Supreme Court of IndiaSupreme Court · 2019Division BenchAppeals dismissed.

SAKETA VAKSANA LLP & ANR. v. KAUKUTLA SARALA & ORS.

Case / Petition Number:
Civil Appeal Nos. 9483 and 9484 of 2019
Neutral Citation:[2019] 17 S.C.R. 396

Case Synopsis & Summary

This appeal relates to interim orders in a suit for specific performance arising from an Agreement of Sale dated 17.11.2017 for land totaling 54 acres 13 guntas in Turkapalli, Telangana. The Appellant-Developer and Respondent-Landowners executed an unregistered sale agreement, under which possession of the entire land was allegedly handed over; four registered Agreements of Sale cum General Power of Attorney were later executed for 36 acres 21½ guntas in favour of the Developer, with the Developer claiming payment of Rs. 17.25 crores against a total sale consideration for the 54 acres. The Respondents dispute payment, asserting only Rs. 14.25 crores was paid and contend the balance for the entire suit property, along with transfers, remains due. The Developer filed a suit for Specific Performance (O.S. No. 213/2018) and sought two interim injunctions: protection of peaceful possession over the entire land and restraint against alienation or creation of third-party rights in the suit property. The Trial Court granted interim relief restricting interference with possession (excluding 12,000 sq ft) and restraining alienation until disposal. The Telangana High Court, in a division bench, set aside these orders, holding no prima facie case and that disputed issues require trial. The Supreme Court held the questions of possession and paid-part consideration to be seriously disputed and not suitable for interim relief, affirmed the High Court, and dismissed the appeals, directing expeditious trial within a year.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Uday Umesh Lalit
  • Indu Malhotra
  • Krishna Murari
Judgment Date
2019-12-17
Court Decision / Holding
The Supreme Court affirmed the Telangana High Court’s vacating of the Temporary Injunctions and held that two questions—possession of the suit property and whether part consideration had been paid—were seriously disputed and would require trial. It noted the absence of a prima facie case for grant of injunctive relief and directed that the ongoing OS 213/2018 be expedited, preferably within one year from today; the Civil Appeals were dismissed, and pending applications disposed of. It left the issues to be resolved at trial, while maintaining that the Developer’s interest in the land had been protected by the High Court’s interim orders up to the disposal of the suit.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • Saketa Vaksana LLP
  • ANR.

Respondents

  • Kaukutla Sarala and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Neeraj Kishan Kaul
  • • Gaurav Aggarwal
  • • Raghavendra Mohan
  • • Garima Bajaj
  • • Ankit Gambhir
  • • Anup Karawadi
  • • Pratha Suri
  • • Buwam Jayant
  • • Sanskar Agarwal

Counsels for Respondents

  • • Ranjit Kumar
  • • S. Udaya Kr. Sagar
  • • T. Sudhakar Reddy
  • • Akanksha Mehra
  • • Vasudha Singh
  • • G. Shridhar Reddy
  • • Elizabeth Antony
  • • Lawyer S Knit & Co.

Provisions of Law Cited

CPC, Order XXXIX Rule 1 and 2

Legal Doctrines & Maxims

  • prima facie
  • balance of convenience

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants/developer argued that possession of the entire suit land was handed over under the 17.11.2017 agreement per Clause 7, that they had paid Rs. 17.25 crore towards four registered sale-cum-GPA agreements and that the balance was payable for the 17 acres 31½ guntas. They contended that there is a prima facie case and that the injunctions were necessary to protect ongoing development and prevent coercive actions by sellers; they urged expeditious trial and requested protection of possession and ingress/egress to plots already sold. They also offered to deposit Rs. 10 crore during proceedings. Respondents countered that possession was only symbolic, demand that the balance consideration be proven, and argued that granting injunction would cause irreparable loss; they claimed the 17 acres 31½ guntas sale stood cancelled for the suit property and that pending trial, the High Court’s order should stand.

