners

  • • U.R. Lalit
  • • Rameshwar Bhargava
  • • Yashpal Dhingra
  • • Baldev Krishan Satija
  • • S.S. Khanduja

Counsels for Respondents

  • • Dr. A.M. Singhvi
  • • Bansal
  • • Cicen Mukhopadhya
  • • R. Sasiprabhu
  • • R.G. Bansal

Provisions of Law Cited

Representation of the People Act, 1951 - sections 9-A, 80, 84, 100, 103, 116-A

Legal Doctrines & Maxims

  • A contract can be terminated by performance; by express agreement; under the doctrine of frustration; or by breach.
  • Subsistence of a contract is a question of fact to be decided on the circumstances of each case.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the contract with the Public Works Department of the Madhya Pradesh Government was not subsisting on the date of filing nominations (1.2.1990). He claimed that the contract existed in his individual capacity and that, after dissolution on 31.12.1989 and a severance letter dated 30.1.1990, there was no subsisting contract; he asserted that assignment to a firm was prohibited absent written approval and there was no evidence of such assignment; he contended that the contract was carried out by his brother Patiram Gupta through proxy, and continued only in name; thus, no disqualifying contract remained on the nomination date. He argued that the Department accepted his severance via separate completion certificates and that the matter was fact-specific, requiring close scrutiny of evidence to determine subsistence.

Contentions of Respondents

The respondent argued that the contract with the PWD was awarded to Sewaram in his individual capacity and that Clause 25 prohibited transfer or assignment without written consent; there was no proof of valid transfer to the firm; the Department treated Sewaram as the contractor and continued dealing with him, with Patiram acting as his power of attorney or agent; the evidence showed continued participation by Sewaram in contract-related activities, including signing measurement books and bills after the alleged severance; the letter dated 30.1.1990 was not reliably delivered to the proper office; nevertheless, the department’s actions and documents suggested subsistence of the contract up to the relevant dates; MP AKVN’s status as “Appropriate Government” was argued as part of the broader question of disqualification under Section 9-A.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Abdul Rahiman Khan v. Sadasiva Tripathi[1969] 1 S.C.R. 351PositiveCited to illustrate that the subsistence of a contract is a question of fact dependent on circumstances.
Konappa Rudrappa Nadgouda v. Vishwanath Reddy & Anr.[1969] 1 S.C.R. 395PositiveCited for principle that partnership interest in government contracts can attract Section 9-A and cannot be escaped by private dissolution without government awareness/consent.
S. Munishamappa v. B. Venkatarayappa and Ors.[1981] 3 S.C.C. 260DistinguishedDistinguished as not directly applicable to the facts; the Court clarifies limitations on applying earlier rulings to present circumstances.
Smt. Aslhing alias Lhingjanong v. L.S. John & Ors.(1984) 1 S.C.R. 863DistinguishedDistinguished for applying a different set of facts in determining whether a contract subsisted after a notice/letter of severance.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•8,267 words•~38 min read

