'
875
S. P. BHATNAGAR ETC.
_v._
STATE OF MAHARASHTRA
_January_ 4, 1979
[JASWANT SINGH AND 0. CHINNAPPA REDDY, JJ.]
_Pre1·e111ion_ _of_ _Corrup•tion_ _Act,_ 1947 _s._ S(l)(d) _&_ _s._ _5(2)-Scope_ _of-Proof_
_of_ _guilt based on circumstantial evidence-Tests for deciding._
Both the appellants were officers of Indian Oil Corporation. The Corpora·
tion invited tenders from experienced contractors for rock cutting, filling and
levelling of cert2.i [1] .1 land acuired by it. On the notified date it opened the
tenders received from eleven contractors. But in the meantime since it made
a change in the specification of work to be done it asked the tenderers to sub·
mit revised tender. The direction to submit fresh tt:nders was restricted only
to the original 11 tenderers. Even so it \\'as alleged that a te\1der form was
issued by the appellants to A-4, who was not one of the 11 tenderers. There
\:Vas age.in a change in the specifr:ation of the work _to_ be done at the suggestion of foreign collaborators. The appellants were alleged to have asked the
concerned officers of the Corporation to make a fresh survey along with A-4,
keepi•.1g in view the suggestion of the foreign collaborators. EventuaJly ~1-'!.e con
tract \Vas giYe11 to A-4. The prosecution alleged that ( 1) the conduct of the
appellants showed their keenness to have the contract entrusted to A-4. (2)
the issue of work order was inflated with :figures relating to rock cutting and
filling; and ( 3) the appellants removed certain original documents fron1 the
departmental files at.1d substituted in their pla;ce fabricated material.
The appellants who were charged with offences under s. 120B and s. 109
IPC ands. 5(2) read withs. 5(l)(d) of the Prevention of Corruption Act, 1947
were convicted and sentenced to undergo imprisonment.
On the question whether the appellants had been rightly convicted under
s. 5(1)(d) of the Prevention of Corruption Act.
A11o\ving the appeals,
HELD : 1. An analysis of the circumstantial evidence adduced by t!le prosecution did not lead to the unerring certainty that the appellants acted with
any dishonest or corrupt motive or abused their position. [904 FJ.
A
B
c
D
E
F
2. (a) It is well settled that abuse of position, in order to come v1ithin G
the mischief of s. 5(1) (d) of the Act, must necessarily be dishonest so that it
may be proved that the ar.:cused caused deliberate loss to the department. Further it is for the prosecution to prove affirmatively that the accused, by corrupt
or i1legal means or by abusing his position, obtained any pecuniary advantage
for some other person. [892 G; 893 A].
(b) Again, the fundamental rule relating to the proof of guilt based on
circumstantial evidence is that there is always danger that conjecture or su~pi~
~ion n1ight take the place of legal proof. In such cases the mind is apt to take
a pleasure in adC:hpting circumstances to one another and even in straining then! a
H
876 SUPREME COURT REPORTS [!979] 2 S.C.R.
**A** little, if need be to force them to forn1 parts of one connected whole and the
more ingenious the mind of the individual the more likely it is, in considering
such matters, to over-reach and mislead itself to supply some little link that
is wanting, to take for gratited some fact consistent with its previo;Js thcoric:s
and necessary to render them complete. [893 B-D].
(c) In cases where the evidence· is of a circumstantial n1ature. the circum**B** stances from which the conclusion of guilt is to be drawn should in the first
instance be fu1Jy established, and all the facts so estah!ished should be consistent only \Yith the hypothesis of the guilt of the accused. Again, t'1e circumstances should be of a conclusive nature and should be such as to t:Al'lndc every
hypothesis but the one proposed, to be proved. In other words there must be
a chain of evidence so far complete as not to give any reasonable ground for
a conclusion consistent with the innocence of the accused and it must be such
**C** as to show that within all human probability the act must have been done by
the accused. [893 D-F].
D
E
_M. Narayanana Nambiar_ v. _State_ _of_ _Kera/a,_ [1963] Supp. 2 SCR
724; _Maior_ S. _K. Kale_ v. _State_ _of_ _Maharashtra,_ AIR 1977 SC 822;
_Hanumant Govind Nergundkar_ v. _State_ _of_ _M.P.,_ [1952] SCR 1091,
AIR 1952 SC 343; _Palvinder Kaur_ v. _State_ _of_ _Pun;ab,_ [1953] SCR
94: AIR 1952 SC 354; _Charan Singh_ v. _State_ _of_ _U.P.,_ AIR 196' SC
529; referred to.
(d) The principle that inculpatory fact must be inconsistent with **the** **in-**
nocence of the accused and i!lcapable of explanation on any other hypothesis
than that of guilt does not mean that any extravagant hypothesis would be
sufficient to sustain the principle, but that the hypothesis suggested must be
reasonable. [893 G].
_Govinda Reddy_ v. _State_ _of_ _Mysore,_ AIR 1960 SC 29; referred to.
In the instant case the conduct of the appel1ants in preferring A~4 to any
ne\V contractor did not savour of dishonest irltcntions on their part. Although
the notice was sent by registered post to the 11 original tenderers there is nothing in that notice or elsewhere on the record to indicate that other contract0rs
**F** were precluded from submitting their tenders or that the corrigendum **extend-**
ing the date for submission of the tenders was neither intended to be published
TI(1f \Vas it actually published. The High Court had missed this fact. Th:! High
Court was also wrong in thinking that out of the nine contractors who sub
-,
"
mitted their revised tenders eight were from the original nine tenderers and
the ninth \Vas A-4. In fact five of the contractors that submitted the fresh
tenders were fresh tenderers. Moreover none of the officers of the Finance
**G** and Engineering Department of the Corporation who handled the file :elating
to the griant of contract ever raised any objection regarding the improper reception or ente1tainment of A-4's tender. This showed that there was nothing
wrong about the issue of tender Form to A-4 or its entertainment by the appellants. The contr21.::t in question was not a specialised job requiring any extraordinary skill. A-4 was the Corporation's old and tried contractcr who had
H
previously executed a number of works including rock cutting.
(2) Though it cannot be gainsaid that the second appellant had been extremely negligent in not scrutinising the papers, he affixed his signature in a
routine manner to the work order prepared by his subordinates without realising
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 877
**the importance** **of** **his act, placing fmplicit faith** **in** **the integrity** **of** **the latter.**
[900 E-Fl
(3) **There** **is** **no clear, cogent and convincing evidence to show that the**
**appellants had** **a1** **hand in the** **removlll** **of** **the level plans from the dcpartn1cntal**
**file** **relating to the contract** **and** **substitution of the faked plans. [900 G).**
CRIMINAL APPELLATE JURISDICTION : Criminal Appeal !'fas. 346
and 387 of 1975.
Appeals by Special Leave from the Judgment and Order dated
**A**
**B**
~ 6-8-75 of the Bombay High Court in Criminal Appeal No. 1005 and
1006 of 1973.
l _La/it Chari,_ _P._ _R. Guna,_ _A._ _K._ _Srivastava_ and _Vineet Kumar_ for
the Appellant in Cr!. A. No. 387 /75. **C**
_R._ _L._ _Kohli,_ _P._ _P._ _Rao,_ _R._ C. _Kohli_ and _R._ _Nagarathnam_ for the
Appellant in Crl. A. No. 346/75.
_V._ _S._ _Desai,_ _H._ _R. Kh,inna_ and _M._ _N._ _Shroff_ for the Respondent
in both the appeals.
The Judgment of the Court was delivered by
JASWANT SINGH, J.-The above noted two criminal appeals which
are directed against the common judgment and order dated August 6,
1975 o( the High Court of Judicature at Bombay a!fuming on appeal
the judgment and order dated August 6, 1973 of the Special Judge,
Greater Bombay, convicting S. P. Bhatnagar, appellant in the aforesaid first appeal, (hereinafter described as A-1) under s. l 20B read
'°'~ with sections 409 and 109 of the Indian Penal Code and s. 5 ( 1) read
with s. 5 (2) of the Prevention of Corruption Act, 1947, and sentencing him to six months simple imprisonment on each of the said two
- coui!ts as well as convicting A. S. Krishnaswamy, appellant in the
**,)c,** aforesaid second appeal (hereinafter described as A-2) under the afore.,- said two counts but reducing his sentence from nine months' imprisonment to,six months simple imprisonment on each one of those
counts, shall be disposed of by this judgment.
