Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2011Single JudgeArbitration Petition disposed of

REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL

Case / Petition Number:
Arbitration Petition No. 18 of 2010
Neutral Citation:2011 (13) ADDL SCR 359

Case Synopsis & Summary

This Arbitration Petition concerns a dispute under a Memorandum of Understanding (MOU) dated 25 September 2007 between REVA Electric Car Co. P. Ltd. (petitioner) and Green Mobil (respondent) regarding supply and marketing of REVA cars in Belgium/Benelux. The MOU provided for a test/trial period and terms for possible renewal into a long-term distributorship; disputes arising “at any time” in relation to the MOU were to be referred to arbitration. The trial period was initially set to end on 31 December 2007, but the petitioner asserted that the MOU was extended by unilateral discretion and informal extensions, leading to termination only on 25 September 2009. In September–October 2009, after the termination, disputes and e-mails emerged, including Brussels court proceedings by the respondent seeking damages. The petitioner invoked arbitration under Clause 11 on 24 March 2010 and nominated a Sole Arbitrator. The respondent contended that the arbitration clause covered only the test period and that post-2007 claims were outside arbitral scope; it also argued that continuing distribution in 2008–2009 was not part of the MOU.” “The Supreme Court held that existence of an arbitration agreement is a jurisdictional fact for the Chief Justice/designate under s.11, that the arbitration clause survives termination under s.16, and that disputes relating to termination and its consequences fall within arbitration. The Court appointed Justice RV Ravendran as Sole Arbitrator and disposed of the petition.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Surinder Singh Nijjar
Judgment Date
2011-11-25
Court Decision / Holding
Arbitration Petition disposed of. The Court held that there is a valid arbitration agreement and that the arbitration clause survives termination; it appointed Hon. Mr. Justice R. V. Ravindran as Sole Arbitrator and directed the registry to communicate accordingly. The Arbitral Tribunal is to adjudicate the disputes arising between the parties on such terms as it deems fit.
Final Disposition
Arbitration Petition disposed of

Parties to the Case

Appellants / Petitioners

  • REVA Electric Car Co. P. Ltd.

Respondents

  • Green Mobil

Legal Representation & Advocates

Counsels for Petitioners

  • • P.S. Narasimha
  • • Vyapak Desai
  • • P.V. Dinesh
  • • Cherrie Alexander

Counsels for Respondents

  • • Tasneem Ahamadi
  • • Sudhir Kumar Gupta
  • • Manish Gupta

Provisions of Law Cited

Arbitration and Conciliation Act, 1996, s.11(4), s.11(5), s.11(6) and s.11(9)Arbitration and Conciliation Act, 1996, s.16(1)(a)Arbitration and Conciliation Act, 1996, s.16(1)(b)Arbitration and Conciliation Act, 1996, s.11(4) and s.6Arbitration and Conciliation Act, 1996, s.16(1)UNCITRAL Model Law, Article 16

Legal Doctrines & Maxims

  • Arbitration clause treated as independent of the contract (severability) – Section 16(1) of the Act.
  • Existence of arbitration agreement as a jurisdictional fact (SBP & Co. v Patel Engineering Ltd.)
  • Arbitration vs. court determination under Section 11 – three categories of issues (as per SBP & Co. and National Insurance)
  • Arbitration settlement by conduct/sub silentio (acceptance by conduct)
  • Arbitration clause survival after termination per Section 16(1) (contract nullity does not automatically nullify arbitration clause)
  • Three-category framework for Section 11(4)-(6) jurisdictional decisions; (i) issues to be decided by Chief Justice, (ii) issues he may decide, (iii) issues to be left to the Arbitral Tribunal
  • UNCITRAL Model Law Article 16 – competence of arbitral tribunal to rule on jurisdiction and the existence/validity of arbitration agreements

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner argued that the MOU dated 25 September 2007 created a valid arbitration agreement (Clause 11) to resolve disputes arising in relation to the MOU, including post‑trial period disputes arising from termination. It contended that the MOU was extended beyond 31 December 2007 by unilateral discretion and informal extensions, and that the termination on 25 September 2009 did not extinguish the arbitration clause. Therefore, the disputes, including those relating to Brussels proceedings, fall within the arbitration clause and must be referred to arbitration. The petitioner nominated a Sole Arbitrator under the Clause 11 scheme and sought referral of disputes to arbitration, contending that the clause survives contract termination (s.16) and that s.11(4) powers permit appointment by the Chief Justice of India (or designate).

Contentions of Respondents

The respondent contended that the MOU expired on 31 December 2007, and the arbitration clause only covered the test period, not post‑2007 disputes arising from the distribution phase. It argued that the Brussels proceedings involved matters beyond the MOU’s term and were outside arbitration coverage. The respondent urged dismissal or rejection of a reference under Section 11, relying on jurisprudence such as SBP & Co. and SBP’s three‑category framework, asserting that arbitration was inappropriate for disputes outside the MOU’s scope. It claimed that even if there was a contract, the contract being terminated would terminate the arbitration clause too, citing the same authorities in support.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (7)

Case NameCitationTreatmentExplanation
A.P. Tourism Development Corporation Ltd. v. Pampa Hotels Ltd.2010 (4) SCR 942; 2010 (5) SCC 425PositiveCited to establish that existing arbitration agreements and the framework governing Section 11 proceedings require evaluating jurisdictional questions, and to support the Court’s approach to invoking arbitration and interpreting the MOU’s arbitration clause.
Alva Aluminium Limited, Bangkok v. Gabriel India Limited2010 (13) SCR 803; 2011 (1) SCC 167PositiveCited for principles on arbitration clause severability and ongoing enforceability despite contract reformation or termination.
Brigadier Man Mohan Sharma, FRGS (Retd.) v. Lieutenant General Depinder Singh2008 (16) SCR 701; 2009 (2) SCC 600PositiveUsed to illustrate scope of arbitration and the court’s jurisdiction under Section 11 and the need to consider arbitration where disputes arise relative to the agreement.
National Insurance Co. Ltd. v. Boghara Polyfab Private Ltd.2008 (13) SCR 638; 2009 (1) SCC 267PositiveCited as authority on jurisdictional questions under Section 11 and the broad reach of arbitration clauses.
SBP & Co. v. Patel Engineering Ltd. & Anr.2005 (4) Suppl. SCR 688PositiveConstitution Bench ruling cited for the categories of issues the Chief Justice/designate may decide and the foundational requirement to ascertain existence of arbitration agreement.
Everest Holdings Ltd. v. Shyam Kumar Shrivastava & Ors.2008 (14) SCR 1221; 2008 (16) SCC 774PositiveCited to support the principle that arbitration clauses can survive despite termination and that independence of arbitration agreement should be respected.
Bharat Petroleum Corporation Ltd. v. Great Eastern Shipping Co. Ltd.2007 (11) SCR 117; 2008 (1) SCC 503PositiveCited to reinforce the proposition that disputes arising under an arbitration clause can be referred to arbitration even when surrounding contracts are in dispute.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•9,066 words•~42 min read

