Supreme Court of IndiaSupreme Court · 2004Division BenchAppeal allowed; High Court order stayed set asi...

Secur Industries Ltd. v. Godrej and Boyce Mfg. Co. Ltd.

Case / Petition Number:
Civil Appeal No. 1417 of 2004
Neutral Citation:[2004] 2 S.C.R. 705

Case Synopsis & Summary

This Supreme Court appeal arises from an interim order of the Bombay High Court staying arbitration proceedings before the Uttar Pradesh Industry Facilitation Council under the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 (the Act). The appellant had filed a claim petition under Section 6(2) of the Act seeking reference to the Industry Facilitation Council to act as arbitrator/concilia tor. Respondent No.1 filed suit for a declaration that the claim petition was ultra vires and for interim relief; the Civil Court granted an ad‑interim injunction but ultimately dismissed relief on the ground that, under the Arbitration and Conciliation Act, 1996 (the 1996 Act), the Court has no jurisdiction to stay arbitration except as provided by the 1996 Act. While an appeal was pending, the High Court stayed the arbitration proceedings on the sole ground that no notice under Section 21 of the 1996 Act had been served. The Supreme Court held that the High Court lacked jurisdiction to stay the Council’s arbitration, since Part I of the 1996 Act governs such proceedings and the non‑obstante provisions of Section 5 limit judicial intervention; Section 16 empowers the Arbitral Tribunal to rule on its jurisdiction, and the Council may determine whether its authority has been invoked properly. The Court distinguished Rohtas Industries on the scope of statutory references and approved the City Civil Court’s approach that arbitration could proceed. The appeal was allowed, the High Court’s stay was set aside, the City Civil Court’s decision was affirmed, and costs were awarded to the appellant.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Ruma Pal
  • P. Venkatramana Reddi
Judgment Date
2004-02-26
Court Decision / Holding
Appeal allowed. The High Court’s order staying arbitration before the Council is set aside. The City Civil Court’s decision is upheld, and the appeal is allowed with costs.
Final Disposition
Appeal allowed; High Court order stayed set aside; City Civil Court’s decision confirmed; costs awarded to appellant.

Parties to the Case

Appellants / Petitioners

  • Secur Industries Ltd.

Respondents

  • Godrej and Boyce Mfg. Co. Ltd.
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Rajiv Tyagi
  • • Ajit Kumar Singh
  • • Ms. Bandana Agarwal

Counsels for Respondents

  • • C.A. Sundaram
  • • Sridhar Y. Chitale
  • • Abhijit P. Medh

Provisions of Law Cited

Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993, Section 6(2)Arbitration and Conciliation Act, 1996 (26 of 1996), Section 16Arbitration and Conciliation Act, 1996, Section 21Arbitration and Conciliation Act, 1996, Section 8(1)Arbitration and Conciliation Act, 1996, Section 8(3)Arbitration and Conciliation Act, 1996, Section 5Arbitration and Conciliation Act, 1996, Section 2(4)Arbitration and Conciliation Act, 1996, Section 2(5)Arbitration and Conciliation Act, 1996, Part IArbitration and Conciliation Act, 1996, Section 7

Legal Doctrines & Maxims

  • Non-obstante clause (Section 5 of the Arbitration and Conciliation Act, 1996)
  • Arbitral Tribunal authority goes to the root of jurisdiction (Section 16)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court had no jurisdiction to stay arbitration before the Industry Facilitation Council; arbitration is governed by the 1996 Act, with Part I applying in full. Section 16 empowers the Arbitral Tribunal to rule on its jurisdiction, and the Council may determine whether it had jurisdiction to proceed. The reference to Section 8(1) and 8(3) requires the Court to refer parties to arbitration if the matter falls under an arbitration agreement, and the merger of Section 6(2) of the Act with the 1996 Act creates a deemed arbitration. The ground of non-service of notice under Section 21 cannot be a basis to stay proceedings, as that issue is to be decided by the Council; the High Court’s stay interfered with arbitration contrary to the statutory regime.

