Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2021Division BenchAppeal partly allowed

Saluja Construction Company v. Northern Coalfields Limited

Case / Petition Number:
Civil Appeal No. 7041 of 2021
Neutral Citation:[2021] 7 S.C.R. 1111

Case Synopsis & Summary

This appeal concerns Saluja Construction Company’s challenge to a High Court order quashing an arbitration award. Under a written contract dated 11 January 1986, Saluja was awarded the contract for construction of 100 B-Type Quarters at the Bina Project. A dispute arose over payment for the Bina works, and Saluja invoked Section 8/20 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator for the Bina Project only. The arbitrator, however, issued an award addressing not only the Bina Project but also disputes relating to Amlohri and Jhingurda projects and other sister-concerns, thereby deciding claims beyond the scope of the written agreement. The High Court of Madhya Pradesh held that the arbitrator exceeded his jurisdiction by including four contracts beyond the Bina Project and quashed the award in its entirety. Saluja challenged this order under Section 37 of the Arbitration Act before the Supreme Court. The Supreme Court agreed that the arbitrator was bound to decide the dispute under the Bina Project written agreement; the High Court was correct to quash the extraneous awards. However, the Court found merit in preserving the Bina Project award of Rs. 5,99,158, and modified the judgment to quash only the claims pertaining to other projects. The appeal was thus partly allowed, with no costs, and the respondent was directed to adjust deposits; any excess deposited amount would be returned. The decision clarifies the limits of an arbitrator’s jurisdiction when the contract contains a single project, and cautions against extending the award to related projects without proper consent.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. Shah
  • Sanjiv Khanna
Judgment Date
2021-11-25
Court Decision / Holding
Appeal partly allowed. The award with respect to the Bina Project (Rs. 5,99,158) is confirmed; the High Court’s quashing of the rest of the award is set aside; the awards relating to four other contracts are quashed; deposits to be adjusted and any excess deposited amount returned; no order as to costs.
Final Disposition
Appeal partly allowed

Parties to the Case

Appellants / Petitioners

  • Saluja Construction Company

Respondents

  • Northern Coalfields Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Pijush K. Roy
  • • Mrs. Kakali Roy
  • • Rajan K. Chourasia

Counsels for Respondents

  • • Vikas Singh
  • • Ashwani Kumar Dubey
  • • Pankaj Sharma
  • • Kshitij Mudgal
  • • Deepika Kalia
  • • Satvik Mishra
  • • Kapish Seth
  • • Ashwini Kr. Upadhyay

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 2(a)Arbitration and Conciliation Act, 1996 - Section 8Arbitration and Conciliation Act, 1996 - Section 20Arbitration and Conciliation Act, 1996 - Section 37

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the arbitration agreement and appointment of arbitrator covered the Bina Project only. The Arbitrator exceeded his jurisdiction by passing an award on disputes relating to Amlohri and Jhingurda projects and other sister-concerns, thereby deciding claims beyond the written agreement. The High Court was right to set aside the award to the extent of those extraneous claims, but the appellant submits that the High Court should have preserved and confirmed the Bina Project award (Rs. 5,99,158) and remitted the rest.

Contentions of Respondents

The respondent argued that the arbitrator, appointed under the 8/20 applications for the Bina Project, had effectively adjudicated all related contracts. The High Court correctly held that the award extended beyond the targeted contracts; the challenge under Section 37 was rightly decided. The respondent contends that the extraneous awards should stand or that the High Court's quashing of the entire award was improper in part.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,378 words•~7 min read