- Briefly put the case as set up by the prosecution was :
In 1964, the Indian Oil Corporation (hereinafter referred to as
'the Corporation') which is a Government owned company, decided
to purchase 13 acres and odd of a hilly tract of land situate in village
Mahul in Trombay (Bombay) from the Tatas for the purpose of erect
ing black furnace oil storage tanks and construction of administrative
buildings. After the area was taken over by the Corporation
Varandani (P. W. 20), Junior Engineer of the Corporation surveyed
the land in October, 1964, under the directions of A-1 and A-2 the
Engineering Manager and Senior Engineer respectively of the Engi
**D**
**E**
**F**
**G**
**H**
**A**
**B**
**c**
**D**
**E**
**F**
**G**
878 SUPREME COURT REPORTS [1979] 2 S.C.R.
neering Department of the Marketing Division of the Corporation
with a view to find out the extent of rock cutting and filling which
might be required to be done for levelling the area of 7 acres out of
the said tract of land. The kacha level plan (Exh. 125) and worksheets prepared by Varandani on October 13, 1964 and November 3,
1964 respectively during the course of his aforesaid survey (which
were signed by A-l and A-2, showed that 16,80,000 cft. of rock
cutting work and 8,00,000 cft. of filling work would have to be done
to suit the purpose for which the land was acquired. Estimate (Exh.
27) prepared by Varandani indicated that expenditure at the rate of
Rs. 30/- per 100 cft. for rock cutting and Rs. 10/- per 100 cft. for
filling would have to be incurred. Pucca tracing (Exh. 34) of level
plan (Exh. 125) and copies thereof signed by A-1 and A-2, and
contour plan prepared by Varandani and approved by Engineering
Manager were kept on the record. On the basis of the survey and
the estimate of expenditure made by Varandani, notice (Exh. 28)
**inviting tenders** **fron1** **experienced civil contractors** **for** **rock cutting,**
filling and levelling of the land in question was prepared by A-2 on
February 2, 1965, and was forwarded (under his signatures) by A-1
to the Finance Department for approval on February 5, 1965. After
the approval of the Finance Department, the Public Relations Oftlcer
of the Corporation by his letter (Exh. 29) dated February 11. l 965
requested Times of India, Indian Express and Free Press to publish
the tender notice (Exh. 28) wherein it was stated that the tenders
which should reach the Corporation by 2.30 P.M. on March 2, 1965
would be opened at 3.00 P.M. on that date. In response to this
notice eleven firms of contractors including Ram & Co. submitted
their tenders. N. N. Desai (hereinafter described as A-4) however
abstained from submitting his tender. In the meanwhile, it was
decided that instead of having stack measurement as provided in
Exhibit 28, it would be desirable to have the measurements on the
basis of differences between the existing and finished levels. Accordingly, on March 5, 1965, the aforesaid eleven tenderers were asked
to submit revised tenders on the basis of the amended tender notice
by March 15, 1965.
Although fresh tenders were restricted to the original eleven
tenderers, a tender form was issued to A-4 in response to the application made by him on March 8, 1965. On opening the tenders on
March 15, 1965, it was found that five out of the eleven original
**H** tenderers and four new ones including A-4 had submitted their tenders, that the tender of Ram & Co. whereby it had quoted Rs. 28/per I 00 cft. for cutting work and 'nil amount for filling was the
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 879
,,_.
)t
..
lowest and that the second lowest tender was of A-4 who had quoted
Rs. 26/- per 100 cit. for cutting and Rs. 6/- per 100 cft. for filling
work. Thus, the actual amount as per quotation of Ram & Co. was
Rs. 4,70,400/- and that of A-4 was Rs. 4,84,800/- for 16,80,000
cit. of cutting work and 8,00,000 cft. of filling work. On discovering
that the tender of his firm was the lowest, Roshan Lal, a partner of
Ram & Co. addressed communication dated March 20, 1965 to the
Managing Director of the Corporation requesting him that the aforesaid job of rock cutting and filling be entrusted to his firm in view
of its working experience detailed therein but handed over the same
to A-1. At or about this time, Messrs Labitos Oil Fields Limited,
a British firm whom the Corporation was trying to collaborate in its
project advised the Corporation that instead of three levels (steppings) which had been planned as per cantour map (Exh. 34) there
should be a single level and instead of the survey being on the basis
of 100 ft. spacing as done earlier by Varadani, it should be on the
basis of 10 ft. spacing. Accordingly A-1 and A-2 told Varadani
(P.W. 20) and S. D. Vaidya, another Assistant Engineer (hereinafter
described as A-3) to make a fresh survey alongwith A-4 according
to the advice of Messers Labitos Oil Fields Limited as it had been
almost decided to entrust the aforesaid work to A-4. Pursuant to
the instructions of A-1 and A-2, B. N. Desai, a representative of
A-4 was associated with the revised survey which was carried from
March 21 to March 26, 1965. As a result of the joint survey, kacha
level plan (Exh. 22) and work-sheet (Exh. 23) were prepared by
A-3 under the directions of Varandani. As a result of this survey,
it was found that rock cutting and filling would have to be done to
the extent of 23,30,454 cft. and 31,500 cft. respectively as against
16,80,000 cft. and 8,00,000 cft. respectively as found as a result of
the earlier survey. Notwithstanding the large variations in the cutting
and filling work which required to be done as a result of the revised
joint survey, the Engineering Department did not invite fresh tendett
but instead prepared another comparative statement on the basis of
the rates quoted by Ram & Co. and A-4 in their tenders opened on
March 15, 1965 and showed therein that the tender of A-4 had
turned out to be the lowest and that of Ram & Co. to be the second
A
B
c
D
E
F
G
- lowest. On April 7, 1965, A-2 drew up tender committee proceedings (Exh. 16) as reproduced below and got them signed by A-1 in
the hope that the recommendations made therein would be accepted
by Srivastava, (P.W. 5) the Financial Controller and Patel. the
Operation Manager of the Corporation, who were the other members H
of the Tender Committee, in addition to A-l and finally by Gopiil
Krishan, the then Chairman of the Company :
'..
A
**B**
c
**D**
**E**
**F**
**G**
**H**
880 SUPREME COURT REPORTS [1979] 2 S.C.R.
"Ref. No. ENG/ASK/Q 250 April 7, 1965.
Subject : Tender Committee proceedings for the finalisation of rock cutting, levelling of plot, taken over
from M/s. Tata at Bombay.
(1) We had taken over 13.5 acres of land from M/s.
Tata Power House at Trombay. It was intended to level
this plot of land and recover about 7 acres of land by cutting and levelling in order to put up our Black Storage tanks
and other allied facilities. Due to the uneven terrain, it
was decided to have two steppings so that the storage tanks
may be installed at a higher level and the remaining administrative blocks, were house stores etc., at a lower level.
Accordingly, Public Tenders were invited for rock cutting
and filling this area on 100 cft. basis.
(2) Subsequently, M/s. Lobitos Oil Fields Ltd. Ellesmere Port, Wirral, Cheshire, had negotiations with us for
putting up a Transformer Oil Blending Plant at this site.
The representatives of the above firm during their discussions with C. & S. M. and M. E. (accused No. 1) stated,
that they would like to have only plain piece of land instead
of steppings as was decided by us previously. This will
entail additional cutting and minimise the quantity of filling.
(3) Our estimated quantity previously was 16,80,000
cft. of cutting and 8,00,000 cft. of filling. As per the revision in the levels to be maintained at this site that the total
quantity of cutting comes to 23,30,456 cft. The quantity
of filling comes to 31,500 cft. The total estimated cost for
the original work was Rs. 6,13,200/-.
A comparative statement has been drawn as per the
tendered rates quoted by the various parties and the position of the first three is as follows
**S.** **Name of Contractor** Qty. **Rate** **Amount** **Total**
No. **%Cft.**
**3.** **Libery Constructions** **Cutting** 23,30,450 28/- 6,52,526'\
Cft.
**1.** **N. N. Desai** **Cutting** 23,30,450 Cft.
26/- Sd. 6,05,917'L 6,07,807
**Filling** 31,500 Cft. 6/- 1,890 _f_
2. Ram & Co. **Cutting** 23,30,450 28/- 6,52,526 6,52,52'6
Cft.
Filling 31,500 cft. free
6,55,676
Filling 31,500 cft.
3,150 J~
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ J.) 881
M/s. N. N. Desai, Contractor arc the lowest. The Tender
Committee therefore recommends that this work may be
allotted to M/s. N. N. Desai, Contractor at their quoted rate
of Rs. 6,07,8071- being the lowest tenderer.
Sd/(S. P. Bhatnagar)
M.E.
Approved
(P. A. Gopalakrishnan)
Chairman.··
(A. K. Srivastava)
F.O.
!H. B. Patel)
O.M.
A
B
c
D
E
F
G
H
Contrary to the expectations of A-1 and A-2, Srivastava (P.W.
5) refused to be a party to the Tender Committee recommendations.
