Rehabilitation Plantations Ltd. v. P.S. Ansary

Case / Petition Number:
A.S. No. 856 of 1998 & A.S. No. 9 of 1999; OS.69/1994 (Sub Court, Kottarakkara)

Case Synopsis & Summary

The Rehabilitation Plantations Ltd. (appellant-plaintiff) filed A.S. Nos. 856 of 1998 and 9 of 1999 against P.S. Ansary for compensation arising from breach of contract in a sale of skim crepe rubber. The contract, dated 7-8-1990, required delivery and removal of goods by specified dates. The respondents breached by delayed removal, paying only partial price, and a later re-sale reduced the appellant’s recovery. The Sub Court held the suits barred by limitation under Article 55, holding the contract breach claims could not extend beyond three years from breach, and relied on Bhajan Singh and Co. v. Karson Agency (Delhi) among others. The appellant urged that Section 23 of the Limitation Act could enlarge or modify the limitation period, especially for ex-contractu actions, citing Eastern Traders (I) Ltd. v. PNB and S.K.A.R.S.M. Ramanathan Chettiar. The court analyzed Article 55 (three years from breach, or from cessation in case of continuing breaches) and Section 23 (time from injury) and traced multiple authorities. It ultimately reaffirmed that Sec.23 does not apply to suits on contracts under Article 55, and that the period began at the breach, with resale damages not creating a fresh cause of action. Consequently, the appeals were dismissed and costs allocated to the parties.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Thomas P. Joseph
Judgment Date
2009-12-21
Court Decision / Holding
These appeals fail and are dismissed. Parties to bear their own costs.
Final Disposition
Appeals dismissed; costs ordered in the circumstances.

Parties to the Case

Appellants / Petitioners

  • The Rehabilitation Plantations Ltd., represented by Managing Director

Respondents

  • P.S. Ansary, 'Shan' Traders, Athira Buildings, Kanjirappally

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. M.C. John
  • • Sri. Jini Joy Pathadan

Counsels for Respondents

  • • Sri. T.I. Abdul Salam

Provisions of Law Cited

Article 55 of the Indian Limitation Act, 1963Section 23 of the Indian Limitation Act, 1963Article 115 of the Old Indian Limitation Act (Old Act)S.73 of the Indian Contract ActS.74 of the Indian Contract ActSection 3(2) of the General Clauses Act, 1897

Legal Doctrines & Maxims

  • Continuing breach gives a fresh cause of action; continuing damage is not.
  • Breach of contract per se gives rise to a cause of action; time begins from the date of breach.
  • Starting point of limitation for contract suits is the breach; re-sale damages do not postpone limitation.

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellant contended that Section 23 applies to ex-contractu actions and could extend the limitation period; relied on Eastern Traders (I) Ltd. v. Punjab National Bank and S.K.A.R.S.M. Ramanathan Chettiar; argued that breach and subsequent loss (including resale damages) could trigger a fresh cause of action, and that the lower court erred in applying Article 55 without considering Sec.23.

Contentions of Respondents

Respondents contended that Section 23 has no application to suits ex-contractu and that Article 55 governs limitation for breach of contract; argued that breach itself creates the cause of action and that subsequent resale damages do not create a new limitation period; relied on Bhajan Singh and Co.’s case and Delta Foundations; asserted that the earlier unreported Latheef decision supports their view.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (16)

