Tenetowl LogoTenetowl
Landmark CasesDivision BenchWrit petitions dismissed; no costs.

SATISH CHANDER SHARMA & ORS. v. STATE OF HIMACHAL PRADESH & ORS.

Case / Petition Number:
WRIT PETITION (CIVIL) NO. 179 OF 2018

Case Synopsis & Summary

SATISH CHANDER SHARMA & ORS. v. STATE OF HIMACHAL PRADESH & ORS. is a Supreme Court writ petition under Article 32 filed by retired officers of the Himachal Pradesh State Forest Development Corporation Limited challenging the 2004 repeal of the 1999 pension scheme and seeking pension benefits under that scheme for pensionary parity. The petitioners had opted for the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999, and sought to count service from joining to superannuation to determine pension under the 1999 Scheme, on par with colleagues who retired before 02.12.2004 or who were already covered by the scheme. The matter traces to High Court litigation culminating in a 2013 order that granted pension under the 1999 Scheme, later reversed by this Court in Rajesh Chander Sood (2016), which upheld the repeal and fixed a cut-off date (02.12.2004). The present three-judge Bench considers whether Rajesh Chander Sood remains good law and whether the petitioners’ reliance on vested rights under the 1999 Scheme is sustainable. After evaluating arguments on vested rights, estoppel, and financial viability, the Court concludes that the State’s withdrawal was lawful and within precedent. The petitions are dismissed with no costs, reaffirming the binding Rajesh Chander Sood decision and the State’s policy judgment.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Surya Kant
  • Dipankar Datta
  • Ujjal Bhuyan
Judgment Date
2025-04-16
Court Decision / Holding
The writ petitions under Article 32 are dismissed. The Court holds that the repeal of the 1999 Scheme was lawful, based on financial viability and policy considerations, and that Rajesh Chander Sood remains binding. No costs are awarded.
Final Disposition
Writ petitions dismissed; no costs.

Parties to the Case

Appellants / Petitioners

  • Satish Chander Sharma
  • and others

Respondents

  • State of Himachal Pradesh
  • others

Legal Representation & Advocates

Counsels for Petitioners

  • • Gopal Sankaranarayan (Senior Counsel)

Counsels for Respondents

  • • Devadatt Kamat (Senior Counsel)

Provisions of Law Cited

Constitution of India Article 32Constitution of India Article 226Constitution of India Article 14Constitution of India Article 300ACentral Civil Services (Pension) Rules, 1972Central Civil Services (Commutation of Pension) Rules, 1981Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999Employees’ Provident Fund Scheme, 1995Companies Act, 1956Notification dated 02.12.2004

Legal Doctrines & Maxims

  • Per incuriam
  • Estoppel / Promissory estoppel
  • Vested rights
  • Finality of lis
  • Severability
  • Bonafides (good faith)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners urge that the 1999 Scheme created vested pensionary rights and that withdrawal of the scheme via the 02.12.2004 repeal notification breached constitutional guarantees (including Article 14 and Article 300A) and violated established precedents; they seek pension benefits under the 1999 Scheme on par with those who contributed under it prior to repeal.

Contentions of Respondents

The State argues that Rajesh Chander Sood (supra) is binding and that the 1999 Scheme was only a welfare measure susceptible to withdrawal given financial viability; it contends the cut-off date of 02.12.2004 was a reasonable administrative decision consistent with precedents like RR Verma and the need to prevent fiscal unsustainability; it differentiates between government employees and corporates and asserts no vested rights were illegally withdrawn.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (14)

Case NameCitationTreatmentExplanation
P.D. Nanda v. State of HP2013 SCC Online HP 5151Mentioned OnlyCited to reflect earlier High Court position; later addressed by Rajesh Chander Sood (supra).
State of Himachal Pradesh v. Rajesh Chander Sood(2016) 10 SCC 77PositiveBinding decision on the present petition; upheld repeal and cut-off date rationale.
R.R. Verma v. Union of India(1980) 3 SCC 402PositiveSupports the proposition that the State may fix cut-off dates in fiscal policy matters.
BALCO Employees’ Union v. Union of India(2002) 2 SCC 333DistinguishedDiscussed as inapplicable context; court notes different factual contexts.
D.S. Nakara v. Union of India(1983) 1 SCC 305Mentioned OnlyCited in argument regarding cut-off principles but not central to outcome.
Naresh Shridhar Mirajkar v. State of MaharashtraAIR 1967 SC 1Mentioned OnlyBackground on Article 32 remedies; not controlling in current dispute.
Sub-Inspector Sadhan Kumar Goswami v. Union of India(1997) 2 SCC 225Mentioned OnlyIllustrates limits on Article 32 challenges to final judgments.
Rupa Ashok Hurra v. Ashok Hurra(2002) 4 SCC 388Mentioned OnlyDiscusses curative jurisdiction; not central to the decision.
A.R. Antulay v. R.S. Nayak(1988) 2 SCC 225Mentioned OnlyCited in context of reconsideration principles under Article 32.
Omprakash Verma v. State of Andhra Pradesh(2010) 13 SCC 158Mentioned OnlyReiterates general principle on challenges to Supreme Court decisions.
Indian Council for Enviro-Legal Action v. Union of India(2011) 8 SCC 161Mentioned OnlyCited regarding maintainability of Article 32 reconsideration petitions.
Khoday Distilleries Ltd. v. Registrar General, Supreme Court of India(1996) 3 SCC 114Mentioned OnlyCited on limits of reconsideration under Article 32.
Green View Tea & Industries v. Collector(2002) 1 SCC 109Mentioned OnlyCited for finality principle in adjudication.
State of Assam v. Barak Upatyaka D.U. Karmachari Sanstha(2009) 5 SCC 694Mentioned OnlyUses a hierarchy principle to illustrate corporate entities’ status.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•7,915 words•~36 min read

In The Court Record

SATISH CHANDER SHARMA & ORS. v. STATE OF HIMACHAL PRADESH & ORS.