Ignoring not only the opposition of Srivastava and the suggestion
of the Accounts Officer of the Finance Department and
the Assistant Finance Controller of the Corporation made vide Exhibit 68 and Exhibit 31 respectively while processing the tender committee proceedings that in view of the fact that both the quantity
and value of the work had increased substantially as a result of the
revised survey, it would be fair and proper to ask all the contractors
"'l who had responded to the tender notice to re-submit their quotations
-- but also the offer made by Ram & Co. (which possessed the requisite
skill and equipment) to execute the contract at the lower rates of
Rs. 20/- per 100 cft. for rock cutting and Rs. 15/- per 100 cit. for
filling as well as the flat refusal to reduce his rates given by A-4
during the negotiations conducted at the suggestion of the Accounts
Departmcr•t of :the Corporation on April 17, 1965 with the three
contractors mentioned in Exhibit 16, A-2 carried on, in pursuance
of the conspiracy entered into between himself and A-1 and A-4 fresh
negotiations with A-4 on or about April 20, 1965 without associating
any member of the Finance Department and persuaded him to accept
the lowest revised rates offered by Ram & Co. although he did not
possess the requisite experience in and equipment for rock cutting
and filling and by passing the Financial Controller forwarded the
papers'to the Operation Manager who not being conversant with the
proceedings supported A-2 for entrusting the contract to A-4 at the
lowest rates offered by Ram & Co. On the Tender Committee _re-_
commendations reaching him in circulation. Srivastava put on record
his bold and emphatic protest but eventually reluctantly gave his con
882 SUPREME COURT REPORTS [1979] 2 S.C.R.
A currence to the recommendations made by A-1 and the Operation
Manager as is evident from the concluding sentence of the Note :
B
c
D
E
F
G
R
"The case is recommended for acceptance of the Chairman only because the Engineering Manager has certified
that he would not be able to accept any responsibility about
the deadline if work is not given to Desai."
Although according to A-2's note (Exh. 33) dated April 19,
1965, the Coordinator and Sales Manager was keen to have the site
developed as early as possible, the latter held up the matter for nearly
three months in the vain expectation that the work would be done
free of cost either by the Government of Maharashtra or the Bharat
Sevak Samaj and it was not before July 15, 1967 that he gave his
approval to A-l's proposal to award the contract to A-4 whereafter
accepting the said proposal the Managing Director of the Marketing
Division and Chairman of the Board of Directors of the Corporation
accorded sanction to the entrustment of the work to A-4. On receipt
of the sanction, A-1 forwarded the papers with his endorsement to
the Financial C:ontro!ler on July 29, 1965. On July 30, 1965, work
order (Exh. 19) manifesting quantity of rock cutting work as
29,30,450 cft., filling work as 90,000 cft. and value of the work as
Rs. 5,99,590/- as against the corresponding figures of 23,30,450 cft.,
31,500 cft. and Rs. 4,70,000/- respectively as specified in the final
sanction which was based on the aforesaid level statement (Exh. 22)
and work sheet (Exh. 23) was prepared and handed over by A-2 to
A-4. Copies of the work order were also endorsed by A-2 to the _f_
Bills Section of the Engineering Department and the Accounts Section of the Finance Department of the Corporation with the endorsement "the above has Chairman's approval on our note of even
reference dated 7th April 1965. Please have the agreement executed. Earnest money of unsuccessful tenderers may also please be
refunded early." On July 30, 1965, formal contract (Exh. 74) mentioning only the number and date of the work order in the blank
columns of the printed forrn was prepared and signed by A-4 and a
representative of the Company. The joint level statement Exhibit
22 and the work sheet Exhibit 23 in respect of the joint survey made
between March 21 and 26, 1965 for ascertaining the extent of rock
cutting and filling which formed the basis for invitation of tenders
and the final sanction in favour of A-4 were not only left unsigned
by the concerned but were actually removed from the file and were
substituted by spurious level plan (Exh. 24) and its copy (Exh. 38)
which were fabricated by A-3 to justify the inflated figures of rock
cutting and filling work mentioned in the work order (Exh. 19) dated
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh, I.)_ 883
July 29/30, 1965. On August 19, 1965, fabricated level plans A
(Exhibits 24 and 38) prepared by A-3 were sent to A-4 as annexures
to Exhibit 106 which ran as under :
B
c
D
E
F
G
"We are enclosing herewith two prints of spot level of land
area to be dressed and levelled at our Trombay plot.
The whole plot should be brought to a level of 102.00
as directed.
Please return to us a copy of the Blue Print showing
spot levels duly signed as a token of acceptance of the same
for payment."
While A-4 retained one of the spurious plans viz. Exhibit 38
with himself, he returned the other viz. Exhibit 24 after putting his
initials thereon. Thereafter A-3 endorsed on the Jetter Exhibit 106
that 'the print signed by A-4 should be filed by Sukhtankar (P.W.
13 J who is in charge of the filing section.' Accordingly, Sukhtankar
filed Exhibit 106 alongwith Exhibit 24 in the Bill Section. The
actual rock cutting operations commenced with effect from August 1,
1965 and on August 27, 1965, A-4 prepared and submitted the first
running bill (Exhibit 51) indicating that 8,00,000 cft. of cutting
work and 80,000 cft. of filling work had been completed. This bill
was accompanied by the certificate of A-3 reading as under :
"The measurements on which column No. 3 of this bill
are based were taken by me on 24-8-65 and recorded at
pages of MMC No. 7201. Certified that the quantities of
work actually executed as shown in column No. 4 has
actually been done and in no case less than the on account
payments claimed.''
The above certificate was countersigned by A-2 on August 26,
1965. A-2, A-3 and A-4 also signed measurement certificate
(Exhibit 52) which read as follows :
"We certify that the measurements given above are
the actual works carried out in accordance with the drawings and specifications as indicated in the work order referred to above."
On the basis of these certificates, the first on account running bill H
was passed and paid for. Thereafter the second and third running
bills and measurement certificates Exhibits 53 and 54 dated Septem
-.A
### ..
A
B
c
D
E
G
H
884 SUPREME COURT REPORTS [1979] 2 S.C.R.
bcr 16, 1965 and November 17, 1965 respectively claiming that the
additional cutting work of 5,00,000 cft. and 8,00,000 cft. had been
done were likewise prepared by A-4 and signed by A-3 and countcrsigned by A-2. The fourth running bill and measurement certificate
(Exh. 55) dated February 22, 1966 claiming that additional work
to the extent of 7,00,000 cft. had been done was prepared by A-4
and signed by A-3. This bill which was countersigned by K. S. Joshi,
another Senior Engineer who was put incharge of the Project in :he
absence of A-2 who had been transferred to Delhi was also paid.
On November 8, 1966, one Gurunath Naik (P.W. 17) who was
working as a Junior or Assistant Engineer for some time in Bombay
and for the remaining period at Allahabad, Kanpur and Mugalsarai
was called by A-1 and asked to see Ramrao, the then Junior Engineering Manager. Accordingly Naik met Ramrao who directed him
to go to the spot and have the level drawings. Pursuant to this
direction, Naik went to the site for spot verification and reported to
Ramrao vide Exhibit 18 that excepting at one place where he got a
level of 102-9 nowhere else did he get a level of 102. Naik also
reported that as against an area of 7 .4 acres which had to be levelled
hardiy an area of 4.8 acres was attempted to be levelled. On
December 30, 1966, A-4 submitted his final bill (Exb. 56) claiming
to have completed the work by August 11, 1966. This bill bore the
certificate dated December 29, 1966 of A-3 to the effect that the
measurements on which column No. 3 of the bill was based was taken
by him on that date, and bad been recorded in the measurements of
the .M.B.M.C. book. A-3 also recorded a further certificate to tho effect
that the work had been completed 100% according to the specifications and drawings. This certificate of A-3 was followed by another
certificate of A-4 that he accepted the above certificate and certifiee
that the amount of payment which he received on that bill would be
in full and final settlement of all his claims in respect of the work
excepting the refund of his security deposit. By this bill, A-4 claimed
to have done 3,84,720 cft. of cutting work and 18,200 cft. of hlling
work in addition to the work covered by the four earlier running bills.
Thus A-4 claimed to have done 31,84,720 cft. of rock cutting
work and 98,200 cft. of filling work. On this bill, which bore
the certificates of A-3 and A-4 was countersigned by Ramrao on
December 30, 1961 and wherein it was falsely claimed by A-4 that
the work was completed on August 11, 1966-although that date
was also much beyond the stipulated clate-A-3 recorded the foilowing note:
,.
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 885
"The final bill amounts to Rs. 6,51,674/- and is in excess of
work order amount by Rs. 52,084. Since this excess is within
10% of the ordered amount, M.E. may kindly approve."
Accordingly the papers were laid before A-1 who accorded the
desired approval the moment the bill was laid before him and sent
it for payment to the Accounts Officer ignoring the practice which
required all such bills involving an excess of 10% over the sanctioned
amount to be submitted to the Chairman for sanction. On the bill
coming before the Accounts Department for scrutiny, it pointed out
that since the actual work exceeded the sanctioned amount by
Rs. 52,084/- for which originally the approval of the Chairman was
taken, the excess needed to be regularised by obtaining his sanction. It
was also pointed out that as the contractor had not completed the
work within the stipulated time, the question of imposition of penalty
also required to be considered. On the pay order being returned to
the Engineering Department, Ramrao, the ·then Deputy Engiueering Manager, submitted the following reply vide Exhibit 59 dated
January 12, 1967 :
A
B
c
D
..