In The Court Record

Sewaram v. Sobaran Singh

A ## SEWARAM _v._ ## SOBARAN SINGH ## SEPTEMBER 15, 1992 ## B ## (KULDIP SINGH AND N.M. KASLIWAL, JJ.) _Representation of the People_ Ac~ _1951: Sections 9A-80, 84, 103 and 116-A._ :~:- _Election-Disqualificatioit-Subsistence of contract with Appropriate_ c _Government-Contract awarded in individual capacity-Assignment of contract not permissible except with written approval of competent authority-Plea by elected candidate that contract was assigned to a firm-No evidence as to assignment of contract-Contract continued through the proxy of real brothe,-.ffeld there was subsisting contract with the Government on_ D _the date of nomination-Election held void._ <>.- ., The appellant was elected for the Legislative Assembly or State or Madhya Pradesh from the Morena Constitnency. The respondent, one of the defeated candidates, filed an Election Petition challenging the E[appellant's election on the ground that ][on ][the date or filing the nomination ] paper on 1.2.1990 and declaration or the result of election on 28.2.1990, the appellant was having subsisting contracts with the Madhya Pradesh Government and therefore he was disqualified under Section 9-A of the Repmentation of the People Act, 1951. F The appellant admitted his contract with the Public Works Department or the Government or Madhya Pradesh as well as with the M.P. Audyoglk Kendra Vlkas Nlgam (Gwalior) Ltd. (MPAKVN) but submitted that no contract with the Apropriate Govemmeut was subsisting on the date or filing the nomination papers and the date or scrutiny. His case was that he carried on his construction business in his individual capacity G upto 31.3.1988 and from 1.4.1988 by a partnership firm named as M/s Sewaram Gupta and the aforesaid contracts also were carried on by the said partnership. Since he intended to contest the elections, he retired from the partnership by duly' executing a deed or dissolution on 31.12.1989 and accordingly gave up his interest In the contract. On the same day, a H[fresh partnership ][was ][entered into ][between ][the remaining partners ][and ] F 512 513 SEWARAM _v._ SOBARAN one 'P' to continue the aforesaid contracts. The appellant also stated that A by bis letter dated 30.1.1990 addressed to Executive Engineer P.W.D. he informed that he has completely severed his connection with the contracts. > Rejecting the appellant's case, the High Court declared his election void declaring him disqualified under Section 9·A holding that the aban· donment of the contracts by appellant was not established and even after B his letter dated 30.1.1990 he continued to be associated with the contracts; that M.P. Audyogik Kendra Vikas Nigam was "Appropriate Government' under Section 9-A of the Act. In appeal to this Court on the question whether the contract taken C by the appellant with the P.W.D. of the Madhya Pradesh Government was subsisting on the date of filing nominations, it was contended on behalf of the appellant that (1) after the appellant's letter dated 30.1.1990 intimal· Ing the Department the he bad withdrawn from the contract no contract subsisted between him and the State Government; therefore there was no question of any disqualification under Section 9-A or the Act; (2) after the D appellant's letter there was no evidence to show that he participated in completing the contract. On behalf of the respondent it was contended that (1) the P.W.D. awarded the contract to the appellant in bis individual capacity and not E to any Orm. Clause 25 of the contract, which prohibited transfer or assignment of contract except with the prior written approval of the competent authority, was not complied with; (2) the sequence of events and documents makes it clear beyond doubt that it was the appellant alone who was participating in the execution or contract mudt after the filing of the nomination paper inasmuch as not only he participated in the F process of adjudiction of extension of time but also continued to sign all bills and Measurement Books in respect of the contract in his own name; and (3) the appellant's stand or severing his connection with contract by the letter dated 30.1,1990 was untenable because the said letter though addressed to Executive Engineer was not delivered In bis omce but was G delivered In the Omce or Sub· Divisional omcer. Dlsmlssln11 the appeal, this Court, HELD1 1. The question of subelstence of a contract with the Ap• proprlate Government makln11 It o dlsquollncotlon under Section 9•A of H 514 SUPREME COURT REPORTS[1992J SUPP. 1 S.C.R. A the Act is a que•tion of fact depending on the facts and circumstances of each case. [525-FJ 2. It is an admitted position that the appellant was awarded the contract by P.W.D. in bis individual capacity. The partnership firm Itself came into existence in 1988 and under Clause 25 or the Tender the B contract could not have been assigned or transferred in favour of the firm without the written consent or the Divisional Officer. There is nothing on record to show that at any time during the subsistence of this contract appellant had ever intimated the P.W.D. Department that the contract may be transferred or assigned in favour of the firm nor any correspon· C dence ever shows that the P.W.D. Department had accepted such transfer or assignment impliedly or expressly in favour or the partnership firm. Thus, it is established beyond any manner or doubt that till the date of filing the nomination paper, the contract with P.W.D. was continuing and dealt with by the appellant in his individual capacity and not by the D partnership firm. [528 A·D] 3. It cannot be said that the contract came to an end. by breach by writing the letter dated 30.1.1990. The facts of the case show that the contract did not came to an end but was songht to be continued through 'P', the appellant's real brother and member or Joint Hindu family with E appellant. Not only that, 'P' was also an attorney holder or appellant during the relevant period. The correspondence even after 30.1.1990 bas been made in the name of appellant though signned by 'P'. In these circumstances, it cannot be believed that appellant had put an end to the contract by breach. The conduct or appellant and bis brother even prior F to and after 30.1.1990 leads to an irresistible conclusion that the contract had not come to an end, and was subsisting, thereby incurring a dis· qualification under Section 9-A of the Act. [530 E-G] F 4. Though, the letter dated 30.1.1990 is addressed to the Executive Engineer, yet in fact, it was delivered not in bis Office but was delivered G in the Office of the Sub-Divisional Officer. It cannot be believed that when all correspondence relating to the contract was dealt with the Office of the Executive Engineer, why such an important letter was submitted to a lower authority or the rank of Assistant Engineer. In case appellant wanted to put an end to the contract, in the normal course of behaviour and human H conduct he sho'uld have gone personally to no less an authority than the SEWARAM _v._ SOBARAN [KASLIWAL, J.] 515 Executive Engineer and to have pnt and end to the contract mutually or A in case the concerned officers were not agreabie to end the contract mutually then he could have taken the step of ending the contract unilaterally by breach taking the risk of damages. The facts therefore lead to the conclusion that the appellant never intended nor in fact put an end to the contract, but continued with the contract through the proxy of his real brother. [529 D·F, 530 G·H, 531-A) B 4.1. The finding recorded by the Higb Court that the contract with the P.W.D. was subsisting on the date of filing the nomination and the date of scrutiny of the nomination papers and the appellant thus incurred a disqualification for contesting the election is affirmed. Steps as con· C templated under Section 103 of the Act shall be taken. [531 B·Dl _Abdul Rahiman Khan_ v. _Sadasiva Tripathi,_ [1969] 1 S.C;R. 351 and _Konappa Rudrappa Nadgouda_ v. _Vishwanath Reddy & Anr.,_ [1969) 1 S.C.R. _395,_ relied on. D S. _Munishamappa_ v. _B. Venkatarayappa and Ors.,_ [1981) 