Purushothaman v. The Secretary, Kerala State Electricity Board and Others

Case / Petition Number:
A.S. No. 719 of 2000

Case Synopsis & Summary

This Kerala High Court appeal arises from O.S.556/95 filed by Purushothaman, a small-scale unit under S.M. Industries, seeking a declaration that it is not liable to pay dues claimed by the Kerala State Electricity Board (KSEB) and a consequential injunction. The unit had to close due to labor issues and financial troubles, leading KSEB to demand Rs. 40,052 for electricity dues from Jan 1992 to 1994. KSEB disconnected service on 29-01-1992 and dismantled the connection on 31-12-1994. The Subordinate Court Irinjalakuda dismissed the suit as not maintainable but suggested appealing to the Board and paying on a schedule, with possible interest if successful. The plaintiff’s heirs (Ratnamma and Pradeep Kumar) were impleaded as legal heirs. The High Court held that, although the suit sought a declaratory remedy, the statute provides an alternate remedy by way of departmental appeal; following Punjab State Electricity Board v. Ashwani Kumar, the civil suit need not be entertained and the matter should proceed under the applicable Rules. The High Court remanded with directions to file an appeal or complaint before the appropriate authority, allow a hearing, and decide in accordance with law, while noting possible consideration of interest as per Supreme Court precedents. Costs were to be borne by the parties.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • M. N. Krishnan
Judgment Date
2010-12-07
Court Decision / Holding
The High Court disposed of the appeal by directing the plaintiff to pursue the statutory remedy via an appeal or complaint before the appropriate authority, with an open hearing to raise all contentions. The authority was to consider Rules 34(c) and (d) and decide in accordance with law, including any interest aspects per Supreme Court decisions. The court also directed the appellants to file the appeal within six weeks from today and stayed coercive proceedings until a final decision. The trial court’s findings were not to be binding in the subsequent proceedings. Costs were to be borne by the parties.
Final Disposition
Appeal disposed of with directions to pursue the statutory appellate remedy; matter to be heard under Rules before the appropriate authority; stay on coercive measures; costs to be borne by the parties.

Parties to the Case

Appellants / Petitioners

  • Purushothaman, S/o Kaithakkadan Konnan, Kunnappilly P.O., Melur, Mukundapuram Taluk (died)
  • Ratnamma, W/o Kaitharath Purushothaman, Kunnappilly P.O., Melur, Mukundapuram Taluk
  • Pradeep Kumar, S/o (deceased) -DO- -DO-

Respondents

  • The Secretary, Kerala State Electricity Board, Thiruvananthapuram
  • The Assistant Executive Engineer, KSEB Major Section, Koratty P.O., Mukundapuram Taluk
  • The Deputy Tahsildar (RR), Mukundapuram Taluk
  • The Village Officer, Melur, Mukundapuram Taluk
  • Government of Kerala, represented by District Collector, Thrissur

Legal Representation & Advocates

Counsels for Petitioners

  • • K. G. Balasubramanian

Counsels for Respondents

  • • Adv. Sri. Asok M. Cheriyan, SC, KSEB
  • • Sri. N. D. Premachandran, SC, KSEB
  • • Govt Pleader (R3-R5)

Provisions of Law Cited

Rules 34(c) and 34(d) of the conditions of supply of electric energyRule 34(c)(ii)Rule 35(d)

Legal Doctrines & Maxims

  • Alternate remedy doctrine: when an adequate remedy exists under statute, civil courts should refrain from interfered action
  • Judicial restraint in entertaining suits when an appellate remedy is available under the statute

Submissions & Arguments

Contentions of Appellants / Petitioners

The learned counsel for the appellant contended that the trial court overlooked Rules 34(c) and (d) of the conditions of supply of electric energy, especially the parameters that energy charges need not be levied during disconnection, though fixed charges may still be payable. It was argued that disconnection on 29-01-1992 and dismantlement on 31-12-1994 violated the six-month norm and related provisions in Rules 34 and 35, rendering the suit for declaration untenable. They asserted that, since an adequate alternate remedy exists under the Rules, the civil suit should not have been entertained and the matter should be heard via the departmental appeal process, with potential interest considerations.

