High Court of KeralaSingle JudgeDismissed

S. Shamsudheen v. Land Revenue Commissioner, Public Buildings, Thiruvananthapuram, Special Tahsildar (LA), PWD (SC), Fort, Thiruvananthapuram; District Collector, Thiruvananthapuram; K. Subramoni; Addl.R5 K. Gopakumar

Case / Petition Number:WP(C).No. 37767 of 2009 (M)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • C.K. Abdul Rehim
Judgment Date
2013-06-19
Court Decision / Holding
Writ petition dismissed; the court held that the petitioner, being a tenant, has no locus standi to challenge the notification or the declaration, and that the entire acquisition procedure has been completed with an award and possession; the dicta in the cited Supreme Court cases were found to have no bearing on the present case.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • S. Shamsudheen

Respondents

  • Land Revenue Commissioner, Public Buildings, Thiruvananthapuram
  • Special Tahsildar, (LA) PWD (SC), Fort, Thiruvananthapuram
  • District Collector, Thiruvananthapuram
  • K. Subramoni
  • K. Gopakumar (Addl.R5)

Legal Representation & Advocates

Counsels for Petitioners

  • • Thirumala P.K. Mani (Advocate)

Counsels for Respondents

  • • S. Shyson P. Manguzha (Govt. Pleader)
  • • D. Sajeev (Advocate)
  • • K.K. Satheesh (Advocate)

Case Synopsis & Summary

The petition challenges Ext.P2, a Land Acquisition notification under Section 4(1) (and dispensing with enquiry under Section 5(a) via Section 17(4)) for widening roads in Thiruvananthapuram. The petitioner, a tenant operating a hotel in a building within the acquired property, contends that a prior acquisition over part of the building had already occurred and that the landlord had exercised option under Section 49 to acquire the entire building; that the earlier stay granted by this court (Ext.P1, 27-08-2001) was in force while part of the property was being acquired; that the current notification is a composite, improperly sequenced notification under 4(1) and 17(4); and that he was denied an opportunity to challenge the proposal and to participate in the Section 5(a) enquiry. The respondents contend the petitioner has no locus standi to challenge the notification or the declaration since the proceedings have progressed to award and possession, and the matter concerns a public road widening project; they rely on a Supreme Court decision (Ext.R4(b)) that the building was liable to be acquired under the landlord’s option under Section 49. The court ultimately held that the petitioner, a mere tenant, cannot challenge the acquisition at this stage and that the earlier Supreme Court decision law has no bearing on the present challenge, leading to dismissal of the writ petition. The judgment emphasizes that the entire acquisition process was completed with an award and possession already taken, and that invoking Section 17(4) in this context is not maintainable.

Provisions of Law Cited

Land Acquisition Act, 1894 - Section 4(1)Land Acquisition Act, 1894 - Section 17(4)Land Acquisition Act, 1894 - Section 5(a)Land Acquisition Act, 1894 - Section 49Land Acquisition Act, 1894 - Section 6(1)Survey and Boundary Act, 1961 - Section 6(1)Land Acquisition Act, 1894 - Section 9(b)Land Acquisition Act, 1894 - Section 15(3)

Legal Doctrines & Maxims

  • Locus standi
  • Composite notification under Section 4(1) and 17(4)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends Ext.P2 is a composite notification under Section 4(1) and 17(4) and that declaration under 17(4) can be made only after publication of 4(1). He asserts denial of an opportunity to challenge the proposal and to conduct the Section 5(a) enquiry, and alleges the acquisition was pursued at the landlord’s instance to eject the petitioner. He argues lack of locus standi to challenge under the prior Supreme Court decision (Ext.R4(b)) and seeks disposal of the proceedings. He maintains the tenancy rights call for protection until due process, and that the 17(4) invocation is not maintainable given the completed procedure and award.

