Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1994Division BenchAppeal allowed. No order as to costs.

Regional Provident Fund Commissioner v. M/s K. Trolling Mills Pvt. Ltd.

Case / Petition Number:
Civil Appeal No. 1639 of 1994
Neutral Citation:1994 Supp (5) SCR 645

Case Synopsis & Summary

The case concerns the power conferred by Section 14-B of the Employees’ Provident Funds and Miscellaneous Provisions Act, 1952 to levy damages for default in payment of contributions. The Regional Provident Fund Commissioner imposed damages of Rs. 52,034.80 for a period of default spanning July 1968 to October 1977; proceedings were initiated in 1985. The Bombay High Court set aside the order on the ground of unreasonable delay. The Supreme Court allowed the appeal, holding that when a statutory power is conferred without a laid‑down time limit, it must be exercised within a reasonable period, and a long delay does not automatically invalidate a damages order, especially where delays were due to the large number of Maharashtra establishments and the detection occurred only in 1985. The Court stressed the object of the Act: to penalize default and to provide redress to employees for losses, recognizing that defaulted employee contributions may have been used by the employer without interest, at the employees’ cost. The Court distinguished Christian Medical College (1989) Supp 2 SCC 95 as distinguishable on the facts. It set aside the High Court’s judgment but allowed the appeal with a condition: if the entire amount is paid within two months, no interest is payable; otherwise, interest at 18% from the date of judgment applies. No costs order was made."

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Kuldip Singh
  • B. L. Hansaria
Judgment Date
1994-11-22
Court Decision / Holding
The appeal is allowed. The High Court’s order is set aside. The respondent may avoid interest if the entire amount is paid within two months from today; if not paid within two months, interest at 18% per annum shall accrue from today until full realization. No order as to costs.
Final Disposition
Appeal allowed. No order as to costs.

Parties to the Case

Appellants / Petitioners

  • Regional Provident Fund Commissioner

Respondents

  • M/s K. Trolling Mills Pvt. Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • J.D. Jain
  • • S.A. Matto
  • • C.V.S. Rao

Counsels for Respondents

  • • K.K Mohan
  • • Pramod Dayal

Provisions of Law Cited

Employees Provident Funds and Miscellaneous Provisions Act, 1952, Section 14-B

Legal Doctrines & Maxims

  • Power conferred by statute must be exercised within a reasonable period where no time limit is prescribed.
  • Damages under Section 14-B serve to penalize default and compensate employees; the object of the provision is remedial and reformatory rather than punitive in isolation.
  • Constructive interpretation of statutory powers to advance the object of welfare legislation.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that Section 14‑B damages are a legitimate instrument to penalize default and compensate employees. Absence of a statutory time limit does not render the power illiberal; delay, though lengthy, must be assessed in light of Maharashtra’s numerous establishments and delayed detection. The objective of the Act requires enforcement even where delay occurred, and the court should not automatically strike down the damages order; if the delinquent party pays promptly, interest may be dispensed with and, if not, interest at 18% should apply.

Contentions of Respondents

The respondent argued that the extraordinary delay in initiating proceedings renders the damages order unreasonable and unconstitutional in effect. The High Court rightly struck it down on delay grounds. It was urged that in similar cases (e.g., Christian Medical College), where arrears arose from disputes on coverage, damages could be avoided. The present case should be guided by the same principles, otherwise the delay would undermine due process and produce an inequitable result.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Christian Medical College and Anr. v. Regional Provident Fund Commissioner(1989) Supp 2 SCC 95DistinguishedCited and distinguished on the facts; not applicable in the present circumstances.
Organo Chemical Industries v. Union of India(1980) 1 SCR 41PositiveCited to explain the purpose of damages under Section 14-B and to uphold constitutionality.
Regional Provident Fund Commissioner v. Sri Krishna Metal Manufacturing Company(1962) Supp. 3 SCR 815Mentioned OnlyCited as background regarding the Act’s objectives, not central to the decision.
Regional Provident Fund Commissioner v. Shibu Metal Works[1965) 2 SCR 72Mentioned OnlyCited as part of historical context on the Act’s enforcement.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,732 words•~8 min read

In The Court Record

Regional Provident Fund Commissioner v. M/s K. Trolling Mills Pvt. Ltd.