Contentions of Respondents

The respondents argued that the notice under Section 21 of the 1996 Act was a prerequisite to the Council’s jurisdiction and that the High Court’s stay was a legitimate exercise of judicial power; they relied on Rohtas Industries to contend that statutory references may limit court intervention in certain contexts and that the Court could not compel arbitration where proceedings were outside the arbitration framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Konkan Railways Corporation Ltd v. Rani Construction Pvt. Ltd.[2002] 2 SCC 388PositiveCited to support the proposition that the Arbitral Tribunal’s authority under Section 16 goes to the root of jurisdiction and that the Council can adjudicate on jurisdiction rather than a Civil Court.
Rohtas Industries Ltd. and Anr. v. Rohtas Industries Staff Union and Ors.[1976] 2 SCC 82DistinguishedCited as a contrary authority; distinguished because it dealt with voluntary references under the Industrial Disputes Act, which is not analogous to the statutory reference under the 1996 Act here.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,893 words•~14 min read

In The Court Record

Secur Industries Ltd. v. Godrej and Boyce Mfg. Co. Ltd.

A SECUR INDUSTRIES LTD. B E _v._ _MIS._ GODREJ AND BOYCE MFG. CO. LTD. AND ANR. FEBRUARY 26, 2004 ## [RUMA PAL AND P. VENKATARAMA REDD!, JJ.] _Interest on Delayed Payments to Small Scale and AncillG1y Industrial Undertakings Act, 1993-Section 6(2)-Claim Petition under Section making reference to the Council to act as arbitrator-Suit for declaration that claim petition_ ultra vires _the provisions of the Act and also application for interim_ C _relief-Dismissal of application by Civil Court as it had no jurisdiction to stay the proceedings before the Council-Appeal-Application for interim relief during pendency of appeal-High Court staying arbitration proceedings before the Council only on the ground that no notice served by supplier on the buyer-On appeal-Held: Having regard to the scope of the authority of the_ D _Arbitral Tribunal, Court could not adjudicate upon the matter, thus, High Court erred in staying the proceedings before the Council--Hence order of High Court set aside-Further as issue of notice was not raised before High Court, it could not be made a ground for interfering with the Council's jurisdiction-Arbitration and Conciliation Act, 1996, Sections 16 and 21._ The appellant filed a claim petition under section 6 of the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, I993 for referring its demand against the respondent to the State Industry Facilitation Council. The respondent No.I then filed a suit in the Civil Court against the appellant and the Council for a declaration that the claim petition was ultra vires the provisions of the Act; and also filed an application for F interim relief. The Civil Court granted an ad interim injunction but ultimately dismissed the application for interim relief holding that the Court could not intervene in arbitration proceedings except to the extent prescribed under the. I996 Act, under which the Court had no jurisdiction to stay the proceedings before the Council. The respondent No.I then filed an appeal. During G pendency, on an application filed for interim relief the High Court stayed arbitration proceedings before the Council only on the ground that no notice had been served by the appellant on the respondent No.1 under Section 21 of the 1996 Act. Hence the present appeal. H 705 SUPREME COURT REPORTS [2004] 2 S.C.R. 706 A Allowing the appeal, the Court HELD: 1.1. The High Court erred in staying proceedings before the Council. It had no jurisdiction to do so. [711-FJ 1.2. The proceedings before the Council are proceedings under the B Arbitration and Conciliation Act, 1996, pursuant to a deemed agreement between the parties to the dispute. With the applicability of Part I of the 1996 Act in all its force, the extent of judicial intervention in arbitrations is limited by the non-obstante provisions of Section 5 of the 1996 Act. Therefore, the Civil Court rightly held that the Court could only intervene in respect of C matters expressly provided for in the 1996 Act. [710-B-C] _Konkan Railways Corporation Ltd_ v. _Rani Construction Pvt. Ltd,_ [2002] 2 sec 388, referred to. > 1.3. Under the 1996 Act, the_Arbitral Tribunal has been given a very wide area of operation and it is the Court's powers which have been statutory D curtailed. Having regard to