Case Synopsis & Summary

This writ petition concerns the appointment of a staff member (2nd petitioner) as UPSA at Kadavoor SN U.P. School during a vacancy period from 31.08.2005 to 30.08.2010. The manager (1st petitioner) appointed the 2nd petitioner on 19.10.2005, who sought approval from the Education authorities. The 5th respondent refused approval (Ext. P4) citing a pending civil dispute over the manager’s right, and the 4th respondent (DEO) concurred (Ext. P5). The Government, in Ext. P11, also rejected approval on the basis that the appointed period (19.10.05–31.07.06) was less than one academic year, which the petitioners challenge as inconsistent with the Kerala Education Rules (KER). The petition was heard after a prior direction in WP(C) No. 9989/07 and relies on the Munsiff’s Court order (Ext. P3) upholding the manager’s right. The court observed that the dispute about management is not a bar to approve an appointment if the vacancy itself is for a duration of one academic year or more, per KER. The judgment references Unni Narayanan v. State of Kerala to emphasize that executive instructions cannot override statutory rules, especially where vacancies are long enough to justify appointment. The court quashed the impugned orders and directed the 5th respondent to approve the appointment and disburse arrears if applicable.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S. Siri Jagan
Judgment Date
2009-05-29
Court Decision / Holding
The impugned orders (Ext. P4, P5, Ext. P7, Ext. P11) are quashed. The 5th respondent is directed to approve Ext. P1, i.e., the appointment of the 2nd petitioner as UPSA in Kadavoor SN UP School for the period from 19.10.05 to 30.08.10. The 1st petitioner shall re-present Ext. P1 or a identical replacement if P1 is not traceable, and the 5th respondent shall pass approval within one month of receipt. Arrears of salary for the actual period worked should be disbursed within two weeks thereafter. The writ petition is disposed of accordingly.
Final Disposition
Writ petition allowed; impugned orders quashed; direction to approve appointment and disburse arrears; case disposed of accordingly.

Parties to the Case

Appellants / Petitioners

  • S. Sugathan
  • Sreelatha V.G.

Respondents

  • The Secretary, General Education Department, Thiruvananthapuram
  • The Under Secretary, General Education (H) Department, Thiruvananthapuram
  • The Director of Public Instructions, Thiruvananthapuram
  • The District Education Officer, Mavelikkara
  • The Assistant Education Officer, Mavelikkara

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri R. Reji
  • • Sri B. Bipin

Counsels for Respondents

  • • Smitha Sukumaran (Government Pleader)

Provisions of Law Cited

KER Chapter XIV A, Rule 7A (including sub-rules 7A(1)–7A(3))KER Chapter XIV A, Rule 92Kerala Education Rules (KER)Vacancies duration rule – one academic year or more may be filled and approved.

Legal Doctrines & Maxims

  • Executive instructions cannot override statutory provisions (Unni Narayanan v. State of Kerala)
  • Vacancies lasting one academic year or more can be filled and must be approved under KER (R.7A)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that the 5th respondent’s refusal to approve the appointment is unjustified and contrary to KER. Ext.P1 clearly sets a period of appointment from 19.10.2005 to 30.08.2010, i.e., a vacancy of one academic year or more. Approvals are to be assessed based on conformity with KER, not on the actual service completion. The existence of a management dispute (Ext.P3) does not bar approval if statutory rules permit it; Ext.P11 misstates the period (19.10.05 to 31.07.06) and cannot override the appointment order (Ext.P1) which exceeds one academic year. Citing Unni Narayanan v. State of Kerala, the petitioners urge that executive directions cannot override statutory rules, and vacancies lasting one academic year or more are eligible for approval. The court is urged to quash Exts. P4, P5, P7, and P11 and direct approval with arrears if due.

Contentions of Respondents

The respondents (State) contend that Ext.P11 reflects the period and that the appointment duration falls short of one academic year, thus not satisfying Rule 7A. They argue that approvals must be grounded in the statutory framework of KER and that the delay or dispute over management should preclude approval. Ext.P11’s revision confirms non-approval due to the period being less than one academic year. They rely on KER provisions to support the position that vacancies shorter than one academic year should not be approved. The Government Pleader also notes that executive instructions lack efficacy to override statutory rules, aligning with UNNI Narayanan's principle, but maintains the position that the facts do not justify approval absent compliance with duration requirements.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Unni Narayanan v. State of Kerala2009(2) KLT 604PositiveThe court cites Unni Narayanan to support that statutory provisions (KER) prevail and that vacancies lasting one academic year or more may be filled and approved, reinforcing the petitioners' position against improper administrative delays.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,503 words•~7 min read