2025 INSC 491 **REPORTABLE** **==> picture [72 x 72] intentionally omitted <==** # **IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION** ## **WRIT PETITION (CIVIL) NO. 179 OF 2018** SATISH CHANDER SHARMA & ORS. PETITIONER(S) VERSUS STATE OF HIMACHAL PRADESH & ORS. RESPONDENT(S) ## **J U D G M E N T** ## **UJJAL BHUYAN, J.** Heard learned counsel for the parties. 2. This is a petition filed by three petitioners under Article 32 of the Constitution of India. Petitioners are retired officers of Himachal Pradesh State Forest Development Corporation Limited (briefly ‘the Corporation’ hereinafter). Signature Not Verified They are aggrieved by denial of pensionary benefits to them in Digitally signed by SATISH KUMAR YADAV Date: 2025.04.16 16:43:26 IST Reason: terms of the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999 discontinued _vide_ the notification dated 02.12.2004, which though carved out an exception for those who had opted for the scheme and had superannuated prior to 02.12.2004. Hence, they seek a direction to the respondents for payment of pension to them upon their superannuation in terms of the said scheme at par with similarly situated employees who had retired prior to 02.12.2004, by counting their pensionable service from the date of joining till the date of their superannuation. 3. This issue was earlier raised by a group of petitioners before the Himachal Pradesh High Court (‘High Court’ hereinafter) by filing writ petitions under Article 226 of the Constitution of India, the lead case being _P.D. Nanda Vs. State of H.P.[1]_ , CWP No. 4425 of 2009. The High Court had allowed the writ petitions _vide_ the judgment and order dated 19.12.2013 by directing the State to provide pension to the retired employees of the Corporation in terms of the aforesaid > 1 2013 SCC Online HP 5151 2 scheme. This decision was reversed by a two-Judge Bench of this Court in _. State of H.P. Vs. Rajesh Chander Sood[2]_ 4. Thereafter, the present writ petition came to be filed before this Court seeking the same relief. Various contentions have been raised including the one that the decision in _Rajesh Chander Sood_ (supra) has ignored several binding precedents of this Court and is, therefore, a decision rendered _per incuriam._ 5. This Court issued notice _vide_ the order dated 20.03.2018. In the said order, a two-Judge Bench of this Court, after observing that since correctness of this Court’s judgment in _Rajesh Chander Sood_ (supra) has been questioned, requested the learned Chief Justice to place the matter before a three-Judge Bench. This is how the matter has been placed before the present Bench and heard accordingly. 6. Though learned senior counsel for the respondentState has raised a preliminary objection as to maintainability of the present writ petition, we are of the view that such an > 2 (2016) 10 SCC 77 3 objection may be considered while considering the stand of the respondents. 7. At the outset, it would be apposite to advert to the relevant facts. 8. The Corporation was incorporated under the Companies Act, 1956 pursuant to a notification dated 26.03.1974 issued by the Government of Himachal Pradesh. It is completely owned and controlled by the State Government inasmuch as 100% of the share capital of the Corporation is owned by the State of Himachal Pradesh. 9. Petitioner No. 1 was appointed as a Clerk in the Corporation on 29.10.1975. On 27.03.1981, he was promoted to the post of Junior Assistant. He was further promoted to the post of Senior Assistant(Senior Accountant) on 07.11.1984. He was promoted to the post of Office Manager(Junior) on 03.04.1989 and, thereafter, to the post of Office Manager (Senior) on 17.11.2011. Petitioner No. 1 superannuated from service on 31.01.2013. 4 9.1. Petitioner No. 2 was appointed as a Clerk in the Corporation on 15.02.1988. He was promoted to the post of Senior Clerk on 15.02.1993 and, thereafter, to the post of Junior Assistant on 01.01.1996. He was further promoted to the post of Senior Assistant on 07.09.2009 whereafter he was promoted to the post of Office Manager (Junior) from which post he superannuated on 30.09.2016. 9.2. Petitioner No. 3 was appointed to the post of Clerk in the Corporation on 05.12.1981. He was promoted to the post of Senior Clerk on 24.05.1985 and, thereafter, to the post of Junior Assistant on 25.04.1992. He was further promoted to the post of Senior Assistant on 24.12.1993. On 08.11.2013, petitioner No. 3 was promoted to the post of Office Manager (Junior) whereafter he superannuated on 30.11.2014. 10. It is stated that following the revision of pay scales of government employees by the State Government, the Corporation also allowed such revision of pay scales. 11. Since the employees of government corporations like the Corporation enjoyed parity with employees of the State Government _qua_ all conditions of service, such as, pay scales, 5 allowances etc., the State Government issued a notification dated 29.10.1999 whereby employees of government corporations i.e. state public sector undertakings like the Corporation were extended parity even as regards pensionary benefits. This scheme was called the Himachal Pradesh Corporate Sector Employees (Pension, Family Pension, Commutation of Pension and Gratuity) Scheme, 1999 (referred to hereinafter as ‘the 1999 Scheme’) and came into effect on and from 01.04.1999. It was mentioned that all pensionary benefits of the employees of the corporate sector were to be determined in accordance with the provisions laid down in the Central Civil Services (Pension) Rules, 1972 and the Central Civil Services (Commutation of Pension) Rules, 1981, as amended, and adopted by the Himachal Pradesh Government for the state government employees. The 1999 Scheme contemplated exercise of option by the employees of the corporate sector as to whether he or she would be governed under the existing statutory provisions or be governed under the 1999 Scheme which contemplated creation of a pension fund. The entire amount of contribution of the concerned 6 public sector undertaking including interest thereon to the Contributory Provident Fund (CPF) upto 31.03.1999 were to be transferred to the corpus fund (pension fund) to be administered and maintained by the Government of Himachal Pradesh in the Finance Department. It was clarified that the existing employees who had opted for the 1999 Scheme would automatically forfeit their claim to the employers’ share of CPF including interest thereon to the State Government upto 31.03.1999. However, the amount of their subscriptions alongwith interest would be transferred to the General Provident Fund (GPF) account, to be allotted and maintained by the concerned public sector undertaking. 12. It is stated that the Corporation had amended its byelaws in order to implement the 1999 Scheme. The three petitioners had exercised their option in favour of the 1999 Scheme since this scheme provided for higher pensionary benefits. 