Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2021Division BenchAppeals allowed; High Court judgment dated 20.0...

SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS

Case / Petition Number:
Civil Appeal Nos. 900-902 of 2021
Neutral Citation:[2021] 3 S.C.R. 68

Case Synopsis & Summary

This appeal concerns three contracts for road works awarded by the Secunderabad Cantonment Board to M/s B. Ramachandraiah & Sons under annual term contracts, each containing an arbitration clause (Clause 17) and a final bill/no-claim framework (Clause 5). After completion, the respondent claimed price variation in material, labour and fuel, issuing notices from 2003 onward. Arbitration requests were made by the respondent on 07.11.2006 and 13.01.2007, with a 30-day period to appoint an arbitrator; the period lapsed on 12.02.2007 without appointment. The respondent continued writing letters into 2009, and a legal notice dated 30.01.2010 reiterated arbitration close. The appellant rejected the claims in 2010, asserting final payments had been made in 2002-2003 and that no dispute subsisted for arbitration. The respondent filed Section 11 applications on 06.11.2013. The Telangana High Court allowed them, appointing an arbitrator, but the Supreme Court held that the limitation period under Article 137 of the Limitation Act commenced on 12.02.2007 and could not be reset by later rejections or notices; even on merits the claim was time-barred. Consequently, the appeals were allowed and the High Court judgment was set aside."

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. F. Nariman
  • B. R. Gavai
Judgment Date
2021-03-15
Court Decision / Holding
Appeals allowed. The High Court’s 20.08.2019 judgment setting aside was reversed; the limitation analysis under Article 137 governs Section 11 petitions, time running from 12.02.2007, with a final rejection not restarting the clock. The merits claim is also time-barred.
Final Disposition
Appeals allowed; High Court judgment dated 20.08.2019 set aside

Parties to the Case

Appellants / Petitioners

  • SECUNDERABAD CANTONMENT BOARD

Respondents

  • M/S B. RAMACHANDRAIAH & SONS

Legal Representation & Advocates

Counsels for Petitioners

  • • P. S. Narasimha, Sr. Adv., M/s. Veritas Legis

Counsels for Respondents

  • • Nithin Pavuluri
  • • Nitin Chowdary
  • • Gp. Capt. Karan Singh Bhati
  • • Jaideep Singh
  • • Ms. Chitrangda Rastravara
  • • Manvendra Singh Rathore
  • • Dashrath Singh

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 – Section 11Arbitration and Conciliation Act, 1996 – Section 11(6)Arbitration and Conciliation Act, 1996 – Section 11(6-A)Arbitration and Conciliation Act, 1996 – Section 21Limitation Act, 1963 – Article 137Limitation Act, 1963 – Section 9Arbitration and Conciliation Act, 1996 – Section 43(1)

Legal Doctrines & Maxims

  • kompetenz-komptenz (principle that arbitration tribunal has jurisdiction to rule on its own jurisdiction)
  • ex facie time-barred (claims plainly time-barred on the face of the record)
  • prima facie test to screen out manifestly ex facie non-existent or invalid arbitration agreements or non-arbitrable disputes
  • time is admissibility not jurisdiction (limitation’s role as an admissibility issue rather than a jurisdictional defect)
  • Mayavati/ Vidya Drolia framework for limiting judicial interference at reference stage

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that the arbitration requests dated 07.11.2006 and 13.01.2007 triggered Article 137 of the Limitation Act, with time starting from 12.02.2007 when no arbitrator was appointed. A final rejection on 10.11.2010 could not restart the limitation clock, and applications filed on 06.11.2013 were hopelessly time-barred. On merits, the final payments were completed by 2003 and the price variation claim arose in 2003-04; even if a claim existed, it was time-barred by 2013. The 2015 amendments (11(6-A)) and Vidya Drolia framework limit judicial intervention at the reference stage, requiring only existence of an arbitration agreement; hence the court should assess only the arbitration agreement’s existence and not re-open merits.

Contentions of Respondents

The respondents argued that the date of accrual for Section 11(6)(c) arises on 10.11.2010 when the appointing authority rejected the request to appoint an arbitrator, and that the action remained alive until then under Section 11. They urged that delays by the appellant in appointing an arbitrator could extend the reference, and relied on the evolving jurisprudence (Geo Miller, Vidya Drolia, Nortel) to justify referral if a prima facie arbitration agreement existed and if disputes remained arbitrable.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (16)

