## **IN THE HIGH COURT OF KERALA AT ERNAKULAM**
## **PRESENT**
**THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE**
**&**
**THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN FRIDAY, THE 24[TH] DAY OF MARCH 2023 / 3RD CHAITHRA, 1945 RFA NO. 270 OF 2017**
**AGAINST THE JUDGMENT AND DECREE DATED 29.10.2015 IN O.S.NO.85/2007 OF III ADDITIONAL SUB COURT, ERNAKULAM**
**------**
## **APPELLANTS/DEFENDANTS:**
- 1 **THE STATE OF KERALA, REPRESENTED BY THE SECRETARY TO GOVERNMENT, PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM.**
- 2 **THE SUPERINTENDING ENGINEER, P.W.D.BUILDINGS & LOCAL WORKS, CENTRAL CIRCLE, T.B.ROAD, THRISSUR.**
**BY SENIOR GOVERNMENT PLEADER, SRI.C.P.PRADEEP**
## **RESPONDENT/PLAINTIFF:**
- **1 **P.K.RAMACHANDRAN, AGED 74 YEARS, S/O.KUNJU PANICKER, RESIDING AT DEEPA MANDIR KARUVELIPADY, KOCHI, THOPPUMPADY VILLAGE, KOCHI TALUK, ERNAKULAM.(DIED)**
- Addl.R2 **A.R.DEEPA, SREELAKSHMI PRRA-9 PALLICHAMBEL ROAD, PALARIVATTOM P.O., KOCHI-682025.**
- Addl.R3 **A.R.DENOOP, DEEPA MANDIR, KARUVELIPADY, THOPPUMPADY P.O., KOCHI-682005.**
**BY ADVS.**
**K.BABU THOMAS MARYKUTTY BABU**
**THIS REGULAR FIRST APPEAL HAVING BEEN FINALLY HEARD ON 17.01.2023, ALONG WITH RFA NO.374/2017, THE COURT ON 24.03.2023 DELIVERED THE FOLLOWING:**
RFA Nos.270 & 374/2017 ..2..
## **IN THE HIGH COURT OF KERALA AT ERNAKULAM**
## **PRESENT**
**THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE**
**&**
**THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN FRIDAY, THE 24[TH] DAY OF MARCH 2023 / 3RD CHAITHRA, 1945 RFA NO.374 OF 2017**
**AGAINST THE JUDGMENT AND DECREE DATED 29.10.2015 IN O.S.NO.85/2007 OF III ADDITIONAL SUB COURT, ERNAKULAM APPELLANT/PLAINTIFF:**
- ***1 P.K.RAMACHANDRAN, DEEPA MANDIR, KARUVELIPADY, THOPPUMPADY P.O., KOCHI TALUK, ERNAKULAM, KOCHI-682005.**
- **Addl.A2 A.R.DEEPA, D/O.LATE P.K.RAMACHANDRAN, AGED 53 YEARS, SREELAKSHMI, PRRA-9, PALLICHAMBEL ROAD, PALARIVATTOM P.O., KOCHI-682025.**
- **Addl.A3 A.R.DENOOP, AGED 45 YEARS,**
**S/O.LATE P.K. RAMACHANDRAN, DEEPA MANDIR, KARUVELIPADY, THOPPUMPADY P.O. KOCHI -682005.**
**(THE LEGAL REPRESENTATIVES OF THE DECEASED SOLE APPELLANT ARE IMPLEADED IN THE PARTY ARRAY AS ADDITIONAL APPELLANTS 2 AND 3 VIDE ORDER DTD.01/08/2018 IN IA 1224/2018**
**BY ADVS. SRI.K.BABU THOMAS SMT.MARYKUTTY BABU**
## **RESPONDENTS/DEFENDANTS:**
- **1 STATE OF KERALA, REPRESENTED BY THE SECRETARY TO GOVERNMENT, PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM-695001.**
- **2 THE SUPERINTENDING ENGINEER, P.W.D.BUILDINGS & LOCAL WORKS, CENTRAL CIRCLE, T.B.ROAD, THRISSUR-680001.**
**BY SENIOR GOVERNMENT PLEADER, SRI.SRI.C.P.PRADEEP**
**THIS REGULAR FIRST APPEAL HAVING BEEN FINALLY HEARD ON 17.01.2023, ALONG WITH RFA.NO.270/2017, THE COURT ON 24.03.2023 DELIVERED THE FOLLOWING:**
RFA Nos.270 & 374/2017 ..3..