REGIONAL PROVIDENT FUND COMMISSIONER A _v._ ## _MIS_ K. TROLLING MILLS PVT. LTD. ## NOVEMBER 22, 1994 ## (KULDIP SINGH AND B.L. HANSARIA, JJ.] _Employees Provident Funds and Miscellaneous Provisions Act, 1952Section 14-B- Default in depositing contribution-Delay of 12 years in initiating proceedings-Whether order levying damages merits to be struck down on ground of delay-Held, No._ c The respondent has defaulted the contribution both of its own as well as of the employees _in_ time. The default related to the period from July, 68 to 6ctober, 77, relating to which proceeding came to be initiated in 1985. The Commissioner after applying his mind to the period of delay as well as to the quantum, imposed damages. The High Court held that the delay in initiating proceedings was unreasonable D and set aside the order of the Commissioner. This appeal has been filed against the judgment of the High Court. ## Allowing the appeal, this Court HELD: 1.1 When a power is conferred by statute without mentioning the period within which it could be invoked, the same has to be dorae within reasonable period, as all powers must be exercised reasonably, and exercise of the same within reasonable period would be a facet of reasonableness. (645 G) > 1.2 In the instant case, though the general period of delay of 12 F years is quite long, unreasonably long, but if it is borne in mind that in > view of large number of establishments in the State of Mahara.shtra, default at hand came to notice only in April, 1985, the killing effect of delay gets eroded. This Court does not, therefore, think if the order merits to be struck down on the ground of delay, when it is also kept in G mind that the delay in default related even to the contribution of the employees which money the respondent (after deducting the same from > the wages of the employees) must have used for its own purpose and that too without paying any interest, at the cost of those for whose > benefit it was meant. Any different stand would encourage the > employers to thwart the object of the Act, which cannot be permitted. 643 644 SUPREME COURT REPORTS [1994) SUPP. _5_ S.C.R A However the respondent would not be called upon to pay any interest on the damages as fixed by the Commissioner, if it woul!i pay the entire amount within two months. On the failure of the respondent to so pay, it shall have to pay interest at the rate of 18% from the date of this judgment till full realisation. B _Christian Medical College and Anr._ v. _Regional Provident Fund Commissioner,_ (1989) Supp 2 SCC 95, distinguished. (646 C, D, G) _Organo Chemical Industries_ v. _Union Of India,_ (1980) 1 SCR 41, relied on. c _Regional Provident Fund Commissioner_ v. _Sri Krishna Metal Manufacturing Company,_ (1962) Supp. 3 SCR 815 and _Regional Provident Fund Commissioner_ v. _Shibu Metal Works,_ [1965) 2 SCR 72, referred to. ## CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1639of1994. D From the Judgment and Order dated 12.7.93 of the Bombay High Court A.No. 384/93 in W.P.No. 3271 of 1987. . J.D. Jain, S.A. Matto, C.V.S. Rao for Anil Katiyar for the Appellant. - K.K Mohan and Pramod Dayal for the Respondents. E The Judgment of the Court was delivered by HANSARIA, J. The Employees, Provident Funds and Miscellaneous Provisions Act, 1952, hereinafter the 'Act', was enacted to serve beneficent purpose and it does constitute a welfare measure, as it seeks to create a fund which could be drawn upon by certain categories of employees working in F factories and some establishments to meet pressing demands so also to provide pension after the employees have ceased to be in service. So the Act has to be construed in such a way, ia1 case two views be possible, which advances the object. This has been the outlook of the court for over three decades by now, as the same was first focussed in _Regional Provident Fund Commissioner_ v. _Sri Krishna Metal Manufacturing Company,_ [1962] G (Supp.) 3 SCR 815 and was reiterated in _Regional Provident Fund Commissioner_ v. _Shibu Metal Works,_ [1965] 2 SCR 72. F H > 2. The purpose of the aforesaid prologue is to find out as to when > power under Section 14-B of the Act should be allowed to be used and whether it would in consonance with the object sought to be achieved by P. F. COMMISSIONER _v._ ROLLING MILLS [HANSARIA, J.] 645 the Act if delay in invoking the power is allowed to stand in the way. As in A the present case we are concerned with the order of the Regional Provident Fund Commissioner, Maharashtra, (the Commissioner) levying damages on the respondent for default in the payment of the contribution in exercise of power under Section 14-B, let it be noted what this Court had said about this Section in _Organo Chemical Industries_ v. _Union of India,_ (1980] I SCR 41. In that case this Court was called upon to decide the B constitutionality of Section 14-B, which was challenged as violative of Article 14 