Samir Narain Bhojwani v. M/s. Aurora Properties and Investments and Anr.

Case / Petition Number:
Civil Appeal No. 7079 of 2018

Case Synopsis & Summary

Samir Narain Bhojwani appeals a Bombay High Court order in a complex property dispute arising from development agreements relating to a Versova land parcel. Respondent No.1, Aurora Properties and Investments, along with Respondent No.2, executed multiple development and tripartite agreements related to the Versova Link Road property, with the Andheri Kamgar Nagar Cooperative Housing Society involved. The dispute centers on allocation of built flats and car parking spaces under the Development Agreement dated 22 September 1999, the Agreement for Development dated 10 March 2003, and a Tripartite Agreement dated 11 September 2009, with later Settlement Agreement dated 4 November 2016 and Consent Terms dated 25 September 2017 between Respondent No.1 and Respondent No.2. Respondent No.1 filed a suit seeking specific performance and interim relief, while the appellant contended that his obligations were limited to the terms of his direct agreement with Respondent No.2 and that the inter se settlement cannot bind him. The Single Judge granted interim relief directing delivery of 8 flats and 16 parking spaces, which was upheld by the Division Bench. The Supreme Court held that interim mandatory relief cannot be granted against a party not bound by the inter se agreements, and that the High Court erred by moulding relief at an interlocutory stage. It revived the ad-interim order but clarified it would operate only until final disposal. The decision hinges on interim-relief doctrine and moulding of reliefs, distinguishing Gaiv Dinshaw Irani while clarifying its limits.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Dipak Misra
  • A.M. Khanwilkar
  • Dr. D.Y. Chandrachud
Judgment Date
2018-08-21
Court Decision / Holding
The appeal is allowed; the High Court’s judgment and order are set aside. The Supreme Court revives the ad-interim order dated 3 December 2012, as corrected on 17 December 2012, which shall operate until the disposal of the suit or until modified by the High Court. No costs. The decision clarifies that interim mandatory injunctions cannot be used to impose obligations on a party not bound by inter se agreements and that moulding of relief at an interlocutory stage is generally inappropriate when the party is not a party to the agreement providing for such relief.
Final Disposition
Appeal allowed; High Court order set aside; ad-interim order revived; No costs.

Parties to the Case

Appellants / Petitioners

  • Samir Narain Bhojwani

Respondents

  • M/s. Aurora Properties and Investments
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Mukul Rohatgi, Senior Advocate

Counsels for Respondents

  • • Respondent No.1: Mr. Shyam Divan, Senior Advocate
  • • Respondent No.2: Mr. Mahendra K. Ghelani

Provisions of Law Cited

Arbitration and Conciliation Act, 1996Section 8 of the Arbitration and Conciliation Act, 1996Section 11 of the Arbitration and Conciliation Act, 1996Section 9 of the Arbitration and Conciliation Act, 1996Order XXXIX, Civil Procedure Code, 1908Order XL, Rule 1, Civil Procedure Code, 1908

Legal Doctrines & Maxims

  • Moulding of relief (Gaiv Dinshaw Irani and Others v. Tehmtan Irani and Others)
  • Guidelines for interim mandatory injunction: (i) prima facie strong case; (ii) irreparable or serious injury; (iii) balance of convenience in favour of the applicant
  • Status quo ante restoration principle (interim mandatory injunction) described in Dorab Cawasji Warden v. Coomi Sorab Warden and Others
  • Interlocutory relief standards from Halsbury's Laws of England (as cited)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the Consent Terms dated 25 September 2017 between Respondent Nos. 1 and 2 were inter se arrangements the appellant was not a party to; therefore, directing the appellant to deliver 8 flats and 16 parking spaces would bind him to obligations not arising from his agreements with Respondent No.2 (the 2003 Development Agreement) and would amount to moulding relief at an interlocutory stage. The arbitration proceedings under the 2003 Agreement and any pending issues between Respondent Nos. 1 and 2 should be resolved without imposing new liabilities on the appellant. The High Court’s reliance on the ad-interim order and the principle of moulding of relief misapplied Gaiv Dinshaw Irani and ignored that the appellant’s rights flow from his own agreement and the Tripartite Agreement, not from inter se settlements. The appellant further argues that handing over flats now would prejudice him if Respondent No.2 ultimately fails to discharge its obligations, and that the final relief must be determined in the main suit, not by interim orders.