Case NameCitationTreatmentExplanation
Geo Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd.(2020) 14 SCC 643; [2019] 11 SCR 1108PositiveRelied on for framework of limitation period for Section 11 applications, clarifying that time runs from accrual and cannot be reset by subsequent communications.
Vidya Drolia v. Durga Trading Corpn.(2021) 2 SCC 1PositiveUsed for narrow interpretation of Section 11(6-A) and for primacy of existence of arbitration agreement at reference stage.
Bharat Sanchar Nigam Ltd. & Anr. v. M/s Nortel Networks India Pvt. Ltd.2021 (4) SCALE 11PositiveCited to reinforce the modern understanding of Sections 8/11 and the impact of amendments on judicial intervention.
Deepdharshan Builders Pvt. Ltd. v. Saroj(2019) 1 AIR Bom R 249Mentioned OnlyReferred to in argument; not central to the core holding.
Damodar Das State of Orissa v. Damodar Das(1996) 2 SCC 216PositiveCited to illustrate historical context of accrual of cause of action for arbitration.
Inder Singh Rekhi v. DDA(1988) 2 SCC 338PositiveUsed to support that reminders do not extend accrual of cause of action; supports the timing framework.
Union of India v. Momin Construction Co.(1997) 9 SCC 97PositiveCited to discuss accrual dates for final bills and related arbitration references.
Duro Felguera SA v. Gangavaram Port Ltd.(2017) 9 SCC 729PositiveCited for Section 11(6-A) interpretation limiting judicial intervention to existence of arbitration agreement.
Mayavati Trading Company Private Ltd. v. Pradyut Dev Burman(2019) 8 SCC 714PositiveCited regarding narrowed interpretation of 11(6-A) after amendments.
Uttarakhand Purv Sainik Kalyan Nigam v. Northern Coal Field Limited(2020) 2 SCC 455Mentioned OnlyNot central to the decision; referenced in relation to Law Commission commentary.
Premium Nafta Products Ltd. v. Fili Shipping Co. Ltd.(UK) 2007 UKHL 40; 2007 Bus LR 1719 (HL)Mentioned OnlyCited in the Vidya Drolia discussion as comparative authority on arbitration law.
C Budhraja v. Chairman, Orissa Mining Corporation Ltd(2008) 2 SCC 444Mentioned OnlyReferenced in the context of pre-amendment jurisprudence on reference.
SBP and Co. v. Patel Engg. Ltd.(2005) 8 SCC 618Mentioned OnlyHistorical reference in discussion of prior jurisprudence on Section 11/8.
Boghara Polyfab (P) Ltd. v. National Insurance Co. Ltd.(2009) 1 SCC 267Mentioned OnlyCited in relation to kompetenz-komptenz jurisprudence.
Panchu Gopal Bose v. Port of Calcutta(1993) 4 SCC 338PositiveCited to illustrate accrual concepts in earlier arbitration law.
Damodar Das State of Orissa v. Damodar Das(1996) 2 SCC 216PositiveCited to discuss accrual of cause of action for arbitration.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•7,474 words•~34 min read

