This is a Supreme Court civil appeal arising from an arbitration award in a long-running contract dispute between a Punjab state-owned supplier and a rice mill operator. In 1996 the appellant entrusted paddy for processing into rice to be delivered to the Food Corporation of India. The arbitration award dated 01.06.2001 granted the appellant a monetary relief for breach of contract, including recovery of losses and certain statutory costs. The respondents challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, but both the Additional District Judge (Jalandhar) and the Punjab and Haryana High Court dismissed the challenge, rendering the award final. The respondents then sought to obstruct enforcement by arguing nine objections under Section 47 of the Civil Procedure Code, including alleged vagueness of the award, improper interest calculations, lack of consent for 21% interest, pendent lite and future interest, miscalculations, and lack of notice for execution. The executing court and the High Court accepted a statement of account showing a sum paid, but the Supreme Court found this misapplied and held that no valid payment had been certified under Order 21 of the CPC. The Court held the award to be final and enforceable as a decree under Section 36, allowed the appeal, and directed full recovery with costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay Manohar Sapre
  • R. Banumathi
Judgment Date
2017-07-11
Court Decision / Holding
The Supreme Court allowed the appeal. It held that Sections 35 and 36 of the Arbitration and Conciliation Act, 1996 make an arbitral award final and enforceable as a decree once challenges under Section 34 are exhausted or time has expired. The execution petition was to proceed as a decree under the CPC, with the award to be enforced like a Civil Court decree. The Court rejected the respondents’ Section 47 objections as unfounded, held that no valid payment had been certified under Order 21, and directed the executing Court to issue warrants for recovery of the full decretal amount within one month, with costs to the appellant (Rs. 25,000).
Final Disposition
Appeal allowed; impugned orders set aside; de novo enforcement of the award as a decree; full recovery ordered with costs.

Parties to the Case

Appellants / Petitioners

  • Punjab State Civil Supplies Corporation Ltd. & Anr.

Respondents

  • M/s Atwal Rice & General Mills Rep. by its Partners

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Ashish Wad

Counsels for Respondents

  • • Mr. Abhishek Vikas

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 34Arbitration and Conciliation Act, 1996 - Section 35Arbitration and Conciliation Act, 1996 - Section 36Code of Civil Procedure, 1908 - Section 47Code of Civil Procedure, 1908 - Order 21 Rules 1-3

Legal Doctrines & Maxims

  • Finality and binding nature of arbitral awards (Arbitration Act)
  • Enforcement of arbitral awards as decree under Section 36 of the Act
  • Judicial restraint in execution proceedings: cannot travel behind the decree; limited inquiry permissible (Kiran Singh & Ors. v. Chaman Paswan & Ors., AIR 1954 SC 340)
  • Award cannot be questioned on merits in execution; only jurisdictional issues may be raised

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the arbitration award dated 01.06.2001 is final and binding under Sections 35 and 36 of the Arbitration and Conciliation Act, 1996. After the expiry of the period for challenging under Section 34, the award may be enforced as if it were a decree. The award should be enforced by the executing courts without re-examining the merits, and objections under Section 47 CPC are not maintainable to stall enforcement. The statement of accounts presented by the judgment debtor is not a valid certified payment under Order 21, Rules 1-3, and there was no proper certification of payments; hence the decree could not be said to be fully satisfied. The Court should set aside perverse orders and direct enforcement of the entire decretal amount, with costs.

Contentions of Respondents

The respondents argued nine objections under Section 47 CPC challenging execution, including that the award is vague, interest calculations are unclear (21% without qualification), pendente lite and future interest, lack of consent of the MD for the rate, miscalculations, no notice of execution, and that they had appealed. They also sought production of complete accounts and contended lack of proper payment, contesting the execution on merits rather than technical grounds.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Kiran Singh & Ors. v. Chaman Paswan & Ors.AIR 1954 SC 340PositiveUsed to justify limited inquiry in execution and to prohibit traveling behind the decree.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,747 words•~18 min read

In The Court Record

Punjab State Civil Supplies Corporation Ltd. & Anr. v. M/s Atwal Rice & General Mills Rep. by its Partners