3 S.C.C. 260 and _Smt. Aslhing alias Lhingjanong_ v. _L.S. John & Ors.,_ [1984] 1 S.C.R. 863, distinguished. CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4390 of 1991. E From the Order dated 28.10.1991 of the Madhya Pradesh High Court in Election Petition No. 40 of 1990. U.R. Lalit, Rameshwar Bhargava, Yashpal Dhingra, Baldev Krishan Satija and S.S. Khanduja for the Appeallant. Dr. A.M. Singbvi, Bansal, Cicen Mukhopadhya, R. Sasiprabhu and R.G. Bansal for the Respondent. The Judgment of the Court was delivered by G KASLIWAL, J. Election for the Morena Legislative Assembly Constituency in State of Madhya Pradesh was held on 27.2.1990. Sewaram, the appellant before us having secured 25,509 votes was declared elected. Sobaran Singh, the respondent in this appeal being one of the defeated candidates having secured 19,055 votes filed an Election Petition under H SUPREME COURT REPORTS[l992] SUPP. 1 S.C.R. 516 A Sections 80 and 84 read with Section 100 of the Representation of the People Act of 1951 (hereinafter referred to as 'the Act') challenging the election of Sewaram. The ground for challenge was based on the allegation that on the date of filing the nomination paper on 1.2.1990 and declaration of the result of the election on 28.2.1990, Sewaram was having contracts B entered with the Madhya Pradesh Government subsisting and as such he was disqualified under Section 9-A of the Act. The details of the subsisting contracts with the Government were given as under in paragraph 4 of the Election Petition: - c D (a) A contract with M.P. Government through the Manag· ing Director, M.P. Industrial Area Development Corporation Ltd., Gwalior for contruction of W.B.M. Road in Industrial Estate, Malanpur, Distt. Bhind of M.P. The contract is for Rs. 51 lacs. The work order was issued on 29.12.88 and the date of completion mentioned in the contract is 28.3.90. Under this contract, the 10th running bill of Rs.1,63,805 is paid on 10.2.1990 and the construction work is still incomplete and being carried. E F G (b) Another contract with M.P. Government through the same authority mentioned in the above clause No. (a) for the construction of W .B.M. Road in Industrial Estate Malanpur Distt. Bhind of M.P. This contract is for Rs.55 lacs. The work order was issued on 10.11.89. The work under this contract is still being carried on. The aforesaid Corporation mentioned in para 4(a) & (b) is a subsidiary Coporation of the M.P. Industrial Development Corporation Ltd., Bhopal and the said Managing Director, Gwalior is a permanent Government servant; The Industries Department of the M.P. Government is the real owner and controller of these Corporations. The total finances and assets of these Corporations belong to the Government of M.P. In brief, these corporations are Government Corporations. Its functions are akin to the Public Works Department of M.P. H (c) A tontractual ngreement with the Governor of M.P. for development, Improvement and malntenanee of the Main 517 SEWARAM _v._ SOBARAN [KASLIWAL, J.] Road between Bus stand of village Rayroo and Gwalior in Distt. Gwalior (M.P.). This agreement No.2/87-88 is for Rs. 37,96,500. The work order No.2477 was issued on 16.4.87 by the Executive Engineer of P.W.D .. of M.P. The running bill for Rs.2,22,416/87 P. is paid in the month of March, 1990 by a cheque issued by the Public Works Department of M.P. The work under this contract is still continuing. The aforesaid work is undertaken and carried on by Madhya Pradesh Public Works Department under M.P. Words Department Manual of 1983 pubished in M.P. Government Gazette Extraordinary dated 20.1.84. The aforesaid portion of the road is part of the road named as National Highway No3 but it is under the jurisdiction of the Government of M.P. As per the provisions of the National Highway Act and related provisions of Law, the road is under the M.P. Government. The Central Public Works Department has nothing to do with the impugned contract." A B c D Sewaram filed a reply to the Election Petition and denied that the alleged contracts mentioned in para 4 (a) and (b) of the petition with the M.P. Audyogik Kendra Vik as Nigam (Gwalior) Ltd., (In short 'MP AKVN') are the contracts/works undertaken by the Madhya Pradesh Government. It was submitted that the said Nigam is a Limited Company incorporated E under the Companies Act, 1956 and as sucb is an independent and sovereign body corporate with perpetual succession, seal and power to hold and manage its own property. It was, therefore, denied that the Industries Department of the Government of Madhya Pradesh was the real owner of the said Company. As such, it was also denied that the contracts with the F said Company can be termed as contracts with the appropriate Government, in terms of Section 9-A of the Act. It was also submitted in the reply that he had been carrying on the construction business by taking contracts. G This business was carried on in his individual capacity upto 31.3.1988. On 1.4.1988, he intered into a partnership for his work contracts with the Indian Railways at Kolaras by duly executing a deed of partnership. The firm was named as "Mis Sewaram Gupta". It was also submitted in the reply that on 1.4.1989 he put his work/contract with the M.P. PWD National H 518 SUPREME COURT REPORTS[l992] SUPP. 1 S.C.R. - A Highways, Gwalior and the first contract with MPAKVN, in the aforesaid firm M/s Sewaram Gupta. The second contract with MP AKVN was also put in the aforesaid firm of M/s Sewaram Gupta on 24.10.1989. The work/business of the aforesaid three contracts was carried on by the said partnership firm thruugh him. B It was further submitted in the reply that on 31.12.1989, he made up his mind to contest the election of the Morena Assembly Constituency and as such opted for a ticket from the Bhartiya Janta Party. It was· admitted that on 31.12.1989, the following contracts with State Government and MPAKVN were subsisting:- c (i) for construction of floodable reach in KM. 105 to 108 of Agra Bombay Road with the M.P., P.W.D. National Highways, Gwalior. D (ii) for the construction of WBM road at Malanpur agreement No.20 with the M.P. Audyogik Kendra Vikas Nigam (Gwalior) Ltd. E (iii) for construction ofWBM road at Malanpur agreement No.28 with M.P. Audyogik Kendra Vikas Nigam (Gwalior) **1 Ltd. '** Shri Sewaram in his reply further submitted that since he intended to contest the election, he decided to severe for good his connection with the aforesaid contracts. He, therefore, decided to and retired from the F aforesaid (partnership) firm by executing necessary documents. But, since the aforesaid works/contracts were at advanced stages, he made alternate arrangements with one Shri Patiram Gupta, who was also a registered contractor with M.P. PWD and the said MP AKVN to undertake and complete the said works. An agreement to this effect was duly executed between him and Shri Patiram Gupta on 31.12.1989 and duly got noted by G a Notary Public. He also retired from the aforesaid partnership firm by duly executing a deed of dissolution on 31.12.1989. On such retirement from the aforesaid firm, a fresh partnership was entered into between the remaining partners and Shri Patiram Gupta on 31.12.1989 to continue the aforesaid works/contracts. The aforesaid deeds of dissolution and fresh H partnership were also duly got noted by a Notary Public on 31.12.1989. F 519 SEWARAM _v._ SOBARAN [KASLIWAL, J.] Sewaram further submitted in the reply that on 29.1.1990 he was A permitted by high command of the Bharti ya J anta Party to file nomination papers for the Morena Vidhan Sabha Constituency. As such, he immediately informed the Executive Engineer, M.P. PWD, N.H. Gwalior and the Managing Director of MPAKVN that since he was willing to contest the election, he was unable to execute and complete the works/contracts and, B as such, he completely withdrew himself from the works/contracts. He also wrote letters to the above effect to the Executive Engineer M.P. PWD, N.H., Gwalior and the Managing Director of MP AKVN on 30.1.1990 and enclosed a copy of his aforesaid agreement dated 31.12.1989 with