In The Court Record

REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL

(2011) 13 (ADDL.) S.C.R. 359 # M/S. REVA ELECTRIC CAR CO. P. LTD. A _v._ ## M/S. GREEN MOBIL (Arbitration Petition No.18 of 2010) NOVEMBER 25, 2011. B ## **[SURINDER SINGH NIJJAR, J]** _ARBITRATION AND CONCILIATION ACT, 1996:_ _s.11 (4), (5), (6) and 9_ - _Decision_ as _to existence of_ a _valid_ c - _arbitration HELD: It_ is _for Chief Justice of India/his designate to decide about the existence of_ a _valid arbitration agreement_ - _In the instant_ case, _the MOU contained an arbitration clause, and there existed_ a _valid arbitration agreement_ - _The contract_ - _existed till the date of its termination Therefore, it cannot_ 0 _be said that the disputes arising between the parties cannot be referred to Arbitral Tribunal_ - _The disputes have arisen in relation to the termination of the MOU and the consequences_ - _thereof Such disputes would be clearly covered under the arbitration clause_ - _Clearly, therefore, the disputes raised bx_ E - _the petitioner needs to be referred to arbitration Under the arbitration clause,_ a _reference_ was _to be made· that the disputes were to be referred to_ a _single arbitrator_ - _Since the parties have failed to appoint an arbitrator under the agreed procedure, it_ is necessary _to appoint an arbitrator- In exercise_ F _of powers_ u/s _11 (4) and (6) of the Act, read with Paragraph 2 of the Scheme of 1996, arbitrator_ is _appointed to adjudicate_ - _the disputes that have arisen between the parties Appointment of the Arbitrators by the Chief Justice of India Scheme, 1996_ - _Para 2._ G _s.16(1)(a)_ - _Arbitration agreement_ - Scope _of_ - _HELD: Section 16(1)(a) provides that an arbitration clause which forms part of the contract shall be treated_ as _an agreement_ - _independent of the other terms of the contract Even on the_ 359 H ## 360 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A _termination of the contract, the arbitration agreement would_ - - _still survive By virtue of s.16(1)(b), it continues to be enforceable notwithstanding_ a _declaration of the contract being null and void_ - _In view of the provisions contained in_ s. _16(1) of the Act, it cannot be said that with the termination of_ - B _the MOU, the arbitration clause would also cease to exist._ The petitioner filed the instant application for appointment of arbitrators stating that memos of understanding (MOU) were entered· into between the parties on 25.9.2007, 22.4.2008, 24.8.2008 and 1.4.2009 for C supply of cars to the respondent to be sold in Belgium · Region. However, as the respondent did not have the necessary resources to build up the brand of the petitioner, the latter through e-mail dated 25.9.2009 terminated the contract and asked the respondent to D immediately cease the sales and marketing activities on its behalf. The petitioner stated to have received a Writ of Summons dated 14.1.2010 of legal proceedings initiated by the respondent in the Commercial Court at Brussels in Belgium claiming damages on ac:count of E termination of fhe MOU dated 25.9.2007. The petitioner thereafter issued' a notice dated 24.3.2010 to the respondent invoking the arbitration clause of the MOU. The respondent in its reply dated 7 .4.2010 denied existence of any contractual relationship between the ·· F parties on the date of termination of MOU on 25.9.2009. The petitioner filed an arbitration application uls 9 of the Arbitration and Conciliation Act 1996 before_the Court of Principal· City Civil and Sessions Judge, Bangalore praying for an order of injunction restraining the G respondent from proceeding with the legal proceedings in the Commercial Court at Brussels, Belgium. The petitioner was granted a of temporary injunction. Thereafter the petitioner filed the instant application. The stand of the respondent was that the MOU dated H 25.9.2007 expired on 31.12.2007, as it related to the "Test REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 361 and Trial period" which came to end on 31.12.2007 after A which the parties decided to enter into a distribution agreement which was sent by the petitioner to the respondent on 15.11.2007 i.e. after 15 days prior to the expiry of MOU. Therefore, the arbitration clause relied ijpon by the petitioner did not cover any disputes/claims B that relate to any period beyond 31.12.2007. ## Disposing of the petition, the Court Held: 1.1 In a petition u/s 11 (4),(5),(6) and (9) of the Arbitration and Conciliation Act, 1996, it is for the Chief C Justice of India/his designate to decide about the existence of a valid arbitration agreement. [para 19] [376A-B] _A.P. Tourism Development Corporation Ltd._ Vs. _Pampa_ o _Hotels Ltd._ 2010 (4) SCR 942 = 2010 (5) SCC 425; and _Alva Aluminium Limited, Bangkok Vs. Gabriel India Limited_ 2010 (13) SCR 803 = 2011 (1) SCC 167; _Brigadier Man Mohan Sharma, FRGS (Retd.) Vs. Lieutenant General Depinder Singh_ 2008 (16) SCR 701 _=2009 (2) SCC 600; National_ E _Insurance Company Limited Vs. Boghara Polyfab Private Limited_ 2008 (13) SCR 638 = _2009(1) SCC 267;_ and _SBP_ & Co. _Vs. Patel Engineering Ltd._ & _Anr._ 2005 (4) Suppl. SCR 688 = _2005 (BJ sec 618_ - relied on 1.2 There is no dispute that the parties had entered F into a legally valid and enforceable MOU dated 25.9.2007. There is also no dispute that Clause 11 provides that the disputes arising between the parties, at any time, in relation to the MOU, shall be referred to arbitration. Clause (2) of the MOU, undoubtedly, fixes the trial period upto G 31.12.2007. However, the clause also provides that the petitioner may unilaterally decide to extend the MOU, if it considers necessary. The correspondence between the parties would show that the petitioner had proposed a draft distribution agreement to the respondent for H ; 362 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. ~ A discussion. Thereafter, a series of e-mails were exchanged between the parties, but making it apparent that no final consensus was reached. It would, therefore, appear that the MOU was duly extended till it was terminated as averred by the petitioner. [para 20) [376-CB E] 1.3 The petitioner has categorically pleaded that the MOU was terminated on 25.9.2009 and has placed on record the e-mail dated 25.9.2009 in which it is clearly stated that MOU was entered into on 25.9.2007 for a test C period of six months from the date of arrival of the trial cars. It is further stated that.this period was extended on an informal and voluntary basis by the petitioner for a period extending to two years from the date of signing of the MOU. During this two years period, a total of 15 D REVA cars have been sold and as the respondents did not have in place the necessary resources to build the REVA brand and to launch the M1 v~hicles introduced by REVA at the Frankfurt IAA, the respondent was asked to immediately cease all sales and marketing activities on E behalf of REVA brand. This termination of the agreement has been acknowledged by the respondents in its e-mail dated 7.10.2009. A perusal of this e-mail would also demonstr~te that the disputes had clearly arisen between the parties at that time. Clearly, therefore, the MOU has F been extended till its termination on 25.9.2009. It is also evident that the parties had failed to reach any fresh agreement with regard to sale of REVA cars in Europe by the respondents. The pleadings and the material on record has clearly established that there was ai valid G arbitration agreement incorporated in Clause 11 of the MOU. [para 21] [376-F-H; 377-A-E] • 2.1 The claims made by the respondents before the Court at Brussels, clearly pertained to the contract under the MOU dated 25.9.2007 which was terminated on H 25.9.2009. It would be for the Arbitral Tribunal to decide ## REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 363 as to whether claims made are within the arbitration A clause. The Arbitral Tribunal would also have to decide the merits of the claim put forward by the respective parties. [para 25 and 27] [379-D-F-G) _Bharat Petroleum Corporation Ltd. Vs. Great Eastern Shipping_ Co. _Ltd._ 2007 (11 ) SCR 117 = (2008 (1) sec 503 - referred to. B 2.2 The conclusion is inescapable that notwithstanding the initial period under the MOU expiring by 31.12.2007, the same was extended by the petitioner C in exercise of its discretion under Clause (2) of the MOU. The extended MOU was terminated only on 25.9.2009. Therefore, it cannot be said that the disputes arising between the parties cannot be referred to the Arbitral Tribunal. The disputes have arisen in relation to the D termination of the MOU and the consequences thereof. Such disputes would be clearly covered under the Arbitration clause which provides that in the event of any dispute or difference _arising at any time_ between the parties _in relation to the agreement_ shall be referred to a E Sole Arbitrator. The clause is