In The Court Record

SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS

68 SUPREME COURT REPORTS [2021] 3 S.C.R. 68 [2021] 3 S.C.R. A ## SECUNDERABAD CANTONMENT BOARD v. ## M/S B. RAMACHANDRAIAH & SONS (Civil Appeal Nos. 900-902 of 2021) B ## MARCH 15, 2021 ## **[R. F. NARIMAN AND B. R. GAVAI, JJ.]** _Arbitration and Conciliation Act, 1996 – s.11 – Limitation Act, 1963 – s. 9 and Art.137 – Appellant floated a notice inviting_ C _tender for a term of annual contract – Three agreements were entered into with the respondent – Agreements had arbitration clause – Work orders were issued – Thereafter, final contract certificates were issued by the appellant and final payment was received by the respondent of the works in question – Respondent then started making demands for reimbursement on account of variation in prices_ D _of material, labour and fuel – By letter dated 07.11.2006, respondent requested for appointment of arbitrator – Respondent issued another letter dated 13.01.2007 and stated that it had no option but to rescind contract and have an arbitrator appointed within 30 days – It is not disputed that 30 day period was over by 12.02.2007, however,_ E _respondent kept on writing letters in 2007-2009, reiterating its claim – Finally, respondent issued a legal notice dated 30.01.2010 and ‘clarification notice’ dated 20.03.2010 – Appellant by letter dated 10.11.2010, rejected the claim of reimbursement and stated that they have made final payments towards the work order – On 06.11.2013, the respondent filed applications u/s.11 of the Act –_ F _The Single Judge of the High Court allowed the application and an arbitrator was appointed – On appeal, held: It is clear that demand for arbitration was made by letter dated 07.11.2006 – Thereafter, another letter dated 13.01.2007 informed the appellant that appointment would have to be made within 30 days – The time begin_ G _to run on and from 12.02.2007 – Once the time started running, any final rejection by the appellant (letter dated 10.11.2010) would not give any fresh start to a limitation period which was already running, following the mandate of s. 9 of the Limitation Act – This being the case, the High Court was clearly in error in stating that since applications were filed on 06.11.2013, they were within the_ H 68 69 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS _limitation period of three years starting from 10.11.2010 – Even_ A _otherwise, the claim of the respondent was also_ ex facie _time barred – Thus, judgment of the High Court is set aside._ ## **Allowing the appeals, the Court** **HELD: 1. Limitation is not a jurisdictional issue but is an admissibility issue. So far as the applicability of Article 137 of the Limitation Act to the applications under Section 11 of the Arbitration Act is concerned, it is clear that the demand for arbitration in the present case was made by the letter dated 07.11.2006. This demand was reiterated by a letter dated 13.01.2007, which letter itself informed the Appellant that appointment of an arbitrator would have to be made within 30 days. At the very latest, therefore, on the facts of this case, time began to run on and from 12.02.2007. The Appellant’s laconic letter dated 23.01.2007, which stated that the matter was under consideration, was within the 30-day period. On and from 12.02.2007, when no arbitrator was appointed, the cause of action for appointment of an arbitrator accrued to the Respondent and time began running from that day. Obviously, once time has started running, any final rejection by the Appellant by its letter dated 10.11.2010 would not give any fresh start to a limitation period which has already begun running, following the mandate of Section 9 of the Limitation Act. This being the case, the High Court was clearly in error in stating that since the applications under Section 11 of the Arbitration Act were filed on 06.11.2013, they were within the limitation period of three years starting from 10.11.2020. On this count, the applications under Section 11 of the Arbitration Act, themselves being hopelessly time barred, no arbitrator could have been appointed by the High Court. [Paras 19, 20][83-A; 85G-H; 86-A-D]** **2. Even otherwise, the claim made by the Respondent was also** _**ex facie**_ **time barred. It is undisputed that final payments were received latest by the end of March 2003 by the Respondent. That apart, even assuming that a demand could have been made on account of price variation, such demand was made on 08.09.2003. Repeated letters were written thereafter by the Respondent, culminating in a legal notice dated 30.01.2010. Vide the reply dated 16.02.2010 to legal notice, it was made clear that** B C D E F G H 70 SUPREME COURT REPORTS [2021] 3 S.C.R. - A **such demands had been rejected. Even taking 16.02.2010 as the starting point for limitation on merits, a period of three years having elapsed by February 2013, the claim made on merits is also hopelessly time barred. For all these reasons, the appeals are allowed and the impugned judgment of the High Court dated 20.08.2019 is set aside. [Paras 21, 22][86-E-F]** ## B _Geo Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd._ , **(2020) 14 SCC 643 : [2019] 11 SCR 1108;** _Vidya Drolia v. Durga Trading Corpn.,_ **(2021) 2 SCC 1;** _Bharat Sanchar Nigam Ltd. & Anr. v. M/s Nortel Networks India Pvt. Ltd._ **2021 (4) SCALE 11 – relied** C **on.** _Deepdharshan Builders Pvt. Ltd. v. Saroj,_ **(2019) 1 AIR Bom R 249 – referred to.** ## **Case Law Reference** |D|**[2019] 11 SCR 1108**|**relied on**|**Para 13**| |---|---|---|---| ||**(2021) 2 SCC 1**|**relied on**|**Para 16**| ||**2021 (4) SCALE 11**|**relied on**|**Para 19**| CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 900E 902 of 2021. From the Judgment and Order dated 20.08.2019 of the High Court for the State of Telangana at Hyderabad in Arbitration Application Nos. 154 of 2013, 155 of 2013 and 156 of 2013. F P.S. Narasimha, Sr. Adv., M/s. Veritas Legis, for the Appellant. Nithin Pavuluri, Nitin Chowdary, Gp. Capt. Karan Singh Bhati, Jaideep Singh, Ms.Chitrangda Rastravara, Manvendra Singh Rathore, Dashrath Singh, Advs. for the Respondents. The Judgment of the Court was delivered by G ## **R. F. NARIMAN, J.** 1. Leave granted. H 2. These appeals arise out of applications under Section 11 of the Arbitration and Conciliation Act, 1996 [“ **Arbitration Act** ”]. On 02.09.2000, the appellant before us, Secunderabad Cantonment Board 71 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] [“ **Appellant** ”], floated a notice inviting tender [“ **N.I.T.** ”] for an annual A term contract for: 1. Repairs to Main Roads (Resurfacing with Centralised with Hot Mix Plant and Paver); 2. Repairs to Main Roads (Widening of Roads with Centralised Hot Mix Plant and Paver); - B 3. Repairs to Internal Roads (Resurfacing with Hot Mix Paver and Plant). 