13. It appears that reservations were expressed regarding the financial stability of the 1999 Scheme. In the above backdrop, the State Government constituted a High Level 7 Committee (‘Committee’ hereinafter) in 2003 (21.01.2003) to review the financial viability of the 1999 Scheme. After a detailed analysis, the Committee submitted a report on 28.10.2003. The Committee was of the view that the 1999 Scheme was not viable on a self-sustaining basis for the following reasons: - i) uncertainty in the rate of interest regime; ii) declining recruitment in the corporate sector would deplete the size of the corpus to be created and it would be difficult to honour liabilities accruing after 10-12 years; - iii) the pension plan envisages payment of pension to corporate sector employees as is being paid to the government employees. Government employees at present are entitled to pension @ 50% of the basic pay last drawn with linkage to their dearness allowance. This return does not appear to be possible from the pension fund proposed to be created for corporate sector employees. 14. After considering the aforesaid report, Government of Himachal Pradesh in the Finance Department issued a notification dated 02.12.2004 whereby the 1999 Scheme was repealed with immediate effect. It was clarified that consequent upon the repeal, barring the employees who had retired from service w.e.f. 01.04.1999 till the date of notification i.e. 02.12.2004, other employees would continue to be covered 8 under those provisions which were applicable to them as on 31.03.1999. While clarifying that the public sector undertakings would be the pension sanctioning/ disbursing authority, the employers’ share of CPF including interest thereon was transferred to the respective public sector undertakings who were required to form a pension fund. In so far those employees of the public sector undertakings who had retired from service during the period w.e.f. 01.04.1999 till the date of publication of the notification i.e. 02.12.2004, the repeal notification stated as follows: Notwithstanding such repeal, the employees of Himachal Pradesh corporate sector who retired from service w.e.f. 01.04.1999 till the date of publication of this notification shall continue to be governed under the provisions of the scheme so repealed; provided such retired employees had opted for such scheme and had otherwise become eligible for pension under the scheme. 15. A large number of writ petitions were filed before the High Court assailing the notification dated 02.12.2004 and seeking a direction that pension of the retired employees of the Corporation should be paid as per the 1999 Scheme. High Court _vide_ the judgment and order dated 19.12.2013 allowed all the writ petitions. The cut-off date 02.12.2004 was declared 9 _ultra vires_ but instead of declaring the notification dated 02.12.2004 as unconstitutional, the same was read down by including the writ petitioners and similarly situated employees who had become members of the 1999 Scheme and had retired after 02.12.2004 as well as those employees who were already in service when the 1999 Scheme was notified and had become members of that scheme and would retire henceforth as eligible for pension under the 1999 Scheme. 16. The aforesaid decision of the High Court was assailed by the State before this Court in _Rajesh Chander Sood_ (supra). A two-Judge Bench of this Court held that it was well within the authority of the State Government in exercise of its administrative powers which it had exercised by issuing the impugned repeal notification dated 02.12.2004 to fix a cut-off date for continuing the right to receive pension for some and denying the same to others. The Bench further held that the government was free to alter its earlier administrative decision and policy though it should be in consonance with all legal and statutory obligations. The Bench noted that it was not a case where the rights which had accrued to the employees under 10 the Employees’ Provident Fund Scheme, 1995 under which the employees were covered prior to their opting for the 1999 Scheme, had in any manner been altered to their disadvantage. All that the repeal notification dated 02.12.2004 says is that the concerned employees would be entitled to all the rights which had accrued to them under the Employees’ Provident Fund Scheme, 1995 and not under the 1999 Scheme. In so far the _bona fides_ of the State Government were concerned, the Bench observed that the State Government as a welfare measure had ventured to honestly extend some postretiral benefits to the employees of independent legal entities like the Corporation on the mistaken belief, arising out of a miscalculation, that the same could be catered out of the available resources. This measure was adopted by the State Government not in its capacity as the employer of the respondent-employees but as a welfare measure. When it became apparent that the welfare measure extended by the State Government could not be sustained as originally understood, the same was withdrawn. Thus, the action of the State Government was _bona fide_ . State Government had taken 11 a conscious decision and the classification made by the State Government by fixing 02.12.2004 as the cut-off date was reasonable and justifiable in law; it also had a nexus to the object sought to be achieved. In the circumstances, the decision of the High Court was interfered with. 17. Mr. Gopal Sankaranarayan, learned senior counsel for the petitioners submits that the present proceeding is concerned with the pensionary rights and entitlement of the petitioners. This is also concerned with the correctness of the judgment rendered in _Rajesh Chander Sood_ (supra). This Court while issuing notice _vide_ the order dated 20.03.2018, _prima facie_ , agreed with the contention of the petitioners that the judgment in _Rajesh Chander Sood_ (supra) required reconsideration by a three-Judge Bench. 17.1. Learned senior counsel submits that the judgment in _Rajesh Chander Sood_ (supra) is not good law and is _per incuriam_ as it fails to consider binding precedents of coordinate and larger benches of this Court. Further, in the said judgment, the Bench contradicted itself by acknowledging the 12 vested right of the employees under the 1999 Scheme but denying the benefits accruing therefrom to them. 17.2. Learned senior counsel has referred to paragraphs 69, 70, 71 and 72 of the judgment in _Rajesh Chander Sood_ (supra) and submits that the Bench had recorded a finding that having exercised their option for the 1999 Scheme and having forgone all their rights under the Employees Provident Fund Scheme, 1995, the employees concerned would be covered by the 1999 Scheme. As soon as they came to be covered by the 1999 Scheme, a contingent right came to be vested in them. As a matter of fact, the Bench had rejected the contention of the State that the rights of the employees under the 1999 Scheme would be vested only upon attaining the age of superannuation and accepted the contention advanced by the employees that any employee governed by a pension scheme, would be entitled to the benefits therefrom on attaining the qualifying service immediately on his enrolment in the said scheme, particularly, when they had expressly chosen to forgo their rights under the Employees’ Provident Fund Scheme, 1995. 