S. Karthik & Ors. v. N. Subhash Chand Jain & Ors.
Case Synopsis & Summary
This is a Supreme Court civil appeal arising from the SARFAESI proceedings in respect of Ace Concrete Pvt. Ltd., four mortgaged properties, guarantees, and several rounds of DRT/DRAT/High Court litigation. The Bank issued notices under Section 13 (2) of the SARFAESI Act and initiated sale processes after the borrower became an NPA in 2011. Four writ petitions were filed in the Madras High Court challenging sale notices and resultant sales. The key controversy concerns the validity of the Second Sale Notice dated 9.7.2012 (and the corresponding auction on 20.7.2012) under Rules 8 and 9 of the Security Interest (Enforcement) Rules, 2002, amid long-pending litigation and interim orders. The appellants invoked decisions like Mathew Varghese and Kalpesh P.C. Surana to argue that Rule 8/9 mandates a mandatory 30-day gap and that a sale not properly notified must be remade, thus nullifying the auction. The respondent‑Bank and the auction purchaser argued the Second Notice was a continuation of the First Notice, with compliance to law, and that the guarantors’ conduct did not warrant setting aside the sale. The Court ultimately held the appellants’ contentions to be without merit, dismissed the appeals with costs, and ordered possession, rent payments to the auction purchaser, and refund of excess amounts to the third party owner where applicable, while upholding the sale.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- L. Narasimha?
- L. Nageswara Rao
- B.R. Gavai
- B.V. Nagarathna
- Judgment Date
- 2021-09-23
- Court Decision / Holding
- Appeals dismissed with costs. The appellants are directed to hand over vacant possession of Items A and D to the auction purchaser within eight weeks, and to pay rent realized from 15.09.2012 till date to the auction purchaser within three months. The Bank is directed to refund the excess amount (Rs. 4.48 crore) to Respondent No.3, with regard to the property owned by her, and to account for rental proceeds. The costs quantified at Rs. 1,00,000 each are payable to the Bank and the auction purchaser. The judgment also clarifies that the first and second notices complied with the procedural requirements and confirms that the sale was valid and should not be set aside on the grounds urged by the appellants.
- Final Disposition
- Appeals dismissed. The appellants to hand over possession and reimburse rents; refund to Respondent No.3; costs awarded.
Parties to the Case
Appellants / Petitioners
- S. Karthik
- Others (Guarantors/Directors/Promoters)
Respondents
- N. Subhash Chand Jain
- Shanthi Sivasamy
- Indian Overseas Bank (as secured creditor)
- Auction Purchaser (as transferee)
- Other Respondents (guarantors)
Legal Representation & Advocates
Counsels for Petitioners
- • K. V. Viswanathan (Senior Counsel)
Counsels for Respondents
- • Anitha Shenoy (Senior Counsel)
- • K.K. Mani (Counsel)
- • Saju Jakob (Counsel)
Provisions of Law Cited
Legal Doctrines & Maxims
- Equity of redemption is not extinguished by mere contract for sale; the mortgagor’s right to redeem survives until completion of sale by a registered deed (Narandas Karsondas / Mathew Varghese rationale)
- The secured creditor acts as a trustee and must comply with statutory sale procedures (Rule 8/9 and 13(8))
- 30 days’ notice to borrower before sale is mandatory under SARFAESI Rules (to enable tendering dues)
- Reading Rule 9(1)’s ‘or’ as ‘and’ to ensure 30 days’ clear notice to borrower and publication before sale
- Ratio from Mathew Varghese and Narandas Karsondas applied to ensure borrower protection during SARFAESI proceedings
Submissions & Arguments
Contentions of Appellants / Petitioners
The Second Sale Notice dated 9.7.2012 provided only a 10‑day period for payment of the revised dues and fixed the sale on 20.7.2012, violating Rule 8(6) and 9(1) of the Security Interest (Enforcement) Rules, 2002. Relying on Mathew Varghese, Vasu P. Shetty, Kalpesh P.C. Surana and J. Rajiv Subramaniyan, the appellants argued that the mandatory 30‑day gap must precede sale; if not, the sale is null and must be redone, with a proper 30‑day notice. They contended that the second sale notice was a continuation, not a fresh notice, and that the inconsistent schedule and amounts signify mala fide action by the Bank. They sought quashing the sale of Items A and D, reversion of possession, and refund of excess payments; they claimed the Bank did not proceed bona fide against the actual borrowers and sought relief for the excess money paid to third parties.
Contentions of Respondents
The Bank argued that the Second Sale Notice is a continuation of the First Sale Notice. Kalpesh Surana v. Indian Bank and Vasu P. Shetty were cited to support that 30 days may not be required in a subsequent notice. Bank contended that the appellants defaulted and that the sale complied with orders from DRT/DRAT/High Court; that the property had to be sold to recover dues, and that interim orders and multiple litigations did not vitiate the sale. The auction purchaser argued for protection of his rights as purchaser and emphasized that the sale was completed in 2012; Respondent No.3 (Shanthi Sivasamy) sought refund of excess money with a position that the excess funds belonged to her property; Bank contended it acted in accordance with tribunals’ orders and with statutory procedure.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (7)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Mathew Varghese v. M. Amritha Kumar and others | (2014) 5 SCC 610 | Positive | Used to elaborate mandatory 30 days’ notice under Rule 8/9 and Section 13(8); supports that notice must be clear and a fresh notice may be required if sale does not occur as scheduled. |
| J. Rajiv Subramaniyan and another v. Pandiyas and others | (2014) 5 SCC 651 | Positive | Cited to reinforce the same legal position on sale procedures under SARFAESI after guidance from Mathew Varghese. |
| Vasu P. Shetty v. Hotel Vandana Palace and others | (2014) 5 SCC 660 | Positive | Used to argue that sale not in line with mandatory procedure would be void or require strict compliance. |
| Kalpesh P.C. Surana v. Indian Bank | (2010) 3 CTC 287 | Positive | Cited to support that there may be differences in mandatory periods between first and subsequent notices. |
| Narandas Karsondas v. S.A. Kamtam and another | (1977) 3 SCC 247 | Positive | Principle on the right of redemption and that redemption survives until sale completed; foundational to SARFAESI interpretation. |
| Shakeena and Anr. v. Bank of India & Ors. | (2019) SCC Online SC 1059 | Positive | Cited regarding bank’s actions and recovery processes; supports the Bank’s approach under SARFAESI. |
| Dwarika Prasad v. State of Uttar Pradesh and others | (2018) 5 SCC 491 | Positive | Used to discuss the rights of purchasers and recoveries, including rent implications and possession. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
S. Karthik & Ors. v. N. Subhash Chand Jain & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.