3. Pursuant to the aforesaid N.I.T., three agreements were entered into with the respondent, M/s Ramachandraiah and Sons [“ **Respondent** ”], the first one dated 23.09.2000 and the other two dated 17.09.2001. Clause 5 of each of the aforesaid agreements, which is in identical terms, is important and reads as follows: “ **5. Final Bill:** The Contractor shall submit his final bil of the work with full and complete measurements showing the deductions on account of part payments received and stores supplied by the Board cost of water and any other items received by him under the contract within 08 days from the date of completion and handing over the work. The contractor shall also submit alongwith his bill a no claim certificate stating that there are no claims from the cantonment board on account of the work undertaken and completed by him under the contract and that no claim thereafter shall be entertainable. The bill shall also contain a statement showing the justification of cement consumed by the Contractor.” 4. The arbitration clause contained in Clause 17 of each of the aforesaid agreements reads as follows: “ **17.LAW Governing the Contract** : The Contract shall be governed by the Indian Law. [A]ll disputes between the parties to this contract or being out of relating to the contract other than those for which the decision of the accepting officer is final and conclusive shall after the written notice given by either party to the other be referred to the sole arbitrator as appointed by the [P]resident Cantonment Board [S]ecunderabad. The award of the Arbitrator shall be final, conclusive and binding on both parties to the contract” C D E F G H 72 SUPREME COURT REPORTS [2021] 3 S.C.R. A 5. Work orders were issued with respect to the aforesaid works. The Appellant argued that the Respondent had failed to complete the work within the stipulated period, but vide its meeting dated 05.10.2002, it resolved to grant an extension of time upto 31.12.2002 on an undertaking from the Respondent that the Appellant would be at liberty to impose penalty as provided in the contracts and as decided by the Appellant in B case balance works were not completed by 31.12.2002. On 30.10.2002, the Respondent submitted the required undertaking. 6. It is not disputed that vide the final contract certificates issued by the Appellant on 18.02.2003 and 26.03.2003, final payment was received by the Respondent in respect of the works in question. After a C hiatus of about six months, the Respondent then started making demands towards reimbursement on account of variation in prices of material, labour and fuel. These demands were made vide letters dated 08.09.2003, 24.07.2004 and 12.10.2004. 7. After a silence of over two years, the Respondent then issued D a letter dated 07.11.2006 by which the Respondent requested for the appointment of an arbitrator in respect of the claim of reimbursement on account of price variation in all the three contracts. It was specifically stated that necessary steps should be taken by the Appellant within 15 days of receipt of the letter. Receiving no reply from the Appellant, the E Respondent issued yet another letter dated 13.01.2007, in which it spoke of a fundamental breach of contractual obligations and then stated that it had no option but to rescind the contracts and have an arbitrator appointed within 30 days, in conformity with the arbitration clause provided in the contracts. F 8. To this letter, a laconic reply was received from the Appellant on 23.01.2007, stating that the matter referred to in their letter was under consideration. It is not disputed that the 30-day period, spoken of in the letter dated 13.01.2007, was over by 12.02.2007. Despite this being the position, the Respondent kept on writing letters at long intervals between the years 2007-2009, reiterating its claim. Finally, by a legal notice dated G 30.01.2010, the Respondent specifically stated: “In order to reiterate the brief details of the Contracts, all the three works have been completed way back in 31.03.2002 and final bill was received under protest. H 73 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] It is also expedient to point out that arbitration proceedings A have already commenced since 07.11.2006 (within intent of the Arbitration and Conciliation Act of 1996). In the event that the Hon’ble appointing authority continues to abdicate his rights to appoint an arbitrator, the only remedy left to us is to seek the appointment of an arbitrator by the Hon’ble B Chief justice of High Court of Andhra Pradesh (to enforce the arbitration clause) as intended by the agreement (since the agreement envisages arbitration as the means of settlement of disputes in preclusion to a court of law).” 9. To this legal notice dated 30.01.2010, the Appellant replied on C 16.02.2010, stating: “ **1.** … Subsequent to awarding those contracts, work orders have been issued and part of works were executed by your client within the stipulated time and the bills for the works executed were cleared on submission of final bills way back in the year 2002D 2003 and your client has received the payments by adhering to Clause 5 of the Contract entered by and between your client and my client. Since the final payments were made for the works executed the copies requested by you may not be available as 8 years time has been elapsed after conclusion of the contract. E **2.** Subsequent to conclusion of the contract and after receipt of final payments, your client has started addressing letters as referred in your notice culminating into the present notice under reply and seeking additional claim towards reimbursement on variation in prices, though there is no such clause in the agreement entered for execution of above referred works to claim amounts on F variation of prices. Moreover the contract period is one year from the date of awarding contract and the contract periods were came to an end by 2001 and 2002 respectively. Whereas your client has got issued final notice under reply on 30.01.2010 and insisting appointment of an Arbitrator though no dispute is subsisting G between your client and my client and moreover your client’s claim is barred under law of limitation.” “ **4.** In the above said background the contention in your notice under reply that your client is insisting for the appointment of an Arbitrator for adjudication of the dispute and that appointing H 74 SUPREME COURT REPORTS [2021] 3 S.C.R. A authority has not appointed the arbitrator and that arbitration proceedings have already commenced since 07.11.2006 and that in the event the Hon’ble Appointing authority continues to abdicate his right to appoint an arbitrator you client is left with no option except to seek appointment of Arbitrator by the Hon’ble Chief Justice of High Court of A.P. is highly objectionable and untenable B and your client has no legal right to raise the dispute after concluding the contract way back in the year 2002. The claim of your client to appoint an Arbitrator cannot be acceded to as there is no arbitral issues are subsisting between your client and my client and furthermore the claim raised by your client is hopelessly barred C under law of limitation and it is incorrect to state that your has received the payments under protest. A **5.** My Client further reiterates that the above referred three contracts were awarded for a period of one year in the year 20002001 and since your client could not complete the works entrusted D to him within the stipulated period, at his request the time was further extended up to 31.12.2002 and by that time he can only complete the work to the tune of Rs.75 lakhs approximately and your client’s request to release work order for balance amount with regard to the works in question were turn down by the Hon’ble High Court of A.P. Hence, the question of reimbursement on E variation in prices as claimed by your client does not arise and he is not entitled for such claims. **6.