Contentions of Respondents

Respondent No.1 and Respondent No.2 submitted that the Settlement Agreement and Consent Terms inter se between the two respondents created a final frame within which Respondent No.1’s entitlement to specific flats and parking spaces could be satisfied, and that the interim relief was a legitimate exercise to prevent third-party rights from being created during ongoing litigation. They argued that the main development and tripartite agreements underpin the relief sought, and that Respondent No.2’s failure to discharge its obligations should not defeat Respondent No.1’s rights; the inter se arrangements between Respondent Nos. 1 and 2 bind the appellant only to the extent of his own agreements with Respondent No.2. They maintained that moulding the relief at interim stage is permissible in appropriate circumstances to do complete justice and to preserve rights under the Settlement/Consent terms while arbitration progresses.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Gaiv Dinshaw Irani and Others v. Tehmtan Irani and Others(2014) 8 SCC 294DistinguishedThe Court cites Gaiv Dinshaw Irani to support moulding of relief but distinguishes its applicability to the present interlocutory context, finding it inapposite.
Dorab Cawasji Warden v. Coomi Sorab Warden and Others(3) (1990) 2 SCC 117PositiveUsed to articulate the criteria for granting interim mandatory injunctions and to emphasize status quo restoration where warranted.
Metro Marins and Another v. Bonus Watch Co. (P) Ltd. and Others(2004) 7 SCC 478PositiveCited for the guidelines on interim relief and for principled exercise of discretion in granting injunctions.
Kishore Kumar Khaitan and Another v. Praveen Kumar Singh(2011) 6 SCC 73PositiveCited in the context of interim relief principles and judicial discretion.
Purshottam Vishandas Raheja and Another v. Shrichand Vishandas Raheja (Dead) through LRS. and Others(2011) 6 SCC 73PositiveCited for the doctrine on interim relief and restoration principles in the context of family/estate-like disputes and partial relief.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,871 words•~27 min read

In The Court Record

Samir Narain Bhojwani v. M/s. Aurora Properties and Investments and Anr.