**A.MUHAMED MUSTAQUE & SHOBA ANNAMMA EAPEN, JJ. ---------------------------------------------RFA Nos.270 & 374 of 2017**
**---------------------------------------------Dated this the 24[th] day of March, 2023**
## **JUDGMENT**
## **A.Muhamed Mustaque, J.**
These appeals arise from the judgment of the
Sub Court, Ernakulam in O.S.No.85/2007 dated 29.10.2015.
2. The above suit was for declaration and
realization of money based on the contract entered
between the plaintiff and the State Public Works Department, the defendants in the suit. The suit
has been decreed substantially in favour of the
plaintiff. These appeals are preferred by the plaintiff and the defendants. The parties, for
brevity, in these appeals are referred to as the plaintiff and the defendants.
3. The plaintiff was awarded a work for the
construction of 350 bedded ward of an Ayurveda
RFA Nos.270 & 374/2017 ..4..
hospital at Thripunithura on 09.09.1997. The period of the contract was 24 months. The work was completed on 14.12.2005. The suit was laid for the unpaid value of the work. The plaintiff's claim and the claim allowed by the trial court can be summarized as follows:
|Nature of claim|Plaint claim|Allowed by the<br>trial court|
|---|---|---|
|The unpaid value of<br>the work carried out<br>between<br>21.9.1999<br>and 1.12.2004 based<br>on 1996 PWD Schedule<br>and<br>1999<br>PWD<br>schedule rate.|Rs.2,35,46,148/-|Rs.2,35,46,148/-|
|The unpaid value of<br>the work carried out<br>between<br>1.12.2004<br>and 14.12.2005.|Rs.47,84,011/-|Rs.45,29,922/-|
|Unpaid agreed rate<br>for flooring with<br>marble tiles.|Rs.89,70,231/-|Rs.87,60,427/-|
|Unpaid<br>value<br>of<br>works using semi-<br>wire cut bricks in<br>the place of country<br>burnt bricks.|Rs.15,72,751/-|Rs.15,72,752/-|
|Interest on delayed<br>payment|Rs.75,48,807/-|Rs.22,48,751/-|
|The value of cement<br>procured from the<br>open market|Rs.10,57,446/-|Rs.10,57,446/-|
RFA Nos.270 & 374/2017 ..5..
4. Heard the learned counsel appearing for the plaintiff and the learned Government Pleader.
5. We note that there was a considerable
delay in handing over the site and in supplying materials as agreed. No one has a case that the plaintiff had committed any default. The plaintiff
was paid a sum of Rs.9,29,06,994/- pending suit on
16.02.2009. The final bill was prepared on
25.11.2005. Though an argument has been raised by
the learned Government Pleader based on
limitation, in the light of the fact that the final bill itself was prepared only in the year
2005 and the suit was filed on 01.02.2007, we find
no merit in this argument. We, thus, overrule the argument of the learned Government Pleader.
6. The following issues were framed by the
court below:
- 1.Whether the plaintiff had made construction as per the agreement or not.
2. Whether the plaintiff is entitled to get a
RFA Nos.270 & 374/2017 ..6..
decree for realization of the amount claimed.
7. We have already overruled the objection of the learned Government Pleader on the point raised on the limitation. According to the learned Government Pleader, the plaintiff received the money after the final bill. The plaintiff also executed a supplemental agreement and in the light of the supplemental agreement and the acceptance of the final bill, the contractor cannot claim any other amount other than as agreed in the
agreement.
8. The learned Government Pleader referred to the following Clauses in the supplemental agreement:
Clause-3 in supplemental agreement No.1 is as follows:
“The decision of the Superintending Engineer regarding the amounts payable for the extra item shall be final and legally binding on the contractor and cannot be questioned by the
RFA Nos.270 & 374/2017 ..7..
contractor in any manner whatsoever.”
The recital in the supplemental agreement No.7 is
as follows:
“whereas the contractor further agreed that no further claim will be preferred on account of extension of the period of the contract”.
Clause 2 in supplemental agreement No.8 is as
follows:
“The contractor shall not claim any enhanced rate or compensation whatsoever for or on account of such extra items due to the increased rate of labour or materials or any other ground.”
The proceedings of the Superintending Engineer and
his order dated 19.4.2020, in Clause 1, states that due to the extension of time for completion, no claim for enhanced rate will be allowed for the work.
9. While allowing the claim, the trial court
relied on the opinion of the expert's report. The
RFA Nos.270 & 374/2017 ..8..
rates were quoted in accordance with the 1996 schedule by 60% in July 1999 and 80% in December,
2004. The expert, accordingly, calculated the
measured work and found that the plaintiff was entitled to a sum of Rs.2,73,33,999/- as against the claim for Rs.2,35,46,148/-. The question is whether the plaintiff is entitled to an enhanced claim in the light of the change of the PWD schedule of rates.