In The Court Record

S. Sugathan and Sreelatha V.G. v. The Secretary, General Education Department, Thiruvananthapuram and others

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE S.SIRI JAGAN FRIDAY, THE 29TH MAY 2009 / 8TH JYAISHTA 1931 WP(C).No. 5578 of 2008(L) ------------------------------------- PETITIONERS: - --------------------- 1. S.SUGATHAN, AGED 48 YEARS, S/O.SUKUMARAN, MANAGER, SNDP UNION SCHOOLS, MAVELIKKARA. 2. SREELATHA V.G., D/O.GANGADHARAN V.R., VILAPARAMBIL, KARITHOTTA MEZHUVELI, NOW RESIDING AT KOTTUPURATHU KIZHAKKETHIL, VATHIKULAM, OLAKETTIYAMBALAM. BY ADV. SRI.R.REJI - SRI.B.BIPIN RESPONDENTS: ------------------------ 1. THE SECRETARY, GENERAL EDUCATION DEPARTMENT, THIRUVANANTHAPURAM. 2. THE UNDER SECRETARY, GENERAL EDUCATION (H) DEPARTMENT, THIRUVANANTHAPURAM. 3. THE DIRECTOR OF PUBLIC INSTRUCTIONS, THIRUVANANTHAPURAM. 4. THE DISTRICT EDUCATION OFFICER, MAVELIKKARA. 5. THE ASSISTANT EDUCATION OFFICER, MAVELIKKARA. BY GOVERNMENT PLEADER SMT.SMITHA SUKUMAR THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 29/05/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## W.P.(C) NO.5578 OF 2008-L ## APPENDIX ## PETITIONERS' EXHIBITS: EXT.P1 TRUE COPY OF THE APPOINTMENT ORDER DATED 19.10.2005 EXT.P2 TRUE COPY OF THE STAFF STATEMENT DATED 19.10.2005 - EXT.P3 TRUE COPY OF THE ORDER IN IA NO.1864/2005 IN OS NO.317/2005 BY THE HON'BLE MUNSIFF COURT, MAVELIKKARA - EXT.P4TRUE COPY OF THE ORDER PASSED BY THE 5TH RESPONDENT DATED 13.2.2006 - EXT.P5 TRUE COPY OF THE ORDER PASSED BY THE 4TH RESPONDENT DATED 24.5.2006 EXT.P6TRUE COPY OF THE REVISION PETITION DATED 26.6.2006 - EXT.P7 TRUE COPY OF THE ORDER PASSED BY THE 3RD RESPONDENT DATED 28.1.2007 - EXT.P8 TRUE COPY OF THE JUDGMENT IN W.P.(C) NO.9989/2007 DATED 23.3.2007 - EXT.P9 TRUE COPY OF THE REVISION PETITION FILED BY THE 1ST PETITIONER DATED 20.6.2007 - EXT.P10 TRUE COPY OF THE STATEMENT FILED BY THE 2ND PETITIONER DATED 7.8.2007 - EXT.P11 TRUE COPY OF THE ORDER PASSED BY THE 2ND RESPONDENT DATED 4.12.2007 EXT.P12 TRUE COPY OF THE GOVT. ORDER DATED 15.6.2004 - EXT.P13 TRUE COPY OF THE GOVT. ORDER VIDE G.O.(P) NO.1/2005/G.EDN. DATED 1.1.2005. / TRUE COPY / ## **S. SIRI JAGAN, J** . ------------------------------------------------- W.P.(C)No. 5578 OF 2008 ------------------------------------------------Dated this the 29[th] day of May, 2009 ## JUDGMENT The 1[st] petitioner is the Manager of the SNDP Union Schools, Mavelikkara which includes S.N. UPS, Kadavoor. The 1[st] petitioner in his capacity as Manager of the SN UPS, Kadavoor appointed the 2[nd] petitioner as UPSA in a leave vacancy of a teacher by name Smt.R.Jyothi for the period from 31.08.05 to 30.08.10. Ext.P1 is that appointment order. That appointment order was forwarded to the 5[th] respondent for approval. The 5[th] respondent by Ext.P4 order refused to approve that appointment on the ground that there is a dispute pending before the Civil Court in respect of the right of the 1[st] petitioner to be the Manager of the school. By Ext.P5 order the 4[th] respondent District Educational Officer affirmed the same. The revision filed before the Director of Public Instruction also met with the same fate for an additional reason that the petitioner worked only for a period of nine months in the school. The 1[st] petitioner challenged the same in WP(C) No.9989/07 in which this Court directed the 1[st] petitioner to file a revision under Rule 92 of Chapter WPC : 5578/08 ## -:2:- XIV A KER. The revision so filed by the 1[st] petitioner was disposed of by Ext.P11 order by the Government, wherein although the Government upheld the right of the 1[st] petitioner to appoint the 2[nd] petitioner, approval was again rejected on the ground that the period of appointment of 2[nd] petitioner was from 19.10.05 to 31.07.06, which is less than one academic year. Petitioners are challenging Exts.P4, P5, P7 and P11 orders, seeking the following reliefs: “i. Issue a writ of certiorari or any other appropriate writ or direction, call for the records leading to Ext.P4, P5, P7 and P11,scrutinize and quash the same. ii. Issue a writ of mandamus or any other appropriate writ or order directing the 5[th] respondent to approve the appointment of the petitioner with effect from 19.10.05.” 2. With the help of the counter affidavit filed on behalf of the 1[st] respondent, the Government Pleader supports Ext.P11 order. 