13 17.3. Adverting to clause 1(2) of the 1999 Scheme, it is submitted by the learned senior counsel for the petitioners that the terms of clause 1(2) are clear and unambiguous. By way of incorporation, the Central Civil Services (Pension) Rules, 1972 and the Central Civil Services (Commutation of Pension) Rules, 1981, stood applicable to the employees upon their opting for the 1999 Scheme. 17.4. In _Rajesh Chander Sood_ (supra), after acknowledging the vested right of the pensioners, this Court considered the issue of cut-off date. He submits that while this Court has upheld fixation of a cut-off date for extending better and higher pensionary benefits, there are no precedents whereby a cut-off date for discontinuing the right to receive pension, _inter se_ , a homogeneous class has been sustained. He submits that reliance placed on the decisions of this Court in _R.R. Verma Vs. Union of India[3]_ and _BALCO Employees’ Union Vs. Union of India[4]_ , was wholly misplaced as those two decisions were rendered in different contexts. > 3 (1980) 3 SCC 402 > 4 (2002) 2 SCC 333 14 17.5. He further submitted that the judgment in _Rajesh Chander Sood_ (supra) sustaining the retrospective withdrawal of the 02.12.2004 notification whereby and whereunder pensionary rights of only those who had superannuated between 01.04.1999 and 02.12.2004 were saved as opposed to saving such rights of all those employees who were in service between 01.04.1999 and 02.12.2004 was explicitly contrary to the principles laid down by this Court in a large number of judgments. If the 1999 Scheme had to be repealed due to the purported object i.e. financial burden on the State, repealing of the same by not saving the rights of all those already covered under the 1999 Scheme would be violative of Article 14 of the Constitution of India. 17.6. Learned senior counsel submits that the cut-off date postulated by the notification dated 02.12.2004 providing that benefits under the 1999 Scheme would be available to those who had retired between 01.04.1999 and 02.12.2004 (date of the notification) thereby dividing a homogeneous class without having any reasonable nexus with the object sought to be achieved would be violative of Article 14 of the Constitution of 15 India. In this connection, he has referred to and relied upon the Constitution Bench decision of this Court in _D.S. Nakara Vs. Union of India[5]_ . He submits that prior judgments of this Court wherein similar cut-off dates based on the date of retirement were struck down by this Court were not considered in _Rajesh Chander Sood_ (supra). 17.7. Mr. Gopal Sankaranarayan, learned senior counsel submits that the right to receive pension is a vested right and once the petitioners had opted for the 1999 Scheme, the same could not have been withdrawn, that too, unilaterally on the ground that the State did not have the financial means to support the scheme. Right to receive pension is not dependent upon the finances of the State. It was improper for the State Government to shrug away its responsibility post-introduction of the 1999 Scheme by labelling it as a self-financing pension fund created under the 1999 Scheme. This critical aspect was over-looked in _Rajesh Chander Sood_ (supra). 17.8. He further submits that contention of the employees based on Article 300A of the Constitution of India was also > 5 (1983) 1 SCC 305 16 summarily rejected by the Bench without any independent analysis. When this Court had recognized that the 1999 Scheme created a vested right on the employees, such a statutory right to receive pension would be in terms of the Central Civil Services (Pension) Rules, 1972. Such a statutory right therefore has to be construed as a property right under Article 300A of the Constitution of India. 17.9. He, therefore, submits that _Rajesh Chander Sood_ (supra) is not a good law and is _per incuriam_ . The present writ petition seeking pensionary rights of the petitioners as per the 1999 Scheme may, thus, kindly be allowed by this Court. 18. _Per contra_ , Mr. Devadatt Kamat, learned senior counsel representing the State of Himachal Pradesh submits that the present writ petition filed under Article 32 of the Constitution of India is totally misconceived inasmuch as the issue raised in the writ petition i.e. entitlement of the petitioners to pension under the 1999 Scheme at par with similarly situated employees of the Corporation who had retired between 01.04.1999 and 02.12.2004 has already been 17 decided by this Court in _Rajesh Chander Sood_ (supra) . On this ground alone, the writ petition is liable to be dismissed. 18.1. Thereafter, learned senior counsel has adverted to the facts of the present case and submits that all the issues raised in the present proceeding were raised in _Rajesh Chander Sood_ (supra) and adjudicated by this Court. 18.2. Learned senior counsel submits that the High Court had allowed the earlier batch of writ petitions _vide_ the judgment and order dated 19.12.2013. This was challenged by the State before this Court in _Rajesh Chander Sood_ (supra) which came to be decided on 28.09.2016. Though the present petitioners had superannuated before that, they did not join the aforesaid proceedings. As a matter of fact, they did not also participate in the proceedings before the High Court. Much after their superannuation, they filed the present writ petition. There is, thus, considerable delay and laches on the part of the petitioners in approaching this Court which would, therefore, disentitle them to any relief. 18.3. Learned senior counsel vehemently argues that the present writ petition is nothing but a collateral challenge to a 18 binding judgment of this Court in _Rajesh Chander Sood_ (supra). It is not open to the petitioners to raise the same set of grounds urged in _Rajesh Chander Sood_ (supra) which were rejected by this Court. A writ petition cannot be filed to doubt the correctness of a decision of this Court, he submits. 18.4. Learned senior counsel submits that the principle of _per incuriam_ is not at all attracted to the facts of the present case. There is no glaring omission of law and precedent to constitute _per incuriam_ . 18.5. On the merits of the case, learned senior counsel submits that financial viability or non-viability was a valid consideration taken into account by the State while issuing the repeal notification. The High Level Committee had examined the issue threadbare and, thereafter, submitted report. Based on the report of the High Level Committee, the repeal notification was issued. 