Shri Patiram Gupta with each of the aforesaid three letters. He also made a request to transfer the works in the name of Shri Patiram Gupta. In each C of these letters, he categorically made it clear that as far as he was concerned, the works stood closed. It was further alleged that he completely severed his connection with and did not even touch the said works. Shri Patiram Gupta started to execute them since then and has been executing the said works/contracts to date. It was further alleged that he filed his first D nomination form on 1.2.1990 and had completely and duly severed his association with the aforesaid contracts. Thus, no contract with the appropriate Government was subsisting on the date of filing the nomination papers and the date of scrutiny. It was also submitted that the alleged running bill as mentioned in para 4 (a) of the Election Petition was prepared by the department and accepted by Shri Patiram Gupta and E payment thereof was also received by Shri Patiram Gupt in terms of the arrangement mentioned in the letter dated 30.1.1990, and he was not concerned at all either with the said work/contract or the alleged running bill or its payment. On the basis of the aforesaid pleadings of the parties, the High Court framed the following issues:- F "(i) Whether M.P. Audyogik Kendra Vikas Nigam can be termed as an "appropriate Govt." within the meaning of Section 9- A of the Representation of Peoples Act, 1951? (2) Whether the contract No.20 as narrated in para 4(a) of the petition, entered between the respondent and the M.P. Audyogik Kendra Vikas Nigam was subsisting during the election i.e. between 1.2.90 to 27.2.90? (3) Whether the contract No.28 as detailed in para 4 (b) H 520 SUPREME COURT REPORTS!1992j SUPP. 1 S.C.R. A of the petition, entered between the respondent and the M.P. Audyogik Kendra Vikas Nigam was subsisting during the related Election? B (4) Whether the contract No.2/87-88 for constructing the road, detailed in para 4( c) of the petition, entered between the respondent and the Rajyapal of Madhya Pradesh was subsisting during the relat@d Election? c (5) Whether the respondent, Sawaram Gupta, validly severed his connection on 31.12.89 with the contracts alleged in paras 4(a), 4 (b) and 4(c) of the Election Petition on or before the relevant date and was not disqualified to stand for Election?" The election petitioner examined 5 witnesses and Shri Sewaram Gupta examined 7 witnesses. Shri N.K Mandloi, Executive Engineer PWD, D N.H. Division, Gwalior was examined as a court witness. The parties also produced documentary evidence. The High Court under issue No.l held that MP AKVN is a Government Company being a subsidiary of M.P. Audyodik Kendra Vikas Nigam Limited, and the State Government and MP AKVN are not separate legal entities, the latter being the machinery is E a part of the State Government entrusted to carry out designated furnctions and activities. The High Court, thus concluded that MP AKVN is "approvpriate Government" within the meaning of the term used in Section 9-A of the Act and accordingly decided issue No.1 in affirmative. The High Court then discussed the oral and documentary evidence F in detail and under issue No.5 held that the plea of severance set up by Sewaram has not been established. The High Court also held that no effect was given to the purported severance contemplated in terms of respondent Sewaram's letter dated 30.1.1990. The Executive Engineer and Superintending Engineer continued to deal with Sewaram treating him as the contractor. Thus, issue No.5 was decided in negative. The High Court G thereafter took issues Nos. 2, 3, and 4 jointly into consideration and held that the abandonment of works in respect of the three contracts, by respondent Sewaram, is not established. Whether those contracts were continued by Sewaram overtly or through his proxy Patiram covertly, matters little. Even after writing his letters dated 30.1.1990, Sewaram Gupta H continued to be associated with those contracts with PWD and MPAKVN. 521 SEWARAM _'v._ SOBARAN [KASLIWAL, J.] The High Court as such decided these issues also in affirmative. As a result A of the findings recorded above, the High Court held that Sewaram was disqualified in terms of Section 9-A of the Act. The election of Sewaram was declared void. It was directed that as contemplated under Section 103 of the Act, steps shall be taken by the Registry to intimate at once the substance of the order to the Election Commission, New Delhi and the B Speaker M.P. Legislative Assembly, Bhopal and in due course to send also to the Election Commission an authenticated copy of the decision. Sewaram aggrieved against the aforesaid Judgment of the High Court has filed the present appeal under Section 116-A of the Act. c We have heard learned counsel for the parties at length and have thoroughly gol\e through the record. It may be mentioned at this stage that in view of the fact that we are affirming the findings of the High Court as regards the contract with the PWD of the Government of Madhya Pradesh subsisting on the relevant dates, we. refrain from recording any finding whether MP AKVN was an appropriate Government within the meaning of D Section 9·A of the Act. In view ofthis we also find it unnecessary to decide the question whether any works/contracts taken by Sewaram with MP AKVN were subsisting or not on the relevant dates. We are, thus, determining the only question whether the work/contract taken by the appellant Sewaram with the PWD of the Government of Madhya Pradesh E was subsisting or not on 1.2.1990 • the date of filiitg nominations. Learned counsel for the appellant submitted that the appellant had clearly intimated to the department that be had withdrawn from the contract and bis interest in the contract bad come to an end vide bis letter F dated 30.1.1990. Any conduct on the part of the department or on the part of Patiram Gupta after the aforesaid date cannot be taken as a cir· cumstance against the appellant. After 30.1.1990 Patiram had dealt with the department and the department had also accepted the work to be done by him ud this clearly goes to show that the contract with the petitioner had come to an end. The department bad given two separate completion G certificates, one to Patiram and the other to the appellant and this clearly shows that the department had treated the appellant as having terminated bis part of the contract on 30.1.1)9(). It was submitted that the contents of letter dated 30.1.1990 leave no 1nanner of doubt that the appellant .had expressly intimated the Executive Engineer that the appellant had H 522 SUPREME COURT REPORTS[1992) SUPP. 1 S.CR. A withdrawn from the contract. No contract can be held as subsisting between the appellant and the Government after such notice sent bY. the appellant ".ide his letter dated 30.1.1990. It was submitted that an unequivocal clear intimation given by the appellant vide his letter dated 30.1.1990 clearly shows a severance of the contract on 30.1.1990 and there was no B question of any disqualification of the appellant under Section 9-A of the Act. it was also contended that even if such intimation given by the appellant is treated as unilateral, there does not remain any disqualification on the basis of any subsisting contract with the appropriate Government under Section 9-A of the Act, Reliance in support of the above contention has been placed on _S. Munishamappa_ v. _B. Venkatarayappa and Others._ C (1981) 3 SCC 260 and _Smt. Aslihing alias Lihinyjanong_ v. _L.S. John_ & _Ors.,_ (1984) 1 SCR 863. lt was further contended·on behalf of the appellant that so far as the PWD contract is concerned, prior to 30.1.1990 Patiram had never participated in any work of this contract inspite of the fact that he was holding a general power of attorney from the appellant. All acticns D prior to 30.1.1990 were taken only by the appellant. After 30.1.1990, there is no evidence to show that the appellant participated in completing the work of the contract. Shri V.P. Srivastava, R.W.7, Sub Divisional Officer working on this contract has expressly stated