Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1996Division BenchAppeal dismissed

SAM HIRING CO. v. A.R. BHUJBAL

Case / Petition Number:
Civil Appeal No. 2503 of 1996
Neutral Citation:[1996] 1 S.C.R.

Case Synopsis & Summary

This appeal arises from an order of the Bombay High Court in W.P. No. 2745 of 1987, and concerns land acquisition under the Maharashtra Housing & Area Development Act, 1976, for City Survey No. 56. The appellant, SAM HIRING CO., is a tenant whose business operates in a shed-like structure within the survey number. The superstructure was dilapidated, prompting the Bombay Housing and Area Development Board to frame a reconstruction scheme and initiate acquisition proceedings under the Act. Notices under Section 5-A were issued to interested persons, including the appellant. The appellant contends that the tenement housing its business is not part of City Survey No. 56; it claims the shed is an independent building not liable to be demolished for acquisition. It argues that under Section 2(7) read with Section 2(9) of the Land Acquisition Act, 1894, the building in exclusive possession as a non-cess payable structure should not be acquired if the value of reconstruction is Rs. 500 per sq. m. or below, and that a certificate supporting this position has already been issued. The appellant asserts that the Land Acquisition Officer did not provide independent hearing nor call the Executive Engineer for cross-examination, violating natural justice. The respondents counter that the shed is part of City Survey No. 56 and that the L.A.O exercised administrative power under Section 5-A with due opportunity of hearing. The Division Bench of the High Court held the structure to be part of the survey and thus liable to acquisition. The Supreme Court upheld this view, concluding that natural justice was complied with and that there is no error warranting interference. The appeal is dismissed with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. RAMASWAMY
  • G.B. PATTANAIK
Judgment Date
1996-01-12
Court Decision / Holding
The appeal is dismissed. No costs.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • SAM HIRING CO.

Respondents

  • A.R. BHUJBAL and ORS.

Legal Representation & Advocates

Counsels for Petitioners

  • • S. K. Dholakia (Senior Counsel) for the Appellant

Counsels for Respondents

  • • M.L. Verma, D.N. Mishra and Sukumaran for Respondent No. 10; M.N. Shroff, Sanjay Parikh, Ms. Anita Shenoi and D.M. Nargolkar for Respondents

Provisions of Law Cited

Land Acquisition Act, 1894: Sections 2(7), 2(9), 5-AMaharashtra Housing and Area Development Act, 1976: Section 76(d)

Legal Doctrines & Maxims

  • Principle of natural justice

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that under Section 2(7) read with Section 2(9) of the Land Acquisition Act, the building occupied by the appellant constitutes a non-cess payable structure and is not liable to be demolished for reconstruction if the value of reconstruction is Rs. 500 per sq. meter or below; a certificate supporting this position has already been issued, rendering demolition and acquisition unlawful. It argues that the Land Acquisition Officer did not grant independent hearing nor summon the Executive Engineer for cross-examination, violating the principles of natural justice. It also contends that the Land Acquisition Officer was not required to elaborate on every objection in the report and that the obligation to hear objections was not properly fulfilled.

Contentions of Respondents

The respondents contend that the shed is part of City Survey No. 56; the structure is within the scope of the reconstruction scheme and is open to acquisition under the Maharashtra Act. They argue that the Land Acquisition Officer, though administrative, complied with the required hearing and considered objections, with the Executive Engineer’s report clarifying the position. They maintain that the L.A.O. was not required to conduct a full quasi-judicial hearing or cross-examination, and that the High Court’s interpretation that the building is part of City Survey No. 56 was correct.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,240 words•~6 min read