18.6. Learned senior counsel submits that petitioners were not employees of the State Government and, therefore, they cannot seek service benefits including retiral benefits at par with State Government employees. State Government had 19 introduced the 1999 Scheme as a welfare measure for the employees of public sector undertakings like the Corporation as a welfare State and not as an employer. But when it was found that available resources were inadequate for funding the 1999 Scheme, the same was withdrawn. However, the interest of those employees who had opted for the 1999 Scheme and had retired before issuance of the repeal notification were protected inasmuch as they were held to be entitled to the benefits under the 1999 Scheme. The intention was not to deprive the employees who had retired during the subsistence of the 1999 Scheme. 18.7. Therefore, he submits that fixation of the date of issuance of the repeal notification as the cut off date for allowing those employees who had retired prior thereto to be entitled to the benefits under the 1999 Scheme, cannot be said to be arbitrary and violative of Article 14 of the Constitution of India. 18.8. Learned senior counsel asserts that the 1999 Scheme was an outcome of a policy decision of the State Government. Withdrawal of the same is also within the realm of policy 20 making. There is no arbitrariness in such withdrawal. Principle of natural justice cannot be extended to such a situation. In the circumstances, learned senior counsel Mr. Kamat submits that there is no merit at all in the writ petition, besides being not maintainable. He, therefore, seeks dismissal of the writ petition. 19. Submissions made by learned counsel for the parties have received the due consideration of the Court. A large number of decisions have been cited at the Bar by both the sides. Those have been considered. However, reference would be made to only those decisions found relevant and necessary. 20. At the outset, let us examine as to how the High Court had dealt with the issue. In _P.D. Nanda_ (supra), High Court held that the moment the employees became members of the 1999 Scheme, they had acquired a vested right and therefore they were required to be heard before they were taken out of the ambit of the 1999 Scheme. High Court observed that when the 1999 Scheme was framed and notified on 29.10.1999 having effect from 01.04.1999, the State Government was aware of all the legal implications but there was remissness on 21 the part of the State Government as well as the public sector undertakings towards implementation of the 1999 Scheme. The public sector undertakings were required to immediately transfer the funds at their disposal towards creation of the corpus fund. When the employees had opted for the 1999 Scheme, they automatically ceased to be members of the previous 1995 Scheme. Therefore, withdrawal of the 1999 Scheme was improper. Though the High Court found the notification dated 02.12.2004 to be bad in law, it expressed the view that to effectuate the purport of the 1999 Scheme, the said notification was required to be read down by including those employees who became members of the scheme and had retired before 02.12.2004 as entitled to the benefits under the 1999 Scheme, instead of declaring the same to be unconstitutional. High Court also rejected the contention of the State Government that the 1999 Scheme could not be implemented due to financial crunch. While allowing the writ petitions, High Court declared the cut-off date of 02.12.2004 to be _ultra vires_ . The repeal notification dated 02.12.2004 was read down by including those writ petitioners 22 and similarly situated employees for the purpose of pensionary benefits. High Court held as follows: **80.** Accordingly, in view of the analysis and discussion made hereinabove, all the writ petitions are allowed. The cut-off date 02.12.2004 is declared ultra vires. Notification dated 02.12.2004 is read down to save it from unconstitutionality, irrationality, arbitrariness or unreasonableness by including the petitioners and similarly situated employees also, who had become members of the scheme notified on 29.10.1999 and have retired after 02.12.2004 and those employees who were already in service when the pension scheme was notified on 29.10.1999 and had become members of that scheme and shall retire hereinafter, for the purpose of pensionary benefits after applying the principle of severability. The Regional Provident Fund Commissioner, Shimla is directed to transfer the entire amount of the CPF to a corpus fund to be administered and maintained by the Government of Himachal Pradesh in the Finance Department including upto date interest, within a period of two weeks. Thereafter, the Pension Sanctioning Authority is directed to sanction the pension/gratuity/commutation of pension after proper scrutiny of the cases forwarded by the concerned Public Sector Undertaking and issue pension payment order to the Pension Disbursing Authority strictly as per 23 para 6 of the scheme notified on 29.10.1999 with interest @ 9% per annum, within a period of 12 weeks from today. Pending application(s), if any, also stand disposed. No costs. 21. This decision of the High Court was challenged by the State Government before this Court in _Rajesh Chander Sood_ (supra). This Court first posed the question as to whether a vested right came to be created in the employees of the corporate bodies when they came to be governed by the 1999 Scheme. On due consideration, this Court expressed the view that such employees who had exercised their option to be governed by the 1999 Scheme came to be regulated by the said scheme immediately on their having submitted their option. In addition, all those employees who did not exercise any option were automatically deemed to have opted for the 1999 Scheme. As soon as the concerned employees came to be governed by the 1999 Scheme, a contingent right stood vested in them. On the question as to whether such a contingent right was binding and irrevocable, this Court held that the same was not binding on the State Government. Before dealing with the said issue, this Court examined the question as to whether the State 24 Government was justified in postulating a cut-off date by which some of the employees governed by the 1999 Scheme (those who had retired prior to 02.12.2004 were entitled to draw pension under the 1999 Scheme whereas those who had not retired by the time the repeal notification was issued on 02.12.2004 were denied such benefit), the above question was answered by this Court in the following manner: **75.