# **REPORTABLE** # **IN THE SUPREME COURT OF INDIA** ## **CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL No.8943 OF 2017** (ARISING OUT OF SLP (C) No.1552/2015) Punjab State Civil Supplies Corporation Ltd. & Anr. ...Appellant(s) ## VERSUS M/s Atwal Rice & General Mills Rep. by its Partners ….Respondent(s) ## **J U D G M E N T** ## **Abhay Manohar Sapre, J.** 1) Leave granted. 2) This appeal is filed against the final judgment and order dated 17.10.2014 passed by the High Court of Punjab & Haryana at Chandigarh in Civil Revision No. 3602 of 2013 whereby the High Court dismissed the revision petition filed by the Signature Not Verified Digitally signed by ASHA SUNDRIYAL Date: 2017.09.04 10:20:54 IST appellants herein and affirmed the order dated Reason: 03.11.2012 passed by Additional District Judge, 1 Jalandhar in Execution SR. No. 37 of 2010 by which the execution petition relating to arbitration award dated 01.06.2001 was dismissed. 3) In order to appreciate the short controversy involved in this appeal, few relevant facts need mention infra. 4) The appellant is a State owned Corporation engaged in supply of civil commodities in the State of Punjab. Respondent No. 1 is a partnership firm whose partners are respondent Nos. 2 to 4. The firm is engaged in the business of running a rice Mill in Jalandhar. 5) On 01.01.1996, the appellant and Respondent No.1 entered into an agreement. In terms of this agreement, the appellant was to give their paddy to the respondents, who were to process the paddy in their Rice Mill and the resultant rice produced after processing paddy were to be delivered to the Food Corporation of India (FCI) for and on behalf of the appellant by the respondents. Since the agreement 2 was in relation to processing of paddy and then supply of rice to public at large through FCI, the time was made the essence of the agreement so that the concerned departments would be able to supply the rice in time to public at large. 6) It is the case of the appellant that the appellant delivered 62944 bags weighing 40790 quintals of fine variety of paddy and 90303 bags weighing 58696.95 quintals of IR 8 variety of paddy to the respondents for processing and converting into Rice for being supplied to the FCI. The respondents duly acknowledged the receipt of paddy from the appellant on 27.11.1995 and 06.12.1995. 7) The respondents, however, could only process and deliver to the FCI 27950.75 quintals of fine variety rice and 22955.32 quintals of IR - 8 variety of rice till 30.06.1996. Thereafter the respondents could deliver 710.00 quintals of fine variety of rice and 14441.04.200 quintals of IR -8 variety of rice in 1075 bags after 30.06.1996. 3 8) Since the respondents failed to process and deliver the full quantity of rice in terms of agreement to the FCI much less within the time framed, it caused money losses to the appellant in addition to sustaining the damages due to non-delivery of the rice. According to the appellant, since the respondents committed breach of the agreement because they were not able to perform their part of the agreement, the appellant became entitled, in terms of the agreement, to recover from the respondents (1) 1½ times economic cost of balance paddy, (2) the cost of balance bags and sales tax @ 4.4% thereon, besides TDS on income tax @ 2.34%, and (3) other recovery. 9) The agreement contained an arbitration clause for resolving all disputes arising between the parties in relation to the agreement. The appellant accordingly gave notice to the respondents requesting them for referring the disputes, which had arisen between them to the Arbitrator. The 4 respondents acceded to the appellant's request and accordingly the disputes were referred to the sole Arbitrator-one Mr. O. P. Garg. The arbitrator embarked upon the reference made to him by the parties. The parties filed their respective claims and adduced evidence in support of their stand. 10) On 01.06.2001, the Arbitrator delivered a reasoned award. The Arbitrator allowed the appellant's claim in part and accordingly passed a money award for Rs.1024847.15 with interest payable at the rate of 21% w.e.f. 01.01.1999 till realization in appellant's favour and against the respondents. 11) The respondents, felt aggrieved of the award, filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) and questioned its legality and correctness before the Additional District Judge, Jalandhar. By order dated 04.06.2009, the Additional District Judge dismissed the application 5 and upheld the award. The respondents, as the records indicate. though claimed to have filed appeal in the High Court but did not pursue the appeal and hence the order dated 04.06.2009 of the Additional District Judge and, in consequence, the award dated 01.06.2001 became final and attained finality. 12) The respondents did not pay the awarded amount to the appellants and, therefore, the appellant filed Execution Petition No.37/2010 under Section 36 of the Act before the Additional District Judge, Jalandhar for enforcement of the award against the respondents. The respondents on being served filed reply to the execution application and raised certain factual objections purporting to be under Section 47 of the Civil Procedure Code, 1908 (hereinafter referred to as “the Code”). The respondents also filed one application praying therein for a direction to the appellant to produce 6 the statement of accounts and the transactions done pursuant to the agreement in question. 