In The Court Record

SAM HIRING CO. v. A.R. BHUJBAL

A SAM HIRING CO. .. B • _)_ c D ' ., E F _v._ ## A.R. BHUJBAL AND ORS . JANUARY 12, 1996 [K. RAMASWAMY AND G.B. PATTANAIK, JJ.] _Land Acquisition Act, I 894 :_ _Sections 2(7), 2(9), 5-A-Notice under S.5-A---Plea that the tenement in_ _**ivhich business was carried on was not part o.f the survey No. which was** acquired-Independent.from that and a 11on-cess payable buildi11g-Ther4ore 11ot liable to be demolished for acquisition-Was only a tenant and the shed part_ ~f _the building--Held, it being .finding of fact no interference called_ _**for-Need to give.further opportunity a.fter Executive Engineer's report--Does not arise-No need to call the Executive Engineer.for cross-examination--Land Acquisition Officer not a judic;ial ,or quasi-judicial authority-Hence not re-** quired to elaborately deal with each of the objectio11s and submit his_ _**report-Since opportunity of hearing given, principle of natural justice com-** plied with._ CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2503 of 1996. From the Judgment and Order dated 3.2.94 of the Bombay High Court in W.P. No. 2745 of 1987. S.K. Dholakia, Mr. Manoj Wad, Ms. Usha Reddy and Ms. J.S. Wad for the Appellant. M.L. Verma, D.N. Mishra and Sukumaran, for the Respondent No. 10. M.N. Shroff, Sanjay Parikh, Ms. Anita Shenoi and D.M. Nargolkar for the Respondents. > The following Order of the Court was delivered : Leave granted. G We have heard the learned counsel on both sides. This appeal arises from the order of the Division Bench of the Bombay High Court made in Appeal No. 893/92. The facts lying in short compass are stated as under: The appellant is the tenant of the land which is a part of City Survey No. 56, which was sought to be acquired under the Maharashtra House & Area H 475 476 SUPREME COURT REPORTS [ 1996] 1 S.C.R. A B c D E Development Act. 1976, (for short, 'Act'). The superstructure in City Survey No. 56 was in a dilapidated condition. Therefore, the Bombay Housing and Area Development Board had examined the position and decided that a scheme was required to be framed under the Act for reconstruction and thereafter for allotment to the persons in occupation. When the acquisition proceedings were initiated after finalisation of the scheme, notices were given .under Section 5-A to the interested persons including the appellant. The appellant had raised the contention that the tenement in which it was carrying on the business was not part of the City Survey No. 56. It is an independent building and, therefore, it is not liable to be demolished for acquisition. Based upon that objection, a report was called for from the Executive Engineer who submitted the report thereon to the Land Acquisition Officer. After considering the report, he submitted a proposal for proceeding with the acquisition. It is not in dispute that except this structure, all other structures have been demolished in 1981 and the construction is yet to start. Ever since all others are, unfortunately, in transit camp. F G H Shri S.K. Dholakia, the learned senior counsel for the appellant, has contended that by operation of the provisions of Section 2(7) read with Section 2(9), the building in occupation of the appellant is non-cess payable building. Consequently, the building which is in exclusive possession in Chapter VIII, is not liable to be proceeded with, if the value of the reconstruction is Rs. 500 per sq. mt. or below. Since a certificate in that behalf has already been issued **in support thereof the action taken for demolition and acquisition is not** according to law. After the report submitted by the Executive Engineer, the Land Acquisition Officer had not given any independent hearing nor called the Executive Engineer for cross-examination. Therefore, it is violative of the principles of natural justice. The third contention raised is that the Land Acquisition Officer should have considered all the objections and given finding on each of the objections before submitting his proposal for further action. Shri M.L. Verma, the learned senior counsel resisted all these conten- **tions.** Having given consideration to the respective contentions, the question arises whether the structure on which the appellant is tenant is an independent building in City Survey No. 56? Before the Division Bench of the High Court, the counter-part of Shri S.K. Dholakia, had conceded that the principal contention raised was that the shed only "is not liable to be acquired even though the shed is a part of the plot, City Survey No. 56." The gravamen of the complaint is that the Board can move the Government only to acquire the building for the purpose of reconstruction exercising power under Section _)_ 477 ' ## SAM HIRING CO. _v._ AR. BHUJBAL 76(d) of the Act. The Division Bench has held that plain reading of Section 2(7) of the definition of 'building' makes it clear that it includes a tenement let or intended to be let or occupied separately and a house, out-house, stable, shed, hut and every other such structure. On account of that finding, it was held that the structure in which the appellant has been carrying on the business is part of City Survey No. 56 as has been conceded by the learned counsel who appeared for the appellant in the High Court and as such is liable to be acquired. Once it is concluded that he is a tenant or that his shed is part of the building, the question whether the tenant is independently paying cess under the Act as defined under Section 2(9) is not of much relevance. It must, therefore, be concluded that the structure in which the appellant is carrying his business is part of the City Survey No. 56. The finding of the authorities cannot be disputed that the structures are in dilapidated condition and require demolition for reconstruction. It being a finding of fact, the necessary **conclusion is that restructure requires to be done in accordance with law.** The question then is : whether the appellant is entitled to the further hearing? After the report was submitted by the Executive Engineer with regard to the objections raised by the appellant, the Division Bench of the High Court has pointed out that the Land Acquisition Officer had considered the objections after hearing him and with a view to satisfy himself whether the objections raised by the appellant were tenable, he required factual material and so he c3lled for the report from the Executive Engineer. The Executive Engineer's report was submitted clearing the position and the finding is not adverse to the appellant but beneficial to him. Therefore, the need to give further opportunity does not arise nor is there any need to call the Executive Engineer for cross-examination. Accordingly, the principle of natural justice has not been violated. The Land Acquisition Officer is not a judicial authority or a quasijudicial authority. He exercist;d the power under Section 5-A, as an administrative authority. But the Act requires that he should consider the objections and, if asked, to give an opportunity of hearing. In this case, opportunity of hearing was given and the objections raised were considered. The principle of natural justice has been complied with. He was not required to elaborately deal with each of the objections and submit the report. Considered from this perspective, we do not think that there is any error of law warranting **interference.** A B c D E F G The appeal is accordingly dismissed. No costs. G.N. Appeal dismissed.
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.