Contentions of Respondents

The respondents argued that disconnection and dismantlement were effected under Board policy, making the consumer liable for fixed charges; the suit sought declaratory relief, which is not maintainable given the statutory remedy. They asserted that the Board’s action was in accordance with law and the Revenue authorities acted on the Board’s requisition, implying the suit against R3–R5 is not maintainable. They urged adherence to Rule 34 and Rule 35 as controlling the service connection and discharge, and maintained that the appellate route should be pursued before any civil action could be entertained.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Punjab State Electricity Board & another v. Ashwani Kumar1997 (5) SCC 120PositiveThe High Court relied on the principle from this Supreme Court decision that where an alternative statutory remedy (departmental appeal) exists, it is preferable to pursue it rather than filing a civil suit, guiding the disposal of the present case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,242 words•~6 min read

In The Court Record

Purushothaman v. The Secretary, Kerala State Electricity Board and Others

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE M.N.KRISHNAN** **TUESDAY, THE 7TH DECEMBER 2010 / 16TH AGRAHAYANA 1932** **AS.No. 719 of 2000()** - **-----------------------------** **OS.556/1995 of ADDL.SUB COURT, IRINJALAKUDA** **....................** ## **APPELLANT/PLAINTIFF:** ## **-----------------------------------** - ***1. PURUSHOTHAMAN, S/O.KAITHAKKADAN KONNAN, KUNNAPPILLY P.O., MELUR,** - **MUKUNDAPURAM TALUK. *(DIED)** ## ***SUPPLEMENTAL APPELLANTS 2 AND 3 IMPLEADED** **2. RATNAMMA, W/O.KAITHARATH PURUSHOTHAMAN, KUNNAPPILLY P.O., MELUR, MUKUNDAPURAM TALUK.** **3. PRADEEP KUMAR, S/O. -DO- -DO-** - **SUPPLEMENTAL APPELLANTS 2 AND 3 ARE IMPLEADED AS THE LEGAL HEIRS OF THE DECEASED FIRST APPELLANT, VIDE ORDER DATED 01/12/2010 IN I.A.4344/2010.** **BY ADV. SRI.K.G.BALASUBRAMANIAN** ## **RESPONDENTS/DEFENDANTS:** ## **---------------------------------------------** **1. THE SECRETARY, KERALA STATE ELECTRICITY BOARD, THIRUVANANTHAPURAM.** **2. THE ASSISTANT EXECUTIVE ENGINEER, KSEB MAJOR SECTION, KORATTY P.O., MUKUNDAPURAM TALUK.** **3. THE DEPUTY TAHSILDAR (RR), MUKUNDAPURAM TALUK.** **4. THE VILLAGE OFFICER, MELUR, MUKUNDAPURAM TALUK.** **AS.No. 719 of 2000** **5. THE GOVERNMENT OF KERALA, REPRESENTED BY DISTRICT COLLECTOR, THRISSUR.** **R3 TO R5 BY GOVT. PLEADER R1 & R2 BY ADV. SRI. ASOK M.CHERIYAN, SC, KSEB, SRI.N.D.PREMACHANDRAN, SC, KSEB.** **THIS APPEAL SUITS HAVING BEEN FINALLY HEARD ON 07/12/2010, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **rs** ## **M.N. KRISHNAN, J.** **= = = = = = = = = = = = = = = A.S. NO. 719 OF 2000 = = = = = = = = = = = = = = = Dated this the 7[th] day of December , 2010.** ## **J U D G M E N T** This appeal is preferred against the judgment and decree passed by the Subordinate Judge, Irinjalakuda in O.S.556/95. The suit is one for a declaration and consequential injunction. The plaintiff is an unfortunate small scale unit 'S.M.Industries' which was started but had only a short span of life. On account of the labour problems and other difficulties repayment to the K.F.C. became an impossibility which resulted in taking possession of the assets of the firm by the Corporation and it led to the non-functioning of the unit. The Kerala State Electricity Board had sent a notice demanding Rs.40,052/- which according to them are the dues from the month of January, 1992 till 1994. It is also contended ## **A.S. 719 OF 2000** -2- that there had been a subsequent dismantlement of connection and therefore the plaintiff prays for the declaratory relief that it cannot be directed to pay amount as it had not been functioning and as electricity connection has been disconnected. 2. Defendants 1 and 2 would contend that there was disconnection of electricity on 29.1.92 and dismantlement of electrical connection on 31.12.94. Irrespective of the question of disconnection the consumer is liable to pay the fixed charges and therefore the demand is in order and further as there is an alternate remedy the suit is not entertainable. The Revenue authorities had acted on the requisition of the K.S.E.B. and they would contend that the suit as filed against them is not maintainable. The learned trial judge on exhaustive consideration of the materials held ## **A.S. 719 OF 2000** -3- that the plaintiff is not entitled to the declaration, found that the suit is not maintainable but ultimately granted a relief in the form of a direction to file an appeal or complaint to the Board and on condition that it deposits the amount in five monthly instalments. There was also a direction, in case of success for the plaintiff, to get back the amount with 12% interest from the K.S.E.B. but ultimately the suit had been dismissed. It is against that decision the plaintiff has come up in appeal. 3. The learned counsel for the appellant would submit before me that the learned Subordinate judge had lost sight of Rules 34(c) and (d) and thereby has committed grave error. As per Rule 34(c) of the conditions of supply of electric energy if the service remains disconnected for more than one month, energy charge will not be levied for that period. But ## **A.S. 719 OF 2000** -4- there is a liability to pay fixed charge. Under Rule 34 clause (c) (ii) normally no service shall be kept disconnected for more than six months continuously at a time and under Rule 35 (d) “no service shall remain disconnected continuously for a period exceeding six months for non-payment of amount due to the Board. If the dues are not paid within the six months period of disconnection, the service shall be dismantled and agreement terminated immediately after the six months of disconnection after giving 15 days notice to the consumer.” 4. In this case admittedly disconnection has been done in the month of January, 1992 more specifically on 29.1.1992 and the dismantlement has been done only on 31.12.94. So it is really against the rules. I have just stated these things for the authority to consider it. ## **A.S. 719 OF 2000** -5- 5. The trial court has non-suited the plaintiff in the light of the decision of the Hon'ble Supreme Court reported in **Punjab State Electricity Board & another v. Ashwani Kumar (1997 (5) SCC 120)** . The learned counsel for the appellant wanted to distinguish that decision stating that it is only one for injunction whereas the suit is filed by the plaintiff is one for declaration. But the principle laid down by the Hon'ble Supreme Court is that when there is an alternate remedy provided under the statute itself by way of departmental appeal then it is desirable to exercise that and not to entertain a case by the civil Court. So in the light of the same I am also to hold that the civil suit need not be entertained but some remedy for a hearing is absolutely necessary for the plaintiff in the light of the rules extracted above. Therefore I close this appeal ## **A.S. 719 OF 2000** -6- with a direction to the plaintiff to file an appeal or complaint as provided under Rules before appropriate authority and direct that authority to consider the case of the plaintiff especially with reference to Rules 34(c) and (d) of the conditions of supply of electrical energy. An open hearing may be provided to raise all contentions by the department as well as by the plaintiff and thereafter the matter may be decided in accordance with law. I also make it clear if at all there is any question regarding interest that also may have to be considered judiciously in the light of the Hon'ble Supreme Court's decisions and the matter be disposed of in accordance with law. 6. The legal representatives of the appellant are directed to prefer an appeal or complaint as the case may be within six weeks from today and it is further made clear till a ## **A.S. 719 OF 2000** -7- final decision is taken in the matter coercive proceedings be averted to realise the amount demanded by the notice. Parties are directed to bear their respective costs. 7. It is made clear that any finding entered into by the trial Court shall not be the criteria for deciding the case and untrammeled by the observations thereunder, the matter can be heard and disposed of. ## **M.N. KRISHNAN, JUDGE.** ul/- **A.S. 719 OF 2000** -8- **M.N. KRISHNAN, J. = = = = = = = = = = A.S. No. 719 OF 2000 = = = = = = = = = = =** **J U D G M E N T 7[th] December, 2010.**
End of Judgment Record
Browse All High Court of Kerala (2010) Decisions
2010-09-09