the scope of the authority of the Arbitral Tribunal under Section 16 of the 1996 Act, the validity of the proceedings before the Arbitral Tribunal is an issue which the Council could adjudicate upon, and not the Court. Therefore, the Council can go into the question whether its authority had been wrongly invoked by the appellant and it is open to it to E hold that it had no jurisdiction to proceed with the matter. Indeed ~t is incumbent on the Court to refer the parties tci. arbitration under Section 8(1) of the_ 1996 Act if a suit is filed in a matter which is the subject matter of an arbitration agreement. Furthermore, even while this question is pending decision before a Court, the Arbitral Tribunal may proceed with the arbitration under Section 8(3) and make its award. [711-C; 710-F-G] F 1.4. The submission that Section 16 of the 1996 Act does not appl~ to the instant case because. the. reference is a statutory one cannot be accepted. [710-H] _Rohtaslndustries Ltd and Anr._ v. _Rohtas Industries Staff Union and Ors.,_ G [19761 2 sec 82, distinguished. 1.5. The High Court stayed the proceedings before the Council, only on the ground of failure of the appellant to serve notice on the respondent No.1 under Section 21 of the 1996 Act. The point was not raised before the H High Court at all by the respondent No.1. Whether the notice was a notice SECUR INDUSTRIES LTD. 1·. GODREJ AND BOYCE MFG. CO. LTD. [PAL. .1] 707 under Section 21 and whether the giving of notice under Section 21 is to be A construed as a pre-condition to the exercise of jurisdiction by the Council are questions to be decided by the Council and could not be a ground for the High Court interfering with the Council's jurisdiction and staying proceedings before it. [711-D-FJ CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1417 of B 2004. From the Judgment and Order dated 21.1.2003 of the Bombay High Court in C Appln. No. 89/2003 in Appeal from Order No. 70 of 2003. Rajiv Tyagi, Ajit Kumar Singh and Ms. Bandana Agarwal for the C Appellant. C.A. Sundaram, Sridhar Y. Chitale and Abhijit P. Medh for the Respondents. The Judgment of the Court was delivered by D RUMA PAL, J. Leave granted. This appeal has been preferred from an interim order granted by the Division Bench of the Bombay High Court staying the arbitration proceedings before the ·uttar Pradesh Industry Facilitation Council (referred to as 'the E Council') set up under the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 (referred to as 'the Act'). ## - > We are not concerned with the merits of the proceedings initiated by the appellant before the Council. The only question is whether the High Court had the jurisdiction to pass the impugned order. > The chronology of events which are relevant for the purposes of this appeal, commenced with a notice dated 11th September 200 I served by the appellant on the respondent raising a demand. The notice also contained the following paragraph: "You may also treat this as a notice under the provisions of the 'Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993'. Failure or non-payment will force us to move our claims as mentioned above to the appropriate authorities G H 708 SUPREME COURT REPORTS [2004] 2 S.C.R. A for recovery of our dues as mentioned above." In October, 2001 the appellants filed a claim petition before the Council. The Council forwarded the claim petition to the respondent No. 1 under cover of its letter dated 27th December 2001 asking the respondent No. 1 to respond to the same within a period of one month. The receipt of the claim B petition was acknowledged by the respondent by letter dated 25th January 2002 and requested for time to submit its reply by six weeks. The prayer for extension of time was, however, made without prejudice to the respondent's "legal rights and contentions relating to the impugned notice dated 27th December and the claim purported to be made under Section 6 of the said Act". c On 12th February 2002 the respondent No. 1 filed a suit in the City Civil Court at Bombay against the appellant who was named as the defendant No. 1 and the Council which was named as the defendant No. 2. The prayers in the plaint are, inter-alia, for a declaration that the claim petition filed by D the appellant before the Council was ultra-vires the provisions of the Act and, therefore, illegal, null and void. A permanent order of injunction was also asked for restraining further proceedings before the Council. An application was