** My client further reiterates that as per clause 5 of the Agreement, final bill amounts will be released on submitting no claim certificate stating that there is no claim form the Cantonment F Board on account of the works undertaken and completed by the contractor and no claim thereafter shall be entertainable. Pursuant to this Clause your client has received final bill amounts, hence there are no issues to be adjudicated by an arbitrator. As referred above in the contract entered by and between your client and my G client, there is no specific clause under which your client is entitled for reimbursement on variation of prices. Hence the same cannot be made an issue to be adjudicated by an arbitrator.” G 10. By way of rejoinder to the aforesaid reply notice, the Respondent issued what it called a “clarification notice” on 20.03.2010, H followed by three letters dated 30.09.2010, reiterating the earlier requests SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] 75 for the appointment of an arbitrator. This was rejected by the Appellant A vide a letter dated 10.11.2010, which letter informed the Respondent that the President of the Secunderabad Cantonment Board had rejected the application for appointment of an arbitrator as all payments were made and nothing remained pending. 11. After a three-year long hiatus, the Respondent then filed applications under Section 11 of the Arbitration Act on 06.11.2013. Vide the impugned judgment dated 20.08.2019, a learned Single Judge of the High Court for the State of Telangana held that the Section 11 applications were within time as they were filed within three years from the letter dated 10.11.2010 rejecting the request to appoint an arbitrator. The learned Single Judge also went on to record: “ **39.** Proceedings dt. 07.11.2003 filed by the respondent of a Board Meeting of the respondent no doubt show payment of Rs. 14,06,580/- in addition to Rs. 14,84,000/- but this payment is not on account of claim under Clause 2.2.46 for reimbursement on variation in prices claimed by the applicant. It is a payment sanctioned for actual quantities of the various items of work which had increased, and so the same cannot be prima-facie construed as a payment towards the claim of the applicant under Clause 2.2.46.” “ **42.** The prolonged silence of the respondent from 08.09.2003 onwards regarding claims made by the applicant under Clause 2.2.46 without any emphatic rejection of the same, prima facie show that there appears to be a live issue In that regard between the parties.” 12. As a result, the Section 11 applications were allowed and Shri Y.V. Ramakrishna (Retired District Judge) was appointed as arbitrator to adjudicate the disputes between the parties arising out of the three agreements. The question of the bar of limitation of the claims made was left open to be considered and decided by the arbitrator. 13. Shri P.S. Narasimha, learned Senior Advocate appearing on behalf of the Appellant, submitted that the date on which the request made for the appointment of an arbitrator was received by the President of the Secunderabad Cantonment Board was 23.01.2007, as a result of which, this is the date on which the limitation period starts running under Article 137 of the Limitation Act, 1963 [“ **Limitation Act** ”] insofar as B C D E F G H 76 SUPREME COURT REPORTS [2021] 3 S.C.R. - A an application under Section 11(6) of the Arbitration Act is concerned. For this purpose he relied upon a judgment of the High Court of Bombay in **Deepdharshan Builders Pvt. Ltd. v. Saroj, (2019) 1 AIR Bom R 249** ,as well as a recent judgment of this Court in **Geo Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd., (2020) 14 SCC 643** .He then argued that even so far as the cause of action on merits is - B concerned, it arose way back on 08.09.2003, when the Respondent raised the claim with regard to the dispute for the first time. Once time begins to run, limitation cannot be extended by writing any number of subsequent letters. He also relied upon the recent judgment of this Court in **Vidya Drolia v. Durga Trading Corpn., (2021) 2 SCC 1** , stating that this - C case falls under paragraph 148 of the judgment, in that the claim was _ex facie_ time barred and dead and that there was no subsisting dispute. 14. In reply, Shri Nithin Chowdary Pavuluri, learned counsel appearing for the Respondent, argued that the request for appointment of an arbitrator was rejected by the Appellant for the first time on D 10.11.2010, and thus, 10.11.2010 would be the date on which the cause of action would arise. He pressed the point that the rejection of the request to appoint an arbitrator constituted a failure to perform the function entrusted to the President of the Secunderabad Cantonment Board under Clause 2.2.52 of the General Conditions of Contract [“ **GCC** ”], and thus the cause of action under Section 11(6)(c) of the E Arbitration Act first arose on 10.11.2010. Till such rejection, the claim would have to be deemed to have been pending and thus, the Respondent’s claim was alive at the time of filing the applications under Section 11 of the Arbitration Act. Further, though he pressed the point that the final bill was received under protest since the price variation bill submitted with F the final bill had not been cleared by the Appellant, he produced no such document evidencing the same. In addition, he sought to distinguish, on facts, the judgments of this Court in **Geo Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd., (2020) 14 SCC 643** and **Vidya Drolia v. Durga Trading Corpn., (2021) 2 SCC 1** from the appeals before us, by arguing that the GCC between the Appellant and G the Respondent specifically provided for a procedure to appoint an arbitrator and that the Appellant was responsible for delaying and sitting on the Respondent’s request. Thus, he supported the impugned judgment of the High Court by which the Section 11 applications were allowed. 15. Having heard learned counsel appearing for both parties, it is H first necessary to refer to the recent judgment of this Court in **Geo** SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] 77 **Miller & Co. (P) Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd., (2020) 14 SCC 643** , which extracts passages from all the earlier relevant judgments, and then lays down as to when time begins to run for the purpose of filing an application under Section 11 of the Arbitration Act. This Court, after referring to the relevant statutory provisions, held: “ **15.** In _Damodar Das_ [ _State of Orissa_ v. _Damodar Das_ , (1996) 2 SCC 216] , this Court observed, relying upon _Russell on Arbitration_ by Anthony Walton (19th Edn.) at pp. 4-5 and an earlier decision of a two-Judge Bench in _Panchu Gopal Bose_ v. _Port of Calcutta_ [ _Panchu Gopal Bose_ v. _Port of Calcutta_ , (1993) 4 SCC 338] , that the period of limitation for an application for appointment of arbitrator under Sections 8 and 20 of the 1940 Act commences on the date on which the “cause of arbitration” accrued i.e. from the date when the claimant first acquired either a right of action or a right to require that an arbitration take place upon the dispute concerned. ## xxx xxx xxx “ **21.