RAMKRISHNA FORGINGS LIMITED v. Ravindra Loonkar, Resolution Professional of ACIL Limited & ANR.
Case Synopsis & Summary
This is a Civil Appeal under Section 62(2) of the Insolvency and Bankruptcy Code, 2016, challenging the orders of the NCLT and NCLAT in a CIRP concerning ACIL Ltd. The Corporate Debtor ACIL Ltd underwent CIRP, with Ravindra Loonkar appointed as Interim Resolution Professional and later as Resolution Professional (RP). The Committee of Creditors (CoC) approved a Resolution Plan submitted by Ramkrishna Forgings Limited (RFL) after multiple revisions, culminating in a final plan dated 05.08.2019 and approved by the CoC on 14.08.2019 with 88.56% votes. The RP filed an Approval Application under Sections 30(6) and 31 seeking Court approval. The NCLT, in 2021, directed revaluation of assets via the Official Liquidator, prompting NCLAT and then this Supreme Court appeal. The appellant contends that valuation should follow CIRP Regulations 27 and 35, with two registered valuers and confidential handling under Section 29(2), and that NCLT exceeded its jurisdiction by ordering revaluation contrary to CoC’s commercial decision and statutory framework. The respondents support the appellant’s position on CoC wisdom and statutory limits. The Court ultimately holds that the NCLT/NCLAT overstepped, reiterating that CoC’s commercial wisdom governs and the valuation mechanism is statutory, not subject to impromptu revaluation. The appeal is allowed and the NCLT’s 01.09.2021 order and NCLAT’s judgment are set aside; the NCLT is to pass appropriate orders within three weeks on the Approval Application, with pending avoidance applications proceeding on their merits.”
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Ahsanuddin Amanullah, J.
- Vikram Nath, J.
- Judgment Date
- 2023-11-21
- Court Decision / Holding
- This appeal is allowed. The order dated 01.09.2021 of the NCLT and the Impugned Judgment dated 19.01.2022 of the NCLAT are set aside. The NCLT shall pass appropriate orders in terms of this judgment on the Approval Application (I.A. No.1636 of 2019 in CP(IB) No.170(PB)/2018) within three weeks from the production of a copy of this judgment. Pending avoidance applications shall proceed on their own merits, but expeditiously. No order as to costs.
- Final Disposition
- Appeal allowed; the NCLT order dated 01.09.2021 and the NCLAT judgment dated 19.01.2022 are set aside; the NCLT to pass appropriate orders on the Approval Application within three weeks; pending avoidance applications to proceed on merits; no costs.
Parties to the Case
Appellants / Petitioners
- Ramkrishna Forgings Limited
Respondents
- Ravindra Loonkar, Resolution Professional of ACIL Limited
- Committee of Creditors of ACIL Ltd.
Legal Representation & Advocates
Counsels for Petitioners
- • Shyam Divan, Senior Counsel (for the Appellant Ramkrishna Forgings Limited)
Counsels for Respondents
- • Counsel for respondents not explicitly named in provided text
Provisions of Law Cited
Legal Doctrines & Maxims
- Commercial wisdom of the Committee of Creditors is binding and not to be interfered with by the NCLT/NCLAT.
- There is no independent equity-based jurisdiction for the adjudicating authorities to intervene in CoC’s commercial decisions under the IBC.
- IBC is a complete code; residual equity-based jurisdiction is not contemplated.
- Reason is the heartbeat of every conclusion; recording reasons for judicial decisions is mandatory.
- Judicial review is confined to the statutory framework (Sections 30-31 IBC) and cannot substitute commercial judgment.
- Valuation mechanics must follow CIRP Regulations (27, 35) and use two registered valuers with confidentiality under Section 29(2).
- Valuation, and avoidance-transactions post-approval, are to be handled within the statutory regime and not via fresh, open-ended jurisdiction.
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant argues that the final Resolution Plan, negotiated extensively and approved by the CoC with an 88.56% majority, represents the commercial wisdom of the creditors and should be approved by the Adjudicating Authority (NCLT). The NCLT’s direction to involve Official Liquidator for asset revaluation was beyond its jurisdiction and inconsistent with CIRP Regulations 27 and 35, which provide a structured valuation mechanism using two registered valuers. The plan provided for monetization proceeds to go to the Financial Creditors; the 2022 Amendment Regulations and decisions such as Maharashtra Seamless and Ebix Singapore support that the CoC’s decisions should not be second-guessed on valuation. The appellant contends that the NCLT/ NCLAT lacked reasoned basis for ordering revaluation, and that the Code is a complete framework; it should not be unsettled by equity-based interventions. The appellate process should preserve speed and efficiency of CIRP; the contractually negotiated terms and the CoC’s commercial decision were duly complied with.