** Having given our thoughtful consideration to the issue canvassed, and having gone through the judgments cited, we are of the considered view that this Court has repeatedly upheld a cut-off date, for extending better and higher pensionary benefits, based on the financial health of the employer. A cut-off date can, therefore, legitimately be prescribed for extending pensionary benefits, if the funds available cannot assuage the liability, to all the existing pensioners. We are, therefore, satisfied to conclude that it is well within the authority of the State Government, in exercise of its administrative powers (which it exercised, by issuing the impugned Repeal Notification dated 02-12-2004) to fix a cut-off date, for continuing the right to receive pension in some, and depriving some others of the same. This right was unquestionably exercised by the State Government, as determined by this Court, in _R.R. Verma_ 25 _case_ [ _R.R. Verma_ v. _Union of India_ , (1980) 3 SCC 402: 1980 SCC (L&S) 423] , wherein this Court held that the Government was vested with the inherent power to review. And that the Government was free to alter its earlier administrative decisions and policy. Surely, this is what the State Government has done in the present controversy. But this Court in the abovementioned judgment, placed a rider on the exercise of such power by the Government. In that, the exercise of such power should be in consonance with all legal and statutory obligations. 21.1. A contention was raised on behalf of the employees that by application of the principle of estoppel/ promissory estoppel, the State should not have gone back on the 1999 Scheme by issuing the repeal notification dated 02.12.2004. This Court repelled the above contention as under: **79.** We are of the considered view that the principle of estoppel/promissory estoppel cannot be invoked at the hands of the respondent employees, in the facts and circumstances of this case. It is not as if the rights which had accrued to the respondent employees under the Employees' Provident Fund Scheme, 1995 (under which the respondent employees were governed, prior to their being governed by the 1999 Scheme) have in any manner been altered to their disadvantage. All that was 26 taken away, and given up by the respondent employees by way of foregoing the employer's contribution up to 313-1999 (including the accrued interest thereon), by way of transfer to the corpus fund, was restored to the respondent employees. All the respondent employees, who have been deprived of their pensionary claims by the Repeal Notification dated 02-12-2004, would be entitled to all the rights which had accrued to them, under the Employees' Provident Fund Scheme, 1995. It is, therefore, not possible for us to accept that the respondent employees can be stated to have been made to irretrievably alter their position, to their detriment. Furthermore, all the corporate bodies (with which the respondent employees, are engaged) are independent juristic entities, as held in _State of Assam_ v. _Barak Upatyaka D.U. Karmachari Sanstha_ [ _State of Assam_ v. _Barak Upatyaka D.U. Karmachari Sanstha_ , (2009) 5 SCC 694 : (2009) 2 SCC (L&S) 109] . The mere fact that the corporate bodies under reference, are fully controlled by the State Government, and the State Government is the ultimate authority to determine their conditions of service, under their articles of association, is inconsequential. Undoubtedly, the respondent employees are not government employees. The State Government, as a welfare measure, had ventured to honestly extend some post-retiral benefits to employees of such independent legal entities, on the mistaken 27 belief, arising out of a miscalculation, that the same can be catered to, out of available resources. This measure was adopted by the State Government, not in its capacity as the employer of the respondent employees, but as a welfare measure. When it became apparent that the welfare measure extended by the State Government, could not be sustained as originally understood, the same was sought to be withdrawn. 21.2. Therefore, this Court held that it was not possible in law to apply the principle of estoppel/ promissory estoppel to the facts of the present controversy. 21.3. As regards the financial viability of the 1999 Scheme, this Court held thus: **84.** Moving to the next contention. A serious dispute has been raised before us, in respect of the financial viability of the 1999 Scheme. Insofar as the appellant State is concerned, it was asserted on its behalf, that a HighLevel Committee was constituted by the Finance Department of the State Government on 21-1-2003. The said committee comprised of Managing Directors of the public sector undertakings and corporations concerned. The task of the High-Level Committee was to examine the financial viability of the 1999 Scheme. The said committee submitted a report dated 28-10-2003, 28 returning a finding that the 1999 Scheme was not financially viable, and would not be self-sustaining. It is, therefore, that a tentative decision was taken by the State Government, to withdraw the 1999 Scheme. **85.** To determine the modalities for withdrawing the 1999 Scheme, on the basis of the above report, the matter was jointly examined by the Finance Department and the Law Department of the State Government, wherein, in consonance with the advice tendered by the Law Department it was decided that the 1999 Scheme should not be withdrawn retrospectively. Based on the advice of the Law Department, it was finally decided that those who had commenced to draw pensionary benefits under the 1999 Scheme, would not be deprived of the same. And that, the 1999 Scheme should be withdrawn prospectively, for those whose right to receive pensionary benefits had not arisen, as they had not yet retired from service. In the above view of the matter, it was contended on behalf of the State Government that the action of the State Government in issuing the Repeal Notification dated 2-12-2004, was certainly not an arbitrary exercise of the power of administrative review. It was submitted that the same was based on two factors. Firstly, the financial unviability of the scheme. And secondly, those who had already commenced to draw pensionary benefits under the 1999 Scheme, were not to be affected. It was, therefore, pointed out that the 29 classification made by the State Government was reasonable and justifiable in law, and it also had a nexus to the object sought to be achieved. **86.