The excess is within 10% of the original estimate,
M.D. is therefore requested to kindly approve the excess
wdrk done and to pass the final bill for Rs. 6,51,674/-.
As per the work order, the work was to be completed
within 4 months (120 working days). However, the Contractors could not complete this work including the disposal
·of the excavated stuff within this time limit due to the fact
that there was no approach available to this plot. The
party has completed the work expeditiously, after the
approach was given to them by M/s. Talas.
M. D. is therefore, requested to consider this aspect
and approve the time limit extension upto 11-8-1966, the
date on which the party has completed the work."
l8-40SCI/79
"The work is now completed as required. However
to acquire the required level and gradient, the quantity of
work has increased. The party has now submitted their E
final bill for this work amounting to Rs. 6,51,674/- which
is in excess by Rs. 52,084/- than the original amount of
work order .
F
G
H
A
B
c
D
E
F
G
H
886 SUPREME COURT REPORTS [1979] 2 S.C.R.
On the matter coming back to the Finance Department, Shende
(P.W. 16) pointed out that not only the quantities of rock cutting and
filling work which were found as a result of the survey made between
March 21 and 26, 1965 had been enormously inflated in the work
order but the work claimed to have been done also exceeded the inflated figures mentioned in the work order. He, therefore, suggested
that the Department might agree to the payment of extra amount to
A-4 subject to A-l's obtaining the Board's ratification. Sometime
before March 28, 1967, Krishnaswamy Rajam (P.W. 1), the Chief
Internal Auditor, was summoned by the Managing Director and the
General Manager and was asked to have a personal talk with A-3 in
connection with the matter. On P.W. l's questioning A-3 on March
28, 1967, the latter made confessional statement (Exh. 21) which is.
reproduced below for facility of reference :
''Regarding rock cutting and filling at T rombay site I
wish to bring to your kind attention the following :
I was assigned to this job after the work was
started at site by M/s N. N. Desai. The original
estimates for cutting and filling were 16,80,000 cft.
and 8,00,000 cft. respectively. It was later revised
to 23,30,450 cft. and 31,500 cft. for cutting and
filling. I have got the workings for this revision
with me at Ahmedabad. (He refers to the genuine
level statements and plans and worksheets Bxs. 22
and 23 which were prepared by him under the directions of Varandani between 21st and 26th March,
1965).
Later on I was advised by my superiors to give
a still further upward revision giving the quantities
as 29,30,450 cft. for cutting and 90,000 cft. for filling. The work sheets prepared by me and signed
by contractor only (N. N. Desai) has no bearing to
actual quantities involved. I had merely acted as
asked by my superiors in preparing worksheets
accordingly which has resulted in this upward revision. I have also given measurement certificates irr
this regard in line with the revised wrong quantities.
I realise now this has resulted in making excess payments to the contractor. I beg to be excused for
having done such a thing which was done solely at
the instance of my superiors in Engineering Depart
....
-y
,
##### f
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 887
ment. E.M. (accused No. 1) and Dy. E.M. are A
aware of this."
I
·~
•' I
,
..
.-;
I
Thereupon P.W. 1 put up the papers before the Managing Director and the General Manager who advised him to start investigation
on particular lines. During the course of the inquiry, A-2 told P.W.
1 that the work order which as far as he remembered was prepared
by A-3 was cursorily signed by him due to heavy rush of work and
that while checking the running bills submitted for payment, he normally checked the percentage of progress of work certified by the
Assistant Engineer. On further investigation made on April I, 1967,
A-3 produced the genuine level statement (Exh. 22) and the work
sheet (Exh. 23) before P.W. 1 and told him that the substitution of
the fabricated level statement and work sheet relating to rock cutting
and filling at Trombay was done at the instance of Joshi, A-2 and
A-1 and that they were aware of the same. To the further question
as to what was the basis for the work order for the figure of 29,00,000
cft. of rock cutting and 90,000 cft. of filling, A-3 told P.W. 1 that
there was no basis for the work order and the quantities were fixed
to suit sanctioned amount. On a query being made by P .W. 1 from
Ramrao regarding the final bill, he admitted that he had not personally
checked the calculations and had counter;signed the bill relying on
the accuracy of the measurements shown in the bill which was prepared by A-3. He further stated that he had not personally checked
the calculations based on the final bill and initialled joint levels which
according to him were normally done by the Assistant Engineer.
During the course of this inquiry, Murthy (P.W. 18) was deputed
by A-1 and Krishnaswamy (P.W. 1) to go to the spot and find out
the work which had actually been done. Thereupon, Murthy (P. W.
18) submitted his interim report on April 6, 1967 pointing out that
at only one place the level was 103.94 and elsewhere it remained
much more. By his final report (Exh. 44) dated April 20, 1967,
Murthy (P.W. 18) pointed out tha~ actually on the spot only 9,73,000
cft. of rock cutting and 50,000 cft. of filling had been done. After
recording the statements of A-2, A-3 and A-4, Krislmaswamy (P.W.
1) submitted a detailed report (Exh. 25) on April 8, 1967 to the
Managing Director through the Financial Controller. In his report,
P.W. 1 also pointed out that contour plan/levels statement which in
case of this nature are jointly signed by the contractor and the representative of the Engineering Department were not available in the
instant case for inspection and that A-3 had produced a level statement alleged to have been processed by him and Varandani which
was not signed by any hody including A-3's superiors. P.W. 1 also
B
c
D
E
F
G
H
**A**
**B**
**c**
**D**
**E**
**F**
**G**
**H**
888 SUPREME COURT REPORTS [1979] 2 S.C.R.
pointed out in the course of the report that the quantities of rock
cutting and filling shown in the work order were 29,30,450 cft. and
90,000 cft. respectively and that there was an increase of 6,00,000
cft. of rock cutting straightaway. Krishnaswamy (P.W. **1)** also mentioned in his report that according to A-3, the level statement giving
the figure of 29,30,450 cft. for cutting and 90.000 cft. for filling had
been signed by A-4. ~
On the report being put up before the then Financial Controller,
he directed that before proceeding with the matter, it was necessary
to call for the comments of A-1. Thereupon after calling for a report
from Ramrao, A-1 gave his comments vide Exhibit 178 dated April
17, 1967 wherein after doubting the competence and qualification of
P.W. 1 to hold the investigation, he offered to send one of the senior
engineers from Western Branch to carry out an independent survey
to find out the quantity of work done by A-4 and suggested that
measurements might be made by reference to the kacha level statement (Exh. 125), the work sheet (Exh. 126) and the contour plan
(Exh. 34) which were checked by A-2 and approved by him and
which must be with the department. On April 18, 1967, A-1 sent
for A-3 and questioned him in regard to the matter. In the statement penned by A-3 himself, he stated that he changed the levels of
drawing of Trombay plot regarding rock cutting and filling job at the
instance of A-2 and KSJ (i.e. Joshi) but did not inform A-1.
On May 3, 1967, A-1 issued show cause notices to A-2 and A-3
with a view to hold departmental enquiry against them. By his reply
dated May 20, 1967 to the show cause notice, A-3 stated that he had
changed the original contour plan at the instance of A-2.
On getting information on July 15, 1967 that A-4 was having
some rock cutting done on the site althougli he had in his final bill
claimed that he had fully completed the work on August 11, 1966,
**A-1** and A-2 visited the site along with Lakshmanan, the Operations
Manager and finding that the work of rock cutting was still going on
and that the claim of A-4 as certified by A-3 and countersigned by
Ramrao about the work having been completed on August **11,** 1966
was apparently false had the measurements of rock cutting and filling
work taken by Ganapathy. As the measurements taken by Ganpathy
were on the basis of level plans prepared by Talas in which the bench
mark was 94.5 as against the bench mark of 100 for the survey **in**
question, the Managing Director had the measurements taken by
M/s **R.** **L.** Dalal & Co. The report of Dalal & Co. showed that the
rock cutting work done was 9,60,000 cft. and filling work was
1,96,000 cft. only.
..
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ J.) 889
~
I
..
,
On July 28, 1967, the Managing Director issued a charge sheet to
**A-1,** A-2, A-3 and Ramrao. In his reply (Exh.64) dated August 4,
1967 to the charge sheet, A-3 submitted that whatever he did was
W1der the orders of A-1 and the Deputy Engineering Manager. This
time he did not mention A-2 to be responsible for anything done by
him. On the same day i.e. August 4, 1967, A-1 sent for A-3 in his
cabin and questioned him in the presence of three other officers viz.