Case NameCitationTreatmentExplanation
Bhajan Singh and Co. v. Karson AgencyAIR 1967 Delhi 101 (FB)DistinguishedCourt notes that Bhajan Singh’s broad statement that Sec.23 applies only where the act itself does not give rise to a cause of action is not controlling for ex-contractu claims; the Full Bench view is not adopted.
Eastern Traders (I) Ltd. v. Punjab National BankAIR 1966 Punjab 303DistinguishedAppellant relied on this case; the present court distinguishes it as not aligning with the contract-suit context under Article 55.
S.K.A.R.S.M. Ramanathan Chettiar v. National Textile Corporation Ltd.AIR 1985 Ker. 262Mentioned OnlyCited by appellant; not central to the court’s ultimate reasoning.
Rehabilitation Plantations Ltd. v. P.M. Abdul Latheef (Unreported)A.S. No. 852 of 1998 (2003)Mentioned OnlyUnreported decision cited by respondents in support of ex-contractu arguments.
Kedar Nath v. Har GovindAIR 1926 Allahabad 605Mentioned OnlyEarly authorities discussed in the context of whether Sec.23 applies to contract actions.
V.M. Gany v. Leong ChyeAIR 1936 Rangoon 510DistinguishedRangoon decision that Sec.24 (Sec.23) applies differently was considered but not adopted.
Annamalai Chettiyar v. GowasjeeAIR 1938 Rangoon 258Mentioned OnlyAdditional Rangoon authority cited in discussion.
Jagath Kishore v. Parmeshwar Singh and OthersAIR 1951 Patna 348PositiveDivision Bench supported Sec.23’s applicability to ex-contractu in proper cases; cited in discussion.
Jagannath Marwari v. KalidasAIR 1929 Patna 245Mentioned OnlyEarlier Patna case referenced in the debate on Sec.23 applicability.
Kumar Nath Bhuttacharjee v. Nobo Kumar Bhuttacharjee[1898] ILR 26 Calcutta 241PositiveEarly authority cited to discuss contract-based action timing.
Battley v. Faulkner[1820] 3 Barn. & Ald. 288Mentioned OnlyQuoted to illustrate damages and breach concepts; not central to holding.
Raghubar Rai and Another v. Jaij Raj and Another[1912] ILR 34 All 429Mentioned OnlyHistorical support discussed for breach-based action timing.
Ragagopala Naidu v. Ayyaswamy ChettiarAIR 1965 Madras 532PositiveMadras High Court held breach date as time of action; cited in reasoning.
Soundararajan & Co. v. Annamalai NadarAIR 1960 Madras 480PositiveMadras decision cited to support breach-based limitation.
Delta Foundations and Constructions v. Kerala State Construction Corporation Ltd.2003 [1] KLT 626PositiveDivision Bench held Article 55 governs suits for breach of contract and starts from breach; distinguished other cases.
Eastern Traders (I) Ltd. v. P.N. BankAIR 1960 Delhi 101DistinguishedCited as controverted by Delta; Indian contract-limitation analysis differs.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,619 words•~21 min read