13) By order dated 03.11.2012, the Executing Court upheld the objections raised by the respondents and, in consequence, dismissed the appellant's execution application. It was held that the respondents having paid a sum of Rs.3,37,885/- towards decreetal amount to the appellant, the award/decree in question stood satisfied fully and hence the execution application filed by the appellant is liable to be dismissed. It was, accordingly, dismissed. 14) The appellant, felt aggrieved, filed revision being Civil Revision No. 3602 of 2013 before the High Court. By impugned order, the High Court dismissed the revision and upheld the order of the Executing Court. It is against this order, the appellant(claimant) has filed this appeal by way of special leave before this Court. 7 15) Heard Mr. Ashish Wad, learned counsel for the appellant and Mr. Abhishek Vikas, learned counsel for the respondents. 16) Having heard learned counsel for the parties and on perusal of the record of the case, we are constrained to allow the appeal and set aside the impugned order. 17) Sections 35 and Section 36 of the Act as it stood at the relevant time are relevant for this appeal. It reads as under : **“35. Finality of arbitral awards. Subject to this Part an arbitral award shall be final and binding on the parties and persons claiming under them respectively.** **36. Enforcement - Where the time for making an application to set aside the arbitral award under Section 34 has expired, or such application having been made, it has been refused, the award shall be enforced under the Code of Civil Procedure, 1908 (5 of 1908) in the same manner as if it were a decree of the Court.”** 18) Section 35 gives finality to every arbitral award and makes the award binding on the parties and all persons claiming under them. So far as Section 36 8 is concerned, it deals with execution of the award. It says that once the Court dismisses the application filed under Section 34 of the Act or if no such application is made and time has expired for making such application, the award shall be enforced as if it is a decree of the Court and the enforcement of the award shall be under the Code. 19) In other words, the arbitral award has been given the status of a decree of the Civil Court and, therefore, it is enforced like a decree of the Civil Court by applying the provisions of Order 21 of the Code and all other provisions, which deal with the execution of the decree of the Civil Court. 20) Coming to the facts of the case, we find that firstly, the award is under the Act; Secondly, the award was challenged under Section 34 by the respondents before the Additional District Judge but the challenge failed vide order dated 03.11.2012 of the Additional District Judge, Jalandhar; Thirdly, the order dated 03.11.2012 attained finality 9 because the matter was not pursued by the respondents in appeal to the High Court; Fourthly, the award, in consequence, also attained the finality by virtue of Sections 35 and 36 of the Act; Fifthly, the award was and continues to be binding on the appellant and the respondents; Sixthly, the award acquired the status of a decree of the civil court by virtue of Section 36 of the Act; Seventhly, the award has to be enforced for recovery of the awarded amount from the respondents like a decree of the civil court under the Code. 21) It is a well-settled principle of law that the executing Court has to execute the decree as it is and it cannot go behind the decree. Likewise, the executing Court cannot hold any kind of factual inquiry which may have the effect of nullifying the decree itself but it can undertake limited inquiry regarding jurisdictional issues which goes to the root of the decree and has the effect of rendering the 1 0 decree nullity (see- **Kiran Singh & Ors.** vs. **Chaman Paswan & Ors.,** AIR1954 SC 340). 22) Let us now see the nature of the objections raised by the respondents in execution proceedings with a view to find out as to whether they or anyone out of them were legally sustainable and which, according to the respondents, resulted in fully satisfying the award/decree in their favour and rightly found acceptance by the Courts below for so holding. 23) The respondents in their application filed under Section 47 of the Code contended that firstly, the award being vague, it is incapable of execution for recovering any sum awarded therein from the respondents; Secondly, the Arbitrator has failed to specify the rates at which the interest were to be charged; Thirdly, the Arbitrator did not mention the words "per annum" to qualify the rate of interest, i.e.,21% awarded; Fourthly, the Arbitrator awarded simple interest whereas the appellant had claimed 1 1 compound interest which is not permissible; Fifthly, the Arbitrator was not competent to award _pendent lite_ and future interest; Sixthly, mandatory consent of the Managing Director of the appellant-Corporation was not obtained by the Arbitrator for awarding interest at the rate of 21%; Seventhly, the calculations made by the appellant in their execution application is wrong being excessive in nature; Eighthly, no notice of execution application was served on the respondents because the application was filed beyond two years from the date of award; Ninthly, the execution application is not maintainable because the respondents have filed appeal before the High Court against the order rejecting their application under Section 34 of the Act. 24) The respondents (judgment debtors) also filed one application seeking direction against the appellant to produce the entire record of the case 1 2 including the accounts relating to the transactions done pursuant to the agreement in question. 