in his evidence that after 30.1.1990 the appellant did not come on the work site. After 30.1.1990 all E documents concerning the PWD contract show that Shri Patiram alone had participated in the work contract. In support of this contention reliance is placed on Exhibit P.60 dated 15.2.1990 by which extention for completing the contract was sought by Patiram. Exhibit R.23 dated 24.2.1990 by which Patiram Gupta communicated that he had completed the work. Exhibit R. F 24 dated 16.3.1990 by which Patiram had asked for the payments. Exhibit P.71 dated 31.3.1990 shows that the running bill was paid to Patiram and this bill was counter signed by many officers including the Executive Engineer and ultimately to complete the formalities a new contract was made in favour of Patiram vide Exhibit R.2. A completion certificate was G given to Patiram vide Exhibit R.20 and a final bill was prepared in the name of Patiram and paid to him vide Exhibit R.25 dated 22.9.1990. It was also submitted that the letter Exhibit R.12 dated 30.1.1990 was accepted by the PWD department and a completion certificate as of 30.1.1990 was issued in the name of the appellant vide Exhibit R.19. The authenticity of the H aforesaid documents is affirmed in the evidence of Shri V .P. Srivastava. He 523 SEWARAM _v._ SOBARAN [KASLIWAL, J.] was the person who was incharge and the evidence of Srivastave is further corroborated by the subsequent act and the steps taken by other officials of PWD at various stages. Learned counsel for the respondent on the other hand submitted that admittedly the contract with PWD was applied for, tendered for and **B** awarded to Sewaram Gupta in his individual capacity and it remianed unchanged at all relevant times. The Chief Engineer, PWD vide his communication dated 3.4.1987 approved the contract in the name of Sewaram Gupta himself and not to any firm. Clause 25 of the contract specifically prohibited and interdicted the transfer or subletting or sub-contracting of the work awarded to Sewaram Gupta except with the prior written apC proval of the Divisional Officer. Admittedly, this clause was never invoked nor any wrtten approval for transfer of the contract in favour of the firm Mis Sewaram Gupta has even been alleged much less proved. There is not a single document or communication or any other piece of evidence to suggest that the PWD ever dealt with Shri Sewaram Gupta as a firm or **D** that at any time it was dealing with anyone else except Shri Sewaram Gupta in person. It was further argued that Shri Patiram Gupta was not a stranger, but was the real brother of Sewaram Gupta as well as power of attorney holder on behalf of Sewaram. It is not the case of Sewaram either set up in the reply or in evidence that it was a case of complete secession or stoppage of work on the part of Sewaram. On the contrary, it is an admitted E case by the appellant himself that the contract was continued and completed by no other person than Patiram who was not a stranger, but the real brother, member of the joint family and a power of attorney holder of Sewaram. It was submitted that not only upto January 1990, but even thereafter at all relevant dates including in February, March and indeed **F** till the service of the summons of the election petition on 22.7.1990, the appellant himself acted in respect of the contract and to execute the contract. It was also submitted that on 15.2.1990 a letter was sent in the name of Sewaram Gupta seeking extention of time in the present contract itself. At the end of the letter, the name of Mr. Sewaram Gupta is typed. **G** It has been contended that it has been sought to be explained on behalf of the appellant that the word 'Sewaram Gupta' at the end of the letter means and should be read as Sewaram Gupta firm, but such plea is palpably dishonest and liable to be rejected. There is no ground or ji:stification for reading the plain word Sewaram Gupta to be read as Sewaram Gupta firm. On 31.3.1990 the Measurement Book (in short 'MB') relating to the present **H** 524 SUPREME COURT REPORTS[1992) SUPP. 1 S.C.R. A contract itself has been signed at the end by Patiram Gupta, but with the name of Sewaram Gupta. The bill prepared on the basis of the aforesaid MB dated 31.3.1990 has been signed by Patiram Gupta for Sewaram Gupta. Communication dated 2.4.1990 from Executive Engineer to Superintending Engineer recommending further extension of time for completion of conB tract makes a mention of Sewaram Gupta and it is addressed to Sewaram Gupta alone. On 2.5.1990 Superintending Engineer, PWD wrote to Sewaram Gupta informing him to attend hearing at which his request for extension of time will be adjudicated. On 25.6.1990, letter has been issued from Superintending Engineer to Executive Engineer, intimating him the decision of the Superintending Engineer granting extension of time after C hearing both the parties incl_uding the i;ontractor and a copy of this letter is marked to Mr. Sewaram Gupta in person. It bas been contended that the above sequence of events and documents makes it clear beyond any manner of doubt that it was Sewaram Gupta alone who was participating in the execution of the contract much after the filing of nomination paper D on 1~.1990. Sewaram Gupta, not only participated in the process of adjudication for extension of time, but also continued to sign all bill and MBs in respect ·of this very contract in his own name. The fact that Patiram Gupta was signing various letters, measurement books and bills is simply because he was acting at all relevant times as the agent of Sewaram. It was further contended that only communication by Patiram Gupta in his own E name occurs after 22.7.1990 which is admittedly the date on which notice of Election Petition had been served on the appellant Sewaram Gupta. There is no communication worth the name by Patiram in his own name as a contractor prior to 22nd July, 1990 and this totally falsifies the stand taken by the appellant that he had severed his connection with the contract F on 30.1.1990 Learned counsel for the respondent further submitted that the contention of the appellant regarding the sending. of letter dated 30.1.1990 is itself wholly untenable and clearly reflects a desperate and afterthought attempt to set up a case of severance of contract in order to wriggle out G of the provisions of Section 9-A of the Act. It was submitted in this regard that this letter dated 30.1.1990 though addressed to the Executive Engineer, but has· supposedly been given to the Office of the Sub Divisional Officer Mr. Srivastava. It has been pointed out in this regard that all communications in respect of the present contract with PWD have been sent to the H Office of the Executive Engineer, but such an important letter dated 525 SEWARAM _v._ SOBARAN [KASLIWAL, J.] 30.1.1990 on which the entire case hinges has not been delivered in the A Office of the Executive Engineer, but to Sub Divisional Officer Mr. Srivastava who has apparently come out to support the appellant. Mr. Mandloi, Executive Engineer appearing as a court witness categorically states that he had no knowledge whatsoeyer of the letter dated 30.1.1990 before 23.7.1990. Clause 28 of the contract also makes it clear that work is to be B done under the direction of the Executive Engineer or Superintending Engineer. It has also been argued that according to the statement of Sewaram, he himself and his friend Rajesh Verma had gone to deliver the letter dated 30.1.1990 and Rajesh Verma also supports the above statement of Sewaram, but Mr. V.P. Srivastava categorically states that Sewaram came along with Patiram and not with Rajesh Verma for delivering the C letter dated 30.1.1990 to him. It was also submitted in this regard that there is no explanation as to why this letter dated 30.1.1990 was not brought to the notice of Shri Mandloi - the Executive Engineer till 23.7.1990 specially when it was addressed to the Executive Engineer and was a very material and important document in order to uphold the contention of the appellant D of severing the contract which was coming in his way for contesting the election. Learned counsel for the respondent on several grounds also assailed the genuineness of the documents brought in existence by the appellant on 31.12.1989 purportedly to show that Sewaram had withdrawn from the partnership of the firm Mis Sewaram Gupta and Patiram Gupta joined the said firm as one of the partners. E We have given our thoughtful consideration to the arguments advanced by learned counsel for both the parties and also the case law cited at the bar. The question of subsistence of a contract. with the appropriate Government making it a disqualification under Section 9-A of the Act is a F question of fact depending on the facts and circumstances of each case. In _Abdul Rahiman Khan_ v. _Sadasiva_ .