In The Court Record

Rehabilitation Plantations Ltd. v. P.S. Ansary

**“C.R.”** ## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE THOMAS P.JOSEPH** **MONDAY, THE 21ST DECEMBER 2009 / 30TH AGRAHAYANA 1931** **AS.NO. 856 OF 1998()** **------------------------** **OS.69/1994 OF SUB COURT,KOTTARAKKARA** **....................** ## **APPELLANT - PLAINTIFF:** **-----------------------------------** **THE REHABILITATION PLANTATIONS LTD., REGD. OFFICE, PUNALUR, REPRESENTED BY MANAGING DIRECTOR.** **BY ADV. SRI.M.C.JOHN SRI.JINI JOY PATHADAN** ## **RESPONDENT – DEFENDANT:** **---------------------------------------** **P.S. ANSARY, 'SHAN' TRADERS, ATHIRA BUILDINGS, KANJIRAPPALLY.** **ADV. SRI.T.I.ABDUL SALAM** **THIS APPEAL SUIT HAVING BEEN FINALLY HEARD ON 21/12/2009 ALONG WITH AS NO. 9 OF 1999 THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **“C.R.”** ## **THOMAS P.JOSEPH, J.** = = = = = = = = = = = = = = = = = = = = = = = = **==> picture [187 x 10] intentionally omitted <==** **==> picture [40 x 9] intentionally omitted <==** **A.S. NO. 9 OF 1999** = = = = = = = = = = = = = = = = = = = = = = = = = Dated this the 21[st] day of December, 2009 ## **J U D G M E N T** --------------------- The question that arises for a decision in these appeals is whether Section 23 of the Indian Limitation Act, 1963 (for short, “the Act”) applies to suits ex-contractu governed by Article 55 of that Act. 2. Short facts in O.S. No.116 of 1994 from which A.S. No.9 of 1999 arose are: Appellant, a Government Company entered into Ext.A1, agreement with the respondents on 7.8.1990 as per which the latter agreed to purchase 25 metric tons of skim crepe rubber at the rate of Rs.17.27 per Kg. Respondents were to pay the price and remove the skim crepe rubber from the factory of appellant at Kulathoopuzha before 25.8.1990. Respondents were given a grace period of 7 days to remove the goods failing which they were to pay ground rent to the appellant at the rate of Rs.5/- per metric ton per day. Appellant reserved right to extend the period for taking delivery of the goods charging ground rent as above. In case of default on the part of respondents, appellant could re-sell the goods at the risk of the respondents. Rupees Ten thousand deposited by the ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 2 :- respondents towards security in that event, was to be forfeited. Respondents paid the price and took delivery of only 9.5 metric tons within the prescribed time. On 4.10.1990 respondents paid price for another 9.5 metric tons of crepe rubber and removed the same by 10.10.1990. As per letter dated 7.11.1991 appellant directed respondents to remove the remaining 6 metric tons of crepe rubber but they did not comply with that direction. Appellant invited tenders for re-sale of the remaining crepe rubber on 12.12.1991 but only one person submitted tender quoting Rs.11.04/per Kg. That tender was not accepted as the price quoted was low and again tenders were invited on 20.2.1992. One person quoted Rs.13/- per Kg., which was accepted on 24.3.1992 and accordingly the 6 metric tons of crepe rubber was sold. Appellant filed the suit claiming compensation which includes advertisement charges, ground rent from the date of agreement till goods were removed by the subsequent purchaser and the short-fall in the price that occurred in the re-sale. In O.S. No.69 of 1995 also the same facts are involved with the difference in the relevant dates and that there was no formal agreement executed by the respondents in favour of the appellant. In spite of direction respondents did not deposit the earnest money or execute the formal agreement. In that suit also ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 3 :- appellant claimed compensation in the same manner as above. Respondents resisted the suits contending inter alia that the suits are barred by limitation since the same are filed after three years of the date on which breach was allegedly committed by not paying the price and removing the goods on or before the due dates. Learned Sub Judge found that there was breach of contract on the part of respondents but held relying on decision of the Delhi High Court in **Bhajan Singh and Co. v. Karson Agency** (AIR 1967 Delhi 101 [FB]) that the suits are barred by limitation. Consequently suits were dismissed. Hence these appeals. It is contended by learned counsel for appellant that even if it is assumed that Article 55 of the Act governed the period of limitation for the suits in question, Sec.23 of the Act is available to the appellant and hence period of limitation would run only from the dates of re-sale consequent to the breach committed by the respondents. Learned counsel relied on the decisions in **Eastern Traders (I) Ltd. v. Punjab National Bank** (AIR 1966 Punjab 303) and **S.K.A.R.S.M. Ramanathan** **Chettiar v. National Textile Corporation Ltd.