T.K. Biju and Gangaprasad S. v. State of Kerala and The Director, Institute of Human Resources Development (IHRD)

This batch of writ petitions challenges the Institute of Human Resources Development’s (IHRD) recruitment process for the Last Grade Service under notification RECT/03/09/HRD (dated 21.1.2009). The core questions concern the validity of the 23.8.2009 written test, the 23.10.2009 short list (main and supplementary) drawn therefrom, and the 19.3.2010 rank list published after interviews. Petitioners—mostly former daily wage/ad hoc employees—also pursue regularisation, arguing that the selection framework and weightage for past service were either discriminatory or inadequately applied. Ext.P4 had disposed of earlier petitions by directing IHRD to finalise recruitment under a resolution dated 9.7.2007, and Ext.P5 laid down the recruitment rules: an objective written test (70 marks) and an interview (30 marks) with category-wise cut-offs (Rule 5.3) and a rank list valid for three years (Rule 5.4). The court holds that deviations such as clause 8 in the hall ticket do not render the process void in the absence of prejudice, and upholds the short-list’s legality to a large extent. However, drawing on Umadevi (3) and Satya Prakash, the court ultimately directs a limited revisiting of the rank list to grant weightage under Rule 5.2 to those petitioners who would have been included, while denying general regularisation. All petitions are disposed with these directions.