clearly not limited to the disputes relating only to the initial period of the MOU till 31.12.2007. [para 30] [381-F-H; 382-A-B] > 2.3 Irrespective of whether the MOU is now in existence or not, the arbitration clause would survive. The disputes that have arisen between the parties clearly pertain to the subject matter of the MOU. [para 31) [382B-C; 383-E] F _Everest Holding Limited Vs. Shyam Kumar Shrivastava_ & _Ors._ 2008 (14) SCR 1221 = 2008 (16) &CC 774 - relied on· G 2.4 Even assuming that MOU was not extended beyond 31.12.2007, it would make little difference. Section 364 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A 16(1 )(a) of the Act provides that an arbitration clause which forms part of the contract shall be treated as an agreement independent of the other terms of the contract. The plain meaning of the said clause would tend to show that even on the termination of the agreement/contract, - B the arbitration agreement would still survive. To ensure that there is no misunderstanding, s. 16(1 )(b) further provides that even if the arbitral tribunal concludes that the contract is null and void, it should not result, as a matter of law, in an automatic invalidat,ion of the - c arbitration clause. By virtue of s.16(1)(b), it continues to be enforceable notwithstanding a declaration of the contract being null and void. In view of the provisions contained in s. 16(1) of the Act, it cannot be said that with the termination of the MOU on 31.12.2007, the arbitration - 0[clause ][would ][also cease to exist. [para 33-34] [383-F-H; ] 385-A-D] ## UNCITRAL Model Law - referred to. - 2.5 In the instant case, the disputes that have arisen - E between the parties clearly relate to the subject matter of the relationship between the parties which came into existence through the MOU. Clearly, therefore, the disputes raised by the petitioner need to be referred to arbitration. Under the arbitration clause, a reference was - F to be made that the disputes were to be referred to a single arbitrator. Since the parties have failed to appoint an arbitrator under the agreed procedure, it is necessary for this Court to appoint an arbitrator. In exercise of powers u/s 11 (4) and (6) of the Act, read with Paragraph - G. 2 of the Appointment of Arbitrator by the Chief Justice of India Scheme, 1996, the Sole Arbitrator is appointed to adjudicate the disputes that have arisen between the parties, on such terms and conditions as the Sole Arbitrator deems fit and proper. [para 34-35] [385-D-H; 386-A] . H REVA ELECTRIC CAR. CO. P. LTD. _v._ GREEN MOBIL 365 ||CaseLaw|LawReference:||A| |---|---|---|---|---| |2007 (11)|2007 (11)SCR117|relied on|para15|| |2008 (14)|2008 (14)SCR1221|reliedon|para15|| |2008 (16)|2008 (16)SCR701|reliedon|para16|B| |2008 (13)|2008 (13)SCR638|relied on|para16|| |2005|2005(4)Suppl. SCR688|relied on|para16|| |2010|2010(4)SCR942|relied on|para18|| |2010 (13)|2010 (13)SCR803|relied on|para18|c| |2007 (11)|2007 (11)SCR117|referredto|para28|| CIVIL ORIGINAL JURISDICTION : Arbitration Petition No. 18 of 2010. D Under Sections 11 (4) and 6 of the Arbitration and Conciliation Act, 1996. P.S. Narasimha, Vyapak Desai, P.V. Dinesh, Cherrie Alexander for the Petitioner. E Tasneem Ahamadi, Sudhir Kumar Gupta, Manish Gupta for the Respondent. The Order of the Court was delivered by ## ORDER F SURINDER SINGH NIJJAR, J. 1. The petitioner has filed the present application under Sections 11 (4) and (6) of the Arbitration and Conciliation Act, 1996 read with paragraph 2 of the Appointment of the Arbitrators by the Chief Justice of India Scheme, 1996. It is stated that the parties had entered G into a legally valid and enforceable Memorandum of Understanding ('MOU') dated 25th September, 2007, providing, _inter alia,_ for the respective obligation of both the parties in connection with the marketing of the cars of the petitioner. :rhough the term of the MOU was till December, H 366 SUPREME COURT REPORTS [2011] 13 (ADDL.) $.C.R. A 2007, it was extended by the acts of the parties in terms of Clause 2 of the MOU. 2. The petitioner makes a reference to various requests made by the respondent for supply of cars in terms of MOU on 22nd April, 2008; 24th August, 2008; and 1st April, 2009. The 8 petitioner further claims that some time in September 2009, disputes arose between the parties. Numerous e-mails were exchanged between the parties, apart from the personal discussions between their representatives, touching and covering the disputes. It is the petitioner's claim that during the C term of MOU, merely 15 cars of the petitioner had been sold in the Belgium Region. The petitioner, therefore, claimed that the respondent did not have in place the necessary resources to build the brand of the petitioner. Consequently, through e- mail dated 25th September, 2009 the petitioner requiested the D respondent to immediately cease sales and marketing activities on its behalf and take necessary steps of providing after sales and service to existing car owners, till such time the petitioner appointed its new distribut x. The petitioner claims that the aforesaid e-mail duly constituted the termination of the E contractual relationship between the parties as covered under the MOU. 3. As a consequence of the aforesaid termination, the parties have exchanged various e-mails raising claims and F counter claims on 6th /7th /8th October, 2009. 4. The petitioner further claims to have received a Writ of Summons dated 14th January, 2010 of legal proceedings initiated by the respondent in Belgium before the First Divisional Court, Room A of the Commercial Court in Brussels. G According to the petitioner, the claims made by the respondent before the Commercial Court, Brussels disclose that the respondent instituted the legal proceedings _inter alia_ claiming damages from the petitioner on account of termination of the MOU dated 25th September, 2007. On 15th March, 2010, the H counsel for the respondent sent an e-mail.communi~tion that ## REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 367 [SURINDER SINGH NIJJAR, J.] the respondent was willing to negotiate a global settlement with A the petitioner and that the respondent through its counsel would be available to discuss any such proposal. According to the petitioner, the aforesaid communication also acknowledges the fact that the rights and obligation of both the parties were covered by the distributorship agreement, i.e. the MOU, which B stood duly terminated. B 5. The petitioner thereafter issued a notice dated 24th March, 2010 through its counsel in terms of Clause 11 of the MOU invoking a:rbitration under the MOU and .referring all disputes between the parties to arbit.ration. The petitioner in fact nominated Mr. Justice Jayasimha Babu (Retired) as the Sole Arbitrator, and failing confirmation by the respondent, as the arbitrator of the petitioner on the three member Arbitral Tribunal to be constituted in terms of Clause 11. C D 6. The respondent through its counsel sent a reply to the notice dated 7th April, 2010 denying existence of any contractual relationship between the parties on the date of termination of MOU on 25th September, 2009. 7. The petitioner, therefore, filed Arbitration Application No.576 of 2010 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Court of the Principal City Civil & Sessions Judge at Bangalore praying for an order of injunction restraining the respondent from proceeding with the legal proceedings initiated before the First Divisional Court, Room A of Commercial Court of Brussels, Belgium. E F 8. The petitioner had also moved l.A.No.1 in the aforesaid suit dated 19th April, 2010 seeking an order of temporary injunction which was granted by the Principal City Civil & G Sessions Judge at Bangalore on 21st April, 2010. Thereafter the petitioner has moved the present application for appointment of the Arbitrator in terms of Clause 11 of the MOU which reads as under:- H ## 368 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A "11. Governing Law and Jurisdiction i. This MOU shall be construed and enforced in· accordance with the laws of India. - ii. In the event of any dispute or difference arising at any - B time between the parties hereto as to the construction, meaning or effect of this Agreement or thing contained herein or the rights, duties, liabilities and obligations of the parties hereto in relation to this Agreement, the same shall be referred to a single arbitrator, in case the parties can - c agree u"pon one (1) within a period of lhirty days upon being called by a party to do so and failing such agreement to three (3) arbitrators one (1) each to be appointed by GREENMOBIL and RECC and the third to be appointed by the two arbitrators so appointed. The - D award passed by such arbitrator(s) shall be final and binding on both the parties. - All such arbitration proceedings shall be held in Bangalore as per the Arbitration and Conciliation