1 ## **REPORTABLE** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **CIVIL APPEAL NO. 7079 OF 2018** (Arising out of SLP (Civil) No.18465/2018) Samir Narain Bhojwani …..Appellant(s) :Versus: M/s. Aurora Properties and Investments and Anr. ....Respondent(s) ## **J U D G M E N T** ## **A.M. Khanwilkar, J.** **1.** The captioned appeal challenges the judgment and order passed by the Division Bench of the Bombay High Court dated 9[th] July, 2018 in Commercial Appeal No.173 of 2017, whereby the Division Bench dismissed the appeal filed by the appellant and upheld the decision of the learned Single Judge dated 9[th] Signature Not Verified October, 2017 in Notice of Motion No.147 of 2013, wherein the Digitally signed by DEEPAK GUGLANI Date: 2018.08.21 11:33:22 IST Reason: learned Single Judge _inter alia_ passed a mandatory 2 interlocutory injunction directing the appellant to hand over 8 (eight) flats along with 16 (sixteen) car parking spaces under the Settlement Agreement dated 4[th] November, 2016 and Consent Terms dated 25[th] September, 2017 between respondent Nos.1 and 2 _inter partes_ . **2.** The relevant facts are as follows: Respondent No.1/plaintiff was appointed by one Andheri Kamgar Nagar Cooperative Housing Society Ltd. (for short, „ **the Society’** ) under a Development Agreement dated 6[th] October, 1996 as a developer under the Slum Development/ Rehabilitation Scheme to develop the suit property in question, being a plot of land situated at Versova Link Road, Taluka Andheri and bearing Survey No. 139, City Survey No. 1319 (Part) admeasuring 8892 sq. mts. or thereabouts as per Indenture of Lease dated 31[st] March, 1993 and 9402 sq. mts. as per City Survey Records. One part of the suit property was for constructing tenements free of charge for project-affected persons and the balance property could be used to develop and sell the balance FSI. Respondent No.1 then executed an 3 Agreement for Sub-Development dated 22[nd] September, 1999 with respondent No.2/defendant No.1, transferring the benefits of development rights in the suit property, with the consent of the aforementioned Society, to respondent No.2 after keeping aside 15,000 sq. ft. for itself i.e. respondent No.1. **3.** Subsequently, respondent No.2 executed an Agreement for Development dated 10[th] March, 2003 with the appellant/defendant No.2, whereunder the appellant would be entitled to 55% of the total area available for free sale buildings and car parking in the suit property and respondent No.2 retained 45% of the total area available for construction of free sale buildings and car parking by utilizing FSI which may be available on the suit property as per the Slum Rehabilitation Scheme. This agreement was entered into without the consent of respondent No.1 and hence, all three parties executed a Tripartite Agreement dated 11[th] September, 2009, referencing the previous agreements of 6[th] October, 1996 and 22[nd] September, 1999 wherein respondent No.1 was entitled to an area of 22,500 sq. ft., an increase from its earlier 4 agreed upon 15,000 sq. ft., which would be allocated out of the 45% share due to respondent No. 2 **4.** Disputes arose during the construction of the building, which resulted in respondent No.1 filing a Commercial Suit No. 62 of 2013 against respondent No.2 and the appellant _inter alia_ seeking specific performance of the Development Agreement dated 22[nd] September, 1999, read with the Tripartite Agreement dated 11[th] September, 2009, including handing over constructed area of 22,500 sq. ft. in the free sale buildings along with proportionate car parking space, in the form of 12 (twelve) flats in Wings „A‟ and „B‟ of the building „Bay – View‟ constructed on the suit property and 24 (twenty four) car parking spaces. Respondent No.1 also took out Notice of Motion No. 147 of 2013 for interim reliefs, seeking to restrain respondent No.2 and the appellant from creating third party rights in the suit property without first handing over possession of the 22,500 sq. ft. constructed area in the form of flats and parking spaces. Respondent No. 1 alleged that this interim relief was necessitated by the fact that its advocate 5 had conducted a search in the sub-registrar‟s office and found a mortgage deed executed by the appellant in favour of a third party with respect to 12 flats and 24 parking spaces in the building „Bay–View‟ and that it apprehended that the appellant would sell or create third party rights in respect of the said flats. The alleged mortgage deed itself was not produced by respondent No.1 on the ground that it had applied for a copy of the same but was yet to receive it. Respondent No.1 also sought to appoint a Court Receiver to take charge of the premises in the suit property comprising its 22,500 sq. ft. constructed area. An ad-interim, consent order was passed on 3[rd] December, 2012, in the said Notice of Motion No. 147 of 2013, whereby respondent No. 2 and the appellant agreed to not dispose of or create third party rights in respect of 8 flats in the completed Wings „A‟ and „B‟ of the building and 4 flats in the under-construction Wing „C‟ of the building, totaling 12 flats. **5.** The parties filed their respective replies and rejoinders in the suit and notice of motion. The appellant‟s stance was that 6 he had completed his contractual obligations and offered respondent No.2 its entitlement of 45% area in the constructed buildings but respondent No.2 had failed to take possession of the same. The subsequent delay in construction of Wing „C‟ of the building was due to the failure of respondent No.2 to obtain a Commencement Certificate for Wing „C‟, resulting in losses to the appellant. Owing to this breach committed by respondent No.2, it was no longer entitled to its 45% share in the constructed area and as a consequence, respondent No.1 was not entitled to its 22,500 sq. ft. area which could only be claimed out of the respondent No.2‟s entitlement. **6.