High Court of KeralaDivision BenchDisposed (Writ Appeal disposed; no interference...

Power Grid Corporation Ltd. v. P.G. Sukumaran and Others

Case / Petition Number:WA.No.269 of 2010

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • P. R. Raman
  • C. N. Ramachandran Nair
Judgment Date
2010-02-22
Court Decision / Holding
Writ Appeal disposed; the High Court did not interfere with the learned Single Judge’s order. The District Magistrate is to consider objections and the claimant may pursue compensation under applicable provisions (Telegraph Act and Electricity Act). The appellant retains remedies to challenge compensation in the District Court via Electricity O.P., while objections to the line are to be decided by the District Magistrate.
Final Disposition
Disposed (Writ Appeal disposed; no interference; remand to District Magistrate for objections and compensation considerations under Telegraph Act; remedies available under Electricity Act)

Parties to the Case

Appellants / Petitioners

  • P.G. Sukumaran

Respondents

  • Power Grid Corporation Ltd.
  • Manoj Kumar
  • Valsalan K.K.

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Thomas Antony
  • • Sri. Titus Mani

Counsels for Respondents

  • • Sri. Millu Dandapani

Case Synopsis & Summary

This writ appeal arises from WPC No.21330/2009 challenging Power Grid Corporation’s plan to draw a 400 kV high-tension line through lands in Vengola Village. The appellant, P.G. Sukumaran (3rd petitioner), contends that entry into land without notice amounts to coercive action and that the corporation has no authority to acquire land beyond the right of user under the Telegraph Act. He claims substantial encroachment (allegedly about 50 cents) and argues that any construction of towers along the route must be done only by following due process and paying proper compensation. The respondents defend the project, arguing towers and posts are necessary for a 400 kV line and that compensation will be paid for diminished land value or trees removed. The writ petition was guided by a Full Bench decision (Bharat Plywood and Timber Products Pvt. Ltd. v. Kerala State Electricity Board, 1970 KLT 872) that any tangible objection to laying the line requires the District Magistrate to apply Section 16(1) read with Section 164 of the Indian Electricity Act, 2003. As per Sections 10, 11 and related provisions of the Telegraph Act, the authority may place lines with as little damage as possible, while preserving ownership with the landowner and paying full compensation. The learned Single Judge directed the District Magistrate to hear objections; the appellate court declined to interfere, leaving remedies under law to adjudicate objections and compensation. The appeal is disposed with directions for further remedies.

Provisions of Law Cited

Indian Telegraph Act, 1885: Section 10Indian Telegraph Act, 1885: Section 11Indian Telegraph Act, 1885: Section 16(1)Indian Telegraph Act, 1885: Section 16(4)Indian Telegraph Act, 1885: Section 3(5)Indian Telegraph Act, 1885: Section 10(d)Indian Electricity Act, 2003: Section 164

Legal Doctrines & Maxims

  • do as little damage as possible (Telegraph Act principle)
  • ownership of land remains with the owner; only right of user is vested in the Telegraph authority
  • Central Government shall not acquire any right other than that of user; full compensation for damage caused

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the project amounts to substantial land acquisition for tower construction, beyond mere placement of an electric line. He asserts that no prior notice was given and that the corporation lacks authority to acquire land save for the user rights under the Telegraph Act; he seeks protection of his property and insists that any encroachment must be supported by due process, statutory compensation, and appropriate remedy. He argues that if towers are placed, compensation for land diminution and trees is mandatory, with the District Magistrate’s review available only after lawful procedures are followed.