** (AIR 1985 Ker. 262). Learned counsel for respondents contend that Sec.23 of the Act has no application to the suits ex-contractu and placed -: 4 :- ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** reliance on the unreported decision of a Division Bench of this Court ## in **The Rehabilitation Plantations Ltd. v. P.M. Abdul** **Latheef** (A.S. No.852 of 1998 decided on 9.7.2003) to buttress his contention. It is also contended that a suit for compensation for breach of contract is governed by Article 55 of the Act and hence period of limitation would begin to run from the date of breach and not from the date on which the loss was quantified. Reliance is placed on the decisions in **Bhajan Singh Co.'s case** (supra), **Delta** ## **Foundations and Constructions v. Kerala State Construction Corporation Ltd.** (2003 [1] KLT 626) and the unreported decision in the **Rehabilitation Plantation Ltd.'s case** . 3. In O.S. No.69 of 1995 there is a contention that as no formal agreement was executed between the parties there is no concluded contract. Absence of a written agreement is fatal when as per the terms and conditions agreed between the parties a formal agreement is necessary to create a concluded contract. The terms and conditions in this case do not prescribe so. Indisputably tender submitted by the respondents was accepted by the appellant and acceptance was intimated to the respondents. That created a concluded contract. ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 5 :- 4. To answer the contentions regarding limitation it is necessary to advert to the relevant provisions in the Act. Article 55 of the Act reads, “Description of suit Period of Time from which limitation period begins to run 55. For compensation for Three years When the contract the breach of any is broken or (where contract, express or there are successimplied not herein ive breaches) specially provided when the breach for in respect of which the suit is instited occurs or (where the breach is continuing) when it ceases.” Section 23 of the Act reads, “23. Suits for compensation for acts not actionable without special damage.In the case of a suit for compensation for an act which does not give rise to a cause of action unless some specific injury actually results ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 6 :- therefrom, the period of limitation shall be computed from the time when the injury results.” Question posed is whether Sec.23 of the Act is applicable to suits excontractu or is it confined to suits for compensation arising from tort alone? In the unreported decision (in A.S. No.852 of 1998) relied on by learned counsel for respondents in a similar situation where the suit was for compensation for breach of contract it was observed by the Division Bench in paragraph 8 of the decision, “Reliance was placed on the provisions of Section 23 of the Limitation Act also. **It is well settled that Section 23 would apply only to suits based on tort.** Breach of contract itself gives rise to a cause of action and time begins to run from the date of breach. In _**Bhajan Singh and Co.**_ (Supra), the Full Bench of the Delhi High Court stated that Section 23 is applicable only to cases where the act in itself will not give rise to a cause of action. Respondent also placed reliance on the decision of the Rangoon High Court in _**V.M.Gany v. Leong Chye**_ (AIR 1936 Rangoon 510) wherein that Court examined the scope of Section 24 of -: 7 :- ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** the Old Limitation Act and opined that Section 24 applies not to suits based on contract, but to suits based on tort….” (emphasis supplied) This according to learned counsel for appellant is not correct since Sec.23 of the Act does not in its application differentiate between a suit on contract and a suit based on tort. 5. One of the early decisions on the point is **Kedar Nath** **v. Har Govind** (AIR 1926 Allahabad 605). That was a suit for compensation based on a contract. Question arose whether Section 24 of the Limitation Act, 1908 (corresponding to Sec.23 of the Act) applied to suits based on contact. Ashworth J, while taking the view that the provision applies to suits based on contract observed, “A reference to the terms of S.73 of the Contract Act shows that a suit can only be brought for injury or loss already caused and not for prospective loss. S.74 makes an exception to this. It allows a suit to be based on mere breach when the contract names a sum to be paid in case of mere breach or contains a stipulation by way of penalty. The ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 8 :- present contract did neither. Where there is no sum named to be paid in case of breach or stipulation by way of penalty, under Indian law a mere breach of the covenant by omission to pay, as in this case, gives no right to a claim for compensation and suit will come within the language of S.24 of the Limitation Act. I may mention that the word ‘act’ in S.24 will include an omission (see S.3(2) of the General Clauses Act, 10 of 1897) it has been urged that S.24 is only applicable to suits based on tort, but no reason appears for holding this….” The Rangoon High Court took a different view in **V.M. Gany v.