** Applying the aforementioned principles to the present case, we find ourselves in agreement with the finding of the High Court that the appellant’s cause of action in respect of Arbitration Applications Nos. 25/2003 and 27/2003, relating to the work orders dated 7-10-1979 and 4-4-1980 arose on 8-2-1983, which is when the final bill handed over to the respondent became due. Mere correspondence of the appellant by way of writing letters/ reminders to the respondent subsequent to this date would not extend the time of limitation. Hence the maximum period during which this Court could have allowed the appellant’s application for appointment of an arbitrator is 3 years from the date on which cause of action arose i.e. 8-2-1986. Similarly, with respect to Arbitration Application No. 28/2003 relating to the work order dated 3-5-1985, the respondent has stated that final bill was handed over and became due on 10-8-1989. This has not been disputed by the appellant. Hence the limitation period ended on 10-8-1992. Since the appellant served notice for appointment of arbitrator in 2002, and requested the appointment of an arbitrator before a court only by the end of 2003, his claim is clearly barred by limitation. A B C D E F G H xxx xxx xxx 78 SUPREME COURT REPORTS [2021] 3 S.C.R. A B C D E **23.** Turning to the other decisions, it is true that in _Inder Singh Rekhi_ [ _Inder Singh Rekhi_ v. _DDA_ , (1988) 2 SCC 338], this Court observed that the existence of a dispute is essential for appointment of an arbitrator. A dispute arises when a claim is asserted by one party and denied by the other. The term “dispute” entails a positive element and mere inaction to pay does not lead to the inference that dispute exists. In that case, since the respondent failed to finalise the bills due to the applicant, this Court held that cause of action would be treated as arising not from the date on which the payment became due, but on the date when the applicant first wrote to the respondent requesting finalisation of the bills. However, the Court also expressly observed that “ _a party cannot postpone the accrual of cause of action by writing reminders or sending reminders_ ”. **24.** In the present case, the appellant has not disputed the High Court’s finding that the appellant itself had handed over the final bill to the respondent on 8-2-1983. Hence, the holding in _Inder Singh Rekhi_ [ _Inder Singh Rekhi_ v. _DDA_ , (1988) 2 SCC 338] will not apply, as in that case, the applicant’s claim was delayed on account of the respondent’s failure to finalise the bills. Therefore the right to apply in the present case accrued from the date on which the final bill was raised (see _Union of India_ v. _Momin Construction Co._ [ _Union of India_ v. _Momin Construction Co._ , (1997) 9 SCC 97] ). ## xxx xxx xxx **29.** Moreover, in a commercial dispute, while mere failure to pay F may not give rise to a cause of action, once the applicant has asserted their claim and the respondent fails to respond to such claim, such failure will be treated as a denial of the applicant’s claim giving rise to a dispute, and therefore the cause of action for reference to arbitration. It does not lie to the applicant to plead that it waited for an unreasonably long period to refer the dispute G to arbitration merely on account of the respondent’s failure to settle their claim and because they were writing representations and reminders to the respondent in the meanwhile.” G 16. The recent judgment of this Court in **Bharat Sanchar Nigam Ltd. & Anr. v. M/s Nortel Networks India Pvt. Ltd.,** delivered on H 10.03.2021 in Civil Appeal Nos. 843-844 of 2021 has also considered 79 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] the entire law on the subject. The first paragraph of the said judgment A reads as follows: “ **1.** The present Appeals raise two important issues for our consideration : (i) the period of limitation for filing an application under Section 11 of the Arbitration and Conciliation Act, 1996 (“the 1996 Act”); and (ii) whether the Court may refuse to make B the reference under Section 11 where the claims are _ex facie_ time-barred?” 17. Insofar as the first issue is concerned, after examining Article 137 of the Limitation Act, this Court held: “ **11.** It is now fairly well-settled that the limitation for filing an application under Section 11 would arise upon the failure to make the appointment of the arbitrator within a period of 30 days’ from issuance of the notice invoking arbitration. In other words, an application under Section 11 can be filed only after a notice of arbitration in respect of the particular claim(s) / dispute(s) to be referred to arbitration [as contemplated by Section 21 of the Act] is made, and there is failure to make the appointment. **12.** The period of limitation for filing a petition seeking appointment of an arbitrator/s cannot be confused or conflated with the period of limitation applicable to the substantive claims made in the underlying commercial contract. The period of limitation for such claims is prescribed under various Articles of the Limitation Act, 1963. The limitation for deciding the underlying substantive disputes is necessarily distinct from that of filing an application for appointment of an arbitrator. This position was recognized even under Section 20 of the Arbitration Act 1940. Reference may be made to the judgment of this Court in _**C. Budhraja v. Chairman, Orissa Mining Corporation Ltd**_ . [ _(2008) 2 SCC 444_ ] wherein it was held that Section 37(3) of the 1940 Act provides that for the purpose of the Limitation Act, an arbitration is deemed to have commenced when one party to the arbitration agreement serves on the other party, a notice requiring the appointment of an arbitrator. Paragraph 26 of this judgment reads as follows : “ **26.** Section 37(3) of the Act provides that for the purpose of the Limitation Act, an arbitration is deemed to have been commenced when one party to the arbitration agreement serves on the other C D E F G H 80 SUPREME COURT REPORTS [2021] 3 S.C.R. A party thereto, a notice requiring the appointment of an arbitrator. Such a notice having been served on 4-6-1980, it has to be seen whether the claims were in time as on that date. If the claims were barred on 4-6-1980, it follows that the claims had to be rejected by the arbitrator on the ground that the claims were barred by limitation. The said period has nothing to do with the period of B limitation for filing a petition under Section 8(2) of the Act. Insofar as a petition under Section 8(2) is concerned, the cause of action would arise when the other party fails to comply with the notice invoking arbitration. Therefore, the period of limitation for filing a petition under Section 8(2) seeking appointment of an arbitrator C cannot be confused with the period of limitation for making a claim. The decisions of this Court in Major (Retd.) Inder Singh Rekhi v. DDA [(1988) 2 SCC 338] , Panchu Gopal Bose v. Board of Trustees for Port of Calcutta [(1993) 4 SCC 338] and Utkal Commercial Corpn. v. Central Coal Fields Ltd. [(1999) 2 SCC 571] also make this position clear.”” D 18. Insofar as the second issue is concerned, this Court went into the position prior to the Arbitration and Conciliation (Amendment) Act, 2015 [“ **2015 Amendment** ”] together with the change made by the introduction of Section 11(6A) by the 2015 Amendment, stating: “ **24.