Roy Chowdhary (P.W.2), who was the Deputy Financial Controller,
Shriyan **(P** .W.23), the Assistant Engineer, and Vora, the Senior Engi
neer. On this Occasion, A-3 allegedly made statement (Exh.43)
absolving A-1 and throwing the entire responsibility on A-2. While
the three other officers and A-1 signed the statement (Exh.48) made
by A-3, A-3 declined to sign it and fled away from the chamber on
some excuse and rushed to the chamber of Krishnaswamy, Chief Inter
In his reply to the charge sheet, Ramrao inter alia stated that he
signed the bill (Exh.56) relying on the certificate of A-3 who had been
assigned to the job and added that according to the practice prevailing
in the Corporation, Senior Engineers were not expected to verify the
measurements. Elaborating his explanation; he stated that just as
Senior Engineer, Doraiswamy could not proceed to a **BPI** nor Senior
Engineer Vora nor Senior Engineer Chari could proceed to an installa
tion just to verify the billed quantities in view of the fact that there
were a number of bills on each work order and so many work orders
for each location. Similarly in the Branches, Senior Engineers who
were controlling the work for so many depots and installations were
not expected to verify the quantities in each bill; that however, if there
was a dispute with the contractor or there was some other reason to
doubt the correctness of the Assistant Engineer's certificate, the Senior
nal Auditor whereupon Roy Chowdhary (P.W.2) also followed A-3 to
the chamber of Kri,shnaswamy. In the chamber of Krishnaswamy,
A-3 resiled from the statement. Having regard to the position adopted
by A-3 in resiling from his earlier statement of that very day before
A-1, Roy Chowdhary reminded him that in the morning ill his pre
sence, he had stated that it was A-2 who was responsible for asking
him to change the drawing and increase the quantities. To this question of Roy Chowdhary in the chall!ber of Krishnaswamy, A-3 replied
in tho negative and stated that A-1 called him and Joshi into his room
and instructed him personally to increase the quantity. When questioned by Roy Chowdhary as to why he did not come out with that
""" truth in the room of A-1 in the presence of Roy Chowdhary, A-3
replied that he did not do so out of fear or A-1.
**A**
**B**
**c**
**p**
**E**
**F**
**G**
**H**
890 SUPREME COURT REPORTS [1979] 2 S.C.R.
.....
#### .J
A
B
c
D
E
F
G
H
during December, 1965 to February, 1966; that A. S. Krishnaswamy
who placed the work order bad countersigned bills upto 21 lakhs cft.
of cutting and 80.ono cft. of filling as early as November 17, 1965
and subsequently K. S. Joshi had countersigned a bill for an additional
7 lakhs cft. of cutting and the contractor had already been paid Rs. 5.72
lakhs less security deposit; that he, therefore' countersigned the bill
dated December 30, 1966 and passed it on to M.E. for approval of
the extra quantity of cutting; that M.E. approved on the same date and
the bills was sent to Engineering Bills for scrutiny by the Accountant
in respect of sanctions, work; order term.s etc; that he also particularly
instructed that the bill should be shown to K. S. Joshi before the pay
order was issued since normally the bill should have gone to him for
counter signature; that the Accountant carried out his inStructions; that
the counter signature did not denote final passing of a bill but only that
it might be proceeded further and subjected to all the necessary administrative and financial checks before payment; that all the bills for
the work bad been certified by the Assistant Engineer incharge who
was fully familiar with work and the previous bills had been counter
Engineer might either take measurements himself or get them taken by
another Assistant Engineer; that subsequent to the counter signature by
the Senior Engineer, the bill was passed on to the Engineering Bills
Section where the bills were checked by the Accountant against sanctions, work order, rates and amounts, deductions for cement A. C.
sheets or other materials supplied ar.d security; deposit etc; that the
Accountant prepared the pay order giving all these details for 'iignaturc
by a Senior Engineer as far as possible other than the countersigning
Senior Engineer; that the bill then went to the Accounts Department
where it was snbjected to further detailed scrutiny before payment;
that on December 30, 1966 Vaidya bronght the bill for Rs.79, 674/dated December 30, 1966 to him for counter signature; that it would
have normally been put up to K. S. Joshi but was brought to him as
he was not available; that Vaidya was the Assistant Engineer who had
handled that contract from the time of placing the work order; that the
bill was for the work carried out by the Contractor subsequent to the
previous 'on account bill' 21-2-66 (nearly 10 months earlier) i.e. about
3.18 lakhs cft. at Rs. 20/- per lCO cft. of cutting and 18,200 dt. of
filling at Rs. 15/- per 100 cft; that he bad visited Trombay number
of times in connection with other works during the period cormnencing from August, 1966 and was aware that the Contractor had carried
out approximately that much work during 1966; that the extra quantity
required sanction of competent authority; that the previous bills passed
showed that the major portion o[ the work was carried out during the
period August to December, 1965 and about 7 lakhs CFr of cu!ting
. •('
## -.
I"
'
,
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 89 l
signed by colleagues of status equal to him; that he had no reasons to
suspect any malpractice or mistakes and also there was no dispute with
contractor; that he had exercise the normal technical checks which
were the functions denoted by counter signature as per the prevailing
practice and that countersignature did not imply correctness of the
quantities certified by the Assistant Engineer (who alone was responsible for the correctness) in either the current or previous bilis.
When the matter was thus pending, a confidential information
reached Rege, the Deputy Superintendent of Police, C.B.I. (P.W. 27)
who registered the case on December 27, 1967. During the course "'.
investigation, he visited the office. of the Corporation, !ook charge of
all the concerned documents. had the site measured by Shivashankar.
Technical Examiner, Central Intelligence Service, ( P.W.4) accnrdin;
to whom the cutting and filling work done by the contractor was to the
extent of 9,61,000 cft. and 1,50,000 cit. resp£ctively and after securing
the requisite sanction, prosecuted A-1, A-2 and A-3 and also submitted the charge sheet against A-4 with the result that all the four accused were convicted.
In these appeals, we have had the advantage of hearing full Jrcsscd
arguments of counsel on both sides who diligently prepared the case
and put across their respective contentions with great ability.
We must point out at the outset that although the trial court had
clearly acquitted A-1 of the charge under section 409 read with section
120-B aqd section 109 of the Indian Penal Code it unfortunately
forgot to keep that fact in mind with the result that while concluding
its judgment it held him guilty on tllat charge as well. Jn the circumstances, it was not open to the High Court in the appeal by A-1 to go
into that charge and reverse the findings arrived at by the trial court.
We will accordingly be concerned with the question of validity of A-1 's
conviction nnder section 5 (2) read with section 5 (1) (d) of the Pre
vention of Corruption Act only but so far as A-2 is concerned, we will
have to examine the validity of his conviction uncler,,)1 the charges.
Before examining the sufficiency or otherwise of the material bearing
on the charges against both the appellants, we consider it necessary
to have a clear concept of the meaning and ambit of the phraseology
"by corrupt or illegal means or by otherwise abusing his position as
public servant" used in section 5(1) (d) of the Prevention of Corruption Act, 1947 (hereinafter referred to as 'the Acl"l for the mnt.cu- . .
vention of which the appellants have been convicted. _It_ will be advantageous in this connection to refer to two decisions rendered by this
A
B
c
D
E
F
G
H
892 SUPREME COURT REPORTS [1979] 2 S.C.R.
A Court in _M._ _Narayanana Nambiar_ v. _State of Kera/a(')_ and _Major_
_S._ _K._ _Kale_ v. _State of Maharashtra.(')_ In the first case, Subba Rao,
J. (as he then was) while construing clause (d) of sub-section (1) of
section 5 of the Act observed :
'
######
B
c
D
E
F
"The pharaseology 'by otherwise abusing his position as public servant' covers acts done otherwise than by corrupt or
illegal means by an officer abusing his position. The gist of
the offence under this clause is that a public officer abusing
his position as a public servant obtains for himself or for any
other person any valuable thing or pecuniary advantage.
"Abuse" means misuse i.e. using his position for something
for which it is not intended. That abuse may be by corrupt or illegal means or otherwise than those means. The
word 'otherwise' has wide connotation and if no limitation
is placed on it the words 'corrupt', 'illegal' and 'otherwise'
mentioned in the clause become surplusage, for on that
construction every abuse of position is gathered by the
clause. So some limitation will have to be put on that word
and that limitation is that it takes colour from the preceding
words along with which it appears in the clause, that is to
say something savouring of dishonest act on his part. The
contention of the learned counsel that if the clause is widely
construed even a recommendation made by a public servant
for securing a job for another may come within the clause
and that could not have been the intention of the Legislature.
But in our view such inocuous acts will not be covered by
the said clause. The juxtaposition of the word otherwise'
with the words "corrupt or illegal means" and the dishonesty
implict in the word "abuse" indicate the necessity for a dishonest intention on his part to bring him within the meaning
of the clause. Whether he abused his position or not
depends upon the facts of each case."
Following the decision in _M._ _Narayanan_ _Nambiar_ v. _State of_
G _Kerala_ (supra), it was beld by this Court in _Major_ S. _K._ _Kale_ v. _State_
_of Maharashtra_ (supra) that tbe abuse of a position in order to come
within the mischief of the section must necessarily be dishonest so that
it may be proved that the accused caused deliberate loss to the department. It was further held in this case that it is for the prosecution to
prove affirmatively that the accused by corrupt or illegal means or by
H abusing his position obtained any pecuniary advantage for some other
..
(I) [19631 Supp. 2. s.c.R. 724.