Contentions of Respondents

Respondents contended that possession alleged by the Appellant was not proven; they asserted that only Rs. 14.25 crore had been paid and sought cancellation of the agreement with respect to the suit property; they argued for vacating temporary injunctions since the Appellant had not established a prima facie case and the balance remained unsettled. They requested that the Trial Court decide the quantum of balance consideration and entitlement to possession, and that alienation of the suit property be restrained to protect their title until final disposal.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,864 words•~14 min read

In The Court Record

SAKETA VAKSANA LLP & ANR. v. KAUKUTLA SARALA & ORS.

396 SUPREME COURT REPORTS [2019] 17 S.C.R. 396 [2019] 17 S.C.R. A ## SAKETA VAKSANA LLP & ANR. v. KAUKUTLA SARALA & ORS. (Civil Appeal No. 9483 of 2019) B ## DECEMBER 17, 2019 ## **[UDAY UMESH LALIT, INDU MALHOTRA AND KRISHNA MURARI, JJ.]** - _Interim Order: Agreement of sale between appellant-_ - C _Developer and respondents- landowners for sale of agricultural land comprising of 54 acres 13 guntas – The said agreement was unregistered – As per the agreement, the possession of entire land was handed over to Developer – Out of total extent of land, four registered agreements of sale cum GPA executed with respect to 36_ - D _acres 21-1/2 guntas of land in favour of Developer – Dispute between parties for payment of balance consideration for land admeasuring 17 acres 31-1/2 guntas (suit property) – Suit for specific performance by Developer – Developer prayed that the landowners be directed to execute the Sale Deed for the suit_ - E _property admeasuring 17 acres 31½ guntas and provide ingress and egress to the land admeasuring 36 acres 21½ guntas for which the registered Agreements of Sale cum GPA had been executed – Developer also filed two interim applications, one seeking temporary injunction restraining landowners from interfering with peaceful possession over entire land and second seeking temporary_ - F _injunction restraining landowners from alienating or creating third party interest in the suit property – In the first interim application, landowners disputed the possession of Developer over suit property and produced rent agreement to show that a parcel of land admeasuring 12000 sq. feet was in possession of a third party –_ - G _Trial court disposed of first interim application granting temporary injunction in respect of property excluding the extent of 12000 sq. feet – In the second interim application, trial court granted temporary injunction restraining landowners from alienating or creating third party interest in suit property till the disposal of suit_ H 396 397 SAKETA VAKSANA LLP v. KAUKUTLA SARALA _subject to deposit of balance sale consideration – Order passed_ A _in first interim application challenged before High Court – Division bench of the High Court by the impugned interim orders set aside the order of Temporary Injunction passed by the trial court in first interim application – Division Bench held that there was no documentary evidence to prima facie case to show that the_ B _Developer was in physical possession of the suit property and furthermore, the issue whether the Developer has paid part consideration for the entire suit property was required to be determined in the trial and therefore, no prima facie case was made out for grant of Temporary Injunction – Developer challenged the_ C _impugned interim orders by way of the instant appeals – Held: There are seriously disputed questions of fact involved in this matter – The first issue is whether possession of the suit property was at all handed over to the Developer or not and second is whether part consideration for the suit property was paid by the Developer_ D _to the landowners or not – Developer submitted that it had paid a total of Rs. 17.25 lacs to the landowners, and only Rs. 3.72 lacs was the balance payable for the suit property – Landowners however, submitted that the Developer had paid only Rs. 14.25 lacs and was still liable to pay Rs. 10.73 lacs towards the balance sale consideration for the entire suit property, as well as some part of_ E _the land already transferred in favour of the Developer – Since both the issues raised are seriously disputed which will be decided during the course of trial, the impugned orders passed by the Division Bench of the High Court did not warrant any interference – High Court has already granted