-Tripath~ [1969) 1 SCR 351, the respondent was declared elected to the Legislative Assembly of Orissa from the Nowrangpur General Constituency. The appellant filed an election petition before the High Court of Orissa for an order setting aside the election of G the respondent, on the ground that the appellant's nomination paper was imporperly rejected and he was illegally deprived of his right to contest the election. It WBI! a common ground that the appellant was carrying on the business of a bulldlng contractor and that in pursuance of a notification issued by the Government of Orlssa he had submitted tenders for construe· tlon of bulldlngs of the Rental Housing Scheme at the rates specified H 526 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R. A therein. The tenders were accepted and the appellant had carried out a part of the construction work, but had thereafter stopped the work because he suffered serious injuries which necessitated his detention in a public hospital. The appellant claimed that at his request the contract was cancelled, and on that account at the date of filing of his nomination there B was, between him and the State of Orissa no subsisting contract for execution of works undertaken by him, and that in any event there was in law no contract between him and the State relating to the execution of works which disqualified him from standing at the election as a candidate for a seat in the State Legislative Assembly. ## C In the facts and circumstances of the above case, it was held that the appellant had commenced execution of the work, but had not completed it. Payment for the work done was not made to the appellant. The contract was not determined _by mutual agreement nor was it abandoned (emphasis supplied)._ ## D In _Konappa Rudrappa Nadgouda_ v. _Vishwanath Reddy_ & _Anr.,_ [1969] 1 SCR 395, the appellant and the first respondent were candidates for election in February, 1967 from the Y adagiri constituency which was won by the first respondent. The appellant challenged his election by a petition on the ground that he was a partner in a firm which had two contracts with E the State Government, one for the construction of a road and the other for the construction of a dispensary building, which were subsisting on the day when nominations were filed; he was therefore disqualified from being a candidate under Section 9-A of the Representation of the People Act, 1951 and his election was void. The High Court dismissed the election petition. F This Court allowed the appeal and held that the High Court was in error in holding that the contracts had been fully performed and Section 9-A did not apply. It was held that the law requires that a candidate should not have any interest in any contract with Government and therefore even a partner in a firm has an interest sufficient to attract the provisions of Section 9-A. The first respondent could not by a private dissolution of the G partnership escape his liability under the contract to the Government, and there was here no novation, because notice of the dissolution was not given to Government and the Government had not accepted the person to whom the business was transferred in place of the respondent's firm. H In _S. Munishamappa_ v. _B. Venkatarayappa and Others,_ [1981) 3 SCC 527 SEWARAM _v._ SOBARAN [KASLIWAL, J.] 260 (supra) on which reliance has been placed by the learned counsel for A the appellant. In that case the letter written by the appellant to the Executive Engineer clearly proceeded on the basis that at that point of time there was no existing contract between him and the Government and he was only asking for a settlement of his bills and for concellation of the licence. The endorsements made on the said letter by the authorities also B indicated that the said position was accepted by them and necessary directions for finalisation of the bills were given. The further fact was that the security deposit had been refunded to the appellant and no penal action had been taken against him and the remaining works had been allowed to be executed by other contractors, also established that the said contract between the parties had come to an end before the appellant filed C his nomination paper. In these circumstances this Court held that the contract was not subsisting on the date the appellant filed his nomination paper. > In _Smt. Aslhing alias Lhingjanong_ v. _L.S. John_ & _Ors.,_ (1984) 1 SCR D 863 (supra), this Court held that the respondent was a party to a subsisting contract with the Government for widening of a road words a letter to the concerned Executive Engineer stating that he was closing the said contract. The appellant contended that the contents of the letter did not have the > effect of putting an end to the contract. Dismissing the appeal this court E held that after the letter, the contract came to an end by breach and was no longer subsisting. Acceptance of the letter by the authorities was unnecessary for putting an end to the contract although the breach may give rise to an action for damages. In the facts of that case this court accepted that a letter was written on 30.11.1979 to the concerned Executive Engineer stating that he was closing the said contract. The last date for F filing nomination was 10.12.1979. This court after going through the contends of the letter held that it was absolutely clear that the contractor unilaterally put an end to the contract and informed the department concerned accordingly and also he had resigned from the contractors' list of PWD Malanpur. It was held that after this letter, the contract came to G an end by breach and the contract was no longer subsisting. Thus, the question of subsistence of the contract at the relevant time has been decided in all the above cases on the basis of the facts and circumstances of each one of those cases. As already held above, such question is a question of fact depending on the facts and circumstances of each case. H _528_ SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R. A In order to decide the controversy, we shall now take into considertion the facts of the case in hand. It is an admitted position that Sewaram in his individual capacity had submitted a tender/application on 6.11.1986 for-seeking the contract for raising of floodable reach in K.M. 105 to 108 of A.B. Road on National Highway No.3 for an amount of Rs. 37,96,500. This tender for the above work was accepted in favour of Sewaram by the B Executive Engineer, PWD, National Highway Division, Gwalior on behalf of the Governor, Madhya Pradesh on 16.4.1987. Clause 25 of the contract clearly provided that the contract shall not be assigned or sublet without the written approval of the Divisional Officer. Admittedly the firm _Mis_ Sewaram Gupta itself came into existence in 1988 and the contract made C originally in fovour of Sewaram in his individual capacity could not have been assigned or transferred in favour of the firm without the consent of the Divisional Officer. Even otherwise, there is nothing on record to show that at any time during the subsistence of this contract Sewaram had ever intimated the PWD department that the contract may be transferred or assigned in favour of the firm nor any correspondence ever shows that the D PWD department had accepted such transfer or assignment impliedly or expressly in favour of the firm M/s Sewaram