** **Leong Chye** (AIR 1936 Rangoon 510) and **Annamalai Chettiyar v. Gowasjee** (AIR 1938 Rangoon 258). In the former case Ba U, J. criticised the decision of Ashworth, J. in **Kedar Nath's case** (supra) that Sec.24 of the Old Act (corresponding to Sec.23 of the Act) applies to the suits based on contract also and held that so far as suits for compensation for breach of contract is concerned time begins to run from the date of breach (as provided in Article 115 of the Old Act) and not from the date of actual loss and hence Sec.24 (of the Old Act) has no application. The view of Ba U, J. was not ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 9 :- accepted by the Patna High Court in **Jagath Kishore v. Parmeshwar Singh and Others** (AIR [38] 1951 Patna 348). The Division Bench referred to the contra views expressed by Ashworth, J. and Ba U, J. (in the decisions referred supra) as to the application of Sec.24 of the Old Act to suits based on contract. Relying on an earlier Bench decision in **Jagannath Marwari v.** **Kalidas** (AIR [16] 1929 Patna 245) it was held in **Jagath Kishore's case** (supra) that the better view is that Sec.24 (of the Old Act corresponding to Sec.23 of the Act) is applicable in the case of actions ex-contractu in proper cases where the terminus a quo was the date of injury and not breach of the covenant. In U.N. Mithra's 'Law of Limitation and Prescription' at page 699 it is stated by the author, “...as the language is general and may in proper cases apply to other acts as well which give rise to a cause of action only when specific injury results therefrom.” To me it appears, there is nothing in Sec.23 of the Act suggesting that the provision is confined in its application to suits based on tort. ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 10 :- Weight of authorities are also in favour of the view that Sec.23 of the Act is not confined in its application to suits for compensation arising from tort and that it could apply to suits based on contract where terminus a quo is the date of injury and not the breach of contract. The Division Bench of this Court while deciding A.S. No.852 of 1998 only considered the decision in **V.M. Gany's case** (supra). The contra authorities on the point were not brought to the notice of the Division Bench. **Bhajan Singh and Co.'s case** (spura) referred to by the Division Bench in A.S. No.852 of 1998 in my view has only said that Sec.23 of the Act applies only to cases where the act (or omission) in itself will not give rise to a cause of action. But a reconsideration of that matter is not necessary on the facts of these cases as the appeals could be decided de hors the question whether Sec.23 is applicable to suits on contract. 6. Now the question for consideration is whether to a case to which Article 55 of the Act applies, Sec.23 would apply so that the period of limitation is either extended or modified. Article 55 of the Act prescribes the period of limitation as three years for suits for compensation for breach of contract, express or implied (corresponding to Articles 115 and 116 of the Old Act). The period of limitation in such cases runs from the date on which the contract is ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** ## -: 11 :- broken and where there are successive breaches from the date on which the breach in respect of which the suit is filed, occur. In the case of continuing breach the day to be reckoned is the day on which it ceases. According to the learned counsel for appellant re-sale of the goods and consequent loss to the appellant gave rise to a fresh cause of action. Learned counsel contends that appellant suffered loss when re-sale for a lesser price was occasioned by the act or omission of respondents. In Halsbury’s Laws of England, 4[th] Edn., Vol.28 in paragraph 662 it is stated, “In an action for a breach of contract the cause of action is the breach. Accordingly such an action must be brought within six years of the breach; after the expiration of that period the action will be barred, although damage may have accrued to the plaintiff within the six years of action brought.” ## 7. In **Kumar Nath Bhuttacharjee v. Nobo Kumar** **Bhuttacharjee** ([1898] ILR [26] Calcutta 241) plaintiffs were held not bound to bring their action for damages (on breach of covenant) within six years from the date of breach. It was held that cause of action for plaintiffs arose when they were damnified. But referring to ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 12 :- that decision the Allahabad High Court said, in **Raghubar Rai and Another v. Jaij Raj and Another** ([1912] ILR [34] Allahabad 429), “With great respect to the learned Judges the rule laid down by them cannot be defended on principle. One breach of a contract can only furnish one cause of action and no more. Actual loss when it occurs is only one of the results of the breach, and is not an act of the party who breaks a contract and can, therefore, create no second cause of action. It is a pity that the case of _**Battley v. Faulkner**_ ([1820] 3 Barn. & Ald. 288) was not brought to the notice of the learned Judges. That is a clear authority for the proposition that consequential damage arising from the breach gives no cause of action......” The observation of **Bayley, J. in Battley v. Faulkner** (supra) that, “...If the plaintiff in this case had released the defendant from the breaches of contract, ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 13 :- that release would have been a bar to the present action for special damages