a Temporary Injunction_ F _restraining the landowners from alienating or creating third party rights in the suit property till the disposal of the Suit – The interest of the Developer has been sufficiently protected with respect to ownership of the suit property – In view of this, order of vacation of Temporary Injunction by High Court whereby the respondents_ G _were restrained from interfering with the possession of the Developer over the suit property is upheld – Trial court to expedite the disposal of the suit – Appeals dismissed._ G CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9483 of 2019 H 398 SUPREME COURT REPORTS [2019] 17 S.C.R. A From the Judgment and Order dated 14.08.2019 of the High Court for the State of Telangana at Hyderabad in I.A. No. 1 of 2019 in CMA No. 646 of 2019 With B Civil Appeal No. 9484 of 2019. Neeraj Kishan Kaul, Sr. Adv., Gaurav Aggarwal, Raghavendra Mohan, Ms. Garima Bajaj, Ankit Gambhir, Anup Karawadi, Ms. Pratha Suri, Bhuwam Jayant, Sanskar Agarwal, Advs. for the Appellants. C Ranjit Kr., Sr. Adv., S. Udaya Kr. Sagar, T. Sudhakar Reddy, Ms. Akanksha Mehra, Vasudha Singh, G. Shridhar Reddy, Ms. Elizabeth Antony, M/S. Lawyer S Knit & Co., Advs. for the Respondents. The Judgment of the Court was delivered by ## D **INDU MALHOTRA, J.** Leave granted. 1. The present Civil Appeals have been filed by the Appellants to challenge the Interim Orders dated 14.08.2019 passed in I.A. No. E 1/2019 and I.A. No. 2/2019 filed in CMA No. 646/2019 by the High Court of Telangana. 2. The factual background is that the Appellant – Developer and the Respondent – Landowners entered into an Agreement of Sale dated F 17.11.2017, whereby the Respondents agreed to sell agricultural land comprising of 54 acres 13 guntas situated in Turkapalli Village, Shamirpet Mandal, Medchal-Malkajgiri District to the Appellant – Developer. The sale consideration was fixed at Rs. 46,00,000/- per acre. The land was divided into 5 schedules, and each schedule of land G was to be sold to the Appellant – Developer upon payment of the proportionate sale consideration. Clause 7 of the Agreement dated 17.11.2017 stated that physical possession of the entire land was handed over to the Appellant – H Developer on the day of execution of the Agreement. 399 SAKETA VAKSANA LLP v. KAUKUTLA SARALA [INDU MALHOTRA, J.] The Agreement of Sale dated 17.11.2017 was an unregistered A document executed on a Stamp Paper of Rs. 100. The Stamp Duty on this Agreement was paid by the Appellant – Developer on 27.08.2018. 3. Out of the total extent of land, the Respondents executed four registered Agreements of Sale cum General Power of Attorney with respect to 36 acres 21½ guntas of land in favour of the Appellant – Developer. The first two Agreements of Sale were executed on 03.01.2018; the third on 24.03.2018; and the fourth on 31.03.2018. B The Appellant – Developer submitted that it has paid Rs. 17,25,00,000/- for the aforesaid four Agreements of Sale. The Respondents have seriously disputed this submission, and stated that an amount of only Rs. 14,25,00,000/- was paid by the Appellant – Developer. This gave rise to disputes between the parties for payment of the balance consideration for land admeasuring 17 acres 31½ guntas (“suit property”). 4. The Appellant – Developer filed a Suit for Specific Performance bearing O.S. No. 213/2018 seeking Specific Performance of the Agreement of Sale dated 17.11.2017 before the XVI Additional District and Sessions Judge, Ranga Reddy District (“Trial Court”). The Appellant/Plaintiff prayed that the Respondents be directed to execute the Sale Deed for the suit property admeasuring 17 acres 31½ guntas; and provide ingress and egress to the land admeasuring 36 acres 21½ guntas for which the registered Agreements of Sale cum GPA had been executed. 5. The Respondents filed the Written Statement cum Counter Claim seeking payment of Rs. 2,55,72,500/- towards the balance consideration for the 36 acres 21½ guntas of land already transferred in favour of the Appellant – Developer. The Respondents further claimed an amount of Rs. 1,00,00,000/- towards the damage caused by the Appellant – Developer to the suit property. C D E F G The said Suit is pending final determination before the Trial Court. 