In The Court Record

Saluja Construction Company v. Northern Coalfields Limited

1111 [2021] 7 S.C.R. 1111 SALUJA CONSTRUCTION COMPANY A v. ## NORTHERN COALFIELDS LIMITED (Civil Appeal No. 7041 of 2021) NOVEMBER 25, 2021 B ## **[M. R. SHAH AND SANJIV KHANNA, JJ.]** _Arbitration – High Court in appeal set aside award passed by the Arbitrator – Propriety – Held: On facts, the Arbitrator was required to adjudicate and decide dispute between the parties with_ C _respect to one Project (Bina Project) only – However, the Arbitrator passed an award not only with respect to the dispute relating to Bina Project but also with respect to other projects – Therefore, the High Court rightly held that the arbitrator while decreeing the award exceeded his jurisdiction in passing award in respect of four contracts – However, at the same time, the High Court at least ought_ D _to have confirmed the claim/amount awarded by the Arbitrator with respect to Bina Project – Order of High Court accordingly modified to that extent – Arbitration and Conciliation Act, 1996 – ss. 2(a), 8, 20 and 37._ CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7041 of 2021. E From the Judgment and Order dated 02.01.2018 of the High Court of Madhya Pradesh at Jabalpur in A.A. No. 30 of 2012. Pijush K. Roy, Mrs. Kakali Roy, Rajan K. Chourasia, Advs. for the Appellant. F Vikas Singh, Sr. Adv., Ashwani Kumar Dubey, Pankaj Sharma, Kshitij Mudgal, Ms. Deepika Kalia, Satvik Mishra, Kapish Seth, Ashwini Kr. Upadhyay, Advs. for the Respondent. The following Order of the Court was passed : G ## **O R D E R** Leave granted 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 02.01.2018 passed by the High Court of Madhya Pradesh H 1111 1112 SUPREME COURT REPORTS [2021] 7 S.C.R. - A at Jabalpur in A.A. No. 30 of 2012, by which the High Court has allowed the said appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (Arbitration Act) and has quashed and set aside the award passed by the learned Arbitrator, the original claimant has preferred the present appeal. - B 2. That the appellant herein was awarded the contract for construction of 100 Nos. B-Type Quarters at Bina (hereinafter referred to as the Bina project). An agreement was entered into between the parties on 11.01.1986. A dispute arose between the parties with respect to the Bina project. The contractor issued a notice under Clause 9 of the agreement to appoint an arbitrator in respect of Bina Project only. The - C respondent rejected the claim of the contractor. The appellant raised a Bill of Rs.2,23,215/- and then filed an application under Section 8/20 of the Arbitration Act for filing of agreement and appointment of arbitrator. Thus it appears that the dispute at the relevant time was only with respect to the work relating to the Bina Project. However, before the learned - D Arbitrator, the claim was raised with respect to the other projects and in relation to the sister concerns regarding ‘Amlohri Project’ and ‘Jhingurda Project’. The learned Arbitrator passed an award with respect to the dispute relating to other agreements/contracts even in relation to sister concerns over and above the dispute with respect to the Bina Project. The appeal under Section 34 of the Arbitration Act against the judgment - E and award passed by the learned Arbitrator came to be dismissed against which the respondent preferred an appeal under Section 37 before the High Court. It was submitted that the learned Arbitrator appointed only for the contract relating to Bina Project and the agreement relating to the Bina Project was filed before the learned Arbitrator. It was submitted - F that as per Section 2(a), 8 and 20 of the Arbitration Act, the mandatory requirement was to decide the dispute in relation to a written agreement which was filed before the arbitrator. Therefore, it was submitted that the learned Arbitrator has travelled beyond in passing the award in respect of four contracts. The High Court in the impugned judgment and order has accepted the submissions on behalf of the respondent and has quashed - G and set aside the award passed by the learned Arbitrator. 3. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court, the contractor has preferred the present appeal. H 1113 SALUJA CONSTRUCTION COMPANY v. NORTHERN COALFIELDS LIMITED 4. We have heard Shri Pijush K. Roy, learned counsel appearing A on behalf of the appellant and Shri Vikas Singh, learned senior counsel appearing on behalf of the respondent. 5. We have gone through the judgment and order passed by the High Court. It is to be noted that the application under Section 8/20 of the Arbitration Act was filed by the appellant – Saluja Construction Company – a partnership firm, with respect to the contract for construction of 100 Nos. B-Type Quarters at Bina Project only. The agreement between the appellant and respondent with respect to the Bina Project was produced in application under 8/20 of the Arbitration act. Therefore, the learned Arbitrator was required to adjudicate and decide the dispute between the parties with respect to the Bina Project only. However, learned Arbitrator passed an award not only with respect to the dispute relating to Bina Project but also with respect to the other projects that too not only with the appellant but with the sister concerns. Therefore, the High Court has rightly observed and held that the arbitrator while decreeing the award exceeded in his jurisdiction in passing the award in respect of 4 contracts/contracts. Therefore, as such the High Court is right in quashing and setting aside the award passed by the learned Arbitrator with respect to the dues/claims with respect to the contracts other than the Bina Project and the contracts with other projects/contractors may be by sister concerns. 6. However, at the same time, learned counsel appearing on behalf of the appellant is right in making the submissions that the High Court at least ought to have confirmed the claim/amount awarded by the learned Arbitrator with respect to the Bina Project. It is submitted that the High Court has set aside the entire award passed by the learned Arbitrator including the award with respect to the Bina Project. Therefore, to that extent the present appeal is required to be allowed in part and the judgment and order passed by the High Court is required to be modified to the extent setting aside the award passed by the learned Arbitrator with respect to the claims with respect to other projects/other contracts other than Bina Project. 7. In view of the above, the present appeal is allowed in part. The impugned judgment and order passed by the High Court is modified to the extent quashing and setting aside the entire judgment and award passed by the learned Arbitrator. The judgment and award passed by the learned Arbitrator except the claims with respect to the Bina Project B C D E F G H 1114 SUPREME COURT REPORTS [2021] 7 S.C.R. - A was required to be quashed and set aside and is accordingly quashed and set aside. Meaning thereby, award passed by the learned Arbitrator with respect to the Bina Project i.e. Rs.5,99,158/- is hereby confirmed. The impugned judgment and order passed by the High Court quashing and setting aside the award passed by the learned Arbitrator with respect to the projects other than Bina Project is rightly set aside by the High - B Court. We confirm the same. It is reported that pursuant to the earlier order passed by the High Court, the respondent has deposited 50% of the amount awarded by the learned Arbitrator. Therefore, whatever the amount deposited in excess of Rs.5,99,158/- with interest @ 8% per annum from the date of the award passed by the learned Arbitrator till - C the amount was deposited pursuant to the interim order passed by the High Court, shall be returned by the appellant to the respondent, if any excess amount is deposited and withdrawn by the appellant. The present appeal is allowed to the aforesaid extent. In the facts and circumstances of the case there shall be no order as to costs. D Bibhuti Bhushan Bose Appeal partly allowed. E F G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.