subsequently occurring, and this shows that the foundation of the action is breach of contract. It was, therefore, from the period when the contract was broken that the cause of action occurred....” was quoted with approval in **Raghubar Rai's case** (supa). In **Kedar Nath’s case** (spura) Ashworth, J. took the view that Sec.24 of the Old Act (corresponding to Sec.23 of the Act) applies to suits on contracts since extent of damages is governed by Sec.73 of the Contract Act and from the time loss is suffered cause of action would arise. But in **Jagath Kishore's case** (supra) the Division Bench of Patna High Court was of the opinion that Ashworth, J. was not quite correct in his view of Sec.73 of the Contract Act and preferred the view of Ba U, J. in **V.M. Gany's case** (supra) that breach of contract per se gives rise to a cause of action and time begins to run from that date. The Contract Act and Limitation Act are not Statutes pari materia. Section 73 of the Contract Act is only a declaration of the common law as to damages. As such it is not ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 14 :- Sec.73 of the Contract Act which governs the period of limitation for the suit. It only helps the plaintiff to quantify the damages to which he is entitled consequent to the breach. 8. The issue was considered by the Madras High Court in **Soundararajan & Co. v. Annamalai Nadar** (AIR 1960 Madras 480). That was a suit for damages suffered on a breach of contract and a consequent re-sale. Contention of plaintiff was that period of limitation would run not from the date of breach but only after re-sale when the exact amount of damages could be ascertained by the plaintiff. Ananthanarayanan J, held, “But we find upon a scrutiny of the relevant dates that this claim is definitely out of time. **It ought to have been instituted within three years of the date of breach of contract and it is no defence to this objection to urge that it was only the occasion of re-sale which enabled the defendant firm to ascertain exactly the degree of damages or the precise amount which would represent the injury suffered by them.** The occasion for ascertainment will have to be distinguished from the date upon -: 15 :- ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** which cause of action arose and from which limitation began to run.” (emphasis supplied) This decision was followed by the same High Court in **Ragagopala Naidu v. Ayyaswamy Chettiar** (AIR 1965 Madras 532). That was a case involving a contract to permit the plaintiff to occupy a certain premises for a period of 15 days during Deepawali each year to enable plaintiff sell crackers at a good price. On 17.10.1953 plaintiff asked for possession of the premises. By notice dated 26.10.1953 defendant repudiated the demand. Plaintiff suffered loss as he could not sell crackers during the period of Deepawali and had to sell out crackers at a loss by 13.11.1953. In the suit for damages that followed question arose whether the period of limitation runs from 6.11.1953 when time for putting plaintiff in possession of the premises expired or on 13.11.1953 when plaintiff suffered damages. The Madras High Court held that breach was completed by 6.11.1953 when time for putting the plaintiff in possession expired and that the fact that plaintiff could determine quantum of damages only later by sale of the entire stock at a loss does not mean that limitation did not commence to run from the date of breach. At page ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** ## -: 16 :- ## 533 it was held, “The acceptance of the contentions urged by the learned counsel for the appellant would be completely opposed to the scheme of Article 115 and Sections 23 and 24 of the Limitation Act. In every case of breach of contract for the sale of goods the plaintiff who comes to court has a duty to mitigate the damages and he may have to take certain steps with regard to the goods in question and it is only after such steps are taken by way of re-sale that the damages could be ascertained. That does not mean that the running of time is postponed till the damages are actually ascertained and after re-sale In this case there is no question of any continuing damage within the meaning of Section 23 nor is it a case in which a cause of action has not accrued to the plaintiff on the date of the breach within the meaning of Sec.24.” 9. Now I shall consider the decision relied on by the counsel for appellant in **Eastern Traders (I) Ltd. v. P.N. Bank** (supra). There, referring to Sec.24 and Article 115 of the Old Act it was held, ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** ## -: 17 :- “a breach in the abstract would not be sufficient, in our opinion, to provide a foot-hold for the plaintiff to file a suit for compensation against the second defendant. It was only when the goods had been disposed of in November, 1948, when the injury was actually sustained and time must run from that date.” This decision was distinguished by the Division Bench of the Delhi High Court in **Bhajan Singh and Co’s case** (supra). In paragraph 35 referring to the decision of the Punjab High Court it was held, “It may be noted that there was no detailed discussion of the