** Sub-section (6A) came up for consideration in the case of E _**Duro Felguera SA v. Gangavaram Port Ltd**_ **.** _[(2017) 9 SCC 729]_ , wherein this Court held that the legislative policy was to minimize judicial intervention at the appointment stage. In an application under Section 11, the Court should only look into the existence of the arbitration agreement, before making the reference. Post the 2015 amendments, all that the courts are F required to examine is whether an arbitration agreement is in existence —nothing more, nothing less. - “ **48.** Section 11(6-A) added by the 2015 Amendment, reads as follows: - “11. (6-A) The Supreme Court or, as the case may be, the - G High Court, while considering any application under subsection (4) or sub-section (5) or sub-section (6), shall, _notwithstanding any judgment, decree or order of any court, confine to the examination of the existence of an arbitration agreement_ .” - H (emphasis supplied) 81 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] From a reading of Section 11(6-A), the intention of the A legislature is crystal clear i.e. the court should and need only look into one aspect—the existence of an arbitration agreement. What are the factors for deciding as to whether there is an arbitration agreement is the next question. The resolution to that is simple—it needs to be seen if the agreement contains a B clause which provides for arbitration pertaining to the disputes which have arisen between the parties to the agreement. ## … **59.** The scope of the power under Section 11(6) of the 1996 Act was considerably wide in view of the decisions in SBP and Co. [SBP and Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] and Boghara Polyfab [National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117] . This position continued till the amendment brought about in 2015. After the amendment, all that the courts need to see is — whether an arbitration agreement exists nothing more, nothing less. The legislative policy and purpose is essentially to minimise the Court’s intervention at the stage of appointing the arbitrator and this intention as incorporated in Section 11(6-A) ought to be respected.” **25.** In _**Mayavati Trading Company Private Ltd. v. Pradyut Dev Burman** [(2019) 8 SCC 714_ ], a three-judge bench held that the scope of power of the Court under Section 11 (6A) had to be construed in the narrow sense. In paragraph 10, it was opined as under : “ **10.** This being the position, it is clear that the law prior to the 2015 Amendment that has been laid down by this Court, which would have included going into whether accord and satisfaction has taken place, has now been legislatively overruled. This being the position, it is difficult to agree with the reasoning contained in the aforesaid judgment [United India Insurance Co. Ltd. v. Antique Art Exports (P) Ltd., (2019) 5 SCC 362 : (2019) 2 SCC (Civ) 785] , as Section 11(6-A) is confined to the examination of the existence of an arbitration agreement and is to be understood in the narrow sense as has been laid down in the judgment in Duro Felguera, SA [Duro Felguera, SA v. Gangavaram Port Ltd., (2017) 9 SCC 729” C D E F G H 82 SUPREME COURT REPORTS [2021] 3 S.C.R. A **26.** In _**Uttarakhand Purv Sainik Kalyan Nigam v. Northern Coal Field Limited**_ [( _2020) 2 SCC 455]_ this Court took note of the recommendations of the Law Commission in its 246th Report, the relevant extract of which reads as : **“7.6.** The Law Commission in the 246th Report [Amendments B to the Arbitration and Conciliation Act, 1996, Report No. 246, Law Commission of India (August 2014), p. 20.] recommended that: “33. … the Commission has recommended amendments to Sections 8 and 11 of the Arbitration and Conciliation Act, 1996. The scope of the judicial intervention is only restricted to situations where the court/judicial authority finds that the arbitration agreement does not exist or is null and void. Insofar as the nature of intervention is concerned, it is recommended that in the event the court/judicial authority is prima facie satisfied against the argument challenging the arbitration agreement, it shall appoint the arbitrator and/ or refer the parties to arbitration, as the case may be. The amendment envisages that the judicial authority shall not refer the parties to arbitration only if it finds that there does not exist an arbitration agreement or that it is null and void. If the judicial authority is of the opinion that prima facie the arbitration agreement exists, then it shall refer the dispute to arbitration, and leave the existence of the arbitration agreement to be finally determined by the Arbitral Tribunal.” C D E In view of the legislative mandate contained in the amended F Section 11(6A), the Court is now required only to examine the existence of the arbitration agreement. All other preliminary or threshold issues are left to be decided by the arbitrator under Section 16, which enshrines the _kompetenz-komptenz_ principle. The doctrine of _kompetenz-komptenz_ implies that the arbitral tribunal is empowered, and has the competence to rule on its own G jurisdiction, including determination of all jurisdictional issues. This was intended to minimise judicial intervention at the pre-reference stage, so that the arbitral process is not thwarted at the threshold when a preliminary objection is raised by the parties.” G (emphasis in original) H 83 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] 19. This Court went on to hold that limitation is not a jurisdictional A issue but is an admissibility issue. It then referred to a recent judgment of this Court in **Vidya Drolia v. Durga Trading Corporation, (2021) 2 SCC 1** , and stated as follows: “ **36.** In a recent judgment delivered by a three-judge bench in _**Vidya Drolia v. Durga Trading Corporation** [(2021) 2 SCC 1_ ], on the scope of power under Sections 8 and 11, it has been held that the Court must undertake a primary first review to weed out “manifestly _ex facie_ non-existent and invalid arbitration agreements, or non-arbitrable disputes.” The _prima facie_ review at the reference stage is to cut the deadwood, where dismissal is bare faced and pellucid, and when on the facts and law, the litigation must stop at the first stage. Only when the Court is certain that no valid arbitration agreement exists, or that the subject matter is not arbitrable, that reference may be refused. In paragraph 144, the Court observed that the judgment in _**Mayavati Trading**_ had rightly held that the judgment in _**Patel Engineering**_ had been legislatively overruled. B C D Paragraph 144 reads as : “ **144.