** The appellant then took out Notice of Motion No. 540 of 2013, seeking to refer the suit to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996 (“ **the Arbitration Act** ”) and Arbitration Application No. 86 of 2013, seeking to appoint an arbitrator under Section 11 of the Arbitration Act. Both these proceedings were rejected by the High Court vide its order dated 30[th] September, 2014 on the ground that while the Development Agreement of 22[nd] September, 1999 between 7 respondent Nos.1 and 2 contained an arbitration clause and similarly, the Agreement of 10[th] March, 2003 between the appellant and respondent No.2 also contained an arbitration clause, however, the Tripartite Agreement of 11[th] September, 2009 itself did not contain an arbitration clause and that a mere reference made in the Tripartite Agreement to the previous agreements would not make the arbitration clauses therein part of the Tripartite Agreement. The appellant challenged that decision right upto this Court in SLP (Civil) No. 2235 of 2015, which stood rejected. **7.** The appellant also initiated proceedings under Section 9 of the Arbitration Act against respondent Nos.1 and 2 before the High Court. The High Court refused to grant any relief in the petition filed under Section 9 of the Arbitration Act. The appellant then withdrew the Section 9 proceedings and initiated arbitration solely against respondent No. 2 under the Agreement dated 10[th] March, 2003. In the said arbitration proceedings, respondent No.2 filed an application for interim reliefs under Section 17 of the Arbitration Act _inter alia_ 8 seeking specific performance of the agreement of 10[th] March, 2003 including possession of its entire 45% share of flats in the buildings constructed on the suit property. Respondent No.2 contended that the application was necessitated by the fact that the appellant had violated the terms of the 10[th] March, 2003 Agreement and had created third-party rights in respect of his 55% entitlement in the suit property, without first providing respondent No.2 with the occupation and possession of its 45% entitlement in the suit property as set out in the said Agreement. Respondent No.2 also submitted that the appellant had deposited a refundable amount of Rs.4 crore as part of his obligation under the Agreement but that refund of the said deposit was not, in any way, connected with handing over of the respondent No.2‟s entitlement of flats. In any event, respondent No.2 had offered to refund the said deposit in exchange for possession of the flats due to it, which the appellant had refused. **8.** By an interim order dated 12[th] October, 2016, the sole arbitrator made _prima facie_ observations that construction of 9 Wing „C‟ in the building situated on the suit property had been delayed owing to respondent No.2‟s failure to obtain the Commencement Certificate for the same. Further, respondent No.2 had allowed the appellant to construct only 88 flats so far, which worked out to 72% of the total area to be constructed. On that basis, the arbitrator was of the opinion that respondent No.2 could not receive its entire 45% share in the constructed area of 88 flats, which worked out to 31.6 flats, but instead, would receive 72% of its 45% share which worked out to 28.5 flats. From these 28.5 flats, 12 flats were to be kept aside for respondent No.1 as directed in the High Court‟s ad-interim order dated 3[rd] December, 2012 and thus, respondent No.2 was entitled to 16.5 flats. Out of 16.5 flats, the appellant was directed to hand over possession of 16 flats to respondent No. 2, after which respondent No.2 would refund the deposit given by the appellant in respect of such flats. The remaining amount of respondent No.2‟s entitlement in one flat would be discharged by both respondent No.2 and the appellant jointly disposing of the said flat at a mutually agreed price. 10 **9.** This order was challenged by the appellant, first before the High Court and having failed there, before this Court in SLP (Civil) No. 35563 of 2016. This Court, vide order dated 14[th] December, 2016, refused to set aside the High Court‟s decision but recorded that the observations made by the sole arbitrator and High Court would not influence the final outcome of the matter. **10.** Reverting to Notice of Motion No.147 of 2013 in the suit filed by respondent No.1, it was then finally heard and judgment reserved. Pending the decision, however, respondent Nos. 1 and 2 filed Consent Terms dated 25[th] September, 2017 according to which respondent No.2 agreed to hand over an additional 8 (eight) flats along with 16 (sixteen) parking spaces to respondent No.1 in full and final settlement of the Development Agreement of 22[nd] September, 1999 and the Tripartite Agreement of 11[th] September, 2009. 11 **11.** The Learned Single Judge vide decision dated 9[th] October, 2017 in Notice of Motion No.147 of 2013, relied upon the interim order of 12th October, 2016 passed by the sole arbitrator, terming it as an interim award. The Single Judge was of the opinion that the apportionment of flats done by the arbitrator had become _res judicata_ . The arbitrator‟s finding, that respondent No.2 was entitled to 28.5 flats, had attained finality since the appeals to the High Court and this Court had been rejected. Further, from these 28.5 flats, 12 flats along with 24 parking spaces formed part of respondent No.2‟s entitlement, which, in turn, belonged to respondent No.1, and had been kept out of the scope of the arbitration since there was an ad-interim order of the High Court operating in that regard. Possession and keys of the remaining 16 flats out of the 28.5 flats had been handed over by the appellant to respondent No.2, for which the appellant‟s deposit had also been refunded by respondent No.2, as directed by the arbitrator. 