Contentions of Respondents
The respondents support the appellant’s position that the CoC’s commercial wisdom should prevail and that NCLT/NCLAT should not substitute its own views on valuation. They contend that valuation is a technical function governed by CIRP Regulations 27 and 35 and Section 29(2), and that the OL’s involvement was not necessary given the lack of objections to the initial resolution plan. They emphasize that the final plan, approved by a wide majority, aligns with statutory requirements, and that the NCLT’s intervention was overbroad, undermining the CoC’s decision-making role and the objective of time-bound CIRP.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (18)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Pratap Technocrats Private Limited v Monitoring Committee of Reliance Infratel Limited | (2021) 10 SCC 623 | Positive | Cited to support the proposition that the Adjudicating Authority’s jurisdiction is statutorily circumscribed and does not extend to reviewing CoC’s commercial decisions; aligns with the decision not to substitute equity for business judgment. |
| Maharashtra Seamless Limited v Padmanabhan Venkatesh | (2020) 11 SCC 467 | Positive | Used to assert that valuations are not open to judicial scrutiny by NCLT and that CIRP valuation can be below liquidation value; supports retention of CoC’s commercial discretion. |
| M K Rajagopalan v Dr Periasamy Palani Gounder | (2023) SCC OnLine SC 574 | Positive | Aids the view that if CoC is fully satisfied with valuation, interference by NCLT/NCLAT is unwarranted. |
| Ebix Singapore (P) Ltd. v Committee of Creditors of Educomp Solutions Limited | (2021) SCC OnLine SC 707 | Positive | Supports the principle that NCLT can examine plan validity under Section 30(2) but cannot compel CoC to renegotiate; respects CoC’s commercial decisions. |
| Kalpraj Dharamshi v Kotak Investment Advisors Limited | (2021) 10 SCC 401 | Positive | Affirms that CoC’s commercial wisdom should not be disturbed by NCLT/NCLAT. |
| Jaypee Kensington Boulevard Apartments Welfare Association v NBCC (India) Limited | (2022) 1 SCC 401 | Positive | Cited for limitation of adjudicatory power and deference to CoC’s decisions. |
| Vallal RCK v Siva Industries and Holdings Limited | (2022) SCC OnLine SC 717 | Positive | Reinforces binding and final nature of approved Resolution Plan by CoC. |
| Arun Kumar Jagatramka v Jindal Steel and Power Limited | (2021) 7 SCC 474 | Positive | Supports limited intervention in the CoC’s commercial decision and minimal judicial innovation. |
| K Sashidhar v Indian Overseas Bank | (2019) 12 SCC 150 | Positive | Affirms that the Court should not undermine CoC’s commercial decision; emphasizes the primacy of commercial wisdom. |
| Committee of Creditors of Essar Steel India Ltd. v Satish Kumar Gupta | (2020) 8 SCC 531 | Positive | Supports the notion that CoC decisions are to be respected and not open to perfunctory judicial second-guessing. |
| Innoventive Industries Ltd. v. ICICI Bank | (2018) 1 SCC 407 | Positive | Important precedent confirming time-bound resolution and statutory framework of IBC. |
| Swiss Ribbons Private Limited v Union of India | (2019) 4 SCC 17 | Positive | Affirms the code-based framework and limited scope of equity-based intervention. |
| Embassy Property Developments Private Limited v State of Karnataka | (2020) 13 SCC 308 | Positive | Cited to discuss procedure and fairness in administrative decisions within statutory limits. |
| Gujarat Urja Vikas Nigam Limited v Amit Gupta | (2021) 7 SCC 209 | Positive | Quoted regarding court’s deference to statutory scheme and need for reasoned orders. |
| Tata Steel BSL Limited v Venus Recruiter Pvt. Ltd. | SCC OnLine Del 155 (Delhi High Court, 2023) | Positive | Used to illustrate the principle that benefits from avoidance applications should be allocated to creditors when plan is silent on treatment. |
| Raj Kishore Jha v State of Bihar | (2003) 11 SCC 519 | Positive | Referenced for jurisprudential context on justice and legality of writs and orders. |
| Kranti Associates Private Limited v Masood Ahmed Khan | (2010) 9 SCC 496 | Positive | Supports the requirement of recording cogent reasons for court/tribunal decisions. |
| Maneka Gandhi v. Union of India | (1978) 1 SCC 248 | Positive | Used to discuss fair procedure within a statutory framework; though court emphasises IBC as a complete code, Maneka is cited for procedural fairness. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
RAMKRISHNA FORGINGS LIMITED v. Ravindra Loonkar, Resolution Professional of ACIL Limited & ANR.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.