exact meaning and scope of section 24 of the Limitation Act and none of the decisions bearing on the matter was considered. Further the actual decision of the case was based on their finding that there was no proof of the damages sustained by the appellant-plaintiff and not on the question of limitation. Thus the observations on the question of limitation were obiter dicta. The decision should, therefore, be regarded as confined to the facts of that particular case and -: 18 :- ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** not as laying down a general proposition of law regarding the scope and applicability of section 24 of the Limitation Act.” Decision of the Punjab High Court was not based on any detailed discussion of the point involved. The Full Bench of Delhi High Court held that Sec.24 of the Old Act (corresponding to Sec.23 of the Act) has no application to suits governed by Article 115 of the Old Act (corresponding to Article 55 of the Act). The Division Bench of this Court in **Delta Foundations and Constructions's case** (supra) distinguished the decision of Punjab High Court in **Eastern Traders (I) Ltd.'s case** (supra) holding that it involved a contract of indemnity coming under Sec.24 of the Old Act (corresponding to Sec.23 of the Act). The Division Bench held that for suits for compensation for breach of contract as in the present case it is Article 55 of the Act (and not Article 113) applied and the starting point of limitation is when the contract is broken. The decision in **S.K.A.R.S.M. Ramanathan Chettiar v. National Textile Corporation Ltd.** (supra) relied on by learned counsel for appellant did not concern Article 55 of the Act. That decision only said that in a breach of contract to supply goods the difference between contract -: 19 :- ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** price and sale price is the true measure of damages. 10. Article 55 of the Act deals with breach of contract, its successive breaches and continuing breaches. Of course in a case where there is successive breach every such breach gives the plaintiff a cause of action. The term 'continuing breach' is intended to apply to contracts obliging one of the parties to adopt some given course of action during the continuance of the contractual obligation. But a continuing breach or wrong is different from a continuing damage. The former gives rise to a fresh cause of action but not the latter. The Patna High Court in **Brahamdeo Narain Rai & Another v. Jaikishan Chaudhury and Another** (AIR 1941 Patna 452) has held that the expression “successive breaches” occurring in Article 115 of the Old Act (corresponding to Article 55 of the Act) refers only to cases in which there is a promise to pay periodically, as for instance, payment of rent, annuities, interest, maintenance etc. But that has to be distinguished from continuing damage. It is true that in these cases as per terms of the contract or tender, re-sale due to breach is at the risk of respondents. But breach of the contract has occurred when respondents failed to pay the price and remove the goods on the due dates. Re-sale effected ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 20 :- by the appellant and short-fall in the price cannot amount to a breach, successive breach or continuing breach as Article 55 of the Act envisages. It only enabled the appellant to ascertain extent of damages it suffered. **Holes v. Chard Union** ([1894] 1 Ch.D. 293) says that a continuing cause of action arises from the repetition of acts or omissions similar to those in respect of which action is brought. Lindley, L.J. Said, “What is a continuing cause of action? Speaking accurately, there is no such thing; but what is called a continuing cause of action is a cause of action which arises from the repetition of acts or omissions of the same kind as that for which the action was brought..” Re-sale of goods in these cases are not act or omission of the same kind as failure to pay price and remove the goods on the due dates and hence cannot give rise to any new cause of action in favour of the appellant. Section 23 of the Act cannot apply to suits governed by Article 55 of the Act where cause of action arises on breach of contract or in the case of continuing breach when such breach ceases. The period of limitation in the present cases began to run on the ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** **==> picture [40 x 9] intentionally omitted <==** dates the contract was broken, i.e., from the dates by which respondents were to pay the price and remove the goods which is indisputably beyond three years preceding the institution of the suits. Learned Sub Judge therefore is correct in holding that the suits are barred by limitation. It follows that appellant is not entitled to the reliefs prayed for. These appeals fail and are dismissed. Parties are directed to suffer their respective costs. **THOMAS P.JOSEPH, JUDGE.** vsv ## **A.S. No.856 of 1998 & A.S. No.9 of 1999** -: 22 :- **“C.R”.** **THOMAS P.JOSEPH, J.** **===================** **A.S. NO.856 OF 1998** **AND** **A.S. NO. 9 OF 1999 ===================** **J U D G M E N T** **21ST DECEMBER, 2009**
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.