12 **12.** The Single Judge further opined that even if respondent No.2 was ultimately held liable to compensate the appellant for damages, the same could not be recovered from the said 12 flats as these flats were ultimately and rightfully due to respondent No.1 (original plaintiff) and out of bounds for the appellant. The Single Judge rejected the appellant‟s argument that since respondent No.1 claimed through respondent No.2, any breach by respondent No.2 would automatically affect the entitlement of respondent No.1 as well. **13.** The question as to whether respondent No.2 was obligated to hand over possession of 8 flats to respondent No.1 as per the settlement agreement dated 4[th] November, 2016 and the Consent Terms dated 25[th] September, 2017 and whether the appellant had to hand over the keys of the said flats to respondent No.1, were answered by the Single Judge in the affirmative, with the finding that respondent No.2 was the rightful owner of the balance 39.6 flats, including the 8 flats, out of the 88 constructed flats, and that the appellant had no rights over the same. The point of respondent No.2 being the 13 rightful owner of the 8 flats was based on the following aspects: - a. Respondent No.2 alone was entitled to develop the suit property as the letter of intent from the SRA was in favour of respondent No.2; - b. The appellant was a contractor who had been given the right to develop the suit property and his rights flowed from respondent No. 2; - c. Respondent No.2 had retained its right to construct 45% of the total area available and the appellant had even executed a Power of Attorney (POA) in favour of respondent no.2 entitling respondent No.2 to execute agreements for sale on ownership basis, leave and license, etc. for the flats and car parking spaces in the suit property, including the said 8 flats and similarly, respondent No.2 had executed a POA in favour of the appellant allowing the appellant to dispose of his flats and car parking spaces which he was entitled to receive as part of his 55% share. This was even conceded to by the appellant in the arbitration proceedings and in light of the 14 same, the appellant was estopped from objecting to respondent No.2 handing over 8 flats to respondent No.1; **14.** On the issue of the appellant not being the owner of the said flats, the Single Judge recorded that merely because the appellant had constructed the said flats and had the keys to the same, he could not be said to be the owner of the flats and he could not prevent respondent No.2 from handing over possession of the 8 flats to respondent No.1. The appellant merely had derivative rights over the suit property, flowing from respondent No.1 through respondent No.2, and any dispute between respondent No.2 and the appellant could not, in any way, affect the right of respondent No.1 over the suit property. The Consent Terms dated 25[th] September, 2017 between respondent Nos.1 and 2 clearly set out that respondent No.2 was obligated to hand over 8 flats to respondent No.1 and the right of respondent No.1 over the said flats was paramount to the rights of the other parties. 15 **15.** The Single Judge thus directed the appellant, by a mandatory order, to hand over keys and possession of the said 8 flats to respondent No.1 along with 16 parking spaces, recording that he had moulded the reliefs originally sought by respondent No.1 in the changed circumstances of the case and in order to shorten the litigation and do complete justice. **16.** Aggrieved by the Single Judge‟s decision, the appellant challenged the said decision before the Division Bench of the High Court in Commercial Appeal No.173 of 2017. It was urged on behalf of the appellant that respondent Nos.1 and 2 had entered into the Consent Terms dated 27[th] September, 2017 with a view to defeat the appellant‟s claim. Unless respondent No.2 completed its entire obligations with respect to the building still under construction in the suit property, respondent No.1 was not entitled to receive its 8 flats as per the Consent Terms. The appellant further contended that the handing over of 8 flats to respondent No.1 was, in effect, a final relief since nothing further remained in the suit and the interim order of the Single Judge was in fact a final order and 16 that the confirmation of the arbitral tribunal‟s order had no effect on the proceedings before the Single Judge. These arguments were countered by respondent No. 1 which _inter alia_ submitted that the actual dispute was between the appellant and respondent No.2 and that it (respondent No.1) was being made to suffer for such dispute. Respondent No.1 contended that the main development agreement had been executed between the Society and respondent No.1 and the rights of the other parties flowed through such agreement. Hence, there was nothing wrong in the Single Judge moulding reliefs in its favour. Respondent No.2 echoed respondent No.1‟s arguments. **17.** The Division Bench by its judgment and order dated 9[th] July, 2018, upheld the mandatory direction issued by the Single Judge at an interlocutory stage and rejected the appeal, holding that the Single Judge had addressed the various issues in detail and that it was right to mould the reliefs, even at the interim stage, in light of changed circumstances in the case. The Division Bench opined that the appellant was not 17 left remediless in case respondent No.1 failed in the suit, as his remedies were kept open. **18.** We have heard Mr. Mukul Rohatgi, learned senior counsel appearing for the appellant, Mr. Shyam Divan, learned senior counsel appearing for respondent No.1 and Mr. Mahendra K. Ghelani, learned counsel appearing for respondent No.2. **19.