** As observed earlier, Patel Engg. Ltd. explains and holds that Sections 8 and 11 are complementary in nature as both relate to reference to arbitration. Section 8 applies when judicial proceeding is pending and an application is filed for stay of judicial proceeding and for reference to arbitration. Amendments to Section 8 vide Act 3 of 2016 have not been omitted. Section 11 covers the situation where the parties approach a court for appointment of an arbitrator. Mayavati Trading (P) Ltd., in our humble opinion, rightly holds that Patel Engg. Ltd. has been legislatively overruled and hence would - - not apply even post omission of sub section (6 A) to Section 11 of the Arbitration Act. Mayavati Trading (P) Ltd. has elaborated upon the object and purposes and history of the - - amendment to Section 11, with reference to sub section (6 A) to elucidate that the section, as originally enacted, was facsimile with Article 11 of the Uncitral Model of law of arbitration on which the Arbitration Act was drafted and enacted.” (emphasis supplied) E F G H 84 SUPREME COURT REPORTS [2021] 3 S.C.R. A B While exercising jurisdiction under Section 11 as the judicial forum, the court may exercise the _prima facie_ test to screen and knockdown _ex facie_ meritless, frivolous, and dishonest litigation. Limited jurisdiction of the Courts would ensure expeditious and efficient disposal at the referral stage. At the referral stage, the Court can interfere “only” when it is “manifest” that the claims are ex facie time barred and dead, or there is no subsisting dispute. Paragraph 148 of the judgment reads as follows : C D E F “ **148.** Section 43(1) of the Arbitration Act states that the Limitation Act, 1963 shall apply to arbitrations as it applies to court proceedings. Sub-section (2) states that for the purposes of the Arbitration Act and Limitation Act, arbitration shall be deemed to have commenced on the date referred to in Section 21. Limitation law is procedural and normally disputes, being factual, would be for the arbitrator to decide guided by the facts found and the law applicable. The court at the referral stage can interfere only when it is manifest that the claims are ex facie time-barred and dead, or there is no subsisting dispute. All other cases should be referred to the Arbitral Tribunal for decision on merits. Similar would be the position in case of disputed “no-claim certificate” or defence on the plea of novation and “accord and satisfaction”. As observed in Premium Nafta Products Ltd. [Fili Shipping Co. Ltd. v. Premium Nafta Products Ltd., 2007 UKHL 40 : 2007 Bus LR 1719 (HL)] , it is not to be expected that commercial men while entering transactions inter se would knowingly create a system which would require that the court should first decide whether the contract should be rectified or avoided or rescinded, as the case may be, and then if the contract is held to be valid, it would require the arbitrator to resolve the issues that have arisen.” In paragraph 154.4, it has been concluded that: G “ **154.4.** Rarely as a demurrer the court may interfere at Section 8 or 11 stage when it is manifestly and ex facie certain that the - arbitration agreement is non existent, invalid or the disputes are non-arbitrable, though the nature and facet of nonarbitrability would, to some extent, determine the level and nature H 85 SECUNDERABAD CANTONMENT BOARD v. M/S B. RAMACHANDRAIAH & SONS [R.F. NARIMAN, J.] of judicial scrutiny. The restricted and limited review is to check and protect parties from being forced to arbitrate when the matter is demonstrably “non-arbitrable” and to cut off the deadwood. The court by default would refer the matter when contentions relating to non-arbitrability are plainly arguable; when consideration in summary proceedings would be insufficient and inconclusive; when facts are contested; when the party opposing arbitration adopts delaying tactics or impairs conduct of arbitration proceedings. This is not the stage for the court to enter into a mini trial or elaborate review so as to usurp the jurisdiction of the Arbitral Tribunal but to affirm and uphold integrity and efficacy of arbitration as an alternative dispute resolution mechanism.” A B C (emphasis supplied) In paragraph 244.4 it was concluded that: “ **244.4.** The court should refer a matter if the validity of the arbitration agreement cannot be determined on a prima facie basis, as laid down above i.e. “ **when in doubt, do refer** ”.” **37.** The upshot of the judgment in _**Vidya Drolia**_ is affirmation of the position of law expounded in _**Duro Felguera**_ and _**Mayavati Trading**_ , which continue to hold the field. It must be understood clearly that _**Vidya Drolia**_ has not resurrected the pre-amendment position on the scope of power as held in _**SBP & Co. v. Patel Engineering**_ (supra). It is only in the very limited category of cases, where there is not even a vestige of doubt that the claim is _ex facie_ timebarred, or that the dispute is non-arbitrable, that the court may decline to make the reference. However, if there is even the slightest doubt, the rule is to refer the disputes to arbitration, otherwise it would encroach upon what is essentially a matter to be determined by the tribunal.” D E F G (emphasis in original) 20. Applying the aforesaid judgments to the facts of this case, so far as the applicability of Article 137 of the Limitation Act to the applications under Section 11 of the Arbitration Act is concerned, it is clear that the demand for arbitration in the present case was made by H 86 SUPREME COURT REPORTS [2021] 3 S.C.R. - A the letter dated 07.11.2006. This demand was reiterated by a letter dated 13.01.2007, which letter itself informed the Appellant that appointment of an arbitrator would have to be made within 30 days. At the very latest, therefore, on the facts of this case, time began to run on and from 12.02.2007. The Appellant’s laconic letter dated 23.01.2007, which stated that the matter was under consideration, was within the 30-day period. - B On and from 12.02.2007, when no arbitrator was appointed, the cause of action for appointment of an arbitrator accrued to the Respondent and time began running from that day. Obviously, once time has started running, any final rejection by the Appellant by its letter dated 10.11.2010 would not give any fresh start to a limitation period which has already - C begun running, following the mandate of Section 9 of the Limitation Act. This being the case, the High Court was clearly in error in stating that since the applications under Section 11 of the Arbitration Act were filed on 06.11.2013, they were within the limitation period of three years starting from 10.11.2020. On this count, the applications under Section 11 of the Arbitration Act, themselves being hopelessly time barred, no arbitrator - D could have been appointed by the High Court. 21. Even otherwise, the claim made by the Respondent was also _ex facie_ time barred. It is undisputed that final payments were received latest by the end of March 2003 by the Respondent. That apart, even assuming that a demand could have been made on account of price E variation, such demand was made on 08.09.2003. Repeated letters were written thereafter by the Respondent, culminating in a legal notice dated 30.01.2010. Vide the reply notice dated 16.02.2010, it was made clear that such demands had been rejected. Even taking 16.02.2010 as the starting point for limitation on merits, a period of three years having F elapsed by February 2013, the claim made on merits is also hopelessly time barred. 22. For all these reasons, the appeals are allowed and the impugned judgment of the High Court dated 20.08.2019 is set aside. - G Ankit Gyan Appeals allowed. H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.