Act, 1996 as amended from time to time." - E 9. In reply to the aforesaid petition, the respondent claimed that the MOU dated 25th September, 2007 expired on 31st December, 2007. The petition does not clearly set out the claim or the period of the claim but the documents and implication F of the contents of the present petition seem to indicate that the claim of the petitioner is in respect of the commercial distribution of the cars which commenced from 1st January, 2008 i.e. after the expiry of Memorandum of understanding. It is also the plea of the respondent that the MOU relate to a test G and trial period which came to an end on 31st December, 2007, after which the parties decided to enter into a distribution agreement which was sent by the petitioner to the respondent on 15th November, 2007, i.e., 15 days prior to the expiry of the MOU. Therefore, the arbitration clause relied upon by the H petitioner does not cover any disputes/claims that relate to any REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL369 [SURINDER SINGH NIJJAR, J.] period beyond 31st December, 2007. It is further claimed that A th·e petition is' only a counterblast to the proceedings filed by the respondent before the Commercial Court at Brussels. This, according to the respondent, is evident from the fact that the respondent had instituted the proceedings in the Commercial Court at Brussels on 14th January, 2010; the petitioner was B intimated about the said proceedings vide e-mail dated 15th March, 201 O; and the notice invoking the arbitration clause in the MOU is dated 24th March, 2010. It is, therefore, clear that the arbitration clause is invoked only to avoid proceedings before the Commercial Court at Brussels. It is emphasised that c the proceedings before the Commercial Court at Brussels related to the period beyond the MOU when the parties had commenced work of distributorship or dealership after the test trial period under the MOU had come to an end. B 10. I have heard the learned counsel for the parties. D 11. Mr. Narasimha, learned senior counsel appearing for the petitioner submits that the averments made by the respondent in reply to the petition make it abundantly clear that the disputes pertained _tq_ the MOU dated 25th September, E 2007. According to the learned counsel, there was no fresh agreement entered into between the parties. Cars were being supplied to the respondent in terms of Clause 2 of the MOU. Making a reference to Clause 2, learned counsel submits that the aforesaid clause makes it clear that the MOU was effective F for a period of three to six months, from the date of arrival of the cars in Belgium. This term was to be considered as the trial period. On completion of the trial period but not later than 3rd December, 2007, the parties were to mutually decide to continue the marketing, sales, and service of the work hours G by the respondent. They were also to enter into a fresh long term agreement on mutually agreed terms and conditions. He submits that till the date of the termination of the MOU, no fresh agreement had been entered into between the parties. Relying on the last sentence of the Clause 2, Mr. Narasimha submits H 370 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A that it was the sole discretion of the petitioner to extend the MOU in case the petitioner believed that the additional time is required to complete the trial period. The aforesaid portion of Clause 2 is as under :- - "RECC, at its sole discretion, may decide to extend the - B MOU if RECC believes that additional time is requir~d complete the trial period." 12. He further submits that although the cars were being supplied to the respondent but the petitioner was not satisfied - C with the prbgress made in the number of cars sold by the respondent. Therefore, the respondent was constrained ·to terminate the MOU, after a period of two years from the commencement. - 0 13. According to Mr. Narasimha, respondent has initiated the proceedings in the Brussels Court only to pre-empt the initiation of legal proceedings by the petitioner. He points out that the pleadings in the Writ of Summons, clearly show: that the respondent was only concerned with the effect of the termination and not the period of the MOU. Respondent has - E admitted that the contractual relationship started in 2007. The respondent has admitted that there is no other subsequent agreement. In Paragraph 18 of the Writ of Summons, the respondent admits that the contractual relationship was subsisting till September, 2009. In Paragraph 30, it is admitted - F by the respondent that "the party summoned below terminated the contract in an untimely and brutal manner on 25th September, 2009". 14. He points out that the disputes have arisen in relation G to the termination of the MOU and the consequences thereof. Such disputes are clearly covered by the arbitration clause which clearly provides for resolution of disputes through arbitration. The clause provides that in the event of any dispute or difference _arising at any time_ between the parties _in relation_ H _to_ the agreement shall be referred to a Sole Arbitrator. The REVA ELECTRIC CAR CO. P LTD. _v._ GREEN MOBIL 371 [SURINDER SINGH NIJJAR, J.) clause, according to the learned senior counsel, is not limited A to the disputes relating only to the initial period of the MOU till 31st December 2007. 15. He submits irrespective of whether the MOU is now in existence or not, the Arbitration clause would survive. He relies 8 on the decisions of this Court in- the cases of _Bharat Petroleum Corporation Ltd._ Vs. _Great Eastern Shipping Company Ltd.[1 ] and Everest Holding Limited_ Vs. _Shyam Kumar Shrivastava_ & _Ors.[2 ]_ He further submits that this Court is required to refer the disputes between the parties to the Sole Arbitrator, without C any in-depth examination of the disputes. The Court is merely to be satisfied that the disputes fall within the ambit of the Arbitration Clause. In support of this submission, he relies on the judgment of this Court in _Brigadier Man Mohan Sharma, FRGS (Retd.)_ Vs. _Lieutenant General Depinder Singh.[3 ]_ He also relies on the judgment in the case of _National Insurance_ D _Company Limite_d_ Vs. _Boghara Polyfab Private Limited[4] ,_ in support of the submission all disputes are such which need to be decided by the Sole Arbitrator on merits, and can not be decided by this Court in a petition under Section 11 (4) and 6 of the Arbitration and Conciliation Act, 1996. Learned counsel E further submits that in accordance with the aforesaid clause the petitioner had already nominated the Sole Arbitrator. The respondent has, however, not accepted the aforesaid arbitrator. At the same time, it had expressed its willingness to negotiate the global settlement with the petitioner. F 16. On the other hand, Ms. Tasneem Ahamadi, has submitted that the MOU having come to an end by efflux of time, there was no question of any termination as claimed by the petitioner. She further submits that the notice invoking arbitration was sent only as a counterblast to the summons 1. 2008 (1) sec 503. 2. 2008 (16) sec 774. 3. 2009 (2) sec 600. 4. 2009 (1) sec 267. H 372 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. A receiyed by the petitioner from the Brussels Commercial Court. Learned counsel further submitted that the disputes which form the basis of the claim in the Brussels Commercial Court pertained to a period subsequent to the period covered by the MOU. The arbitration clause in the MOU relates only to disputes B which relate to the test and trial period. Hence, an arbitrator can not be appointed for settlement of disputes which occurs _I_ relate to a period after 31st December, 2007. The disputes raised before the Commercial Court at Brussels are not covered by the arbitration clause in the MOU. She had made a detailed C reference to numerous e-mails exchanged between the parties to submit that the parties had in fact entered into a long term contract. This was only to be reduced to a formal document. Since the disputes are not covered by the arbitration clause, there can be no reference. In support of the aforesaid submission, learned counsel relies on a judgment of this Court ' 0 in the case of _SBP_ & Co. Vs. _Patel Engineering Ltd._ & _Anr._[5] • In view of the law laid down in the aforesaid judgment, according to the learned counsel, the arbitration petition deserves to be dismissed. E E 17. I have considered the submissions made by the learned counsel for the parties. It appears that the submissions made by Ms. Ahamadi that the question with regard to the existence of a valid arbitration agreement would have to be decided by this Court, is not without merit. This Court has on a F number of occasions examined the scope and ambit of the jurisdiction of the Chief Justice or his designate under Section 11 of the Arbitration and Conciliation Act, 1996. A reference in this connect.ion can be made to the judgment of this Court in _SBP_ & Co. (supra) wherein a Constitution Bench of this Court G has clearly held as under : "39. It is necessary to define what exactly the Chief Justice, approached with an application under Section 11 of the Act, is to decide at that stage. Obviously, he has to decide - H 5. 