filed in the suit for interim relief by the respondent No. 1. By an order dated 5th February 2002 the City Civil Court granted an ad-interim injunction staying the proceedings under the Act. The application for interim relief was, E however, ultimately dismissed by the City Civil Court on 28th November 2002 principally on the ground that the claim had been filed by the appellant under Section 6(2) read with Section 8(1) of the Arbitration and Conciliation Act, 1996 (which we will refer to as the 1996 Act) and in view of Section 5 of the 1996 Act no Court could .intervene in arbitration proceedings except _p_ to the extent prescribed under the 1996 Act. According to the City Civil Court, the reliefs claimed for the respondent No. 1 in its suit did not fall within the ambit of those situations where interference by Court was permissible and consequently the Court had no jurisdiction to stay the proceedings before the Council. G The respondent No. 1 preferred an appeal from the decision of the City Civil Court before the High Court. The appeal is pending. On an application for interim relief filed by the respondent No. 1 pending the appeal, the High Court by its order dated 21st January 2003 stayed the proceedings before the Council only on the ground that no notice had been served by the appellant on the respondent No. 1 under Section 21 of the 1996 Act. The High Court H rejected the appellant's application for expediting the appeal on 2nd May - - -- SEC UR INDUSTRIES LTD. _v_ GODREJ AND BOYCE MFG. CO LTD. [PAL, J.] 709 2003. Both these orders of the High Court are questioned before us in these A appeals. Section 6 of the Act provides as follows: "Recovery of amount due - - (1) The amount due from a buyer, together with the amount of B interest calculated in accordance with the provisions of Sections 4 and 5 shall be recoverable by the supplier from the buyer by way of a suit or other proceedings under any law for the time being in force. - (2) Notwithstanding anything contained in sub-section (1), any party C to a dispute may make a reference to the Industry Facilitation Council for acting as an arbitrator or conciliator in respect of the matters referred to iq that sub-section and the provisions of - . the Arbitration and Conciliation Act 1996 (26 of 1996) shall apply to such disputes as if the arbitration or conciliation were D pursuant to an arbitration agreement referred to in sub-section (1) of section _1_ of that Act. Sub-section (2) of Section 6 expressly incorporates the provisions of the 1996 Act. Apart from such express incorporation, sub-section (2) of Section 6 goes further and creates a legal fiction whereby disputes referred E are to be deemed to have been made pursuant to an arbitration agreement as defined in Section 7 of sub-section (1) of the 1996 Act. Incorporation of the provisions of the 1996 Act into Section 6(2) of the Act has also been effected by sub-sections (4) and (5) of Section 2 of the 1996 Act which say: F (4) This Part except sub-section (I) of section 40, sections 41 and 43 shall apply to _every arbitration under any other enactment for the time being in force, as if the arbitration were pursuant to an arbitration agreement and as if that other enactment were an arbitration_ G _agreement,_ except in so far as. the provisions of this Part are inconsistent with that other enactment or with any rules made thereunder. (5) Subject to the provisions of sub-section (4), and save in so far as is othe1wise provided by any law for the time being in force or in any H agreement in force between India and any other country or countries, [2004] 2 S.C.R. 710 SUPREME COURT REPORTS A this Part shall apply to all arbitrations and to all proceedings relating thereto". (emphasis added) The "Part" referred to in this sub-section is Part I of the 1996 Act B which deals with domestic arbitrations. The proceedings before the Council, therefore, are proceedings under the 1996 Act, pursuant to a deemed agreement between the parties to the dispute. With the applicability of Part I of the 1996 Act in all its force, the extent of judicial intervention in arbitrations is limited by the non-obstante provisions of Section 5 of the 1996 Act, which stipulate: C "Notwithstanding anything contained in any other Jaw for the time being in force, in matters governed by this Part, no judicial authority shall intervene except where so provided in this Part". The City Civil Court was right in its approach when it said that the Court