6. The Appellant – Developer filed two I.A.s in the Suit praying for Temporary Injunction under Order XXXIX Rule 1 and 2 of the CPC before the Trial Court. H 400 SUPREME COURT REPORTS [2019] 17 S.C.R. A I.A. No. 766/2018 was filed for a temporary injunction restraining the Respondents from interfering with the peaceful possession and enjoyment of the Appellant – Developer over the entire land admeasuring 54 acres 13 guntas. I.A. No. 767/2018 was filed for a temporary injunction restraining B the Respondents from alienating or creating any third-party interest in the suit property admeasuring 17 acres 31½ guntas. 7. In I.A. No. 766/2018, the Respondent/Defendants disputed the possession of the Appellant – Developer over the suit property C admeasuring 17 acres 31½ guntas. They produced a Rent Agreement to show that a parcel of land admeasuring 12,000 sq. feet was in the possession of a third party. However, in the Agreements of Sale executed by the Respondents in favour of the Appellant – Developer, it was mentioned D that possession of the entire land admeasuring 54 acres 13 guntas was handed over to the Appellant – Developer at the time of the execution of the Agreement dated 17.11.2017. The Trial Court passed an Interim Order dated 01.05.2019 in I.A. No. 766/2018 with respect to the prayer for injunction restraining the E Respondents from interfering with the peaceful possession of the Appellant – Developer over the suit property, and held that the issue with respect to possession of the suit property admeasuring 17 acres 31½ could only be decided in trial. F In view of the aforesaid facts, the Trial Court held that the Appellant – Developer made out a _prima facie_ case, and the balance of convenience was in their favour. The Trial Court granted a temporary injunction restraining the Respondents from interfering with the possession of the Appellant – Developer over the suit property excluding the extent of 12,000 sq. feet. G 8. In I.A. No. 767/2018, the Trial Court _vide_ Interim Order dated 01.05.2019 granted a Temporary Injunction restraining the Respondents from alienating or creating third party interest in the suit property till the disposal of the suit, subject to the Appellant – Developer depositing the balance sale consideration @Rs. 46,00,000/- per acre. H 401 SAKETA VAKSANA LLP v. KAUKUTLA SARALA [INDU MALHOTRA, J.] 9. The Appellant – Developer filed two Miscellaneous Appeals A bearing C.M.A. No. 535/2019 and C.M.A. No. 536/2019 before a Single Judge of the High Court to challenge the Interim Orders passed by the Trial Court. 10. The Respondents filed a cross Miscellaneous Appeal bearing C.M.A. No. 646/2019 before the division bench of the High Court praying for setting aside the Temporary Injunction restraining them from interfering with the peaceful possession of the Appellant – Developer over the suit property. B It is relevant to note that the Order dated 01.05.2019 passed by the Trial Court in I.A. No. 767/2018 has not been challenged by the Respondent – Landowners. C 11. A Single Judge of the High Court _vide_ Interim Order dated 22.05.2019 directed that the Temporary Injunction restraining the Respondents from interfering with the peaceful possession of the Appellant – Developer would extend to the entire suit property, including the parcel of 12,000 sq. feet of land. D The Single Judge _vide_ a further Interim Order dated 22.05.2019 directed that the injunction restraining the Respondents from creating third party rights in the suit property would operate, without the condition of depositing the balance sale consideration. E 12. In C.M.A. No. 646/2019, the division bench of the High Court _vide_ the impugned Interim Orders dated 14.08.2019 has set aside the Order of Temporary Injunction dated 01.05.2019 passed by the Trial Court in I.A. No. 766/2018. F The division bench held that there is no documentary evidence to _prima facie_ show that the Appellant – Developer is in physical possession of the suit property. Furthermore, the issue whether the Appellant – Developer has paid part consideration for the entire suit property was required to be determined in the trial. The division bench took the view that the Appellant – Developer had not made out a _prima facie_ case for grant of Temporary Injunction. The Respondents being the lawful owners of the suit property, granting such an injunction would cause irreparable loss and hardship to them. G H 402 SUPREME COURT REPORTS [2019] 17 S.C.R. A Consequently, the Temporary Injunction restraining the Respondents from interfering with the peaceful possession of the Appellant – Developer in the suit property was vacated. 