** It is in the above scenario that the legality and justiciability of the 1999 Scheme, will have to be examined. The submission advanced at the behest of the respondent employees was that it was not permissible for the State Government to advance any such plea, because the State Government must be deemed to have examined the financial viability of the Scheme, before the 1999 Scheme was given effect to. And that, it does not lie in the mouth of the State Government, after giving effect to the 1999 Scheme, to assert that the 1999 Scheme was not financially viable. It was insisted that even if data pertaining to the financial viability of the Scheme, as was sought to be relied upon was correct, financial deficiencies, if any, could be catered to by the State Government, from the vast financial resources available to it. And further, that the 1999 Scheme in terms of the determination rendered by the High Court, even if permitted to be repealed, should not impact the rights of the respondent employees, towards pensionary benefits. **87.** We have given our thoughtful consideration to the above contention. It is not possible for us to accept the instant contention, advanced on behalf of the 30 respondent employees. The calculations projected at the behest of the State Government, to demonstrate the financial unviability of the Scheme, have not been disputed. The same have been detailed in paras 10 and 11 above. The basis thereof, projected by the High-Level Committee, admittedly constitutes the rationale for issuing the Repeal Notification dated 02-12-2004. We are of the view that the consideration at the hands of the State Government was conscious and pointed, and was supported by facts and figures. It is apparent that out of 17 corporations/boards who were invited to express their views on the issue, only 7 had actually done so. It is not the case of the respondent employees that any one of those who had expressed their views, contested the fact that the pension scheme was not self-financing. Those who expressed their views affirmed that the pension scheme could be salvaged only with government support. Those who did not express their views, obviously had no comments to offer. The position projected by the State Government, therefore, cannot be considered to have been effectively rebutted. Certain facts and figures, have indeed been projected, on behalf of the respondent employees. These have been recorded by us in paras 60 and 61. Financial calculations cannot be made casually, on a generalised basis. In the absence of any authenticity, and that too with reference to all the 20 corporate entities specified in Schedule I of the 1999 31 Scheme, the projections made on behalf of the respondent employees, cannot be accepted, as constituting a legitimate basis, for a favourable legal determination. Since the respondent employees have not been able to demonstrate that the foundational basis for withdrawing the 1999 Scheme, was not premised on any arbitrary consideration, or alternatively, was not founded on any irrelevant consideration, it is not possible for us to accept the contention that the withdrawal of the 1999 Scheme, was not based on due consideration, or that, it was irrational or arbitrary or unreasonable. We are also satisfied that the action of the State Government, in allowing those who had already started earning pensionary benefits under the 1999 Scheme, was based on a legitimate classification, acceptable in law. In the above view of the matter, the action of the State Government cannot be described as arbitrary, and as such, violative of Article 14 of the Constitution of India. We are also satisfied in concluding that the understanding of the State Government (which had resulted in introducing the 1999 Scheme) on being found to be based on an incorrect calculation, with reference to the viability of the corpus fund (to operate the 1999 Scheme), had to be administratively reviewed. And that the State Government's determination in exercising its power of review, was well founded. 32 21.4. Having held so, this Court accepted the contention canvassed on behalf of the State that budgetary allocations are a matter of policy decision and that the High Court should not have transferred the financial liability of the Corporation to run the 1999 Scheme to the State Government. This Court held as follows: **88.** It is also not possible for us to accept that any court has the jurisdiction to fasten a monetary liability on the State Government, as is the natural consequence, of the impugned order passed by the High Court, unless it emerges from the rights and liabilities canvassed in the lis itself. Budgetary allocations, are a matter of policy decisions. The State Government while promoting the 1999 Scheme, felt that the same would be self-financing. The State Government never intended to allocate financial resources out of State funds, to run the pension scheme. The State Government, in the instant view of the matter, could not have been burdened with the liability, which it never contemplated, in the first place. Moreover, it is the case of the respondent employees themselves, that a similar pension scheme, floated for civil servants in the State of Himachal Pradesh, has also been withdrawn. The State Government has demonstrated its incapacity, to provide the required financial resources. We are, therefore, of 33 the view that the High Court should not (as it could not) have transferred the financial liability to run the 1999 Scheme, to the State Government. Similar suggestions made by the corporate bodies concerned, cannot constitute a basis for fastening the residuary liability on the Government. 21.5. This Court rejected the contention of the employees that they should be treated similarly like government employees. Claim for parity with government employees was held to be wholly misconceived. Thereafter, this Court held that the State Government had the competence to repeal the 1999 Scheme. By doing so, the State Government had not curtailed the right of the employees to receive pension; they would continue to receive pension under the erstwhile pension scheme but would not get the additional benefits under the 1999 Scheme. 22. Though learned senior counsel for the petitioners had argued that the judgment in _Rajesh Chander Sood_ (supra) is _per incuriam,_ we are unable to hold so. This Court had given elaborate reasons while allowing the civil appeal of the State thereby reversing the judgment of the High Court, including 34 upholding the cut-off date of 02.12.2004. Merely because according to the petitioners the reasons given in the judgment while accepting the stand of the State may not be in sync with previous decisions, it cannot be said to be a judgment rendered _per incuriam._ The concept of _per incuriam_ is too well settled to warrant a detailed analysis here. The judgment rendered in _Rajesh Chandra Sood_ (supra) by no stretch can be said to have ignored any binding precedent. Hence, the same cannot be said to be a judgment rendered _per incuriam._ 23. From the above, it is evident that the contentions that are being raised now were all advanced before this Court in _Rajesh Chander Sood_ (supra) and those were all adjudicated. It is not open for the petitioners to once again seek the same reliefs as was sought in the earlier round of litigation which were negatived by this Court. High Court had allowed the claim of the employees (petitioners of the previous round and similarly situated employees like the present petitioners). When this Court had set aside the judgment of the High Court, it is evident that the claim of not only those petitioners but similarly situated employees (like the present petitioners) were 35 also negatived. Therefore, there cannot be any challenge either directly or collaterally to the decision of this Court in _Rajesh Chander Sood_ (supra) in a proceeding under Article 32 of the Constitution of India. 