2005 (8) sec 618. REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 373 [SURINDER SINGH NIJJAR, J.] his own jurisdiction in the sense whether the party making A the motion has approached the right High Court. He has to decide whether there is an arbitration agreement, as defined in the Act and whether the person who has made the request before him, is a party to such an agreement. It is necessary to indicate that he can also decide the B question whether the claim was a dead one; or a longbarred claim that was sought to be resurrected and whether the parties have concluded the transaction by recording satisfaction of their mutual rights and obligations or by receiving the final payment without objection. It may c not be possible at that stage, to decide whether a live claim made, is one which comes within the purview of the arbitration clause. It will be appropriate to leave that question to be decided by the Arbitral Tribunal on taking evidence, along with the merits of the claims involved in 0 the arbitration. The Chief Justice has to decide whether the petitioner has satisfied the conditions for appointing an arbitrator under Section 11 (6) of the Act. For the purpose of taking a decision on these aspects, the Chief Justice can either proceed on the basis of affidavits and E the documents produced or take such evidence or get such evidence recorded, as may be necessary. We think that adoption of this procedure in the context of the Act would best serve the purpose sought to be achieved by the Act of expediting the process of arbitration, without too F many approaches to the court at various stages of the proceedings before the Arbitral Tribunal." In the case of _National Insurance_ Co. _Ltd._ (supra), this Court again examined the question with regard to the scope of the jurisdiction under Section 11 (6). In doing so, this Court G explained the ratio of the Constitution Bench in SBP & Co. (supra). In Para 21 of the Judgment, the power of the Arbitral Tribunal in cases where the disputes are referred to arbitration without the intervention of the court has been distinguished from the power in matters where the intervention of the court is sought H G 374 SUPREME COURT REPORTS [2011] 13 (AODL.) S.C.R. A for appointment of an Arbitral Tribunal. In case where the matters are sought to be referred to arbitration _without the intervention of the court_ it has been held that the Arbitral Tribunal can decide the following questions l:lffecting its jurisdiction: (a) whether there is an arbitration agreement; (b) whether the B arbitration agreement is valid; (c) whether the contract in which the arbitration clause is found is null and void, and if so, whether the invalidity extends to the arbitration clause also. 18. In matters, where the intervention of the Chief Justice C of India has been sought for appointment of a sole arbitrator under Section 11(4), (5) and (6) of the Arbitration Act, 1996, the Chief Justice or his designate will have to decide certain preliminary issues. It would be apposite to notice here the relevant observations made in Para 22, which are as follows :- - **D "22.** This Court identified and segregated the preliminary issues that may arise for consideration in an application under Section 11 of the Act into three categories, that is, _(1)_ issues which the Chief Justice or his designate is bound to decide; _(i1)_ issues which he can also decide, that is, - E issues which he may choose to decide; and _(iii)_ issues which should be left to the Arbitral Tribunal to decide. **22.1.** The issues (first category) which the Chief Justice/ his designate will have to decide are: F (a) Whether the party making the application has approached the appropriate High Court. G (b) Whether there is an arbitration agreement and whether the party who has applied under Section 11 of the Act, is a party to such an agreement. **22.2.** The issues (second category) which the Chief Justice/his designate may choose to decide (or leave them to the decision of the Arbitral Tribunal) are: H (a) Wtiether the claim is a dead (long-barred) claim REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 375 [SURINDER SINGH NIJJAR, J.] or a live claim. A _(b)_ Whether the parties have concluded the contract/transaction by recording satisfaction of their mutual rights and obligation or by receiving the final payment without objection. B **22.3.** The issues (third category) which the Chief Justice/ his designate should leave exclusively to the Arbitral Tribunal are: _(1)_ Whether a claim made falls within the arbitration c clause (as for example, a matter which is reserved for final decision of a departmental authority and excepted or excluded from arbitration). _(ii)_ Merits or any claim involved in the arbitration." These observations were further reiterated by this Court in the case of _A.P. Tourism Development Corporation Ltd. Vs. Pampa Hotels Ltd.[8 ] •_ The aforesaid ratio of law has been reiterated by this Court in _Alva Aluminium Limited, Bangkok Vs. Gabriel India Limited[7] ._ Upon consideration of the entire case law, it has been observed as follows :- D E **"18.** It is in the light of above pronouncements, unnecessary to delve any further on this issue. It is clear that once the existence of the arbitration agreement itself is questioned by any party to the proceeding initiated under Section 11 of the Act, the same will have to be decided by the Chief Justice/designate as the case may be. That is because existence of an arbitration agreement is a jurisdictional fact which will have to be addressed while making an order on a petition under Section 11 of the Act." F G 19. In view of the aforesaid authoritative dicta, the 6. [2010 (5) sec 425.J. _1._ 12011 (1) sec 161. H 376 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A submission of Ms. Ahamadi has to be accepted that in a petition under Sections 11 (4)(5)(6) and (9) of the Arbitration Act, 1996, it is for the Chief Justice of India/his designate to decide about the existence of a valid arbitration agreement. Now let me examine the facts in the present case keeping in view the - s aforesaid well settled principles. 20. There is no dispute that the parties had entered into a legally valid and enforceable MOU dated 25th September, 2007. There is also no dispute that Clause 11 provides that C disputes arising between the parties, at any time, in relation to the MOU, shall be referred to arbitration. Clause (2) of the MOU, undoubtedly, fixes the trial period upto 31st December, 2007. However, the clause also provides that the petitioner may unilaterally decide to extend the MOU, if it considers necessary. The correspondence between the parties would show that the D petitioner had proposed a draft distribution agreement to the respondent for discussion. Thereafter, a series of e-mails were exchanged between the parties, but making it apparent that no final consensus was reached. It would, therefore, appear that the MOU was duly extended till it was terminated as averred E by the petitioner. 21. The petitioner has categorically pleaded that the MOU was terminated on 25th September, 2009. The petitioner has placed on record the e-mail dated 25th September, 2009 in F which it is clearly stated that MOU was entered into on 25th September, 2007 for a test period of six months from the date of arrival of the trial cars. It is further stated that this period was extended on an informal and voluntary basis by the petitioner for a period extending to two years from the date of signing of G the MOU. During this two years period, a total of 15 REVA cars have been sold. It is pointed out-that inspite of the best efforts of the respondent and the efforts of the petitioner to support the respondent, following a review of the European operations it is believed that the respondents do not have in place the resources to build the REVA brand, invest in the appropriate H REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 377 [SURINDER SINGH NIJJAR, J.] infrastructure, obtain necessary fiscal and/or subsidy and A infrastructure support and are not adequately prepared to launch the M1 vehicles introduced by REVA at the Frankfurt IAA. Thereafter it requests the respondents to immediately cease all sales and marking activities on behalf of REVA brand. This termination of the agreement has been acknowledged by the B respondents in its e-mail dated 7th October, 2009. A perusal of this e-mail would also demonstrate that the disputes had clearly arisen between the parties at that time. The e-mail makes a grievance that the respondents had