Contentions of Respondents

The respondents contend that the notification under 4(1) was valid, with a later Section 6(1) process and award, and that the petition challenges only the procedural aspects after the award. They argue the petitioner, as a tenant, has no locus standi to challenge the acquisition, especially since the ongoing project involves road widening and the entire procedure has been completed with possession already handed over. They rely on the Supreme Court decision (Ext.R4(b)) to show the building’s liability to be acquired under Section 49, and assert that Section 17(4) invocation is not applicable to this case.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Baburam and another v. State of Haryana and another2009 (10) SCC 115Mentioned OnlyCited by counsel; the court stated its dicta have no bearing on this case.
Union of India and others v. Mukesh Hans2004 8 SCC 14Mentioned OnlyCited by counsel; the court stated its dicta have no bearing on this case.
State of Uttar Pradesh v. Radhey Shyam Nigam and others1989 (1) SCC 591Mentioned OnlyCited by counsel; the court stated its dicta have no bearing on this case.
Civil Appeal No. 5972/2001Civil Appeal No. 5972/2001PositiveExt.R4(b) Supreme Court judgment cited to support the proposition that the building is liable to be acquired under Section 49; used to assert lack of locus standi of the petitioner.
Writ Appeal No. 1166/2000Writ Appeal No. 1166/2000Mentioned OnlyExt.R4(a) cited as an exhibit; content not discussed in detail.
OP No. 8105/2000OP No. 8105/2000Mentioned OnlyExt.R4(c) cited as an exhibit; content not discussed in detail.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against S. Shamsudheen v. Land Revenue Commissioner, Public Buildings, Thiruvananthapuram, Special Tahsildar (LA), PWD (SC), Fort, Thiruvananthapuram; District Collector, Thiruvananthapuram; K. Subramoni; Addl.R5 K. Gopakumar and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT:** **THE HONOURABLE MR.JUSTICE C.K.ABDUL REHIM** **WEDNESDAY, THE 19TH DAY OF JUNE 2013/29TH JYAISHTA 1935** **WP(C).No. 37767 of 2009 (M)** **----------------------------** ## **PETITIONER :** - **----------** **S.SHAMSUDHEEN, TC NO.19/990, THAMALAM, MUDAVANMUGAL P.O., THIRUVANANTHAPURAM.** **BY ADV. SRI.THIRUMALA P.K.MANI** ## **RESPONDENTS :** **----------------------------** ## **1. LAND REVENUE COMMISSIONER, PUBLIC BUILDINGS, THIRUVANANTHAPURAM.** **2. SPECIAL TAHSILDAR,** - **(LA) PWD (SC), FORT, THIRUVANANTHAPURAM.** **3. DISTRICT COLLECTOR, THIRUVANANTHAPURAM.** ## **4. K.SUBRAMONI,** - **S/O.LATE P.KRISHNAN ASARI, T.C. NO.38/2380 ARYASALA, THIRUVANANTHAPURAM.** ***ADDL.R5 IMPLEADED :** **5. K.GOPAKUMAR, S/O.LATE P.KRISHNAN ASARI, T.C.38/2382, ARYASALA, CHALA P.O., THYCAUD VILLAGE, THIRUVANANTHAPURAM-695036.** - ***ADDL.R5 IS IMPLEADED AS PER ORDER DT 14/3/.2011 IN IA 4212/11.** **R1 TO R3 BY GOVERNMENT PLEADER SRI.SHYSON P. MANGUZHA R4 BY ADV. SRI.D.SAJEEV ADDL.R5 BY ADV. SRI.K.K.SATHEESH** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 19-06-2013, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **BP** ## **WP(C).No. 37767 of 2009 (M)** ## **APPENDIX** ## **PETITIONER'S EXHIBITS :** - **P1: COPY OF THE ORDER IN SLP (CIVIL) NO. 14591/2000 OF THE SUPREME COURT DT 27/8/2001.** - **P2: COPY OF THE NOTIFICATION NO. LA55-15089/2004 DT 19/6/2006.** - **P3: COPY OF THE NOTICE IN LAC NO. 164/2009 DT 2/11/2009.** - **P4: COPY OF THE RECEIPT THE COPY OF THE OBJECTION FILED BY THE PETITIONER BEFORE THE R3 DT 23/12/2009.** - **P5: COPY OF THE NOTICE ISSUED BY THE R3 DT 12/1/2010** ## **RESPONDENT'S EXHIBITS :** **EXT.R4(a): COPY OF THE JUDGMENT DT 27/6/2000 IN WRIT APPEAL NO. 1166/2000 OF THIS HON'BLE COURT.** **EXT.R4(b): COPY OF THE ORDER DT 12/2/2009 INCIVIL APPEAL NO. 5972/2001 OF THE HON'BLE SUPREME COURT OF INDIA** **EXT.R4(c): COPY OF THE JUDGMENT DT 22/5/2000 IN OP NO. 8105/2000 OF THIS HON'BLE COURT.** **EXT.R4(d): COPY OF THE ORDER OF THE SECRETARY THIRUVANANTHAPURAM CORPORATION DT 10/3/2000.** **//TRUE COPY//** **P.A. TO JUDGE** **BP** ## **C.K. ABDUL REHIM, J. -----------------------------------W.P.(C). No. 37767 of 2009 --------------------------------------------------Dated this the 19[th] day of June, 2013** ## **JUDGMENT** Ext.P2 notification issued under Section 4(i) of the Land Acquisition Act is under challenge. The petitioner is admittedly a tenant conducting business in a building situated in the property sought to be acquired. 2. It is avered that, earlier there was another acquisition proceedings with respect to the very same property, in which a portion of the building was acquired. It is stated that, at that time the landlord had exercised option under Section 49 of the Land Acquisition Act and sought for acquisition of the entire building. Steps taken under Section 49 by landlord was challenged by the petitioner before this court. The matter was taken by the petitioner upto the hon'ble Supreme Court. Under Ext.P1 order, dispossession of the petitioner was stayed on 27.08.2001. In the meanwhile, the acquisition proceedings impugned herein was initiated, on the basis of Ext.P2 notification. The petitioner was issued with a notice of the award passed, as per Ext.P3. On getting such notice the W.P.(C). No. 37767 of 2009 -2- petitioner submitted Ext.P4 representation before the District Collector requesting to drop the acquisition proceedings. Since it was not considered, this writ petition is filed. 