(2) A.l.R. 1977 S.C. 822.
_,
r
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ J.) 893
person. It would, therefore, be necessary to find out in this case as
to whether the accused abused their position and acted dishonestly or
with a corrupt or oblique motive in having the contract in question entrusted tc A-4. As the courts below have rested their judgments on a cons ..
tellation of circumstances, it would be well to bear in mind the fundamental rule relating to the proof of guilt based on circumstantial evidence which has been settled by a long line of decisions of this Court.
The rule is to the effect that in cases depending on circumstantial evidence, there is always the dang.\Or that conjecture or suspicion may take
the place of legal proof. In such cases the mind is apt to take a
pleasure in adapting circumstances to one another, and even in straining them _zo_ llttle, if need be, to force them to form parts of one connected whole; and the more ingenious the mind of the individual, the
more likely it is, considering such matters to cover reach and mislead
itselt. to supply some little link that is wanting, to take for granted some
fact consistent with its previous theories and necessary to render them
complete.
A
B
c
D
E
F
...
~Jl •
In cases where the evidence is of a circumstantial nature, the
circumstances from which the conclusion of guilt is to be drawn should
in the first instance be fully established, and all the facts so established
should be consistent only with the hypotheisis of the guilt of the accused. Again, the circumstances should be of a conclusive nature and
they should be such as to exclude every hypothesis but the one pro' posed to be proved. In other words, there must be a chain of evi
- ' dence so far complete as not to leave any reasonable grounds for
a conclusion consistent with the innocence of the accused and it must
be such as to show that within all human probability the act must have
been done by the accused. (See _Hanumant Govind Nargundkar_ v. _State_
_of_ M.P.,(1) _Palvinder Kaur_ v. _State_ _of_ _Punjab(')_ and _Charan Singh_ v .
_State_ _of_ _U.P._ ( [3] ).
..
The principle that inculpatory fact must be inconsistent with the
innocence of the accused and incapable of explanation on any other
hypothesis than that of gnilt does not mean that any extravagant G
hypothesis would be sufficient to sustain the principle, but that the
hypothesis suggested must be reasonable. (See _Govinda Reddy_ v .
_State_ _of_ _Mysore(')._
(1) [!952] S.C.R. 1091~A.I.R. 1952 S.C. 343.
(2) [1953] $.C.R. 94~A.I.R. 1952 S.C. 354
(3) A.I.R. 1967 S.C. 520.
( 4) A.I.R. 1960 S.C. 29.
H
**A**
**B**
**c**
**D**
**E**
**F**
**G**
**H**
894 SUPREME COURT REPORTS [1979] 2 s.c.R.
Keeping in view the aforesaid construction placed on section
_5_ (l)(d) of the Act and the principles with regard to proof of guilt
based on circumstantial evidence, let us now turn to the various circumstauces which have been relied upon by the High Court in holding
the appellants guilty and see whether they factually exist and if so
whether they are of such a character as to be wholly incompatible
with the innocence of the appellants and consistent only with their
guilt. In so doing, we purpose to divide the aforesaid circumstances
under the following broad heads and deal with them seriatim :
1. The conduct of the appellants evidencing their keen
ness to have the contract entrusted to A-4.
2. Issue of work order (Exh. 19) with inflated figures
relating to rock cutting and filling.
3. Removal of statement of level plan (Exh. 22) and
work sheet (Exh. 23) from the departmental file and
fabrication and substitution in their place of the fabricated ones by **A-3.**
4. Despatch on August 19, 1965 of spurious level plan
(Exh. 24) and its copy (Exh. 38) by A-2 to A-4 as
annexures to Exhibit 106.
_5._ Counter-signing of the on running bills by A-2.
6. The initialling of the final bill by A-1.
The first circumstance relied upon by the High Court in this
behalf is that though the revised tender notice was limited to the
eleven contractors who had originally submitted their tenders in
response to the Tender Notice (Exh. 28), the appellants improperly
got a tender form issued to A-4 and entertained by the Tender
Committee. It is true that the copies of Exhibit 15 on which the
prosecution has sought to rely were sent by registered post to the
eleven original tenderers by the Engineering Department of the Corporation but it cannot be overlooked that there is nothing in Exhibit
15 or elshhere on the record to indicate that other contractors
were precluded from submitting their tenders or that the corrigendum
extending the date for submission of the tenders was neither intended
to be published nor was it actually published. It seems that the attention of the High Court was not drawn to the co=unication (Exh.
29) dated March 9, 1965 addressed by Ranganath, Public Relations
1
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _J.)_ 895
Officer, to the Advertisement Manager, Times of India and others and A
the corrigendum forming annexure thereto which ran as under :
INDIAN OIL CORPORATION LIMITED
(MARKETING DIVISION)
Clarke Road, Mahalaxmi,
Bombay-34, WB, India
IN REPLY PLEASE REFER TO
PR 31 317
9th March, 1965
The Advertisement Manager,
The Times of India, (Bombay)
The Indian Express, (Bombay)
Free Press Journal, (Bombay)
Subject : Tender No. 249/65 Corrigendum
B
c
D
E
t
(
"
To
Dear Sir,
Attached is text of an advertisement for IMMEDIATE Publication utilising the minimum possible space under Public Notice/Tenders or in its appropriate place.
We would appreciate your treating this request as URGENT.
Thanking you.
Yours faithfully,
Sd/
(B. V. Ranganalh) F
Public Relations Officer
Encl One.
c.c. Engineering Manager, H.O. with reference to their
inter-office memo No- Eng/ ASK dated 9-3-1965. We
are trying to get it published on March 10.
INDIAN OIL CORPORATION LTD.
(MARKETING DMSION)
Corrigendum to Public Tender No. 249 /65
G
The last date for receiving this Tender has been exten- H
ded to 15th March, 1965 at 2-30 P.M. and will be
_opened_ _the_ _same_ day at 3-00 P.M."
A
B
c
D
E
F
G
H
896 SUPREME COURT REPORTS [1979] 2 s.c.R.
The attention of the High Court also does not seem to have been
invited to the above noted endorsement at the foot of Exhibit 29.
The High Court also seems to be wrong in thinking that out of
the nine contractors who submitted their tenders in response to the
revised tender notice, eight were from the original nine tenders and
the ninth was A-4. A comparison of the two lists viz. the one of
the original tenders and the other of those contractors who submitted
their tenders in response to the revised tender notice would make it
clear that five contractors appearing in the second list were fresh tenderers.
The Financial Controller's note (Exh. 17) dated April 2, 1965
which appears to be the outcome of some personal pique itself shows
that it was only on April 15, 1965 that it was agreed between the
members of the Tender Committee that the grant of the contract would
be confined to one out of the three lowest tenderers, one of whom was
A-4.
The fact that none of the eleven officers of the Finance and the
EnginG-ering Department of the Corporation who handled the file relating to the grant of the contract in question ever raised any objection
regarding the improper reception or entertainment of A-4's tender by
the Engineering Department is a proof positive of the fact that Lhere
was nothing wrong about the issue of tender form to A-4 or its entertainment by the appellants.
Thus it is clear that the first circumstance relied upon by the High
Cour.t had no factual existence and could not be pressed into service
against the appellants.
The next finding of the High Court that while Ram & Co. was
best fitted for entrustment of the contract in question in view of the
vast experience and equipment possessed by it, A-4 did not have any
such merit. It is a matter of common knowledge that rock cutting is
not a specialised job and no extra-ordinary skill or experience is
required for the same and that every civil construction involves some
sort of rock cutting. It is also in evidence that A-4 who was the
Corporation's old and tried contractor had previously executed 98
works including the one on the An-top Hill in Bombay for the Corporation to its entire satisfication, and out of the aforesaid works
many related to installations which were more complicated than rock
cutting and filling. It would also be noticed that in the notes put up
--•"
1
'
_<_
..
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ /.) 897
by them neither Srivastava (P.W. 5) nor Shivananda, Superintendent,
llOr Khurana, Assistant Financial Controller of the Finance Department, nor the Operation Manager ever pointed out that A14 lacked
the requisite experience or competence which disentitled him to the
grant of the contract. In fact Shivananda and Khurana had suggested as an alternative to inviting fresh tenders that A-4 should be asked
to reduce his rates in view of the revised figures on account of which
the value of the contract had gone up considerably.
It wonld also be noticed that the High Court while rightly holding
that Exhibit 122 was not delivered to A-1 by Roshan Lal (P.W. 19)
tell into an error in observing that A-1 had a hand in suppressing it.
It seems to have escaped its notice that at the negotiations conducted
on April 17, 1965 with the three lowest tenderers viz. Ram and Co.,
Liberty and Co., and A-4 by the Tender Committee, of which P.W. _5_
was a prominent member, Roshan Lal was present and while pressing
his firm's claim to the grant of the contract he did draw the attention
of the members of the Committee to the contents of Ext. 122 sent
earlier by his firm to the Corporation. This is evident from Roshan
Lal's own admission that he informed the corporation in writing as to
his experience in the line and whatever he had written he had also told
the concerned officers who were two or three in number. If A-1 wonld
have had a hand in suppressing Ext. 122 he would not have allowed it
to remain on the file. That apart a barn.perusal of report Ext. 33 which
i's fairly ddailed is enough to show that neither A-1 nor A-2 was intere'sted in suppressing or distorting any material fact. There was,
therefore, hardly any justification for the observation in question.
