Power Grid Corporation of India Ltd. v. Sreedevi Amma

Case / Petition Number:
CRP.618/08

Case Synopsis & Summary

This Kerala High Court Civil Revision petition (CRP No. 618/2008) challenges the order of the Additional District Judge, Alappuzha, in O.P. (EA) No. 98/2002, awarding compensation for trees cut and injurious affectation of land to lay a Kayamkulam–Edamon 220 kV transmission line on the claimant Sreedevi Amma’s property. About 140 yielding rubber trees and three coconut trees on roughly one acre were removed. The court below had earlier awarded Rs. 1,55,835; on remand after fresh evidence, it fixed an enhanced sum of Rs. 81,386 for trees and Rs. 60,000 for land diminution, with 6% interest from the date of cutting till payment. The revision petitioner contends that the compensation is excessive and not scientifically assessed, criticizing the use of an annuity-based method (10% previously used by the Corporation) and relying on older precedents (Kumba Amma v. K.S.E.B) despite the later Livisha principle (K.S.E.B. v. Livisha) favoring a 5% annuity. The claimant opposes interference, urging no infirmity in the lower award. The High Court, acknowledging Livisha and the hardship of remand, upholds the revised assessment as not improper and dismisses the revision, but directs specific interest adjustments from the petition and cutting dates. Overall, the decision preserves the lower award with a modified interest regime.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S.S.Satheesachandran
Judgment Date
2010-02-17
Court Decision / Holding
Revision is dismissed. The High Court upholds the enhanced compensation awarded for trees and land diminution (Rs. 81,386 and Rs. 60,000 respectively), and directs modification of interest: the claimant is entitled to interest on Rs. 1,55,835 from the date of cutting till payment, and on the enhanced compensation from the petition date to realisation at 6% per annum.
Final Disposition
Revision dismissed

Parties to the Case

Appellants / Petitioners

  • Power Grid Corporation of India Ltd.

Respondents

  • Sreedevi Amma

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri.Millu Dandapani

Counsels for Respondents

  • • Sri P.B. Sahasranaman
  • • Sri K.Jagadeesh
  • • Sri T.S.Harikumar

Submissions & Arguments

Contentions of Appellants / Petitioners

Counsel for the revision petitioner contends that the compensation awarded is excessive and not based on a reliable, scientific assessment. It is argued that the court below adopted an annuity approach (10% in earlier stages) contrary to established principles, and should follow the 5% annuity standard now recognized in Livisha (K.S.E.B. v. Livisha). The remand ordered earlier caused hardship, and the court should avoid further remand by applying a correct 5% framework. The corpulent calculation for trees and diminution of land value (Rs.81,386 for trees; Rs.60,000 for land) is challenged as unsupported by evidence. The rate of interest and its starting point are also disputed, and it is urged that the award be recalibrated under the correct model.

Contentions of Respondents

The claimant submits that interference with the lower award is unwarranted as it is supported by substantial evidence. The property’s use as rubber plantation and the required clearances for 220 kV lines justify the enhanced compensation for trees and the injurious effect on land value. The respondent argues that remand is unnecessary and that the court below’s findings, including the land diminution assessment, are reasonable and properly computed. The award aligns with the line’s impact on cultivation, and no infirmity in the assessment has been shown.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Kumba Amma v. K.S.E.B2000 (1) KLT 542 (FB)OverruledThe Kerala High Court notes this 5% annuity principle has been practically negated by the Supreme Court in K.S.E.B. v. Livisha, so Kumba Amma’s principle is not upheld.
K.S.E.B. v. Livisha2007 (6) SCC 792PositiveLivisha provides the 5% annuity approach that the court applies in determining compensation for tree loss in public works.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,358 words•~7 min read