** From the chronology of events, it is indisputable that the present appeal emanates from an interlocutory order passed by the learned Single Judge of the High Court on an application under Order XXXIX which, in turn, has been confirmed by the Division Bench. That interlocutory order has been passed in the suit filed by respondent No.1 against the appellant and respondent No.2 for the following substantive reliefs: “a) this Hon‟ble Court be pleased to declare that the suit agreement i.e. the said Development Agreement dated 22[nd] September 1999 (Exhibit “B” to the Plaint), read with the said Agreement dated 11[th] September 2009 (Exhibit “J” to the plaint), are valid, subsisting and binding between the Plaintiff and the Defendants. 18 b) this Hon‟ble Court be pleased to order and decree the specific performance of the suit agreements dated 22[nd] September 1999 (Exhibit “B” to the plaint), read with Agreement dated 11[th] September 2009 (Exhibit “J” to the plaint) including handing over to the Plaintiff constructed area of 22500 sq.ft. in the free sale buildings along with proportionate car parking space in the form of 12 flats in Wings “A” and “B” of the building “Bay –View” situated on the property described in Exhibit “A” to the plaint and 24 car parking spaces. c) In the alternative to prayer clause (b) this Hon‟ble Court be pleased to order, decree and direct the Defendants to refund a sum of Rs.75,00,000/- together with interest at 18% as set out in the Particulars of Claim at Exhibit “M” to the plaint; d) In the alternative to prayer (a) and (b) and in addition to prayer (c) above, this Hon‟ble Court be pleased order, decree and direct the Defendants to pay damages of Rs.173,47,53,425/- (Rupees One Hundred Seventy Three Crores Forty Seven Lacs Fifty Three Thousand Four Hundred Twenty Five Only) as set out in particulars of Claim at Exhibit “M” to the plaint. e) This Hon‟ble Court be pleased to pass an order of Mandatory and Permanent Injunction against the Defendants, their servants, agents, assigns and/or any other person acting through or under them from in any manner directly or indirectly dealing with or disposing of or alienating or parting with the possession of or creating third party rights in respect of the premises coming to the share of the Defendants in Wings ”A” & “B” of the building “Bay-View” situated on the property described in Exhibit “A” to the plaint without first delivering to the Plaintiff, the possession of 22500 sq.ft. constructed areas per SRA sanctioned plan with proportionate car parking space in the form of 12 flats in Wings “A” and “B” of the building “Bay –View” situated on the property described in Exhibit “A” to the plaint and 24 car parking spaces.” 19 ## **20.** During the pendency of the suit for aforementioned reliefs, respondent No.1/plaintiff filed Notice of Motion No.147/2013 for the following interim reliefs: “(a) Pending the hearing and final disposal of the present suit, this Hon‟ble Court be pleased to injunct the Defendants, servants, agents, assigns and/or any other persons acting through or under them from in any manner directly or indirectly dealing with or disposing of or alienating or parting with the possession of or creating third party rights in respect of the premises coming to the share of the Defendants in Wings “A” & “B” of the building “Bay-View” situated on the property described in Exhibit “A” to the Plaint without first delivering to the Plaintiff, the possession of 22500 sq.ft. constructed areas per SRA sanctioned plan with proportionate car parking space in the form of 12 flats in Wings “A” and “B” of the building “Bay-View” situated on the property described in Exhibit “A” to the plaint and 24 car parking spaces. (b) Pending the hearing and final disposal of the present suit, this Hon‟ble Court be pleased to appoint Court Receiver, High Court, Bombay and/or such other fit and proper person as Receiver of premises coming to the share of the Defendant No.1 in Wings “A” & “B” of the building “BayView” situated on the property described in the Exhibit “A” to the Plaint with all powers under Order XL Rule 1 of the Code of Civil Procedure Code 1908 including the power to take possession of premises coming to the share of the Defendant No.1 in Wings “A” and “B” of the building “Bay-View” situated on the property described in the Exhibit “A” to the plaint and hand over to the Plaintiff the possession of constructed area as per SRA sanctioned plan in the free sale building in the form of 12 flats in Wings “A” and “B” of the building “Bay-View” situated on the property described in Exhibit “A” to the Plaint and 24 car parking spaces. (c) ad interim reliefs in terms of prayer (a) & (b). (d) for costs of the suit; 20 (e) for such further and other reliefs as this Hon‟ble Court may deem fit and proper in the nature and circumstances of the case.” **21.** Indeed, the learned Single Judge of the High Court granted ad-interim relief on 3[rd] December, 2012 during the pendency of the Notice of Motion. The same reads thus: “Heard the Learned Senior Advocates appearing for the parties. The following order is passed by consent without going into the merits of the case and keeping all the contentions of the parties open. (i) The Defendants shall not sell, dispose of, alienate, encumber, part with possession and/or create third party rights in respect of 4 flats in Wing “A” and 4 flats in Wing “B” which flats are already constructed and occupation certificate is obtained in respect of the same. The said 8 flats are identified on the sanctioned plan which is taken on record and marked “X” for identification. (ii) The Defendants shall also not sell, dispose of, alienate, encumber, part with possession and/or create third party rights in respect of 4 flats in Wing “C”, the construction of which is in progress. The said four flats are identified on the plan tendered in Court and marked “X”. (iii) It is clarified that the above 12 flats pertain to 45 per cent share in flats of Defendant No.1 as per the agreements entered into by and between Defendant Nos.1 and 2. The Defendant No.2 has informed the Court that Defendant No.2 will be contending that Defendant No.1 is not entitled to their 45 per cent share in the flats so constructed on the ground that Defendant No.1 has allegedly not complied with their obligations under the Agreements. (iv) The Defendants shall also not sell, dispose of, alienate, encumber, part with possession and/or create third party rights in respect of the proportionate car parking spaces in respect of the above 12 flats also identified on the plan marked “X”. 