The third finding of the High Court that the appellants told
Vrindani (P.W. 20) and Vaidya (A-3) that it had already been
decided to entrust the contract to A-4 and in order not to loose time,
a joint survey should be made, is also erroneous. It is unbelievable
that A-1 and A-2 who were pre-occupied with several projects would
go and tell Vrindani who was three or four steps below them and was
admittedly not a member of the conspiracy nor concerned with policy
matters that it had been already decided to assign the contract to A-4.
The aforesaid briefing attributed to the appellants also seems to be
incredible in view of the fact that it was only on the basis of the level
measurements taken by P.W. 20 and A-3 during the survey made by
them between March 20 and 26, 1965 that A-4 turned out to be the
lowest tenderer and at the time when the briefing is alleged to have
been given the lowest tender was of Ram & Co.
A
B
c
D
F
G
H
# •
1
..
••
A
B
c
D
E
F
G
H
898 SUPREME COURT REPORTS [1979] 2 S.C.R.
The insinuation implicit in the fourth finding of the High Court
that Exts. 16, 17, 30-33 and 123 led to the inference that A-1 was
the author and architect of the proposal for acceptance of A-4's
tender, is also unwarranted. There is nothing in these documents
which can be interpreted to indicate that the appellant was actuated
by any ulterior or corrupt motive or that he was guilty of any mis-demeanour, irregularity or impropriety. _Pn_ the contrary the said documents
particularly Exts. 16 and 33, which like an open book fairly set-out
all the facts and circumstances bearing upon the allotment of the contract in question including the claim thereto of Ram & Co. not only
manifest, that the procedure referred to by P.W. 1 in his deposition for
inviting and finalizing the tenders was meticulously followed in the
present case, but also establish A-l's bona fides. It has also to be
borne in mind that the Tender Committee wbich comprised of the
Operation Manager and the Financial Controller in addition to A-1
had only an advisory role to play and the decision to entrust the contract to a particular contractor lay with the Chairman of the Board of
Directors in consultation with the coordinator and Sales Manager who
was above the Tender Committee. That the appellant's proposal
favouring A-4 was in the interest of the corporation both from the
point of view of economy as well as speedy and satisfactory execution
of work and was solely inspired by his concern tu avoid the sad
experience which the corporation had in respect of rock cutting work
at An-top hill with the Kore Brothers which was a new party is
evident from the following endorsement made on A·33 by H. B. Patel,
Operation Manager :
"In view of the urgency and our past experience with a
new party at An-top hill, I agree to Senior Engineer's proposal that we give the job to M/s. N. N. Desai at the lowest
tendered rates."
The fifth finding of the High Conrt that the appellants had negotiations on their own with A-4 with a sinister object is also against the
weight of the material on the record. The act of the appellants in trying to ascertain from A-4 whether he was prepared to reduce his rates
to the level of M/s. Ram & Co. which seems to have been taken in
consultation and agreement with P.W. 5 was, in our opinion, guiltless,
It would be well to remember in this connection that Shrivastava
P.W. 5 himself admitted in the course of his deposition that there was
practice in their corporation of asking the second lowest tenderer to
match his rates with the lowest tender. The proposal about the allotment of work in favour of A-4 was, therefore, not only consistent with
the practice but was also in the interest of the corporation.
s. P. BHATNAGAR ~- MAHARASHTRA _(Jaswant Singh,_ _J.)_ 899
In view of the foregoing we arc inclined to think that the conduct A
of the appellants in prefering A-4 to any new contractor did not savour
of dishonest intention.
r
'
..
_Re._ 2 : Coming to the work order (Exh. 19) containing inflated
figures which is the comer stone of the prosecution case, it may be
pointed out that the prosecution has not been able to produce any
evidence showing the circumstances under which it was prepared. The
observation of the High Court that the work order must be the creation of not only A-2 but of A-1 as well seems to be based upon mere
conjecture. It would be noticed that the work order does not bear the
signatures of A-1 and there is nothing to show that in the normal
course, the work order had to come to A-I before being issued to A-4.
We cannot also in this connection afford to lose sight of the observations made by the trial court at page 279 of the Paper Book that 'it is
a common ground that accused No. i is not concerned with the making of the order and that it is also a common ground that a work order
is issued by the Engineer Incharge'. In these circumstances, it is difficult to understand how the High Court came to the conclusion that the
work order (Exh. 19) was the creation of not only A-2 but of A-I as
well. It seems that the finding of the High Court was influenced by
its finding with regard to Exhibits 16 and 33. In view, however, of our
finding with regard to Exhibits 16 and 33, the observation of the High
Courc that the work order was also the creation of A-1 cannot be substained. We will, accordingly advert to the material on the record with
a view only to see how far it reflects on the bonafides of A-2. The
prosecution has not led any evidence to prove that A-2 dictated or
prepared the work order. The proven facts show that according to the
normal practice prevalent in the department it is not the Senior
Engineer like appellant No. 2 who is incharge of the Project that prepared a work order but an assistant or Junior Engineer in charge of
the work working under him. Although Varandani has in the course
of his deposition tried to suggest that the work order was prepared by
A-2, his suggestion cannot be relied upon in the face of Exhibit 67
whcreia he told P.W. 1 that the work order was presumably prepared
by Vaidya, A-3. It is highly improbable that on the very day of the
grant of the sanction of the contract in question A-2 would take the
extremely hazardous step of inflating the figures to obtain undue
advantage for A-4 specially when he knew that the fraud would be at
once discovered by reference to the sanction which bad been transmitted to the Finance Department.
The prosecution theory that the work order giving inflated figures
was not only signed but was also prepared by A-2 is also negatived
B
c
D
E
F
G
H
900 SUPREME COURT REPORTS (1979) 2 S.C.R.
**A** by the following endorsement on the copy of the work order sent to
the Bills and Accounts Sections of the Engineering Department of the
Corporation :
**B**
**c**
**D**
E
**F**
**G**
**H**
"The above has Chairman's approval on our note of
even 1eference dated 7th April, 1965. Please have the
agreement executed. Earnest money of unsuccessful tenderer; may be refunded early."
The above quoted endorsement completely demolished the prosecution case. If A-2 had been the author of Exhibit 19, or had suspected that his subordinate would have dared to inflate the quantities
of the work, it is inconceivable that he would have made the above
quoted insertion giving the particulars of the above mentioned note
meant for the Chairman's aproval in the copy of the work order
addressed to the Bills and Accounts Sections which would have furnished a valuable clue for the speedy detection of the fraud that is
alleged to have been perpetrated.
Again if A-2 were really a conspirator who had falsely inflated
the figures of rock cutting and filling in the work order he would have
seen to it that the potential documentary evidence embodied in Exhi
bit 125 which showed the genuine levels on the spot was destroyed
or done away with. The fact that be did not do anything of the kind
raises a strong doubt about his culpability.
Thus though it cannot be gainsaid that A-2 has been extremely
negiigent in not ~crutinising the papers, it seems to us that he affixed
his signatures in a routine manner to the work order prepared by his
subordinate engineer without realizing the importance of his act
placing implicit faith in the integrity of the latter.
_Re._ 3 _:_ There is no clear, cogent and convincing evidence to show
that A-1 or A-2 or both had a hand in the removal of the level plan
(Exh. 22) or the work sheet (Exh. 23) from the departmental file
relating to the contract in question and substitution in their place of
the faked level plan (Exh. 24) and work sheet (Exh. 38) which were
admittedly fabricated by A-3. The statements made from time to
time by A-3 in this behalf being contradictory and discrepant as would
be evident from the following table :
S. Date No. of the **Text of the statement**
No. **Exhibit**
-------- -----------I. 28-3-1967 21 **The original estimates for cutting and filling were**
16,80,000 cft. and 8,00,000 cft. respectively. It
was later revised 23,30,450 cft and 31,<00 cft.
_**_.-r**_
..
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ _!.)_ 901
S. Date No. of the Text of the statement
No. Exhibit
**A**
**for cutting and filling ............ Later on I was**
**advised** **by** **my superior** **in** **Engineering Depart ..**
ment, E. and Dy. E.M. to give a still further UP·
**ward** **revision** **giving** **the** **quantities** **as** **29,30,450 cft.**
for cutting and 90,000 cft. for filling. **B**
2. 1-4-1967 J6 ASK, KSJ and SPB asked me to substitute SHS
**relating to rock** **cutting and filling** **at** **Trombay**
**which has** **resulted in larger** **quandties of cutting and**
**filling** **and** **they are fuUy** **aware of it.**
3&4 18-4-1967 39 & 41 I told R. Krishnaswamy when he called me on
29-3-1967 that A.S. Krishnaswamy and K. S.