3. I have considered the rival contentions in detail. I note that by Ext.P3 order of the Munsiff's Court, Mavelikkara, the right of the 1[st] petitioner to be the Manager of the school during the period when Ext.P1 appointment order was issued, had been upheld. In fact that right has also been upheld in Ext.P11 order by the Government. WPC : 5578/08 -:3:- Therefore, the dispute regarding management is no longer an issue for the purpose of deciding the claim for approval of appointment of the 2[nd] petitioner. The only question that needs to be considered is whether the finding in Ext.P11 that as the period of appointment of the 2[nd] petitioner as UPSA is from 19.10.05 to 31.07.06 which is less than one academic year, the approval is liable to be rejected. 4. Ext.P1 is the appointment order. It categorically states that the 2[nd] petitioner is appointed as UPSA for the period from 19.10.05 to 30.08.10, in the vacancy of Smt.R.Jyothi, UPSA entering on leave without allowances from 31.08.05 to 30.08.10. When an appointment order is forwarded to the 5[th] respondent for approval what the 5[th] respondent is expected to ascertain is whether that appointment is in accordance with the provisions of KER. The 5[th] respondent cannot wait till the expiry of one year to see that the appointee has in fact worked for one year and grant approval only if the appointee has worked for one year. Such a procedure is not contemplated in the KER at all. Further, if appointments are made to vacancies having duration of one academic year or more, they are liable to be approved. It has been held so by a Division Bench of this WPC : 5578/08 -:4:- ## Court in _**Unni Narayanan v. State of Kerala**_ [2009(2) KLT 604]. In paragraph 7 & 8 of that decision it is held thus: “7. In certain circumstances, the Government may be able to issue executive instructions, but they have no efficacy to override the statutory provisions. We agree with the contentions of the writ petitioners that the offending conditions in Ext.P2 Government Order cannot stand with the statutory rules. Therefore, for enforcing them, the relevant rules require amendment. As long as the rules are not amended, Ext.P2 cannot be pressed into service by the Government. In this context, we notice R.7A of Chap.XIV A of the KER., which reads as follows: “7A(1) xxx xxx (2) Posts that my fall vacant on the closing date shall not be filled up till the reopening date except in the case of posts of non-vacation staff. (3) Vacancies, the duration of which is less than one academic year, shall not be filled up.” 8. We notice that sub-r.(3) of R.7A speaks of vacancies, the duration of which is less than one academic year. In other words, if the vacancy is having a duration of one academic year or more, appointment can be made to fill up the same. The term of appointment need not be co-terminous with the term of the vacancy. If, in fact, the vacancy is having a duration of one academic year or more, even if, there is some delay in making the appointment, such appointment will have to be approved. The reason is that R.7A speaks of duration of vacancy and not duration of appointment. So, we are of the view that if appointments are made to vacancies, having duration of one academic year or more, they are liable to be approved.” WPC : 5578/08 -:5:- 5. Here in Ext.P11 the Government has stated that the period of appointment of the 2[nd] petitioner is from 19.10.05 to 31.07.06 which is totally wrong, insofaras inExt.P1 appointment order, the 2[nd] petitioner has been appointed for the period from 19.10.05 to 30.08.10, which is for a period of more than one academic year. I also note the contention of the 2[nd] petitioner that she could not work in the school after 31.07.06 only because the contesting factor of the SNDP Union, which owns the school physically prevented her from entering the school. Whether that is correct or not, insofaras the appointment of the 2[nd] petitioner is clearly in accordance with the provisions of KER, approval could not have been rejected as done in the impugned orders. Accordingly, the impugned orders are quashed. The 5[th] respondent is directed to approve Ext.P1 appointment order by which the 1[st] petitioner has appointed the 2[nd] petitioner as UPSA in Kadavoor SN UP School for the period from 19.10.05 to 30.08.10. For this purpose the present Manager shall re-present Ext.P1 appointment order or another identical appointment order, if Ext.P1 is not traceable now, before the 5[th] respondent. The 5[th] respondent WPC : 5578/08 -:6:- shall pass orders approving that appointment of the 2[nd] petitioner within one month of the date of receipt of the same. Arrears of salary due to the 2[nd] petitioner for the period she actually worked should also be disbursed within another period of two weeks therefrom. The writ petition is disposed of as above. **S. SIRI JAGAN, JUDGE** ttb
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.