10. The learned counsel for the plaintiff Sri.Babu Thomas, placing reliance on the judgments in **M/s.Aries and Aries v. Tamil Nadu Electricity**
**Board [AIR 2017 SC 1897** ] and **Assam State**
**Electricity Board and others v. Buildworth Pvt.Ltd. [AIR 2017 SC 3336]** , argued that the plaintiff is entitled to escalation charges for the works delayed beyond the scheduled period of completion if the plaintiff is not at fault in completing the work.
11. The contract provisions have to be read
RFA Nos.270 & 374/2017 ..9..
keeping in mind the duty attached to the parties to the contract to perform the contract in accordance with the terms and conditions in the contract. The various clauses referred to as above cannot deter the plaintiff from claiming escalation charges if the delay was not occasioned by the act of the plaintiff. In this case, the site was handed over to the plaintiff after two years. The materials were not supplied as per the
agreement. No attribution of the fault has been made as against the plaintiff. The trial court correctly came to the conclusion that the delay was occasioned by the PWD itself. In **P.M.Paul v. Union of India [1989 supp.(1) scc 368],** the apex
court opined that escalation is a normal incident arising out of a gap of time in this inflationary age in performing any contract. No one has a case that a calculation made by experts based on the prevalent schedule is erroneous. In such circumstances, we affirm the impugned judgment
RFA Nos.270 & 374/2017 ..10..
awarding unpaid value work for Rs.2,35,46,148/and Rs.45,29,922/-.
12. The next claim is for the value of
marble. As per the contract, the agreed rate for
flooring the marble tiles included in item No.49
of the schedule of works, the plinth area was
10564.15 sq. m. The rate agreed was 1073.38 per
sq.m.. The plaintiff admittedly carried out the marble flooring in the additional area. As per the
expert report, the total area is 11169.45 sq.m.
The plaintiff was paid for 10564.15 sq.m. in 2004. The expert opined that for the additional work done, the plaintiff was entitled to
Rs.87,60,427/-. We do not find any error in the calculation of this amount.
13. The next claim was for the unpaid value of
the work using semi-wire cut bricks in the place of country bricks. The expert calculated the total value of the semi-wire cut machinery at Rs.56,72,560/-. The plaintiff was paid
RFA Nos.270 & 374/2017 ..11..
Rs.40,99,808/-. The balance has thus arrived at Rs.15,72,752/-. We also affirm the finding of the
trial court.
14. The next claim was for reimbursement of
the materials procured from the open market.
Exts.A9, A14, A20, A33, A38, A41, A42, A43, A62,
A63, A65, A70 and A78 were relied by the plaintiff to substantiate his claim. The above are
communications issued by the plaintiff. There is
no contradiction of the claim for these amounts as
referred to in the above letters. Admittedly, the
Department failed to provide the materials in time. We, thus, affirm that finding also.
15. The plaintiff filed a claim for
Rs.75,48,807/- towards interest for the delayed payment. The court below allowed Rs.22,48,751/-
towards interest for the delayed payment. This was subsequently incorporated in the original decree as it appears that there was an omission to include it in the judgment pronounced on
RFA Nos.270 & 374/2017 ..12..
29.10.2015. This portion was included only on
05.07.2016 as per the order in I.A. No.980/2016.
It is seen from the judgment, 6% interest was allowed. The amount was calculated at
Rs.22,48,751/- and subsequently incorporated in the decree. This can be treated as a clerical mistake and no illegality has been committed by
the court below in calculating the interest.
16. The claim for the plaintiff that he is
entitled to the enhanced rate of interest is
untenable as it is not a commercial transaction. However, the plaintiff is entitled to _pendente_
_lite_ interest at 6% and future interest. So also
the plaintiff is entitled to the cost before the
court below though it was not granted by the trial
court. Thus:
I. RFA 270/2017 is dismissed. No order as
to costs.
II. RFA No.374/2017 is partly allowed. The plaintiff is entitled to _pendente lite_
RFA Nos.270 & 374/2017 ..13..
and future interest at 6% till realization of decree on the reliefs granted other than for the decreed amount of
Rs.22,48,571/- ordered to be paid towards
interest.
III. The plaintiff is also entitled to the proportionate cost in the trial court. The plaintiff is also entitled to
proportionate cost in the appeal.
**Sd/-**
**A.MUHAMED MUSTAQUE, JUDGE**
**Sd/SHOBA ANNAMMA EAPEN, JUDGE**
ln
RFA Nos.270 & 374/2017 ..14..
## **APPENDIX OF RFA 270/2017**
PETITIONER ANNEXURES ANNEXURE I TRUE COPY OF SIGNED MEASUREMENT BOOK DATED 09.02.2009.