having conferred unguided power. It rejected the contention. It also spelt out the purpose of imposition of damages, stating that the same was meant to penalize defaulting employer, as also to provide reparation for the amount of loss suffered by the employees. It was pointed out that it is not only a warning to employers in general not to commit a breach of the C statutory requirements, but at the same time it is meant to provide compensation or redress to the beneficiaries i.e. to recompense the employees for the loss sustained by them. 3. There is no dispute in the present case that the respondent had defaulted in depositing the contributions both its own and as well as of the D employees in time. The Commissioner, after applying his mind to the period of delay as well as to the quantum, imposed a sum of Rs. 52,034.80 as .damages. The order of the Commissioner came to be challenged before the Bombay High Court by the respondent who has set aside the order solely on the ground that the proceeding was bad because of unreasonable delay in initiating the same. The Court pointed out that though Section 14-B E has not laid down any period of limitation, the power has to be exercised within reasonable time. As the default related to the period from July 68 to October 77, relating to which proceedings came to be initiated in 1985, the High Court regarded the delay as unreasonable, and so, fatal. The Regional Provident Fund Commissioner has preferred this appeal with the aid of F Article 136 of the Constitution. 4. There can be no dispute in law that when a power is conferred by statute without mentioning the period within which it could be invoked, the same has to be done within reasonable period, as all powers must be exercised reasonably, and exercise of the same within reasonable period G would be a facet of reasonableness. When this appeal was heard by us on 7.9.94 and when this aspect of the matter came to our notice, we desired an affidavit from the Commissioner to put on record regarding the point of time when he knew about the default and to explain the cause of delay. Pursuant to that order, the Commissioner filed his affidavit on 10.11.94, according to which the power of levying damages came to be delegated to H 646 SUPREME COURT REPORTS (1994] SUPP. _5_ S.C.R - A the Commissioner by an order dated 17.10.73. As, however, large number of establishments were in existence in the State of Maharashtra - the number of which 1985 was 22, 189 - and there was only one Regional Provident Fund Commissioner having power to levy damages, delay was caused in detection of the cases of belated payment. According to the affidavit, the default at hand was located on 19.4.85 and the damages came - B to be levied by order dated 5.11.86. _5._ The aforesaid shows that the delay was of 12 years viewed generally and was 1-1/2 years qua the case at hand. Though the general period of delay is quite long, unreasonably long, but if it is borne in mind that in view of large number of establishments in the State of Maharashtra, default at c hand come to notice only in April 1985, the killing effect of delay gets eroded. We do not, therefore, think ifthe order merits to be struck down on the ground of delay, when it is also kept in mind that the default :-elated even to the contribution of tire employees, which money the respondent (after deducting the same from the wages of the employees) must have used for its own purpose and that too without paying any interest, at the cost of D those for whose benefit it was meant. Any different stand would encourage the employers to thwart the object of the Act, which cannot be pennitted. D E F 6. Shri Mohan, learned counsel for the respondent, pleads that keeping in view what had been ordered by this Court in _Christian Medical College, and Brown Memorial Hospital_ v. _Regional Provident Fund Commissioner,_ [1989] Supp 2 SCC 95, we may not sustain the order of the Commissioner. In that case dues were not paid in time because of some controversy as to whether hospitals are covered by the Act. It was, therefore, contended that as the appellants would be complying with the provisions of the Act and would pay all the arrears, damages for dalayed payment of the arrears may not be approved. This Court, having regard to the facts of that case, accepted the submission. The facts of the present case are entirely different. 7. We, therefore, set aside the impugned Judgment of the High Court. But then we state that the respondent would not be called upon to pay any interest on the damages as fixed by the Commissioner, if it would pay the entire amount within two months from today. On the failure of the G respondent to so pay, it shall have to pay interest at the rate of 18% from today till full realization. 8. The appeal is allowed accordingly. No order as to costs. - A.G. - Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1994) Decisions
1994-01-28