Contentions of Respondents

The respondents urge that a 400 kV line necessitates towers and posts to support the line, and the Telegraph Act authorizes such placements with due compensation for damages. They emphasize remedies exist for disputes over compensation (via Tahsildar/Tahsildar calculations, and section 10(d) of the Telegraph Act allows filing Electricity O.P. in the District Court for compensation disputes). They contend that the District Magistrate will decide objections to the drawing of the line and that full compensation will be paid for any land value diminution.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Bharat Plywood and Timber Products Private Ltd. v. Kerala State Electricity Board1970 KLT 872PositiveCited as a Full Bench decision that supports directing District Magistrate under Section 16(1) read with Section 164 of the Indian Electricity Act, 2003 for objections regarding laying the line.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Power Grid Corporation Ltd. v. P.G. Sukumaran and Others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HON'BLE THE ACTING CHIEF JUSTICE MR.P.R.RAMAN & THE HONOURABLE MR. JUSTICE C.N.RAMACHANDRAN NAIR MONDAY, THE 22ND FEBRUARY 2010 / 3RD PHALGUNA 1931 WA.No. 269 of 2010 -------------------AGAINST THE JUDGEMENT IN WPC.21330/2009 Dated 15/12/2009 .................... APPELLANT/3RD PETITIONER: -------------------------------- P.G.SUKUMARAN, PALATHANATHU, VENGOLAKARA, VALAYANCHIRANGARA P.O., ERNAKULAM DISTRICT-683 556. BY ADV. SRI.THOMAS ANTONY SRI.TITUS MANI RESPONDENTS/1ST & 2ND PETITIONERS: ---------------------------------------------- 1. POWER GRID CORPORATION LTD., REPRESENTED BY ITS C.A.O., CONSTRUCTION AREA OFFICE, "CHANDINI", PLOT NO.190-B, MAVELIPURAM COLONY, KAKKANADU, KOCHI. 2. MANOJ KUMAR, S/O.KESAVAN ILAYATHU, KADAMBANATH ILLAM, VENGOLAKARA, VALAYANCHIRANGARA P.O.,ERNAKULAM DISTRICT 683 556. 3. VALSALAN K.K., S/O.LATE KURIAKOSE, KILITHATTIL HOUSE, VENGOLA KARA, VALAYANCHIRANGARA P.O.,ERNAKULAM DISTRICT 683 556. R1 BY ADV. SRI. MILLU DANDAPANI. THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 22/02/2010, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **P.R.Raman, Ag. C.J. & C.N.Ramachandran Nair, J.** ------------------------------------------ ## **W.A.No.269 of 2010 & C.M.Appln.No.136 of 2010** -----------------------------------------Dated this the 22[nd] day of February, 2010 ## **JUDGMENT** ## **P.R.Raman, Ag. C.J.** Heard. Delay in filing the appeal is condoned. 2. Appellant is the third petitioner. He is one of the owners of lands situated in Sy.Nos.168/7, 168/4, 577/6A-1 and 413/10 in Vengola Village. The first respondent is Power Grid Corporation Ltd. The writ petition was filed to restrain the respondent Corporation from entering into their properties, for the purpose of drawing an High Tension Electric Line. It was contended that no notice was sent to the appellant/petitioner before the respondent or their men entered into the property. It is also contended that the respondent has no authority under the Indian Telegraph Act, 1885. 3. The learned Single Judge after referring to a Full Bench decision of this Court in Bharat Plywood and Timber Products Private Ltd. v. Kerala State Electricity Board (1970 KLT 872) held that when any tangible objection is raised in the matter of drawing of electric W.A. No.269 of 2010. **==> picture [20 x 9] intentionally omitted <==** lines through the land of the objector, the authority under the Indian Telegraph Act has to approach the District Magistrate for necessary orders under Section 16(1) of the said Act read with Section 164 of the Indian Electricity Act, 2003. Ext.R1(c) is the notification issued by the Government of India investing the same powers under the provisions of the Telegraph Act on the respondent Corporation. Thus it cannot be said that the respondent has no authority to exercise the powers under the Telegraph Act. Therefore, the learned Single Judge rightly held that the respondent has got necessary authority within the meaning of the Telegraph Act. Now that an objection has been raised by the appellant/petitioner in the matter of drawing the electric line, the respondent was directed to approach the District Magistrate who has to consider the objection raised by both sides and pass appropriate orders. Petitioner is not satisfied with the said judgment and hence this appeal. 4. Sri.Thomas Antony who appears on behalf of the appellant/petitioner contends that it is not merely a drawing of electric line, but according to him the respondent has virtually taken away W.A. No.269 of 2010. **==> picture [20 x 9] intentionally omitted <==** large extent of land from his possession for the purpose of constructing towers. According to him, 50 cents of land is taken. It is also contended that except by way of acquiring the land in accordance with law they cannot construct towers in the manner as proposed. 