13. The Appellant – Developer has challenged the Interim Orders dated 14.08.2019 by way of the present Civil Appeals. B We have heard Mr. Neeraj Kishan Kaul, Sr. Adv. on behalf of the Appellant – Developer and Mr. Ranjit Kumar, Sr. Adv. on behalf of the Respondents, and perused the material on record. 14. The Appellant – Developer submitted that they have C developed and sold plots on the tract of land admeasuring 36 acres 21½ guntas to third parties. It was prayed that unless an Agreement of Sale with respect to the suit property admeasuring 17 acres 31½ guntas is registered in their favour, they cannot provide ingress and egress to the plots already sold by them. As a consequence, the purchasers of those D plots have been threatening to initiate criminal proceedings against the Appellant – Developer. 15. The Respondent – Landowners submitted that the Appellant – Developer has ingress and egress to the land admeasuring 36 acres 21½ guntas, which has already been transferred. The Respondents had E filed a Counter Claim in the Suit before the Trial Court for payment of the balance sale consideration for 36 acres 21½ guntas of land which had already been transferred to the Appellant – Developer. It was further submitted that the Appellant – Developer has not F paid any consideration whatsoever with respect to the suit property admeasuring 17 acres 31½ guntas. Consequently, the Agreement of Sale dated 17.11.2017 stands cancelled _qua_ the suit property. 16. We find that there are seriously disputed questions of fact involved in this matter. The first issue is whether possession of the suit G property was at all handed over to the Appellant – Developer or not. On the one hand, the Appellant – developer relied on Clause 7 of the Agreement dated 17.10.2017 to show that possession of the suit property was handed over to them at the time of execution of the H Agreement. 403 SAKETA VAKSANA LLP v. KAUKUTLA SARALA [INDU MALHOTRA, J.] On the other hand, the Respondents submitted that it was only symbolic possession which was given to the Appellant – Developer, while physical possession remained with the Respondent – Landowners. The Respondents averred that they are growing vegetables, and have a guest house, servant quarters and a shed on the suit property. 17. The second issue is whether part consideration for the suit property was paid by the Appellant – Developer to the Respondent – Landowners or not. The Appellant – Developer submitted that it had paid a total of Rs. 17,25,00,000/- to the Respondents, and only Rs. 3,72,03,750/- was the balance payable for the suit property. The Respondents however, submitted that the Appellant – Developer had paid only Rs. 14,25,00,000/-, and was still liable to pay Rs. 10,73,95,000/- towards the balance sale consideration for the entire suit property, as well as some part of the land already transferred in favour of the Appellant – Developer. 18. During the course of hearing, the Senior Counsel for the Appellant – Developer made an offer to deposit Rs. 10,00,00,000/- in this Court on a “without prejudice” basis. The Respondents however, rejected the said offer. A B C D E 19. Since both the issues raised are seriously disputed which will be decided during the course of trial, we are of the view that the Orders dated 14.08.2019 passed by the division bench of the High Court do not warrant any interference. F The High Court has already granted a Temporary Injunction restraining the Respondents from alienating or creating third party rights in the suit property till the disposal of the Suit. The interest of the Appellant – Developer has been sufficiently protected with respect to ownership of the suit property. 20. In view of the aforesaid discussion, we affirm the Orders dated 14.08.2019 passed by the division bench of High Court, whereby the Temporary Injunction restraining the Respondents from interfering with the possession of the Appellant – Developer over the suit property has been vacated. G H 404 SUPREME COURT REPORTS [2019] 17 S.C.R. - A 21. We have expressed no opinion on the merits of the matter, since the observations have been made at an interim stage of the proceedings. 22. We however direct that the hearing of O.S. No. 213/2018 pending before the XVI Additional District and Sessions Judge, Ranga B Reddy District be expedited, and disposed of preferably within a period of one year from today. The Civil Appeals are therefore, dismissed. Pending Applications if any, are accordingly disposed of. - C Ordered accordingly. Devika Gujral Appeals dismissed. D E F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.