REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL
Case Synopsis & Summary
This Arbitration Petition concerns a dispute under a Memorandum of Understanding (MOU) dated 25 September 2007 between REVA Electric Car Co. P. Ltd. (petitioner) and Green Mobil (respondent) regarding supply and marketing of REVA cars in Belgium/Benelux. The MOU provided for a test/trial period and terms for possible renewal into a long-term distributorship; disputes arising “at any time” in relation to the MOU were to be referred to arbitration. The trial period was initially set to end on 31 December 2007, but the petitioner asserted that the MOU was extended by unilateral discretion and informal extensions, leading to termination only on 25 September 2009. In September–October 2009, after the termination, disputes and e-mails emerged, including Brussels court proceedings by the respondent seeking damages. The petitioner invoked arbitration under Clause 11 on 24 March 2010 and nominated a Sole Arbitrator. The respondent contended that the arbitration clause covered only the test period and that post-2007 claims were outside arbitral scope; it also argued that continuing distribution in 2008–2009 was not part of the MOU.” “The Supreme Court held that existence of an arbitration agreement is a jurisdictional fact for the Chief Justice/designate under s.11, that the arbitration clause survives termination under s.16, and that disputes relating to termination and its consequences fall within arbitration. The Court appointed Justice RV Ravendran as Sole Arbitrator and disposed of the petition.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Surinder Singh Nijjar
- Judgment Date
- 2011-11-25
- Court Decision / Holding
- Arbitration Petition disposed of. The Court held that there is a valid arbitration agreement and that the arbitration clause survives termination; it appointed Hon. Mr. Justice R. V. Ravindran as Sole Arbitrator and directed the registry to communicate accordingly. The Arbitral Tribunal is to adjudicate the disputes arising between the parties on such terms as it deems fit.
- Final Disposition
- Arbitration Petition disposed of
Parties to the Case
Appellants / Petitioners
- REVA Electric Car Co. P. Ltd.
Respondents
- Green Mobil
Legal Representation & Advocates
Counsels for Petitioners
- • P.S. Narasimha
- • Vyapak Desai
- • P.V. Dinesh
- • Cherrie Alexander
Counsels for Respondents
- • Tasneem Ahamadi
- • Sudhir Kumar Gupta
- • Manish Gupta
Provisions of Law Cited
Legal Doctrines & Maxims
- Arbitration clause treated as independent of the contract (severability) – Section 16(1) of the Act.
- Existence of arbitration agreement as a jurisdictional fact (SBP & Co. v Patel Engineering Ltd.)
- Arbitration vs. court determination under Section 11 – three categories of issues (as per SBP & Co. and National Insurance)
- Arbitration settlement by conduct/sub silentio (acceptance by conduct)
- Arbitration clause survival after termination per Section 16(1) (contract nullity does not automatically nullify arbitration clause)
- Three-category framework for Section 11(4)-(6) jurisdictional decisions; (i) issues to be decided by Chief Justice, (ii) issues he may decide, (iii) issues to be left to the Arbitral Tribunal
- UNCITRAL Model Law Article 16 – competence of arbitral tribunal to rule on jurisdiction and the existence/validity of arbitration agreements
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner argued that the MOU dated 25 September 2007 created a valid arbitration agreement (Clause 11) to resolve disputes arising in relation to the MOU, including post‑trial period disputes arising from termination. It contended that the MOU was extended beyond 31 December 2007 by unilateral discretion and informal extensions, and that the termination on 25 September 2009 did not extinguish the arbitration clause. Therefore, the disputes, including those relating to Brussels proceedings, fall within the arbitration clause and must be referred to arbitration. The petitioner nominated a Sole Arbitrator under the Clause 11 scheme and sought referral of disputes to arbitration, contending that the clause survives contract termination (s.16) and that s.11(4) powers permit appointment by the Chief Justice of India (or designate).