21 2. Place the above Notice of Motion along with Notice of Motion (L) NO.3338 of 2012 taken out by Defendant No.2 under Section 8 of the Arbitration and Conciliation Act, 1996 for hearing and final disposal on 15[th] January, 2013.” The aforementioned order was corrected on 17[th] December, 2012 in the following terms: “This application is for speaking to the minutes of the order dated 3[rd] December, 2012. 2. In clause (i), 4 flats in Wing “A” and 4 flats in Wing “B” be read as 5 flats in Wing “A” and 3 flats in Wing “B”. Application is accordingly disposed of.” **22.** The said ad-interim arrangement continued during the pendency of Notice of Motion. However, while finally disposing of the Notice of Motion No. 147/2013, the learned Single Judge of the High Court vide judgment and order dated 9[th] October, 2017 passed a mandatory order directing the appellant to hand over 8 flats and 16 parking spaces to respondent No.1/plaintiff. For passing such mandatory order the learned Single Judge placed reliance on the decision of this Court in _**Gaiv Dinshaw Irani and Others Versus**_ 22 _**Tehmtan Irani and Others**_[1] , holding that the Courts ought to mould the relief in accordance with the changed circumstances for trying the litigation or to do complete justice. The view so taken by the learned Single Judge commended to the Division Bench. **23.** What has, however, been glossed over by the High Court is that the Settlement Agreement dated 4[th] November, 2016 and the Consent Terms dated 29[th] September, 2017 have been entered into between the respondent No.1/plaintiff and respondent No.2/defendant No.1 _inter partes_ . That could not be thrust upon the appellant/defendant No.2 who had executed a separate agreement with respondent No.2/defendant No.1. The appellant could be bound only by the agreement dated 10 March, 2003 in his favour and executed by him. Admittedly, the said agreement is the subject matter of arbitration proceedings, _inter alia_ because respondent No.2 had failed to discharge its obligation thereunder. The appellant has already parted with the > 1 (2014) 8 SCC 294 23 possession of flats to respondent No.2 in furtherance of agreement dated 10[th] March, 2003 and respondent No.1/plaintiff could be accommodated only against those flats. Asking the appellant to hand over additional 8 flats and 16 parking spaces by way of mandatory order, would be to superimpose the liability of respondent No.2/defendant No.1 on the appellant for discharging its obligation qua respondent No.1/plaintiff in relation to the agreement entered between them dated 22[nd] September, 1999 and including Settlement Agreement dated 4[th] November, 2016 and Consent Terms dated 25[th] September, 2017, to which the appellant is not a party. **24.** That apart, the learned Single Judge as well as the Division Bench have committed fundamental error in applying the principle of moulding of relief which could at best be resorted to at the time of consideration of final relief in the main suit and not at an interlocutory stage. The nature of order passed against the appellant is undeniably a mandatory order at an interlocutory stage. There is marked distinction 24 between moulding of relief and granting mandatory relief at an interlocutory stage. As regards the latter, that can be granted only to restore the status quo and not to establish a new set of things differing from the state which existed at the date when the suit was instituted. This Court in _**Dorab Cawasji Warden Versus Coomi Sorab Warden and Others** ,_[2] has had occasion to consider the circumstances warranting grant of interlocutory mandatory injunction. In paragraphs 16 & 17, after analysing the legal precedents on the point as noticed in paragraphs 11-15, the Court went on to observe as follows: “16. **The relief of interlocutory mandatory injunctions are thus granted generally to preserve or restore the status quo of the last non-contested status which preceded the pending controversy until the final hearing when full relief may be granted or to compel the undoing of those acts that have been illegally done or the restoration of that which was wrongfully taken from the party complaining** . But since the granting of such an injunction to a party who fails or would fail to establish his right at the trial may cause great injustice or irreparable harm to the party against whom it was granted or alternatively not granting of it to a party who succeeds or would succeed may equally cause great injustice or irreparable harm, courts have evolved certain guidelines. Generally stated these guidelines are: (1) The plaintiff has a strong case for trial. That is, it shall be of a higher standard than a prima facie case that is normally required for a prohibitory injunction. > 2 (1990) 2 SCC 117 25 (2) It is necessary to prevent irreparable or serious injury which normally cannot be compensated in terms of money. (3) The balance of convenience is in favour of the one seeking such relief. 