24. In _Naresh Shridhar Mirajkar Vs. State of Maharashtra[6]_ , a nine-Judge Bench of this Court considered the question as to whether a judicial order passed by the High Court prohibiting publication in newspapers of evidence given by witnesses pending the hearing of the suit was amenable to be corrected by a writ of certiorari under Article 32(2) of the Constitution of India. Other issues were also gone into by this Court but that may not be relevant for the purpose of the present discourse. After deliberating on the facts and law, this Court opined that validity or propriety of such an order passed by the High Court could not be raised in writ proceedings taken out for the issuance of a writ of certiorari under Article 32. This Court declared that it was impossible to accept the argument of the petitioners that judicial orders passed by the > 6 AIR 1967 SC 1 36 High Courts in or in relation to proceedings pending before them are amenable to be corrected by this Court under Article 32 of the Constitution of India. 25. This Court in _Sub-Inspector Sadhan Kumar Goswami Vs. Union of India[7]_ , considered a writ petition filed under Article 32 of the Constitution of India seeking to reopen a judgment of this Court rendered under Article 136 of the Constitution of India. After an analysis of the facts, this Court declared that merely because the petitioners were not parties to the previous decision, they could not file a writ petition under Article 32 of the Constitution of India. In fact, this Court took serious exception to the filing of such writ petitions. 26. _Rupa Ashok Hurra Vs. Ashok Hurra[8]_ was a case where a Constitution Bench of this Court considered the question as to whether a writ petition under Article 32 of the Constitution of India can be maintained to question the validity of a judgment of this Court after the petition for review of the said judgment was dismissed. While deliberating upon the said > 7 (1997) 2 SCC 225 > 8 (2002) 4 SCC 388 37 question, this Court referred to its previous decision in _A.R. Antulay Vs. R.S. Nayak[9]_ where a seven-Judge Bench of this Court held that an order of this Court was not amenable to correction by issuance of a writ of certiorari under Article 32 of the Constitution of India. _Rupa Ashok Hurra_ (supra), of course, went on to hold that to prevent abuse of its process and to cure gross miscarriage of justice, this Court may reconsider its judgment(s) in exercise of its inherent power. For that, this Court provided for a curative jurisdiction postdismissal of review petition by filing curative petition. In the present proceedings, we are not required to delve into the contours of curative jurisdiction. 27. This Court in _Omprakash Verma Vs. State of Andhra Pradesh[10]_ reiterated the well-settled principle that a judgment of the Supreme Court cannot be collaterally challenged on the ground that certain points had not been considered. 28. Again, in the case of _Indian Council for Enviro-Legal Action Vs. Union of India[11]_ , this Court held that a writ petition > 9 (1988) 2 SCC 602 > 10 (2010) 13 SCC 158 > 11 (2011) 8 SCC 161 38 filed under Article 32 of the Constitution of India assailing the correctness of a decision of the Supreme Court on merits or seeking reconsideration is not maintainable. Referring to its earlier decision in _Khoday Distilleries Ltd. Vs. Registrar General, Supreme Court of India[12]_ , the Court held that reconsideration of the final decision of the Supreme Court after review petition is dismissed by way of a writ petition under Article 32 of the Constitution of India cannot be sustained. Judgment and order of this Court passed under Article 136 of the Constitution of India is not amenable to judicial review under Article 32 of the Constitution. 29. Thus, law is well settled that a decision rendered by this Court, be it at the stage of special leave petition or post grant of leave while exercising jurisdiction under Article 136 of the Constitution of India, cannot be assailed directly or collaterally under Article 32. Remedy of an aggrieved litigant is to file for review. If the grievance persists even thereafter, he may invoke the curative jurisdiction subject to compliance of the requirements of such jurisdiction. But certainly it is not > 12 (1996) 3 SCC 114 39 open for him to file a writ petition under Article 32 of the Constitution of India seeking the same relief. 30. Therefore, it is crystal clear that the present writ petition is thoroughly misconceived and is liable to be dismissed. However, before parting with the record, we would like to emphasize and reiterate the principle of finality of an adjudication process. Finality of a _lis_ is a core facet of a sound judicial system. Litigation which had concluded or had reached finality cannot be reopened. A litigant who is aggrieved by a decision rendered by this Court in a special leave petition or in a civil appeal arising therefrom can seek its review by invoking the review jurisdiction and thereafter through a curative petition. But such a decision cannot be assailed in a writ proceeding under Article 32 of the Constitution of India. If this is permitted, then there will be no finality and no end to litigation. There will be chaos in the administration of justice. 31. In _Green View Tea & Industries Vs. Collector[ 13]_ , this Court expressed the view that finality of an order of the Supreme Court should not lightly be unsettled. This salutary > 13 (2002) 1 SCC 109 40 principle was reiterated by this Court in _Indian Council for_ . _Enviro-Legal Action Vs. Union of India[14]_ 32. Thus, having regard to the discussions made above, we are of the unhesitant view that the present writ petition filed under Article 32 of the Constitution of India is wholly misconceived. The decision of this Court in _Rajesh Chander Sood_ (supra) is clearly binding on the petitioners. That being the position, there is no merit in the writ petition which is accordingly dismissed. 33. Considering the fact that petitioners are retired employees and senior citizens, we refrain from imposing any cost. **..……………………………J. [SURYA KANT]** **……………………………..J. [DIPANKAR DATTA]** **……………………………..J. [UJJAL BHUYAN]** **NEW DELHI; APRIL 16, 2025.** > 14 (2011) 8 SCC 161 41
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.