**Joshi told me to change the levels** **of drawings** **of**
**Trornbay plot regarding rock cutting/filling** **job·**
**In** **reply to the further** **query** **of R. Krishnaswamy,**
I told him that I did not inform M.E. about this
**and** **that** **he** **n1ight** **be** **knowing.**
_5._ 20-5-1967
6. 4-8-1967
7. 4-8-1967
69 In addition to the statement dated 18-4-1967, I
**have to** **submit that I was asked to change the**
**original** **contour, plane by A.S. Krishnaswamy,**
**Senior Engineer.**
**43** **Sometime** **in** **September>** **1%5.** **A.S. KrishnaswamY**
**told me to increase the levels** **at** **random and bring**
**the quantity to about 30** **lakhs** **cft.** **I** **did so**
**accordingly.**
**42 The** **Engineering Manager** **called me and Shri**
**Joshi** **into his room one day and instructed** **me**
**personally to increase the quantity.**
**c**
**D**
**E**
**F**
**G**
**H**
,
the prosecution ought to have made a serious attempt to produce
K. S. Joshi whose testimony was essential to clear up the mystery in
which the whole affair is shrouded. The non-production of **K.** **S.**
Joshi who appears to have been one of the main actors in the drama
has left a lacuna which is very difficult to bridge. In thB present
state of evidence, it is inconceivable that A-1 who admittedly had a
meritorious record of service, had won commendation from the Board
of Directors for designing a tank and saving considerable sums of
money and who was the only Head of Department to be given three
advance increments for his integrity and efficient work and who had
no are to grind would be a party to the unholy conspiracy for the
removal of genuine level plan and work sheet and their substitution
by spurious ones simply to obtain some pecuniary advantage for A-4
who was neither his friend nor relative. The position of A•2 is also
902 SUPREME COURT REPORTS [1979] 2 S.C.R.
A not materially different as in his case also the prosecution has not been
able to show that he derived any monetary gain out of the transaction.
B
c
D
E
F
G
H
_Re._ 4 :-A bare perusal of statement contained in Exhibit 43
which according to H.N. Roy Chowdhary (P.W. 2) and C. L. Shriyan
(P.W. 23) was voluntarily and without any pressure made by A-3
is enough to show that it was in September, 1965 that A-3 incrca,cd
the levels shown in the original drawings and brought up the quant:'.y
of rock cutting to 30 lakhs cft. This statement totally knocks the
bottom out of the prosecution case that the spurious level plan and
the work sheet were despatched to A-4 on August 19, 1965 as
anncxures to Exhibit 106. If the spurious plan and the work sheet
came into existence in September, 1965, it is difficult to underst;md
how they could be despatched to A-4 along with Exhibit 106 en
August 19, 1965. The conclusion, therefore, is irresistible that when
the communication (Exh. 106) was despatched to A-4, it was nc·t
accompanied by fabricated level plan (Exh. 24) and work sheet
(Exh. 38) but by the genuine ones viz. Fxbib;ts 22 and 23 and that
it was later on that the genuine ones were removed and retained by
A-3 who during the course of the enquiry by R. Krisbnaswamy
(P.W. 1) brought them from Abmedabad and banded them over to
P .\'II. 1. The ommission on the part of Shriyan who claims to be
certain that A-3 got the tracings Exhibits 24 and 38 prepared by him
in April/May, 1965 to contradict A-3 when he made the aforesaid
statement (Exh. 43) is also intriguing and lends assurance to the
correctness of our conclusion.
_Re. 5_ :-The first thing to be borne in mind with regard to the
measurement certificates on the running bills is that it is the Assistant
Engineer incharge of the work who is responsible for taking measurements of the actual quantities of the work executed by the contractor
for entering the same in the measurement book and for recording a
certificate that the measurements given in the bill are of the actual
work carried out on spot in accordance with the Department's drawings and specifications. It has also to be remembered that A-1 had
to look after the Corporation's projects and installations all over India nnd
A-2 had to look after and supervise a large number of the Corporation's projects under the Western Branch which included installations
at Sabarmati, Ahmedabad, Okba and Kandla in Gujarat and Sewri,
Wadala and Trombay in Maharashtra and parts of Madhya Pradesh.
It cannot also be ignored that according to Ganpati (D.W. 3) when
a Senior Engineer visits the site, he determines the progress of the
work by visual inspection determining visually the approximate
t
s. P. BHATNAGAR _v._ MAHARASHTRA _(Jaswant Singh,_ J.) 903
quantity of the work done. All this apart, an examination of the
running bills (Exhibits 51, 53, 54, _55_ and 56) shows that all of them
bear the certificates as referred to and reproduced at page 11 of this
judgment. It would be noted that whereas first three of these bills
bear the counter-signatures of A-2, Bill (Exh. 55) bears the countersignatures of K. S. Joshi, Senior Engineer and Bill (Exh. _5_ 6) bears
the counter-signatures of Ramrao, another Senior Engineer, who was
absolved in the departmental enquiry. Now the fact that A-2
countersigned the first three bills does not appear to be material in
view of the following statement made by Ramrao vide Exi1ibit
107
"I had no reason to doubt Shri Vaidya's figures.
Countersignature of a bill as per our prevailing practice is
not indicative of verification but only indicates that there
is no reason to doubt the correctness of the figures."
**A**
**B**
c
The fact that K. S. Joshi, Senior Engineer, also countersigned the
bill (Exh. 55) which contains inflated figures and no action was **D**
taken against him also lends assurance to the inference that the
counter-signatures were appended merely as a routine by the Senior
Engineers who seem to have reposed blind and nnllinching faith on the
honesty of their subordinates.
Now if Ramrao who countersigned the bill (Exh. 56) showing
the quantity of cutting work: as 31 lak:hs cft. was exonerated in the
departmental enquiry and no action was **taken** against **K.** S. Joshi
who made the wrong endorsement in respect of the measurement on
Exhibit _55_ or against Vora who had prepared the note (Exh. 58)
showing that the work had been completed, it is difficult to understand how A-2 could be treated differently and criminal intention
attributed to him. The finding of the High Court in respect of the
third running bill (Exh. 54) that the very defence of A-2 would itself
furnish the best evidence of the conspiracy involving A-1 is not correct
for apart from other infirmities from which if suffer, it is well settled
that the defence taken by one accused cannot in law be treated as
evidence against his co-accused.
_Re._ 6 :-The finding of the High Court that A-1 signed the bill
(Exh. 56) and sanctioned excess amount involved knowing full well
that the bill was not true is also against weight of the evidence on the
record. It cannot in the first instance be forgotten that it was on
July 29, 1965 that A-1 could have had occasion to see **the** figures of
the work for which sanction was granted by the Chairman of the
Board of Directors and the bill (Exh. 56) was put up to him on
**E**
**F**
**G**
**H**
904 SUPREME COURT REPORTS [1979] 2 s.C.R.
December 30, 1967. In the absence of the sanction from which the
genuine figures could have been gleaned, it would not be reasonable
to expect A-1 to remember the sanctioned figures after the lapse of
17 months specially when it is admitted on all hands that being the
head of the E_ngineering Department, he had to tour extensively to
supervise several projects spread all over the country and to discharge
multifarious duties in connection therewith. The bill, it would be
noted was prepared by A-3 and was countersigned by no less a functionary than the Deputy Engineering Manager, Ramrao, who was
next below A-1 in the hierarchy of the Department. In the note
prepared by him, it was not pointed out by A-3 that the bill had to
gQ to the Managing Director. The evidence in the case also shows
that A-1 was not expected to meticulously scrutinize the bill but was
conci;med only with the initialling of the note which although it had
passed through several hands did not indicate that the competent
authority to grant sanction for the excess amount was the Chall:man
of the Board of Directors.
It will also be wrong to hold A-1 responsible for simply initialling
the note contained in Exhibit 56 without examining Ramrao who
approved the bill including the note and also countersigned the
measurement certificate before it came to A-1. In the circumstances,
the mere initialling by A-1 of the bill alongside the note marked for
him by A-2 is, therefore not a circumstance which can unmistakably
be said to point to the guilt of the appellant.
An analysis of the circumstantial evidence adduced by the prosecution does not in our opinion lead to an unerring certainty that
A-1 and A-2 acted with any dishonest or corrupt motive or abused
their position.
A
B
c
D
E
F
G
In conclusion we cannot help observing that non-examination by
the prosecution of Ramrao, Joshi, Vora and Patel who were material
witnesses for the unfolding of its case has left some yawning gaps in
the evidence which we have found very difficult to bridge. If these
per~ons had been produce many of the points which have remained
obscure and hidden up would have been cleared up.
For the foregoing reasons, we allow the appeals, set aside the
convictions of the appellants and the sentences imposed upon them
and acquit them of the offences with which they were charged.
B
P.B.R.
40SCI/79-2500-21-8-79-GIPF .
_Appeals allowed._