2010-01-21

State of Kerala and District Collector, Kollam v. K. Raghavan

This is a review petition filed by the State of Kerala and the District Collector, Kollam, challenging the High Court’s 23 March 2009 judgment in W.P.(C).29695 of 2005, which directed the Government to consider a freedom fighter’s pension claim and to grant pension from the date of application. The petition traces a long history: the applicant, aged about 75 at the time of filing on 29.12.1995, faced earlier adverse orders in 1987 and 1989; after litigation, the 2005 judgment directed reconsideration and culminated in a 2009 order granting pension in December 2009 but from the date of sanction rather than from the date of application. The review petition contends that the Supreme Court’s decision in State of M.P. and Another v. Devkinandan Maheshwari (2003) and a Division Bench decision followed in W.A. Nos.1419/2006 & 1818/2006 require pension from the date of sanction, not the application date, and thus the judgment should be recalled. It also relies on Dokka Samuel v. Dr. Jacob Lazarus Chelly (1997) to assert that omitting authorities is not a ground for review. The Court, however, finds that omission to cite authorities cannot ground a review and that the government’s delay in compliance violates the Court’s directions, warranting dismissal of the review petition with costs.

2010-02-23

Anitha Rajan v. Revenue Divisional Officer, Thrissur; Thasildar, Chavakkad; Village Officer, Nattika; Sub Registrar, Thriprayar

Anitha Rajan, the petitioner, purchased 50 cents of land in Re-Survey No.166/1, Nattika village, Thrissur district, from the legal heirs of late Gangadharan via Ext.P3 sale deed registered at Triprayar. The conveyance, through power of attorney documents Ext.P1 (executed by Ajayan in Dubai in favor of his mother Rathnabhai) and Ext.P2 (executed by Usha in India), prompted mutation proceedings before the Revenue Divisional Officer (RDO). The RDO refused to effect mutation unless the original Ext.P1 POA was produced for adjudication of stamp duty under the Kerala Stamp Act, 1959, claiming non-compliance with stamping and the need to determine stamp duty under sections 31 and 32. The petitioner contends that it is not mandatory to submit every PoA executed outside India for adjudication; only instruments chargeable with duty which cannot be stamped by private persons must be taken to the Collector under section 18(2). Ext.P1, though executed abroad, is on Indian stamp paper and was presented at registration, having been stamped Rs.150 under Article 44(f). The court analyzed sections 18(1), 18(2), 31 and 32 and held that section 18 applies to instruments executed outside India; since Ext.P1 is duly stamped, Section 18 has no application and Sections 31-32 cannot be invoked to compel production. Relying on Madras High Court decisions Manoharan v. Velu and R.B.K. Rajeswari Nachiar, the court held the Village Officer erred in requiring Ext.P1 before the RDO, quashed Exts.P4 and P6, and directed mutation actions to be completed within two months of certified judgment copy.

2010-03-23

V. Mohanan Nair v. Babu Pillai and others

This writ petition arises from a complex land dispute in Nedumangad where the petitioner, V. Mohanan Nair, challenged a trial court order that set aside a commissioner's report and remitted for a fresh report. In O.S. 380/2005 the plaintiff sought a permanent injunction; in O.S. 542/2005 the second respondent sought declaration of title and possession based on deeds executed in 2005. To resolve the location of the plaint schedule property, a commission was appointed, and Ext. P2 report and plan were filed. Subsequently, I.A. 4808/2009 was filed by the second respondent seeking to set aside the commission report and plan and remit for a fresh report. The trial court remitted the matter; Ext.P8 records the order, which the petitioner challenged in this Writ Petition. The respondents relied on a decision in Sarojini v. Karthiyani Amma to contend that Article 227 petitions against commission reports are not maintainable, while the petitioner argued lack of justification for remitting and the undue delay in filing the petition. The Kerala High Court, while recognizing the normal reluctance to exercise visitorial jurisdiction, held that exceptional circumstances permit interference under Article 227 and remanded the matter for fresh consideration, directing that the trial court assess sufficiency of Exts. C1, C1(a), C1(b) and allow further inspection if needed. The result is a remand to ensure a fair adjudication on the commission report."