BILLA JAGAN MOHAN REDDY AND ANR. v. BILLA SANJEEVA REDDY AND ORS.

This is a Supreme Court decision arising from a Land Acquisition Act reference under Section 30, where the appellants (the first party) sought to claim a 1/4 share of compensation based on pre-existing title evidenced by entries in the record of rights and other revenue records. To prove title, the appellants filed copies of family holdings, khasra Pahani, and certified copies from revenue authorities spanning 1954-70 and other documents, and moved for condonation of delay under Order XIII, Rule 1 CPC for production of these public documents. The trial court refused the application, and the High Court affirmed. The Court held that documentary evidence to be produced at or before settlement of issues must be produced in possession and, if not in possession, filed with an application to condone the delay, and the Court shall receive such documents if accompanied by an accurate list. Although there was a delay, the Court emphasized that, if the documents are relevant to decide the real issue and the interest of justice requires it, the appellate court can receive them under Order XLI, Rule 27 CPC. Consequently, the delay was condoned, and the trial court was directed to receive the documents, allow proof and rebuttal, and dispose of the reference according to law. The appeal was allowed.

1994-07-14

M/S Pankaj Jain Agencies v. Union of India

The petitioner, M/s Pankaj Jain Agencies, challenges Notification No. 142/86-Cus., dated 13 February 1986, issued under Section 25(1) of the Customs Act, 1962, which amended the earlier exemption Notification No. 70/85-Cus. The impugned notification pertains to rates of customs duty on imports of parts and sub-assemblies of ball and roller bearings, specifically “cups” supplied from Singapore for component parts of bearings. Two consignments arrived at Bombay Port in January–February 1986; the petitioner filed two Bills of Entry for home consumption. The central issue is whether the notification reduces the exemption and thereby imposes a higher duty, or creates a fresh duty on spare parts not contemplated by the Customs Tariff Act of 1975. The petitioner argued that import was complete before the notification came into force; that the notification was ultra vires Section 25(1) and violated Section 25(3) by exceeding the statutory duty; and that the increased duty violated Article 19(1)(g) by imposing an unreasonable restriction on trade. The Respondents contended that the notification merely curtailed an exemption, the rates did not exceed the statutory duty, and publication in the Official Gazette gave operativeness. The Supreme Court held that subordinate legislation must be published to take effect, and publication sufficed for operativeness; it rejected the ultra vires and fundamental-right challenges, and dismissed the petitions with costs, underscoring the principle that delegated legislation must be published to be effective.

1994-09-14

COMMISSIONER OF INCOME TAX, HYDERABAD v. M/s. P.J. CHEMICALS LTD. ETC.

This judgment addresses whether subsidies granted to industries on a percentage of capital cost should be deducted from the "actual cost" for computing depreciation under Section 43(1) of the Income Tax Act, 1961. Judicial opinions across Indian High Courts diverged: several held such subsidies non-deductible as they are incentives rather than payments toward asset cost, while others (including some Punjab and Haryana, Allahabad, Bombay, Calcutta, and Gauhati courts) treated the subsidy as deductible from actual cost. The matter was heard in two batches: revenue appeals challenging the Andhra Pradesh High Court’s view, and assessee appeals in the opposite camp. The Supreme Court discusses the meaning of "actual cost", urging liberal interpretation, and reinforces the majority view that government subsidies of this nature are incentives to attract investment, not amounts paid toward meeting the asset’s actual cost. It traces the legislative history, including amendments to the 1922 Act and the 1953 amendment, to explain the intended construction of the term. The Court overrules the contrary Punjab and Haryana decision in Jindal Brothers Rice Mills and sustains the rest of the High Court dissents in favor of the assessee. Consequently, Revenue appeals are dismissed and assessee appeals are allowed, with no costs."

1994-02-15

STATE OF KERALA v. MCDOWELL CO. LTD.

The Kerala Abkari Act governs the manufacture, sale and export of Indian made Foreign Liquor (IMFL) within Kerala. Distillers could export liquor outside Kerala with permission, but were required to execute a bond to secure payment of excise duty on export. The Board of Revenue issued a circular in 1982 treating such documents as agreements rather than bonds; the Board later held the instrument was a bond, while the Kerala High Court held it to be an agreement not liable to stamp duty, prompting Kerala to appeal. The central issue was whether Form VI, executed under the Distillery and Warehouse Rules, constitutes a Bond under the Kerala Stamp Act or merely an Agreement, affecting stamp duty liability under Entry 32 (Indemnity Bond) or Entry 13 (Bond) of the Schedule. The Supreme Court majority held that the instrument in Form VI is a bond within the meaning of the Kerala Stamp Act and liable to stamp duty under Entry 32, as it creates an obligation to pay money to the State on breach of conditions, a liability arising from the instrument itself, not merely from the Abkari Act. The dissent (Sahai, J.) argued the instrument arises from the Abkari Act, making it an Agreement rather than a Bond under the Stamp Act, and that duty would not arise from the instrument itself. The appeal was allowed and the writ petition disposed accordingly, with a refund of excess duty where needed.