In The Court Record

Power Grid Corporation of India Ltd. v. Sreedevi Amma

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE S.S.SATHEESACHANDRAN** **WEDNESDAY, THE 17TH FEBRUARY 2010 / 28TH MAGHA 1931** **CRP.No. 618 of 2008()** **--------------------OPEA.98/2002 of ADDL.D.C. & ADDL.MACT,ALAPPUZHA.** **....................** ## **REVN. PETITIONER(S)/IST RESPONDENT:** **-----------------------------------** **THE MANAGING DIRECTOR, POWER GRID CORPORATION OF INDIA LTD, NAGIARKULANGARA.P.O, HARIPAD.** **BY ADV. SRI.MILLU DANDAPANI** ## **RESPONDENT(S)/PETITIONER:** **-------------------------** **SREEDEVI AMMA,W/O.LATE V.SUKUMARAN NAIR, EDANGELOOR PRASANTH BHAVAN, KANNANAKUZHY.P.O, CHARUMOODU, THAMARAKULAM VILLAGE.** **ADV. SRI.P.B.SAHASRANAMAN FOR R1 SRI.K.JAGADEESH FOR R1 SRI.T.S.HARIKUMAR FOR R1** **THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON 17/02/2010, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:** ## **ORDER IN I.A.NO.325/09 IN CRP.NO.618/08** **DISMISSED.** **17.2.2010** **SD/- S.S.SATHEESACHANDRAN, JUDGE** **/TRUE COPY/** **P.A. TO JUDGE** ## **S.S.SATHEESACHANDRAN, J. ------------------------------C.R.P.NO.618 OF 2008 () ----------------------------------Dated this the 17[th] day of February, 2010** ## **O R D E R** Revision is directed against the order dated 18.10.2006 in O.P.(EA.).No.98 of 2002 passed by the learned Additional District Judge, Alappuzha. The respondent, hereinafter referred to as the 'claimant' feeling aggrieved by the compensation adjudged and paid by the revision petitioner, hereinafter referred to as the 'Corporation', filed the above original petition seeking enhanced compensation for the trees cut and removed and damages caused to her property by the drawing of overhead lines through that property. The Corporation, for the purpose of drawing Kayamkulam-Edamon 220 KV electric transmission line, cut and removed 140 yielding rubber trees from the property of the claimant, which has an extent of one acre and ten cents. A sum of Rs.1,55,835/- was awarded to the claimant as compensation for the loss caused by the drawing of the overhead lines. Aggrieved by the compensation awarded, the claimant sought CRP.618/08 2 for enhanced compensation. Corporation resisted that claim contending that just and reasonable compensation had been paid. Previously, the court below, after conducting enquiry, had passed an award fixing a total compensation of Rs.2,35,834/-. Challenging that award as excessive, the Corporation had filed a revision before this Court. The revision was allowed and the case was remanded for fresh consideration. Pursuant to such remission, both parties adduced further evidence. After considering the materials produced and hearing the counsel on both sides, a revised order was passed by the court below awarding the enhanced compensation of Rs.1,41,386/- directing the Corporation to pay such sum with 6% interest per annum from the date of cutting of trees till realisation. Compensation so fixed and awarded by the court below is challenged in this revision. 2. I heard the counsel on both sides. Compensation awarded is excessive and unreasonable, and further, there was no scientific assessment with reference to the relevant factors in adjudging the compensation, is the submission of CRP.618/08 3 the learned counsel for the Corporation. On the other hand, the learned counsel for the claimant submitted no interference with the award passed by the court below is warranted as there is nothing to show that the adjudging of the compensation suffer from any infirmity. Admittedly, 140 yielding rubber tress and three yielding coconut trees had been cut and removed to facilitate the drawing of 220 KV electric transmission lines over the property of the claimant. The Corporation has assessed compensation for the trees cut and removed on the basis of annuity return of 10%, which time and again has been found not proper and correct under a series of judicial pronouncements rendered by this Court. Though the decision rendered by this Court in **Kumba Amma** **v. K.S.E.B (2000 (1) KLT 542 (FB))** holding that the annuity return in respect of the loss arising from the cutting and removing of the trees has to be assessed with reference to 5% annuity return stands practically negatived and not a correct principle by the decision rendered by the apex court in **K.S.E.B. v. Livisha ((2007) 6 SCC 792)** . I have to take note that in the present case, the revised order had been CRP.618/08 4 passed on the basis of the directions issued by this Court by the remand order, after setting aside the previous order of the court below. The trees were cut and removed at least prior to 2000 and remitting the case again for reassessment of the compensation with reference to the principles laid down in Livisha's case, in my view, is likely to cause much hardship and irreparable injury to both sides. Such a course need be followed only if it is seen that the compensation adjudged by the court is excessive and unreasonable, or suffered from any serious infirmity. What I notice is that the court below has awarded only an enhanced compensation of Rs.81,386/towards the compensation for the trees cut and removed on refixing such compensation with reference to 5% annuity return. Needless to point out, in the matter of fixing compensation, certain amount of arbitrariness cannot at all be ruled out. It is practically impossible to determine with precision the compensation payable towards the trees cut and removed, whether it be for drawing of the lines or for any other purpose. An yield of a tree differ from one tree to another. Only some average formula alone is possible in fixing CRP.618/08 5 the compensation. In the given facts of the case, I find that the fixation of the enhanced compensation at Rs.81,386/- by the court below cannot be stated to be improper or incorrect. Then the only question that is to be looked into is whether the award of compensation made towards the diminution of land value by the court below calls for any interference. Admittedly, the lines drawn through the property were 220 KV transmission lines. Sufficient clearance of both sides of the line was necessary to avoid any mishap and also for safeguarding the free flow of energy through those lines. When clearance to be provided from such lines is taken note of it has to be held that the claimant will be prevented from making use of substantial portion of her land in the manner she wanted. It is further noticed that the land was used as a rubber plantation, and so much so, it may not be possible for the claimant to make use of it even for any profitable agricultural purpose in the immediate future. True, the claimant can have some sort of cultivation underneath the area covered by the lines, but, the fertility of the land which had been previously rubber plantation should also be taken CRP.618/08 6 into consideration to assess how far it had been injuriously affected by the drawing of the line. The court below has held that 50 cents of land out of one acre ten cents of the property of the claimant had been injuriously affected at least to the extent of 30%. Though the land value of Rs.50,000/- was claimed by the claimant, the court below had fixed the land value only at Rs.4,000/- per cent. Injurious affectation over the land was held to be at 30% and in that view, compensation towards diminution of land value was fixed. A sum of Rs.60,000/- has been awarded towards the diminution of the land value. I do not find any impropriety or illegality in the assessment so made and the compensation awarded for injurious affection of the land especially where it is seen that sufficient clearing area was required when a 220 KV lines are drawn over a property. The learned counsel for the Corporation submitted that the interest awarded from the date of cutting till realisation require to be modified as from the date of petition. Corporation has no case that it has paid any interest on the amount already paid from the date of cutting of the trees. So much so, in modification of the order of the CRP.618/08 7 court below with respect to the awarding of interest, there will be an order that the claimant will be entitled to claim interest on the amount at Rs.1,55,835/- paid by the Corporation from the date of cutting of the trees till such payment and on enhanced compensation by the court form the date of petition till date of realisation at the rate of 6% interest per annum. Revision is closed. ## **S.S.SATHEESACHANDRAN JUDGE** prp
End of Judgment Record
Browse All High Court of Kerala (2010) Decisions
2010-09-09