25) It is pertinent to mention here that the executing Court did not decide any of the objections (nine) set out above but confined its inquiry to one statement of accounts filed by the respondents, which according to them, was given to them by the appellant. The executing Court, on perusal of the account statement, held that a sum of Rs.3,37,885/- was paid by the respondents to the appellant on 29.08.2011 which, as per the statement, was credited in appellant's account and hence such payment having been made has resulted in fully satisfying the decree in question and, therefore, the respondents are not liable to pay any amount towards decree in question. It is essentially with this factual finding, the executing Court came to a conclusion that the award/decree stood fully satisfied and hence no recovery of any awarded 1 3 amount can be made and, therefore, dismissed the appellant's execution application. 26) It is apposite to reproduce the finding of the executing Court hereinbelow because it is this finding which was upheld by the High Court by impugned order giving rise to filing of this appeal by special leave. **“8. I have thoroughly considered the contentions of the learned counsel for both the parties and have gone through the documents as referred to by the learned counsel for both the parties. It is clear that statement of account was supplied by the decree holder department itself to the judgment debtor, copy of which has been placed on file and even it is not denied by the decree holder. This statement of account dated 29.08.2011 shows that as on 29.08.2011, a sum of Rs.3,37,885/- was outstanding to be paid by the judgment debtor to the decree holder as per this statement of account supplied by the decree holder. Nor corresponding to the other document, i.e., certificate issued by Punjab National Bank, said amount of Rs.3,37,885/was paid by the judgment debtor and was credited in the account of the decree holder M/s Punjab State Civil Supplies Corporation Limited, Jalandhar. The plea of the learned counsel for the decree holder that the other statement of account, which shows that a sum of Rs.8,86,248/- is to be repaid may be considered, is not acceptable for the reason that the statement of account supplied by the decree holder department itself shows that the judgment debtor was given said** 1 4 **statement of account on 29.8.2011 and this statement of account is admitted to have been issued by the decree holder itself. The statement of account as relied upon by the counsel for the decree holder does not mention any date. More so, it is not justified by the decree holder as to how the amount of Rs.8,86,248/- has swollen to the amount of Rs.3495,886.15 paise regarding which the present execution is filed. On the other hand, the statement of account dated 29.8.2011 shows that a sum of Rs.3,37,885/was found to be due against the judgment debtor, which was paid by the judgment debtor and deposited in the account of the decree holder and this fact is clear from the certificate given by the concerned bank. Hence, considering all these documents, it is clear that whatever money was due to be paid by the judgment debtor to the decree holder as per statement of account supplied by the decree holder itself, has been paid by the judgment debtor and as such award regarding which the present execution has been filed stands fully satisfied. Resultantly, objections filed by the judgment debtor are accepted and the execution petition stands dismissed. Whatever property belonging to the judgment debtor, which has been attached in the present execution is ordered to be released henceforth. File be consigned to the record room.”** 27) We are constrained to observe that the executing Court and the High Court either did not understand the controversy or if understood, miserably failed to decide the same in accordance with law. Indeed, both the orders clearly show the 1 5 total non-application of mind by the two Courts because both the Courts neither set out the facts much less properly nor dealt the issues arising in the case and nor applied the principle of law which governs the controversy. 28) Both the orders are, therefore, wholly perverse, illegal and without jurisdiction. This we say for more than one reason as detailed by us hereinbelow. 29) In the first place, none of the objections (nine) raised by the respondents were decided by the executing Court or/and the High Court. Indeed, they were not even referred to in the orders. If the objections had been raised by the judgment debtor under Section 47 of the Code challenging the decree then it was necessary for the executing Court to deal with the objections and record its finding one way or other in accordance with law. Secondly, assuming that these objections were to be decided then also, in our opinion, none of them had any 1 6 merit whatsoever and they simply deserved rejection at the outset. 30) Thirdly, all the objections referred above ought to have been raised by the respondents before the Arbitrator or/and Additional District Judge under Section 34 of the Act but certainly none of them could be allowed to be raised in execution once the award became final and attained finality as decree of the Civil Court. 