3. Ext.P2 notification is challenged on the ground that it is a composite notification issued under Section 4(i) and Section 17(4) of the Act. According to the petitioner a declaration under Section 17(4) can be made only after publication of Section 4(1) notification and any steps taken on the contrary is unsustainable. It is further contended that, denial of opportunity to challenge the proposal for acquisition and dispensation of the enquiry under Section 5(a) cannot be justified. It is also alleged that the impugned acquisition proceedings was initiated only at the instance of the landlord, in order to get rid of the petitioner from occupation of the building. According to the petitioner the invocation of Section 17(4) itself was not maintainable. 4. In the counter affidavit filed by the 4[th] respondent it is mentioned that the petitioner had W.P.(C). No. 37767 of 2009 -3- approached this court suppressing material facts in a manner abusing the process of law. It is stated that, challenge against exercise of Section 49 was finally decided by the hon'ble Supreme Court in the judgment in Civil Appeal No. 5972/2011 dated 12.02.2009. Despite the same the petitioner had produced only the interim order. It is contended that the petitioner has no right to challenge the notification issued under Section 4(1) or any declaration made under Section 17(4), because he has no right to continue in the acquired premises when the hon'ble Supreme court held that the building in question is liable to be acquired on the basis of option exercised by the landlord under Section 49. 5. In the counter affidavit filed on behalf of the 1[st] respondent it is mentioned that the present acquisition is for widening of Kalady-Maruthoorkadavu road and Karamana - Thaliyal road. Ext.P2, Section 4(1) notification, was duly published. Thereafter a notification under section 6(1) as per the Survey and Boundary Act 1961 was also published on 19.6.2006. Pursuant to this W.P.(C). No. 37767 of 2009 -4- the survey and sub division records were approved by the District Survey Superintendent and draft declaration under section 6(1) of the Land Acquisition Act was approved by the Commissioner, Land Revenue, on 24.9.2007. It was published in the official gazette, news papers as well as at the site. Notice under section 9(b) was also served to the parties concerned regarding the award enquiry. Award in this case was passed as early as on 26.9.2009. It is stated that, as per the land acquisition case, an extent of 1.21 Ares of land was acquired from one P.Krihnan Achari who had expired. The possession of the land with structures has already been handed over by the awardees on 10.12.2009. The petitioner is one of the 3 tenants in the shop room situated in the acquired property. The other two tenants have already been dispossessed. Therefore a notice under section 15(3) was issued to the petitioner on 14.1.2010. It is further stated that originally an extent of 2.15 Ares was acquired for widening of Karamana-Kilippalam road and with respect to the said acquisition the petitioner had filed cases up to the W.P.(C). No. 37767 of 2009 -5- Hon'ble Supreme Court. The petitioner is only a tenant running a hotel in the building which is sought to be acquired. The entire land acquisition proceedings were pursued in strict compliance with all the legal procedure. Therefore the petitioner cannot challenge the acquisition proceedings at this stage, is the contention. 6. While appreciating the grounds raised in challenge of the acquisition proceedings, it is noticed that the building in which the petitioner is conducting business was ordered to be acquired in the earlier proceedings by virtue of option exercised by the landlord under section 49. The petitioner failed in his challenges against the exercise of option under section 49. The matter now stands concluded through judgment of the Hon'ble Supreme Court, copy of which is produced as Ext.R4(b). As such the petitioner has no locus standi to challenge the fresh acquisition proceedings initiated. Even with respect to the grounds raised in this writ petition, it is to be observed that the petitioner has no locus standi to question the notification on the basis that it is a composite W.P.(C). No. 37767 of 2009 -6- notification issued under section 4(1) and 17(4). Going by Ext.P2 it is evident that it is only a notification issued under section 4(1) wherein it is mentioned that the Land Revenue Commissioner had permitted to proceed with further steps dispensing enquiry contemplated under section 5(a). It is evident from the facts narrated through counter affidavit of the 1[st] respondent that all the procedure for the acquisition now stands completed and an award has already been passed. Under such circumstances the claim of the petitioner regarding any irregularity with respect to dispensing with enquiry contemplated under section 5(a) cannot be considered. 7. Learned counsel for the petitioner had drawn my attention to various decisions of the Hon'ble Supreme Court such as **Baburam and another vs. State of Haryana and another (2009 (10) SCC 115), Union of India and others vs. Mukesh Hans (2004 8 SCC 14) and State of Uttar Pradesh vs. Radhey Shyam Nigam and others (1989 (1) SCC 591).** The dictum laid in all these cases with respect to exercise of power W.P.(C). No. 37767 of 2009 -7- under section 17(4) has no bearing in this case, in view of the fact that, the challenges raised by the petitioner, who is only a tenant, can at best only to the extent to the proportionate compensation out of the award. Further it is to be noticed that all the procedural formalities with respect to the acquisition has completed and award has already been passed. Under such circumstances the writ petition deserves no merit and the same is accordingly dismissed. Sd/- ## **C.K. ABDUL REHIM, JUDGE** /True copy/ P. A. to Judge pmn/Pn