Ravinder Singh Chana v. Khanna Properties and Infrastructures Pvt. Ltd.
Case Details & Bench
- Court
- High Court
- Hon'ble Judges
- S. Abdul Nazeer
- J.K. Maheshwari
- Judgment Date
- 2022-08-24
- Court Decision / Holding
- The National Commission’s order was set aside; the State Commission’s order dated 15.10.2020 was restored. The respondent is directed to pay/refund the amount in terms of the State Commission’s order within two months from today if not already paid/refunded, including the Rs.21,18,000 and applicable interest and costs as specified in the State Commission’s order.
- Final Disposition
- Appeal disposed of.
Parties to the Case
Appellants / Petitioners
- Ravinder Singh Chana
Respondents
- Khanna Properties and Infrastructures Pvt. Ltd.
Legal Representation & Advocates
Counsels for Petitioners
- • Akshat Shrivastava
- • Satvic Mathur
Counsels for Respondents
- • Yashish Chandra
- • Yash Agrawal
- • Devesh Pratap Singh
Case Synopsis & Summary
This Supreme Court Civil Appeal concerns a consumer dispute arising from a housing project where the builder failed to complete construction after receiving payment within the fixed time. The Madhya Pradesh State Consumer Disputes Redressal Commission (State Commission) on 15 October 2020 ordered the respondent to refund a total of Rs. 21,18,000 to the appellant, along with simple interest at 9% per annum from the date of the last deposit (19.01.2015) till realization, and Rs. 5,000 as litigation costs, to be paid within two months. The National Consumer Disputes Redressal Commission (National Commission) issued a contrary order directing a refund of Rs.16,18,000 with interest within two months from its order. The appellant challenged the National Commission’s partial reversal, arguing that the State Commission’s full relief should stand and that the National Commission exceeded its remit by reducing the amount payable. After hearing both sides and examining the record, the Court held that the National Commission erred in partially reversing the State Commission’s order. The National Commission’s order was set aside, and the State Commission’s order dated 15.10.2020 was restored. The respondent was directed to comply with the State Commission’s directions to refund the amount in terms of that order within two months, if not already paid. The appeal was disposed of accordingly.
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contended that the State Commission’s complete relief directing the refund of Rs.21,18,000 with interest and costs should be upheld, and that the National Commission’s partial reversal diminished the relief mandated by the consumer protection statutes. The appellant urged adherence to the State Commission’s unequivocal order and restoration of full relief without dilution.
Contentions of Respondents
The respondents argued in favor of the National Commission’s partial reversal, seeking to limit the refund amount and sustain the adjusted relief stated therein, asserting that recalibrated relief aligns with the project status and related considerations.
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Ravinder Singh Chana v. Khanna Properties and Infrastructures Pvt. Ltd. and instantly map out authorities that support, challenge, or govern your position.