T.K. Biju and Gangaprasad S. v. State of Kerala and The Director, Institute of Human Resources Development (IHRD)

This batch of writ petitions challenges the Institute of Human Resources Development’s (IHRD) recruitment process for the Last Grade Service under notification RECT/03/09/HRD (dated 21.1.2009). The core questions concern the validity of the 23.8.2009 written test, the 23.10.2009 short list (main and supplementary) drawn therefrom, and the 19.3.2010 rank list published after interviews. Petitioners—mostly former daily wage/ad hoc employees—also pursue regularisation, arguing that the selection framework and weightage for past service were either discriminatory or inadequately applied. Ext.P4 had disposed of earlier petitions by directing IHRD to finalise recruitment under a resolution dated 9.7.2007, and Ext.P5 laid down the recruitment rules: an objective written test (70 marks) and an interview (30 marks) with category-wise cut-offs (Rule 5.3) and a rank list valid for three years (Rule 5.4). The court holds that deviations such as clause 8 in the hall ticket do not render the process void in the absence of prejudice, and upholds the short-list’s legality to a large extent. However, drawing on Umadevi (3) and Satya Prakash, the court ultimately directs a limited revisiting of the rank list to grant weightage under Rule 5.2 to those petitioners who would have been included, while denying general regularisation. All petitions are disposed with these directions.