not been notified of the termination of its dealership activities a few weeks ago C when it had informed the petitioner of its negotiations with potential Dutch partners. The respondents also repeated its disappointment that the win-win soft-landing solution it proposed on 25th September, 2009 was rejected by the petitioner. Rest of the correspondence between the parties continues in the same tenor.. Clearly, therefore, the MOU has been extended till D its termination on 25th September, 2009. It is also evident that the parties had failed to reach any fresh agreement with regard to sale of REVA cars in Europe by the respondents. In my opinion, the pleadings and the material on record has clearly established that there was a valid arbitration agreement E incorporated in Clause 11 of the MOU. E 22. This takes me to the second submission of Ms.Ahamadi that, in any event, the disputes cannot be referred to arbitration as it pertained to a period subsequent to the term F of the MOU. Mr.Narasimha has, however, pointed out that according to the case pleaded by the respondents in the Brussels Court which is evident from the writ of summons, all the disputes pertained to the period prior to the termination of the agreement by the petitioner. The writ of summons clearly G mentions as follows : "Whereas the first cars of the make REVA were marketed in India from June 2001 onwards, then in the UK in 2003 and worldwide from 2007. H 378 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. ## A That the party summoned below had however promised the arrival of more performing Lithium batteries that would be installed in their vehicles from the middle of 2008, as well as a new or more competitive and more attractive car model by the end of 2008, the REVA 'NXR'. B Whereas the contractual relationships between the petitioner and the party summoned below started in 2007. Whereas the distribution of the REVA cars by the petitioner took place in two stage. c That during an initial period the petitioner ran a pilot project for the party summoned below to assess the marketing possibilities of the REVA on the Belgian market. D That after a certain period of time the petitioner became an exclusive distributor of REVA cars for the BENULEX." 23. The writ of summons further mentions that the petitioner had to run a pilot project of three to six months to test the marketing possibilities of the REVA cars on the Belgium E market. It is further pleaded that at the end of the test period and at the latest on 31st December, 2007, the parties had to decide jointly whether the petitioner would continue to provide the promotion, sales and service of REVA Cars in Belgium within the framework of a long-term distribution contract. The F respondents further pleaded that :- 'Whereas, in spite of the absence of the signing of a written contract between the parties, the petitioner de facto became the exclusive distributor of REVA vehicles in the BENELUX starting the month of January, 2008." ## G 24. Thereafter the respondents gave details of the efforts made by it for marketing of the REVA Cars from January, 2008 onwards. In paragraph 19 of the writ of summons, it is clearly admitted as follows:- H REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 379 [SURINDER SINGH NIJJAR, J.) "Whereas on the 25th of September, 2009, as soon as the A first REVA cars fitted with Lithium batteries and of the new REVA NXR model arrive in Belgium the petitioner is going to be ejected all of a sudden by the party summoned below. B That during a telephone conversation on 25th September, 2009, confirmed in an email of the same date the party summoned below suddenly announced its decision to terminate the concession granted to the petitioner for the Belelux, with immediate effect; c That the party summoned below asked the petitioner to immediately stop the sale and promotion of the REVA cars as well as the use of the REVA mark." 25. The claims made by the respondents clearly pertained o to the contract which was terminated on 25th September, 2009. In paragraph 30 of the writ of summons, it is pleaded as under "That the parties summoned below terminated the contract in any untimely and brutal manner on 25th September, E 2009." 26. On the aforesaid basis, the responde_nts claim compensation and damages amounting to Euro 454,000. F 27. The aforesaid averments and the material on record would clearly demonstrate that the disputes that have arisen between the parties clearly relate to the MOU dated 25th September, 2007. It would be for the Arbitral Tribunal to decide as to whether claims made are within the arbitration clause. The G Arbitral Tribunal would also have to decide the merits of the claim put forward by the respective parties. In view of the material placed on record, it would not be possible to accept the submissions of Ms. Ahamadi that the disputes were beyond the purview of the arbitration clause. H 380 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. A 28. A similar matter was examined by this Court in the case of _Bharat Petroleum Corporation Ltd._ Vs. _Great Eastern Shipping_ Co. _Ltd.[8 ]_ In the aforesaid case, an agreement called • time charter party was entered into between the appellant and the respondent on 6th May, 1997 for letting on hire vessels for B a period of two years from 22nd September, 1996 to 3oth June, 1997 and from 1st July, 1997 to 30th June, 1998. It appears that certain disputes arose between the parties. Thereafter, on the basis of the correspondence exchanged between the parties with regard to the disputes, claims and counter claims c were filed before the Arbltral Tribunal. Issues were duly framed of which the following three issues may be of some relevance in the present context viz. - "issue 1.-Whether the Hon'ble Arbitral Tribunal has no jurisdiction to adjudicate upon the dispute between the - D claimant and the respondent for the period September 1998 to August 1999 irr respect of the vessel _Jag Praja_ for the reasons stated in Para 1 of the written statement? issue 2.-Whether there is any common practice that if the E vessel is not redelivered at the end of the period mentioned in the time charter the vessel would be governed by the charter party under which originally it was chartered? - • • • F issue 5.-Whether the time charter party dated 6-5-1997 came to an end by efflux of time on 30-8-1998? • 29. The Arbitral Tribunal by its order dated 12th May, 2003 came to the conclusion that the appellant having invoked the G arbitration clause contained in the charter party agreement dated 6th May, 1997, which was valid upto 31st December, 1998 and as the dispute between the parties related to the period subsequent to 31st August, 1998, they had no jurisdiction to decide the reference. The tribunal held that the H 8. 12008) c1) sec so3J. ## REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 381 [SURINDER SINGH NIJJAR, J.] charter party agreement dated 6th May, 1997 was superseded A by .a fresh agreement. Therefore, original charter party dated 6th May, 1997 got extinguished. The respondents challenged the said award before the High Court. Learned Single Judge set aside the award and held that the Arbitral Tribunal has the jurisdiction to adjudicate the disputes between the parties as B the vessel continued to be hired by the appellant for the period subsequent to 31st August, 1998 on the same terms and conditions, as were contained in charter party agreement dated 6th May, 1997. It was held that the charter party dated 6th May, 1997 did not come tci an end by efflux of time and it was c extended by the party on the same terms and conditions. Correctness of this order was challenged in this Court. On examination of the entire fact situation, it was held as follows :- "19. It is, no doubt, true that the general rule is that an offer is not accepted by mere silence on the part of the offeree, yet it does not mean that an acceptance always has to be given in so many words. Under certain circumstances, offeree's silence, coupled with his conduct, which takes the form of a positive act,,.may constitute an acceptance-an agreement _sub silentio._ Therefore, the terms of a contract between the parties can be proved not only by their words but also by their conduct." D E 30. Examining the fact situation in the present case, I am of the opinion that the conclusion is inescapable that notwithstanding the initial period under the MOU expiring by 31st December, 2007, the same was extended by the petitioner in exercise of its discretion under Clause (2) of the MOU. The extended MOU was terminated only on 25th September, 2009. Therefore, it is not possible to accept the submission of Ms. Ahamadi that the disputes arising between the parties cannot be referred to the Arbitral Tribunal. In my opinion, Mr. Narasimha has rightly submitted that the disputes have arisen in relation to the termination of the MOU and the consequences