Contentions of Respondents
The respondent contended that the MOU expired on 31 December 2007, and the arbitration clause only covered the test period, not post‑2007 disputes arising from the distribution phase. It argued that the Brussels proceedings involved matters beyond the MOU’s term and were outside arbitration coverage. The respondent urged dismissal or rejection of a reference under Section 11, relying on jurisprudence such as SBP & Co. and SBP’s three‑category framework, asserting that arbitration was inappropriate for disputes outside the MOU’s scope. It claimed that even if there was a contract, the contract being terminated would terminate the arbitration clause too, citing the same authorities in support.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (7)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| A.P. Tourism Development Corporation Ltd. v. Pampa Hotels Ltd. | 2010 (4) SCR 942; 2010 (5) SCC 425 | Positive | Cited to establish that existing arbitration agreements and the framework governing Section 11 proceedings require evaluating jurisdictional questions, and to support the Court’s approach to invoking arbitration and interpreting the MOU’s arbitration clause. |
| Alva Aluminium Limited, Bangkok v. Gabriel India Limited | 2010 (13) SCR 803; 2011 (1) SCC 167 | Positive | Cited for principles on arbitration clause severability and ongoing enforceability despite contract reformation or termination. |
| Brigadier Man Mohan Sharma, FRGS (Retd.) v. Lieutenant General Depinder Singh | 2008 (16) SCR 701; 2009 (2) SCC 600 | Positive | Used to illustrate scope of arbitration and the court’s jurisdiction under Section 11 and the need to consider arbitration where disputes arise relative to the agreement. |
| National Insurance Co. Ltd. v. Boghara Polyfab Private Ltd. | 2008 (13) SCR 638; 2009 (1) SCC 267 | Positive | Cited as authority on jurisdictional questions under Section 11 and the broad reach of arbitration clauses. |
| SBP & Co. v. Patel Engineering Ltd. & Anr. | 2005 (4) Suppl. SCR 688 | Positive | Constitution Bench ruling cited for the categories of issues the Chief Justice/designate may decide and the foundational requirement to ascertain existence of arbitration agreement. |
| Everest Holdings Ltd. v. Shyam Kumar Shrivastava & Ors. | 2008 (14) SCR 1221; 2008 (16) SCC 774 | Positive | Cited to support the principle that arbitration clauses can survive despite termination and that independence of arbitration agreement should be respected. |
| Bharat Petroleum Corporation Ltd. v. Great Eastern Shipping Co. Ltd. | 2007 (11) SCR 117; 2008 (1) SCC 503 | Positive | Cited to reinforce the proposition that disputes arising under an arbitration clause can be referred to arbitration even when surrounding contracts are in dispute. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
REVA ELECTRIC CAR CO. P. LTD. v. GREEN MOBIL
Related Decisions & Precedents from Supreme Court of India (2011)
GRASIM INDUSTRIES LTD. v. UNION OF INDIA
Grasim Industries Ltd. v. Union of India deals with whether metal scrap or waste generated during repair of worn-out machinery used in a cement manufacturing plant constitutes manufacture and thus obligations to pay Central excise duty. The core dispute arose after Grasim repaired plant components and generated scrap, which was cleared without duty; the Tribunal later held that such scrap did not arise from any manufacturing activity and was not excisable. The Rajasthan High Court initially upheld the duty demand and penalties, while the Tribunal had dropped them. The Supreme Court reversed the High Court, restoring the Tribunal’s order and allowing the appeal. The Court held that although repair work produces metal scrap, this scrap does not participate in the manufacture of cement and cannot be treated as a by-product of the final product. It emphasized that excise duty is on manufacture of goods, requiring that the goods be produced or manufactured in India, and the charging Section 3 applies only when the goods are excisable under Section 2(d) and are manufactured under Section 2(f). Section 2(f) defines manufacture as including any process incidental or ancillary to the completion of the manufactured product, involving transformation of raw material into a new or distinct excisable product. The process of repair, using non-raw materials, does not satisfy this test. The Court also cautioned against deeming provisions in tariff notes as creating manufacture unless expressly stated, relying on various precedents such as Shyam Oil Cake, Ujagar Prints, Hindustan Polymers, and Union of India v. Delhi Cloth and General Mills, among others, to delineate the law of manufacture.