2010-01-21

State of Kerala and District Collector, Kollam v. K. Raghavan

This is a review petition filed by the State of Kerala and the District Collector, Kollam, challenging the High Court’s 23 March 2009 judgment in W.P.(C).29695 of 2005, which directed the Government to consider a freedom fighter’s pension claim and to grant pension from the date of application. The petition traces a long history: the applicant, aged about 75 at the time of filing on 29.12.1995, faced earlier adverse orders in 1987 and 1989; after litigation, the 2005 judgment directed reconsideration and culminated in a 2009 order granting pension in December 2009 but from the date of sanction rather than from the date of application. The review petition contends that the Supreme Court’s decision in State of M.P. and Another v. Devkinandan Maheshwari (2003) and a Division Bench decision followed in W.A. Nos.1419/2006 & 1818/2006 require pension from the date of sanction, not the application date, and thus the judgment should be recalled. It also relies on Dokka Samuel v. Dr. Jacob Lazarus Chelly (1997) to assert that omitting authorities is not a ground for review. The Court, however, finds that omission to cite authorities cannot ground a review and that the government’s delay in compliance violates the Court’s directions, warranting dismissal of the review petition with costs.

2010-02-23

Anitha Rajan v. Revenue Divisional Officer, Thrissur; Thasildar, Chavakkad; Village Officer, Nattika; Sub Registrar, Thriprayar

Anitha Rajan, the petitioner, purchased 50 cents of land in Re-Survey No.166/1, Nattika village, Thrissur district, from the legal heirs of late Gangadharan via Ext.P3 sale deed registered at Triprayar. The conveyance, through power of attorney documents Ext.P1 (executed by Ajayan in Dubai in favor of his mother Rathnabhai) and Ext.P2 (executed by Usha in India), prompted mutation proceedings before the Revenue Divisional Officer (RDO). The RDO refused to effect mutation unless the original Ext.P1 POA was produced for adjudication of stamp duty under the Kerala Stamp Act, 1959, claiming non-compliance with stamping and the need to determine stamp duty under sections 31 and 32. The petitioner contends that it is not mandatory to submit every PoA executed outside India for adjudication; only instruments chargeable with duty which cannot be stamped by private persons must be taken to the Collector under section 18(2). Ext.P1, though executed abroad, is on Indian stamp paper and was presented at registration, having been stamped Rs.150 under Article 44(f). The court analyzed sections 18(1), 18(2), 31 and 32 and held that section 18 applies to instruments executed outside India; since Ext.P1 is duly stamped, Section 18 has no application and Sections 31-32 cannot be invoked to compel production. Relying on Madras High Court decisions Manoharan v. Velu and R.B.K. Rajeswari Nachiar, the court held the Village Officer erred in requiring Ext.P1 before the RDO, quashed Exts.P4 and P6, and directed mutation actions to be completed within two months of certified judgment copy.

2010-03-23

V. Mohanan Nair v. Babu Pillai and others

This writ petition arises from a complex land dispute in Nedumangad where the petitioner, V. Mohanan Nair, challenged a trial court order that set aside a commissioner's report and remitted for a fresh report. In O.S. 380/2005 the plaintiff sought a permanent injunction; in O.S. 542/2005 the second respondent sought declaration of title and possession based on deeds executed in 2005. To resolve the location of the plaint schedule property, a commission was appointed, and Ext. P2 report and plan were filed. Subsequently, I.A. 4808/2009 was filed by the second respondent seeking to set aside the commission report and plan and remit for a fresh report. The trial court remitted the matter; Ext.P8 records the order, which the petitioner challenged in this Writ Petition. The respondents relied on a decision in Sarojini v. Karthiyani Amma to contend that Article 227 petitions against commission reports are not maintainable, while the petitioner argued lack of justification for remitting and the undue delay in filing the petition. The Kerala High Court, while recognizing the normal reluctance to exercise visitorial jurisdiction, held that exceptional circumstances permit interference under Article 227 and remanded the matter for fresh consideration, directing that the trial court assess sufficiency of Exts. C1, C1(a), C1(b) and allow further inspection if needed. The result is a remand to ensure a fair adjudication on the commission report."