thereof. Such disputes would be clearly covered under the F G H ' 382 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. A Arbitration clause which provides that in the event of any dispute or difference _arising at any time_ between the parties _in relation to the agreement_ shall be referred to a Sole Arbitrator. The clause is clearly not limited to the disputes relating only to the initial period of the MOU till 31st December, 2007. B 31. I also find merit in the submission of Mr. Narasimha that irrespective of whether the MOU is now in existence or not, the arbitration clause would survive. The observations made by this Court in the case of _Everest Holding Ltd._ (supra) would clearly support the submission made by the learned senior C counsel. In the aforesaid case, the parties had entered into a Joint Venture Agreement·(tor short 'JVA') dated 25th September, 2003 for the purpose of mining, processing and export of Iron Ore. On 26th March, 2004, another JVA was executed between the parties, particularly to iron out certain D controversy in respect of JVA dated 25th September, 2003. Article 14.3 of the said JVA contained an arbitration clause providing that if the parties failed to resolve the matter through mutual agreement, the dispute shall be reft::1Ted to an Arbitrator appointed by mutual agreement of the two parties. The stand E of the petitioner in the aforesaid case was that on 20th September, 2004, it was shocked and surprised to receive unwarranted notices for cancellation of JV A. The aforesaid notice was replied on 6th October, 2004. Since the disputes between the parties were not resolved, the petitioner invoked F the arbitration clause. Respondent No. 1 in reply to the notice refuted the claim of the petitioner and also refused to refer the matter to arbitration on the ground that the JVA between the petitioner and the respondent No.1 is not in existence as the same had been terminated by respondent No.2. It was stated G that in view of the aforesaid position, there could be no invocation of Clause 14.3 of JVA. 32. Considering the aforesaid fact situation, this Court observed that under Clause 14.2, the parties had agreed that they would use all reasonable efforts to resolve ~he disputes, H REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 383 [SURINDER SINGH NIJJAR, J.] controversy or claim arising out of or relating to these A agreements. Since the parties have failed to resolve their differences, the same had to be referred to Arbitration under Clause 14.3. It was held that there is a valid Arbitration Agreement between the parties as contained in the JVA, which the parties are required to adhere to and are bound by the B same. In other words, if there is any dispute between the parties to the agreement arising out of or in relation to the subject matter of the said JVA, all such disputes and differences have to be adjudicated upon and decided through the process of Arbitration by appointing a mutually agreed Arbitrator. This c Court observed as follows:- "Though the JVA may have been terminated and cancelled as stated. but it was a valid JVA containing a valid arbitration agreement for settlement of disputes arising out of or in relation to the subject-matter of the JV A. The D argument of the respondent that the disputes cannot be referred to the arbitration as the agreement is not in existence as of today is therefore devoid of merit." In my opinion, the aforesaid observations are squarely E applicable to the facts in the present case. The disputes that have arisen between the parties clearly pertain to the subject matter of the MOU. 33. Even if, I accept the submission of Ms.Ahamadi that F MOU was not extended beyond 31st of December, 2007, it would make little difference. Section 16(1 )(a) of the Arbitration and Conciliation Act, 1996 provides that an arbitration clause which forms part of the contract shall be treated as an agreement independent of the other terms of the contract. The plain meaning of the aforesaid clause would tend to show that · G even on the termination of the agreement/contract, the arbitration agreement would still survive. It also seems to be the view taken by this Court in _Everest Holdings Ltd._ (supra). Accepting the submission of Ms.Ahamadi that the arbitration H 384 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. - A clause came to an end as the MOU came to an end by efflux of time on 31st December, 2007 would lead to a very uncertain state· of affairs, destroying the very efficacy of Section 16(1). The aforesaid section provides as under : - "16. Competence of arbitral tribunal to rule on its - B jurisdiction -(1) The arbitral tribunal may rule on its own jurisdiction, including ruling on any objections with respect to the existence or validity of the arbitration agreement, and - - for that purpose - c (a) an arbitration clause which forms part of a contract shall be treated as an agreement independent of the other terms of the contract; and - (b) a decision by the arbitral tribunal that the contract - D is null and void shall not entail _ipso jure_ the invalidity of the arbitration clause." - . 34. The aforesaid provision has been enacted by the - legislature keeping in mind the provisions contained in Article 16 of the UNCITRAL Model Law. The aforesaid Article reads - E as under:- - - "Article 16 Competence of arbitral tribunal to rule on its - - jurisdiction - (1) The arbitral tribunal may rule on its own jurisdiction, - F including any objections with respect to the existence or validity of the arbitration agreement. For that purpose, an arbitraiion clause which forms part of a contract shall be treated as an agreement independent of the other terms of the contract. A decision by the arbitral tribunal that the - G contract is null and void shall not entail _ipso Jure_ the invalidity of the arbitration clause. - (2) ............................................................ .. - (3) .............................................................. : - H REVA ELECTRIC CAR CO. P. LTD. _v._ GREEN MOBIL 385 [SURINDER SINGH NIJJAR, J.] Under Section 16(1 ), the legislature makes it clear that A while considering any objection with respect to the existence or validity of the arbitration agreement, the arbitration clause which formed part of the contract, has to be treated as an agreement independent of the other terms of the contract. To ensure that there is no misunderstanding, Section 16(1)(b) B further provides that even if the arbitral tribunal concludes that the contract is null and void, it should not result, as a matter of law, in an automatic invalidation of the arbitration clause. Section 16(1)(a) presumes the existence of a valid arbitration clause and mandates the same to be treated· as an agreement c independent of the other terms of the contract. By virtue of Section 16(1)(b), it continues to be enforceable notwithstanding a declaration of the contract being null and void. In view of the provisions contained in Section 16(1) of the Arbitration and Conciliation Act, 1996, it would not be possible to accept the 0 submission of Ms.Ahmadi that with the termination of the MOU on 31st December, 2007, the arbitration clause would also cease to exist. As noticed earlier, the disputes that have arisen between the parties clearly relate to the subject matter of the relationship between the parties which came into existence through the MOU. Clearly, therefore, the disputes raised by the E petitioner needs to be referred to arbitration. Under the arbitration clause, a reference was to be made that the disputes were to be referred to a single arbitrator. Since the parties have failed to appoint an arbitrator under the agreed procedure, it is necessary for this Court to appoint the Arbitrator. F E F 35. In exercise of my powers under Section 11 (4) and (6) of the Arbitration and Conciliation Act, 1996 read with Paragraph 2 of the Appointment of Arbitrator by the Chief Justice of India Scheme, 1996, I hereby appoint Hon.Mr.Justice R.V. Raveendran, R/o 8/2, Krishna Road, Basavangudi, Bangalore, Former Judge of the Supreme Court of India, as the Sole Arbitrator to adjudicate the disputes that have arisen between the parties, on such terms and conditions as the G H 386 SUPREME C.OURT REPORTS (2011] 13 (ADDL) S.C.R. A learned Sole Arbitrator deems fit and proper. Undoubtedly, the learned Sole Arbitrator shall decide all the disputes arising between the parties without being influenced by any prima facie opinion expressed in this order, with regard to the respective claims of the parties. B 36. The registry is directed to communicate this order to the Sole Arbitrator to enable him to enter upon the reference and decide the matter as expeditiously as possible. 37. The Arbitration Petition is accordingly disposed of. c R.P. Arbitration Petition disposed of.
End of Judgment Record
Browse All Supreme Court of India (2011) Decisions
2011-10-13