17. Being essentially an equitable relief the grant or refusal of an interlocutory mandatory injunction shall ultimately rest in the sound judicial discretion of the court to be exercised in the light of the facts and circumstances in each case. Though the above guidelines are neither exhaustive nor complete or absolute rules, and there may be exceptional circumstances needing action, applying them as prerequisite for the grant or refusal of such injunctions would be a sound exercise of a judicial discretion.” (emphasis supplied) **25.** The Court, amongst others, rested its exposition on the dictum in Halsbury‟s Laws of England, 4[th] edition, Volume 24, paragraph 948, which reads thus: “A mandatory injunction can be granted on an interlocutory application as well as at the hearing, but, in the absence of special circumstances, it will not normally be granted. However, if the case is clear and one which the court thinks ought to be decided at once, or if the act done is a simple and summary one which can be easily remedied, or if the defendant attempts to steal a march on the plaintiff, such as where, on receipt of notice that an injunction is about to be applied for, the defendant hurries on the work in respect of which complaint is made so that when he receives notice of an interim injunction it is completed, a mandatory injunction will be granted on an interlocutory application.” 26 **26.** The principle expounded in this decision has been consistently followed by this Court. It is well established that an interim mandatory injunction is not a remedy that is easily granted. It is an order that is passed only in circumstances which are clear and the _prima facie_ material clearly justify a finding that the status quo has been altered by one of the parties to the litigation and the interests of justice demanded that the _status quo ante_ be restored by way of an interim mandatory injunction. (See _**Metro Marins and Another Versus Bonus Watch Co. (P) Ltd. and Others[3] , Kishore Kumar Khaitan and Another Versus Praveen Kumar Singh[4]**_ and _**Purshottam Vishandas Raheja and Another Versus Shrichand Vishandas Raheja (Dead) through LRS. and Others[5]**_ ) **27.** In the factual scenario in which mandatory order has been passed against the appellant, in our opinion, is in excess of jurisdiction. Such a drastic order at an interlocutory stage ought to be eschewed. It cannot be countenanced. - 3 (2004) 7 SCC 478 4 (2006) 3 SCC 312 5 (2011) 6 SCC 73 27 **28.** Reverting to the decision in _**Gaiv Dinshaw Irani**_ , (supra), relied upon by the High Court, the Court moulded the relief in favour of the party to the proceedings to do substantial justice whilst finally disposing of the proceedings and did not do so at an interlocutory stage. In other words, reliance placed on the principle of moulding of relief is inapposite to the fact situation of the present case. **29.** Resultantly, the invocation of principle of moulding of reliefs so also the exercise of power to grant mandatory order at an interlocutory stage, is manifestly wrong. To put it differently, while analysing the merits of the contentions the High Court was swayed away by the consent agreement between the respondents _inter partes_ to which the appellant was not a party. Thus, he could not be bound by the arrangement agreed upon between the respondents _inter se._ The appellant would be bound only by the agreement entered with respondent No.2 dated 10[th] March, 2003 and at best the tripartite agreement dated 11[th] September, 2009. The respondent No.2 having failed to discharge its obligation under 28 the stated agreement dated 10[th] March, 2003, cannot be permitted to take advantage of its own wrong in reference to the arrangement agreed upon by it with respondent No.1/plaintiff and including to defeat the claim of the appellant in the arbitration proceedings. **30.** It would have been a different matter if the High Court were to continue the ad-interim arrangement directed in terms of order dated 3[rd] December, 2012 and as corrected on 17[th] December, 2012, until the final disposal of the suit. However, by no stretch of imagination, the appellant could be directed to hand over 8 additional flats and 16 parking spaces to respondent No.1 with whom the appellant has had no independent agreement in that regard. The fact that respondent No.1 would get a right in the suit property in terms of agreement dated 22[nd] September, 1999, Settlement Agreement dated 4[th] November, 2016 and Consent Terms dated 25[th] September, 2017 with respondent No.2, cannot be the basis to set up a claim against the appellant and, especially because complying with the directions in the 29 impugned order would result in bestowing advantage on respondent No.2 who has failed to discharge its obligation under the agreement dated 10[th] March, 2003 with the appellant. **31.** In view of the above, we have no hesitation to conclude that the High Court committed manifest error and exceeded its jurisdiction in granting interlocutory mandatory injunction against the appellant. **32.** Accordingly, the impugned judgment and order passed by the High Court deserves to be set aside but while doing so, we deem it appropriate to revive the ad-interim order passed by the Single Judge of the High Court on 3[rd] December, 2012 in Notice of Motion No.147/2013 and as corrected on 17[th] December, 2012, which shall operate until the disposal of the suit or until it is modified by the High Court on account of subsequent developments, if any, as and when occasion arises. 30 **33.** While parting, we make it clear that the observations made in this judgment are only for considering the matter in issue under consideration and shall not influence the substantive proceedings pending between the parties. The same be decided on its own merits. **34.** The appeal is allowed in the aforementioned terms. No costs. .………………………….CJI. **(Dipak Misra)** …………………………..….J. **(A.M. Khanwilkar)** …………………………..….J. **(Dr. D.Y. Chandrachud)** **New Delhi; August 21, 2018.**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.