Gupta. Thus, it is established beyond any manner of doubt that till 1.2.1990 the date of filing the nomination paper, the contract with PWD was continuing and dealt with Sewaram in his individual capacity and not with the firm Sewaram Gupta. The E appellant has taken the stand that an agreement was executed between him and Patiram on 31.12.1989 by which he gave up his interest in the existing contract with PWD and MP AKVN and executed another document on the same day dissolving the partnership firm and a new partnership deed was executed on the same date between Patiram and other persons. There is a F serious controversy raised in this regard on behalf of the respondent that all these documents as alleged to have been executed on the stamp paper supplied by one Narayan Swaroop Saxena, stamp vendor are forged and void. This Narayan Swaroop Saxena has appeared in the witness box and has deposed that he did not enter the sale of the stamps to the appellant Sewaram in his register and has further admitted that the stamp paper G alleged to have been sold to appellant Sewaram bearing the serial number 13429 had been sold to a third party stranger namely Budh Ram who had purchased the same on behalf of lady Radha Bal, It has also been argued on behalf of the respondent that the notary Shri Chhinga I.al Gupta was a relation of Sewaram and thou11h there were various notaries having jurisH diction In Morena, the document was 11ot notari1ed frum Shrl Chhinga Lal SEWARAM _v._ SOBARAN [KASLIWAL, J.] 529 Gupta, a notary from Gwalior. Many other circumstances have been shown A in order to establish that all the documents. brought into existence on 31.12.1989 were forged and manufactured, but we do not consider it necessary to record a positive finding in this regard, in view of the fact that nothing material turns out on these documents for deciding the main controversy raised in the present case. Even if, for arguments sake it may be admitted that Sewaram had dissolved the partnership firm Mis Sewaram B Gupta and Patiram was introduced as a new partner in this firm on 31.12.1989, it is neither established in fact, nor it was permissible to transfer or assign the contract in favour of the firm at any time without the approval of the Divisional Officer as per terms of Clause 25 of the contract. c Now we shall consider the main plank of the contention on which the entire edifice has been built by Sewaram that he had submitted a letter dated 30.1.1990 whereby he had severed all his connections with the contract in question and after this date there was no subsisting contract so as to incur any disqualification under Section 9-A of the Act. Admittedly, D this letter dated 30.1.1990 is addressed to the Executive Engineer, but in fact, it was delivered not in the Office of Executive Engineer Mr. Mandloi, but had been delivered in the Office of the Sub Divisional Officer Mr. Srivastava. It is important to note that all correspondence in respect of the contract in question has been done by Sewaram with the office of the Executive Engineer except the letter dated 30.1.1990 in question which E alone according to the appellant had been submitted to Shri V .P. Srivastava, the Sub Divisional Officer sitting in a different office and far away from the Office of the Executive Engineer. According to Sewaram, one Rajesh Verma accompanied him while delivering this letter to Srivastava, but according to Srivastava, Patiram had accompanied Sewaram and not F Rajesh Verma. It cannot be believed that when all correspondence relating to the contract was dealt with the Office of the Executive Engineer, why such an important letter dated 30.1.1990 was not submitted in the Office of the Executive Engineer and is alleged to have been submitted to a lower authority of the rank of Assistant Engineer. We see force in the submission of the learned counsel for the respondent in this regard that Shri Mandloi, G the Executive Engineer was not willing to oblige the appellant by taking a false stand and as such the appellant took a false plea that he had given such letter dated 30.1.1990 to Mr. Srivastava. It is important to note that Mr. Mandloi in his statement has clearly stated that he never saw nor had any knowledge of the letter dated 30.1.1990 prior to 23.7.1990. Even if, for H 530 ## SUPREME COURT REPORTS[1992] SUPP. l S.C.R. - A arguments sake it may be considered that the appellant had submitted the letter dated 30.1.1990 _bonafidely_ for some reasons on the same day in the Office of the Assistant Engineer Mr. Srivastava, it was incumbent upon the appellant to see that the letter should have reached immediately in the Office of the Executive Engnieer who alone was competent to deal with such important matter. Admittedly, the letter was addressed to the Execu- - B tive Engineer and it came to his notice on 23.7.1990 after the service of the notice of the Election Petition on the appellant. The contract can come to an end by any of the following modes:- ( 1) By performance; c - {2) By express agreement; - {3) Under the doctrine of frustration; and - ( 4) By breach. D Mr. Lalit, learned senior counsel appearing on behalf of the appellant frankly and rightly submitted that in the present case by letter dated 30.1.1990, the contract did not ocme to an end under the above mentioned three categories, but according to him, the case of the appellant falls under the fourth category of contract coming to an end by breach. We are not E satisfied that in the present case the contract came to an end by breach by writing the letter dated 30.1.1990 as sought to be submitted on behalf of the appellant. In the facts of the present case the contract had not come to an end but was sought to be c:Ontinued tbrough Patiram Gupta. It is an admitted fact that Patiram Gupta is the real brother and member of joint F Hindu family with Sewaram' appellant.. Nat only that, patiram was also an attorney, holder of Sewaram during the relevant period. The correspondence even after 30.1.1990 has been made in the name of Sewaram appellant though signed by Patiram. In these circumstances, it cannot be believed that Sewaram had put an end to the contract by breach and the conduct of Sewaram and Patiram even prior to and after 30.1.1990 leads to an G irresistible conclusion that the contract had not come to an end, and was subsisting, thereby incurring a disqualification under Section 9-A of the Act. In case Sewaram wanted to put an end to the contract, in the normal course of behaviour and human conduct he should have gone personally to no less an authority than the Executive Engineer and to have put an end H to the contract mutually or in case the concerned officers were not aggree- F 531 SEWARAM _v._ SOBARAN [KASLIWAL, J.] able to end the contract mutually then he could have taken the step of A ending the contract unilaterally by breach taking the risk of damages. The facts of the present case lead us to the conclusion that the appellant never intended nor in fact put an end to the contract, but continued with the contract through the proxy of his real brother Patiram. In the circumstances mentioned above, we are in agreement with B findings recorded by the High Court in this regard that the contract with the PWD was subsisting on the date of filing the nomination and the date of scrutiny of the nomination papers and the appellant thus incurred a disqualification for contesting the election of Morena Assembly Constituency in the State of Madhya Pradesh. C As we are dismissing the appeal filed by the appellant on one **question alone, we are not expressing any opinion on any other question** decided by the High Court and leave all other questions open. In the result, we· find no force in this appeal and it is accordingly dismissed with costs. Future steps as contemplated under Section 103 of the Act shall now be taken as directed by the High Court. In view of the appeal having been dismissed, any interim orders passed during the pendency of this appeal stand automatically vacated. T.N.A. Appeal dismissed.
End of Judgment Record
Browse All Supreme Court of India (1992) Decisions
1992-01-07