5. The learned counsel for the respondent, on the other hand, contends that for the purpose of drawing the electric line as authorised by the Telegraph Act electric posts will have to be fixed. In this case a 400 KV electric line is being drawn and therefore, necessarily towers will have to be constructed to support the electric line. That is all that has been done and in case the land value has been diminished to the fullest extent, necessarily, the respondent will pay compensation for the same. It is also contended that it is not a case where the respondent is drawing the electric line without paying the compensation and reasonable compensation as entitled by law will be paid. 6. Heard both sides. In the matter of drawing the electric line by the Corporation, they have all the authorities under the Telegraph Act as notified. As per Section 10 of the Indian Telegraph W.A. No.269 of 2010. - 4 - Act, the telegraph authority may, from time to time, place and maintain a telegraph line under, over, along, or across, and posts in or upon, any immovable property. But such powers shall be exercised as per the provisos only for the purposes of a telegraph established or maintained by the Central Government or to be so established or maintained and then the Central Government shall not acquire any right other than that of user only in the property under, over, along, across, in or upon which the telegraph authority places any telegraph line or post and in so exercising powers they shall do as little damage as possible, and, when it has exercised those powers in respect of any property other than that referred to in clause (c), shall pay full compensation to all persons interested for any damage sustained by them by reason of the exercise of those powers. Section 11 also empowers them for the purpose of examining, repairing, altering or removing any telegraph line or post, enter on the property under, over, along, across, in or upon which the line or post has been placed. In case of any dispute Section 16 provides the mechanism to resolve the dispute by approaching the District Magistrate. Sub-section (4) of Section 16 more particularly W.A. No.269 of 2010. **==> picture [20 x 9] intentionally omitted <==** empowers the District Magistrate to decide as to the person entitled to receive compensation and also to determine the compensation payable under due notice to the parties. 7. The word 'post' is defined in Section 3(5) of the Telegraph Act. The 'post' means a post, pole, standard, stay, strut or other above ground contrivance for carrying, suspending or supporting a telegraph line. Therefore, posts and towers are intended to support a telegraph line. Due to the fact that as in this case a 400 KV electric line is proposed, a tower is required to be constructed for supporting the line. As contemplated by the Telegraph Act and referred to above, it can be seen that the ownership of the land where such a tower is erected still continues to vest with the owner and it is only the right of user of the same that is vested with the Corporation and even as a result of the construction of the tower if the land owner cannot do anything in the said portion of the land occupied by tower, necessarily he will have to be paid hundred percent compensation which the appellant/petitioner is entitled to. It is open to the appellant herein to place all relevant materials and claim that there is hundred W.A. No.269 of 2010. **==> picture [20 x 9] intentionally omitted <==** percent diminution in land value and claim compensation for the same and if he is not satisfied with the compensation determined, he can approach the District Court by filing an Electricity O.P. As regards the objection that is raised against the drawing of the electric line, it is the District Magistrate to decide the same. Thus disputes centering round the compensation payable for diminution of the land value or trees cut if any, awarded by the Tahsildar can be raised before the District Court by filing an Electricity O.P. as provided for under Section 10(d) of the Telegraph Act. But if there is any objection regarding the drawing of electric line, the District Magistrate will decide the same. Therefore the appellant has got ample remedy to vindicate his grievance under the provisions of the Telegraph Act before the appropriate forum. 8. In the circumstances, leaving open the right of the appellant to work out his remedy in terms of the provisions contained in the Indian Telegraph Act and in view of the fact that the learned Single Judge has only directed the District Magistrate to consider the petition for removal of the obstruction and the objection of the W.A. No.269 of 2010. - 7 - appellant, we do not find any reason to interfere with the said judgment. All the contentions, if any, may be looked into by the District Magistrate in the matter of removal of obstruction or objection to the same and in the matter of compensation payable, the District Judge will consider the same on application, if any, made by the appellant. Clarifying the above position, the writ appeal is disposed of. **P.R.Raman, Ag. Chief Justice** **C.N.Ramachandran Nair, Judge** vns