31) In other words, having regard to the nature of objections, it is clear that such objections were not capable of being tried in execution proceedings to challenge the award. It is for the reason that they were on facts and pertained to the merits of the controversy, which stood decided by the Arbitrator resulting in passing of an award. None of the objections were in relation to the jurisdiction of the Court affecting the root of the very passing of the decree. If the executing Court had probed these objections then it would have travelled behind the 1 7 decree, which was not permissible in law. An inquiry into facts, which ought to have been done in a suit or in an appeal arising out of the suit or in proceedings under Section 34 of the Act, cannot be held in execution proceedings in relation to such award/decree. 32) Fourthly, and apart from what is held above, by no stretch of imagination, the award/decree could be held fully satisfied on alleged making of the payment of Rs.3,37,885/- by the respondents to the appellant. This factual finding to say the least is perverse to its extreme. 33) It is not in dispute that the awarded principal sum even without interest was for Rs.10,24847.15. In these circumstances, we are at loss to understand as to how and on what basis, the executing Court could ever come to a conclusion that the entire money decree which was admittedly for more than Rs.10 lacs could be held fully satisfied against making of so-called payment of 1 8 Rs.3,37,885/- by the respondents to the appellant assuming that such payment was held to had been made. 34) Order 21 Rule 1 of the Code prescribes the modes of paying money under the decree. Subclause(a) provides that the decreetal money has to be deposited in Court or by postal money order or through Bank. Clause(b) provides that amount, if paid out of court, then it has to be by postal money order or through Bank or by any mode where payment is evidenced in writing. If the payment is made under clause(b) then clause(c) prescribes the procedure as to how the money has to be paid and what details are required to be given by the judgment debtor in support of making payment. 35) Order 21 Rule 2 of the Code deals with the cases where the judgment debtor makes the payment of decreetal amount either full or part out of the Court to the decree holder. Sub-clause(1) empowers the decree holder to apply to the 1 9 executing Court to get the amount received from the judgment debtor certified from the Court and it is only when the Court certifies the amount to have been paid, it can be adjusted against the decreetal sum. Clause(2) empowers the judgment debtor to apply to the executing Court and get the certification done by the Court of the amount paid by them to the decree holder after notice to the decree holder. Rule 2(A) provides that no payment made by the judgment debtor shall be adjusted unless he ensures compliance of sub clause (a) or (b) or (c). Rule 3 provides that if the Court does not certify the payment made by the judgment debtor then such payment shall not be recognized by any Court executing the decree for the purpose of giving adjustment to the judgment debtor against the decretal amount. 36) Keeping in view the mandatory requirements of Order 21 Rules 1 and 2 relating to payment of decretal dues made by the judgment debtor and 2 0 applying the said provisions to the undisputed facts of this case, we have no hesitation in holding that the sum of Rs.3,37,885/- which the respondents claimed to have paid to the appellant towards the decretal sum and which found acceptance to the two Courts below could never have been regarded as the payment made by the respondents to the appellant in conformity with the requirements of either Rule 1 or Rule 2 of Order 21. It is not in dispute that such payment was never certified by the Court as contemplated under Rule 2 of Order 21 at the instance of respondents or at the instance of the appellant. Indeed, there was neither any evidence to prove the factum of payment except one copy of the statement which also remained unproved nor any evidence was led to prove the certification done by the Court as required under Order 21 Rule 2 so as to recognize making of such payment by the respondents to the appellant. 2 1 37) We are, therefore, of the considered opinion that firstly, the execution application filed by the appellant (decree holder) for execution of the award/decree dated 01.06.2001 was maintainable and it should have been so held; Secondly, no amount was paid by the respondents to the appellant pursuant to the award/decree so as to enable the executing Court to record its full satisfaction in accordance with the provisions of Order 21 Rules 1 and 2 and lastly, all objections raised by the respondents under Section 47 of the Code against the award/decree are liable to be rejected as being wholly devoid of any merits. We, accordingly, hold so against the respondents. 38) In view of foregoing discussion, the appeal succeeds and is allowed with cost quantified at Rs.25,000/- payable by the respondents to the appellant. The impugned order and the order of the executing Court dated 03.11.2012 are set aside. 2 2 39) As a consequence thereof, the executing Court is directed to issue warrant for recovery of the entire awarded decretal amount against the respondents after verifying and calculating the decretal amount till date in terms of award/decree. 40) Let this be done within one month. ………...................................J. [ABHAY MANOHAR SAPRE] ……..................................J. [R. BANUMATHI] New Delhi; July 11, 2017 2 3
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.