could only intervene in respect 'of matters expressly provided for in the 1996 Act. The validity of the proceedings before the Arbitral Tribunal is an issue which the Council, and not the Court, D could decide under Section 16 of the 1996 Act. Sub-section (1) of Section I 6 opens with the words " The Arbitral Tribunal may rule on itsjurisdiction ... ". It has been held by this Court that the Arbitral Tribunal's authority under Section I 6 is not confined to the width of its jurisdiction but goes to the very root of its jurisdiction. _(Konkfn Railways Corporation ltd._ v. _Rani_ E _Construction Pvt. Ltd.,_ (2002] 2 SCC 388. Therefore, the Council can go into the question whether its authority had been wrongly invoked by the appellant and it is open to it to hold that it had no jurisdiction to proceed with the matter. The arguments which have been raised before us by the learned counsel F on behalf of the respondent to a large extent related to the merits of the appellant's claim before the Council. Having regard to the scope of the authority of the Arbitral Tribunal. under Section I 6, this is not a matter which the Court can adjudicate upon. Indeed it is incumbent on the Court to refer the parti.es to arbitration under Section 8(1) of the I 996 Act if a suit is filed G in a matter which is the subject matter of an arbitration agreement. Furthem1ore, even while this question is pending decision before a Court, the Arbitral Tribunal may proceed with the arbitration under Section 8(3) and make its award. The High Court could not, therefore, have stayed the proceedings before the Council. H We are also unable to accept the submission of the respondent No. that Section I 6 of the 1996 Act does not apply to the present case because SECUR INDUSTRIES LTD. _v._ GODREJ AND BOYCE MFG. CO. LTD. [PAL, .I.] 711 the reference is a statutory one. The decision relied upon by the respondent A No. 1 in support of this submission, namely, _Rohtas Industries Ltd. and Anr._ v. _Rohtas Industries Staff Union and Ors.,_ [1976] 2 SCC 82 related to a voluntary reference of an industrial dispute under Section IOA of the Industrial Disputes Act. Section IOA of the Industrial Disputes Act, 1947 permits the employer and the workmen to.agree to refer the dispute to the arbitration to a Labour Court or a Tribunal for adjudication "where any industrial dispute B exists or is apprehended". Therefore, if there was no such industrial dispute there could be no arbitral reference. This Court therefore held that the disputes spilt 'into areas where the arbitrator deriving authority under Section 1 OA has no jurisdiction". The provisions of Section lOA are entirely different from the provisions of Section 16 of the 1996 Act. There is in this case, no C question of dispute spilling into areas where the Arbitral Tribunal does not have jurisdiction. Under the 1996 Act, the Arbitral Tribunal has been given a very wide and deep area of operation and it is the Court's powers which have been statutory curtailed. This brings us to the ground on which the High Court stayed the D proceedings before the Council, namely, the alleged failure of the appellant to serve notice under Section 21 of the 1996 Act. The point was not raised before the High Court at all by the respondent No. 1. This was candidly stated by the learned counsel for the respondent No. l. Our attention was not drawn to any other legal proceeding which requires a notice to be given prior E to commencing proceedings apart from Section 21 of the 1996 Act. Whether the notice was a notice under Section 21 and whether the giving of notice under Section 21 is to be construed as a pre-condition to the exercise of jurisdiction by the Council are questions which the Council will have to decide. This debate could not be a ground for the High Court interfering with the Council's jurisdiction and staying proceedings before it. F To sum up: The High Court erred in staying proceedings before the Council. It had no jurisdiction to do so. Having regard to our conclusion, and as has been agreed by the parties, the appeal before the High Court has really become infructuous. We, therefore, set aside the decision of the High Court and treat the appeal of respondent No. I before the High Court as having been decided by this order. The decision of the City Civil Court is confirmed and the appeal is allowed with costs. NJ. Appeal allowed. H
End of Judgment Record
Browse All Supreme Court of India (2004) Decisions
2004-05-26