GRASIM INDUSTRIES LTD. v. UNION OF INDIA

Grasim Industries Ltd. v. Union of India deals with whether metal scrap or waste generated during repair of worn-out machinery used in a cement manufacturing plant constitutes manufacture and thus obligations to pay Central excise duty. The core dispute arose after Grasim repaired plant components and generated scrap, which was cleared without duty; the Tribunal later held that such scrap did not arise from any manufacturing activity and was not excisable. The Rajasthan High Court initially upheld the duty demand and penalties, while the Tribunal had dropped them. The Supreme Court reversed the High Court, restoring the Tribunal’s order and allowing the appeal. The Court held that although repair work produces metal scrap, this scrap does not participate in the manufacture of cement and cannot be treated as a by-product of the final product. It emphasized that excise duty is on manufacture of goods, requiring that the goods be produced or manufactured in India, and the charging Section 3 applies only when the goods are excisable under Section 2(d) and are manufactured under Section 2(f). Section 2(f) defines manufacture as including any process incidental or ancillary to the completion of the manufactured product, involving transformation of raw material into a new or distinct excisable product. The process of repair, using non-raw materials, does not satisfy this test. The Court also cautioned against deeming provisions in tariff notes as creating manufacture unless expressly stated, relying on various precedents such as Shyam Oil Cake, Ujagar Prints, Hindustan Polymers, and Union of India v. Delhi Cloth and General Mills, among others, to delineate the law of manufacture.

2011-03-02

Bharat Petroleum Corporation Ltd. v. Chembur Service Station

This Supreme Court appeal concerns BPCL’s licence-based relationship with a dealer at a Retail Petroleum Outlet (RPO) in Chembur, Mumbai. BPCL (then Burmah Shell) leased the land and services premises to operate the RPO; in 1972 a DPSL (Dispensing Pump and Selling Licence) granted the respondent the right to sell BPCL’s petroleum products from the outlet. A 1995 renewal extended the arrangement. In 2007, a show-cause notice alleged tampering with dispensing equipment, prompting BPCL to terminate the dealership. The respondent filed suits in the Court of Small Causes claiming tenancy or deemed tenancy under rent-control laws and sought an injunction to continue supply, while BPCL argued the arrangement was a revocable licence, not a tenancy, and the remedy lay in due process and contract law, not eviction under rent-control statutes. The lower courts issued status-quo orders preserving possession and continuing supplies, with various challenges under Public Premises Act and rent-control regimes. The Supreme Court clarified that the DPSL licence creates a limited, revocable right to enter and use the premises to sell BPCL’s products, not a tenancy; the licence terminates with revocation and the licensee has no independent right to possession. The Court ultimately referred the matter to a larger Bench due to divergent views and, in the order, dismissed the appeal with directions to proceed under due process of law.

2011-07-04

Sudam @ Rahul Kaniram Jadhav v. State of Maharashtra

Sudam alias Rahul Kaniram Jadhav challenged a conviction for the murder of a woman with whom he lived as husband and wife and her four children. The victims were found in a village pond in August 2007. The trial court convicted the appellant under IPC Sections 302 and 201 and sentenced him to death; the Bombay High Court affirmed. The State relied on circumstantial evidence: the victims were last seen alive with the appellant; he had posed as single, later marrying another woman (PW-6); the deceased had agreed to pay Rs. 15,000 to PW-6 to settle the dispute; extra-judicial confessions were made by the appellant to PW-6 and PW-9; he absconded and could not explain the deaths. The defense argued that the circumstantial chain was not complete and could admit alternate explanations; there were no direct eyewitnesses. The Supreme Court reiterated the standard for circumstantial evidence: the evidence must be cogently and firmly established, form a complete chain, point to guilt beyond reasonable probability, and be inconsistent with innocence. It concluded all five deaths were homicidal and, applying the rarest-of-the-rare doctrine, upheld the conviction and the death sentence, while dismissing the appeals.

2011-04-18

J.S. Yadav v. State of U.P. & ANR.

This case concerns a challenge to a May 28, 2008 notification declaring the appellant, a member of the Uttar Pradesh State Human Rights Commission, ceased to hold office after amendments to the Protection of Human Rights Act, 1993 were introduced by the Protection of Human Rights (Amendment) Act, 2006. The appellant joined the Commission on 29 June 2006 for a five-year tenure and argued that the amendment, which requires seven years of experience as a District Judge for eligibility, could not curtail an incumbent’s tenure and could not be applied retrospectively. He also contended that Section 26 of the Act guarantees that terms and conditions of service shall not be varied to his disadvantage after appointment, and that the proposed reconstitution would deprive accrued rights. The State argued that fresh appointments to the Commission had to be made, that the amendment could alter service conditions, and that public funds cannot pay two persons for one post; non-joinder of relatives and the lack of a suitable remedy rendered the petition academic. The Supreme Court held that tenure posts must be allowed to endure to the end of the fixed term and that accrued rights cannot be taken away by a repealing or amended statute without express or necessary implication. It held the 2006 Amendment prospective and the impugned notification illegal, allowed the appeal to the extent discussed, and awarded Rs. 1 lakh as costs to the appellant.