SANGHAR ZUBER ISMAIL v. MINISTRY OF ENVIRONMENT, FORESTS AND CLIMATE CHANGE AND ANOTHER
Case Synopsis & Summary
This Civil Appeal challenges the grant of an environmental clearance (EC) dated 5 January 2021 for expanding a refinery’s capacity at Vadinar, Gujarat, from 20 MMTPA to 46 MMTPA. The appellant approached the National Green Tribunal (NGT) alleging that the expansion would cause adverse impacts on the marine environment, including mangroves and marine biology. The NGT, after considering the EIA/EMP study prepared by CSIR–NEERI and the second respondent’s assurance that EC conditions would be complied with and mitigation measures implemented, concluded there was no ground to interfere with the EC but directed safeguards and EC compliance, and even constituted a three-member expert committee. The appellant contends that the NGT failed to exercise its appellate jurisdiction independently, relying on the proponent’s statements rather than conducting an independent appraisal of the substantive grounds, and that delegating adjudicatory tasks to committees undermines the tribunal’s function. The Supreme Court held that the NGT’s appellate function requires an independent examination of the grounds of challenge; reliance on statements by the project proponent and the use of committees cannot substitute the NGT’s own adjudicatory decision. The court remanded and remitted the matter for fresh disposal by the NGT, keeping rights and contentions open and disposing of any pending applications.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Dr Dhananjaya Y. Chandrachud
- Mr. Justice MR Shah
- Justice Hima Kohli
- Judgment Date
- 2021-08-31
- Court Decision / Holding
- Appeal allowed. The impugned order dated 8 June 2021 is set aside. Appeal No. 5/2021 (WZ) is restored to the file of the NGT for disposal afresh. All the rights and contentions of the parties on the merits are kept open. Pending applications, if any, stand disposed of.
- Final Disposition
- Appeal allowed; matter remanded to the National Green Tribunal for disposal afresh with the parties’ rights and contentions preserved; pending applications disposed of.
Parties to the Case
Appellants / Petitioners
- Sanghar Zuber Ismail
Respondents
- Ministry of Environment, Forests and Climate Change
- Another
Legal Representation & Advocates
Counsels for Petitioners
- • Purvish Jitendra Malkan
- • Ms. Dharita P Malkan
- • Ms. Deepa Gorasia
- • Alok Kumar
- • Ms. Nandini Chhabra
- • Ms. Bhavna Sarkar
- • Ms. Khushboo Vinodray Malkan
Counsels for Respondents
- • Dhruv Mehta, Sr. Adv.
- • Somiran Sharma, Advs.
Provisions of Law Cited
Legal Doctrines & Maxims
- Adjudicatory function cannot be delegated to committees or expert committees; the decision must be that of the NGT
- NGT is an expert adjudicatory authority under an Act of Parliament; its discharge of functions cannot be obviated by tasking committees to carry out a function which vests in the tribunal
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that the expansion poses serious hazards to marine biology and mangroves, and that the NGT’s appellate function requires independent consideration of substantive grounds of challenge. It is argued that relying on a statement by the project proponent and creating a committee does not substitute for the NGT’s own adjudicatory duty; the appellant’s materials, including the EIA copy, should be independently evaluated, and the matter requires a fresh, merits-based assessment by the tribunal.
Contentions of Respondents
The respondents contend that the EC conditions would be duly complied with and mitigation measures implemented to protect mangroves and marine life. They emphasize the existence of the EIA/NEERI study and argue that safeguards were already contemplated; a three-member committee was constituted to ensure compliance, and there is no continuing grievance against the project’s functioning. The respondents urge deference to the EC and the tribunal’s limited scope to ensure safeguards while preserving the ongoing project’s approvals.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
SANGHAR ZUBER ISMAIL v. MINISTRY OF ENVIRONMENT, FORESTS AND CLIMATE CHANGE AND ANOTHER
Related Decisions & Precedents from Supreme Court of India (2021)
HARI OM @ HERO v. STATE OF U.P.
This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.
INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL
This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.
Hasmat Ali v. Amina Bibi & ORS.
This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.
Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.
This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.