State of West Bengal v. Haresh C. Banerjee and Ors.

This appeal concerns the constitutional validity of Rule 10(1) of the West Bengal Services (Death-cum-Retirement Benefit) Rules. The Calcutta High Court had previously held the rule ultra vires the Constitution and had struck down the power to conduct a departmental inquiry against a retired employee. The Supreme Court granted special leave and noted that even if the appeal were to succeed, the benefit already due to respondent No. 1 in the High Court’s order would not be recalled; arrears would be paid by the State within the time prescribed. The sole question before the Court is the validity of Rule 10(1) and its relation to the West Bengal (Classification, Control and Operation) Rules, 1971, including sub-rule (1) of Rule 10, which governs classification and control of service. The Court observed that the issue raises a larger question of operation that could affect a large number of employees, and therefore it is appropriate to refer the matter to a larger Bench for authoritative adjudication. The matter is thus directed to be placed before a larger Bench, and the judgment does not finally decide the vires of Rule 10(1). In short, the Court stayed further adjudication on the matter of validity and opted for an expeditious reference to a larger judicial forum. The background also includes the Court’s directive in leave proceedings that arrears, if any, would be payable according to the High Court’s order, not recalled pending appellate resolution.

2004-05-05

Commissioner of Customs & Central Excise & Ors. v Charminar Nonwovens Ltd.

The case concerns the proper classification and duty liability of Floor G Coverings and Filter Fabrics under the Central Excises and Salt Act, 1944, specifically whether these goods fall under Tariff sub-headings 5703.90 (30% ad valorem) or 5703.20 (5% ad valorem). The respondent, Charminar Nonwovens Ltd., received a detention memo and a show-cause notice challenging the classification and the related duty. An appellate authority had previously upheld the assessee's classification on a similar adjudication, and the Andhra Pradesh High Court later quashed the show-cause notice on the ground that the appellate order had become final. The petitioners challenged this, arguing that classification must be decided on facts arising in each case and that new facts or changes in law may warrant re‑examination, not interference by the High Court at the show-cause stage. The Supreme Court held that classification and the determination of duty are case-specific, and even if a decision was taken earlier, further investigation can reveal new facts or a change in law requiring re‑examination. The High Court's interference at the show-cause stage was improper. The Court then set aside the High Court order and remitted the matter to the Adjudicating Authority for fresh adjudication, with similar directions to related appeals. The overarching principle is that revenue classifications are not frozen by earlier judgments and must be reconsidered as facts or law evolve.

2004-08-16

G. B. LAHOTI v. S. J. CHOURASIYA

This Supreme Court decision concerns substitution of legal heirs in a pending appeal arising from a land-lord–tenant dispute. The landlord sued for possession; the trial court decreed possession due to unlawful sub-letting. The tenant’s successor-deceased Ganesh Prasad Lahoti’s heirs sought substitution under Order XXII Rule 11 after the defendant’s death; the first substitution application Exh. 22 was rejected on a technical ground, and three further applications followed (for setting aside abatement, for condonation of delay, and for interim relief). The appellate court dismissed these on merits and on the ground of res judicata, and the High Court dismissed revisions. The Court held that the doctrine of res judicata does not bar such subsequent applications where, as in this case, there was no inaction or negligence by the heirs and the delay was explained by the circumstances—knowledge of pendency arose only after a letter from the advocate confirming hearing. The Supreme Court allowed the appeal, set aside the lower orders, and directed the lower appellate court to hear the appeal on merits in accordance with law, with an award of costs (Rs. 10,000) within three months, and a fresh deadline for a merits decision by Aug. 31, 2005. The decision clarifies substitution rights in the context of pending appeals and limits of res judicata in substitution petitions.

2004-05-05

SHAKUNTALA BAI v. NARAYAN DAS

This Supreme Court decision arises from a long-drawn eviction suit under the Madhya Pradesh Accommodation Control Act, 1961, filed for bona fide landlord’s need to carry on business in a non-residential premises. The trial court decreed eviction; during appeal, the landlord died and his heirs sought to amend the plaint to plead their own bona fide need. The tenant urged amendment of his pleadings to claim that, after the landlord’s death, the personal need ceased. The High Court dismissed the suit on the ground that after the landlord’s death the personal need could not be pursued by heirs. The Supreme Court, allowing the appeals, held that the bona fide need of the landlord must be examined as on the date of institution of proceedings, and if a decree for eviction is passed, the death of the landlord during pendency of the appeal does not invalidate the Plaintiffs’ right to defend the estate. It clarified the law: the bar under s.12(1) prevents filing the suit except on listed grounds; the need may be tested with amended pleadings after remand; the object of the Act is expeditious disposal and not perpetual litigation. Citing earlier decisions, the Court ultimately restored the trial court’s decree, set aside the High Court’s dismissal, and granted four months for eviction with an undertaking. The decision reaffirms that heirs may defend the estate where a valid eviction decree has been issued.