Bharat Petroleum Corporation Ltd. v. Chembur Service Station
This Supreme Court appeal concerns BPCL’s licence-based relationship with a dealer at a Retail Petroleum Outlet (RPO) in Chembur, Mumbai. BPCL (then Burmah Shell) leased the land and services premises to operate the RPO; in 1972 a DPSL (Dispensing Pump and Selling Licence) granted the respondent the right to sell BPCL’s petroleum products from the outlet. A 1995 renewal extended the arrangement. In 2007, a show-cause notice alleged tampering with dispensing equipment, prompting BPCL to terminate the dealership. The respondent filed suits in the Court of Small Causes claiming tenancy or deemed tenancy under rent-control laws and sought an injunction to continue supply, while BPCL argued the arrangement was a revocable licence, not a tenancy, and the remedy lay in due process and contract law, not eviction under rent-control statutes. The lower courts issued status-quo orders preserving possession and continuing supplies, with various challenges under Public Premises Act and rent-control regimes. The Supreme Court clarified that the DPSL licence creates a limited, revocable right to enter and use the premises to sell BPCL’s products, not a tenancy; the licence terminates with revocation and the licensee has no independent right to possession. The Court ultimately referred the matter to a larger Bench due to divergent views and, in the order, dismissed the appeal with directions to proceed under due process of law.
Sudam @ Rahul Kaniram Jadhav v. State of Maharashtra
Sudam alias Rahul Kaniram Jadhav challenged a conviction for the murder of a woman with whom he lived as husband and wife and her four children. The victims were found in a village pond in August 2007. The trial court convicted the appellant under IPC Sections 302 and 201 and sentenced him to death; the Bombay High Court affirmed. The State relied on circumstantial evidence: the victims were last seen alive with the appellant; he had posed as single, later marrying another woman (PW-6); the deceased had agreed to pay Rs. 15,000 to PW-6 to settle the dispute; extra-judicial confessions were made by the appellant to PW-6 and PW-9; he absconded and could not explain the deaths. The defense argued that the circumstantial chain was not complete and could admit alternate explanations; there were no direct eyewitnesses. The Supreme Court reiterated the standard for circumstantial evidence: the evidence must be cogently and firmly established, form a complete chain, point to guilt beyond reasonable probability, and be inconsistent with innocence. It concluded all five deaths were homicidal and, applying the rarest-of-the-rare doctrine, upheld the conviction and the death sentence, while dismissing the appeals.
J.S. Yadav v. State of U.P. & ANR.
This case concerns a challenge to a May 28, 2008 notification declaring the appellant, a member of the Uttar Pradesh State Human Rights Commission, ceased to hold office after amendments to the Protection of Human Rights Act, 1993 were introduced by the Protection of Human Rights (Amendment) Act, 2006. The appellant joined the Commission on 29 June 2006 for a five-year tenure and argued that the amendment, which requires seven years of experience as a District Judge for eligibility, could not curtail an incumbent’s tenure and could not be applied retrospectively. He also contended that Section 26 of the Act guarantees that terms and conditions of service shall not be varied to his disadvantage after appointment, and that the proposed reconstitution would deprive accrued rights. The State argued that fresh appointments to the Commission had to be made, that the amendment could alter service conditions, and that public funds cannot pay two persons for one post; non-joinder of relatives and the lack of a suitable remedy rendered the petition academic. The Supreme Court held that tenure posts must be allowed to endure to the end of the fixed term and that accrued rights cannot be taken away by a repealing or amended statute without express or necessary implication. It held the 2006 Amendment prospective and the impugned notification illegal, allowed the appeal to the extent discussed, and awarded Rs. 1 lakh as costs to the appellant.