Jaiswal v. Debi Mukherjee

Dr. P. K. Jaiswal challenged a UPSC process for the post of Assistant Director General (Prevention of Food Adulteration). The Union Government had initially asked UPSC to fill the post by direct recruitment but, before advertisements, informed it to withhold the process while examining possible promotion from Assistant Secretary and amending recruitment rules to create higher tiers. Despite this, the UPSC advertised the post and the appellant was interviewed. Debi Mukherjee, then Assistant Secretary and seeking promotion upon the rule-amendment, obtained an interim stay from the Central Administrative Tribunal and later a direction to provide promotional avenues. In the meantime, two higher-pay tiers were created, without separate designations, under an amendment directed by the Court in a related matter. The appellant argued that once the selection process begins, the Government and Tribunal cannot freeze it and that the Commission should complete the selection; and that overlooking the two new layers amended later was erroneous. The respondents contended on points of vested rights and the proper policy- and rule-based framework for promotions versus direct recruitment. The Supreme Court held that the Government can withdraw the requisition before the advertisement if it intends to amend rules to permit promotion, that the Government’s pre-advertisement decision is permissible, and that a right to be considered for selection crystallizes only after advertisement and interview. The appeal was dismissed.

1992-09-24

S.B. Dogra v. State of Himachal Pradesh and Ors.

This Civil Appeal concerns the seniority of S.B. Dogra in the Himachal Pradesh Police Service in the wake of the demobilised armed forces concession. After HP State was formed, Rule 5(1) of the Demobilised Armed Forces Personnel (Reservation of Vacancies in the HP State Non-Technical Services) Rules, 1972, provided that the seniority of officers appointed against reserved vacancies shall be determined on the assumption that they joined the service at the first opportunity after their military service or training prior to commission. Dogra, who had military service and later joined the HP Police Service against a reserved vacancy for Demobilised Armed Forces Personnel, was placed with a notional entry year (1964) and thus ahead of some officers, including Durga Shanker Amist. The dispute escalated through High Court proceedings and a Central Administrative Tribunal decision relying on earlier cases. The Supreme Court, comparing Rule 5(1) with Punjab/Haryana rules and distinguishing the applicable statutory framework, held that the Tribunal erred in confining the seniority to the period of actual military service during the emergency. It noted that the rules are not pari materia with Haryana’s rules and that the language of Rule 5(1) permits a broader interpretation for notional entry. The Court distinguished certain earlier rulings (A.S. Parmar; Narendra Nath Pandey) as inapplicable here, while applying the State of Madhya Pradesh v. Rameshwar Prasad approach to preserve fair seniority. Ultimately, the appeal was allowed, the Tribunal’s seniority order was set aside, and the prior position was restored with directions for implementation of the judgment.

1992-12-11

State of Maharashtra v. Rattanlal

This is a Supreme Court decision interpreting the revisional powers of the State Government under the Maharashtra Agricultural Land (Ceiling and Holdings) Act, 1961. The respondent-declarant had a declaration under Sec. 12; the Surplus Land Determination Tribunal found surplus land (9 acres 8 guntas). On appeal, the Revenue Tribunal modified the resumption from Survey No. 11 to Survey No. 29, which was upheld. Later, after undisclosed lands came to light, the Additional Commissioner issued a show cause, remitted the matter to the primary Tribunal for redetermination and delimitation, and the High Court held that once an appeal under Sec. 21 is filed and an order is made, the Commissioner or the State Government lacks jurisdiction to determine the ceiling area. The State Government challenged this view. The Court held that under Sec. 45(2) and (3), the Commissioner has revisional powers, either suo motu or on an aggrieved person’s application, to call for records of inquiries under Secs. 17–21 and to pass orders after a hearing, subject to provisos including time limits and restrictions when appeals are pending. The decision also clarifies that suo motu revisional action can correct fraud or suppression of material facts, and that finality does not bar such action in cases of concealed lands. The High Court’s view was set aside and the Commissioner's order restored, with the appeal allowed along with costs.

1992-10-13

State of Madhya Pradesh and Anr. v. Syed Naseem Zahir and Others

State of Madhya Pradesh and Anr. v. Syed Naseem Zahir and Others concerns the legality and timing of the 'sealed cover' procedure used by the Departmental Promotion Committee (DPC) for recommending promotions when disciplinary proceedings were contemplated. Syed Naseem Zahir, who rose to Superintending Engineer, was included in a 1987 panel for promotion to Chief Engineer, but his name was kept in sealed cover due to potential misconduct. A charge-sheet was issued in 1988. The Madhya Pradesh Administrative Tribunal later directed promotion based on the sealed-cover recommendation, prompting the State's special leave appeal. The Supreme Court held that the departmental enquiry had been completed and the charges proved, and while it emphasized that Jankiraman's case governs sealed-cover use, the peculiar facts allowed keeping the sealed cover unopened until the disciplinary proceedings concluded. The Court outlined that if exonerated, the sealed-cover would be opened and the respondent would be notionally promoted from the date a junior was promoted, with consequential benefits, including back wages; if punished, action would be taken in accordance with Jankiraman's guidelines. The Court set aside the Tribunal's order and allowed the State's appeal, directing that no promotion be granted until proceedings end, and that the sealed-cover mechanism be used consistent with the facts.