High Court of KeralaSingle JudgeThe Sessions Court’s order is set aside; the Su...

Pokker A v. State of Kerala

Case / Petition Number:CRL.R.P No.469/21
Neutral Citation:/

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Bechu Kurian Thomas
Judgment Date
2023-08-09
Court Decision / Holding
The High Court set aside the Sessions Court’s order in Crl.R.P No.9/2021 and upheld the Sub Divisional Magistrate’s order dated 15.03.2021 in MP No.02/2021, directing removal of the unauthorised arch on the public road. The court held that no cause was shown against the conditional order and that the road is a public way; it reaffirmed the binding principles to remove encroachments on public streets, citing relevant case law.
Final Disposition
The Sessions Court’s order is set aside; the Sub Divisional Magistrate’s order dated 15.03.2021 in MP No.02/2021 is upheld; the criminal revision petition against the SDM’s order is disposed in favor of upholding the SDM’s order, directing removal of the arch on the public road.

Parties to the Case

Appellants / Petitioners

  • Pokker A

Respondents

  • State of Kerala
  • Ramakrishnan

Legal Representation & Advocates

Counsels for Petitioners

  • • SRI.V.JOHN MANI
  • • SRI.S.JAYANT
  • • SRI.JACKSON JOHNY
  • • SRI.VARGHESE SABU
  • • SMT.K.K.SETHULAKSHMI
  • • SMT.GAYATHRI MENON

Counsels for Respondents

  • • SRI.C.N PRABHAKARAN, Public Prosecutor

Case Synopsis & Summary

Pokker A v. State of Kerala (CRL.R.P No.469/21) concerns an arch erected by the Mambatta Shiva Temple on a public panchayat road near Kandamangalam, Palakkad. The temple’s semicircular arch, constructed at the beginning of the public road, allegedly encroached upon a public way, reducing the road width from 4.15 metres to about 3.65 metres and constraining vehicular access. The petitioner (complainant) filed a complaint under section 133 Cr.P.C alleging unlawful obstruction to a public road; the Sub Divisional Magistrate (SDM) issued a conditional order directing removal of the obstruction, which, after several postings, was made absolute on 15.03.2021. The temple president filed a criminal revision before the Sessions Court (Crl.R.P. No.9 of 2021), arguing procedural irregularities in the SDM’s conduct before making the order absolute and seeking remand for fresh evidence. The Sessions Court allowed the revision, remanding for fresh consideration. The High Court, however, allowed the revision petition to the extent of setting aside the Sessions Court’s order and upheld the SDM’s order, ruling that no cause was shown against the conditional order and that the road is a public road; no permission from the Panchayat had been obtained for the arch. The court relied on binding precedents and directed removal of the obstruction, emphasizing that unauthorised encroachments on public streets must be removed, following Supreme Court and Kerala decisions on encroachments.

Provisions of Law Cited

Section 133 Cr.P.CSection 133(1) Cr.P.CSection 138(1) Cr.P.C

Submissions & Arguments

Contentions of Appellants / Petitioners

Pokker A contended that the public road traverses through the area of his residence and is a public thoroughfare. He alleged that the arch created by the temple encroached on public space, reducing the road width and obstructing vehicular and pedestrian access. He emphasized that no Panchayat permission was obtained for the arch and that the records show the road’s width reduced from 4.15 m to 3.65 m due to the construction. Since no objection or denial of public rights was advanced, the Magistrate could legally proceed to make the conditional order absolute under section 133(1) Cr.P.C without requiring further evidence. He relied on precedents directing removal of encroachments on public streets and argued that unauthorised constructions on public property must be removed promptly.

Contentions of Respondents

The temple (respondent) contended that the Sessions Court correctly held procedural defects in the SDM’s approach before making the conditional order absolute and that the matter required fresh evidence. Their case leaned on the procedure under section 138(1) Cr.P.C and argued that the SDM had not properly followed due process, warranting remand. The temple argued that the absence of opportunity to present evidence against the conditional order necessitated a reevaluation, and that the court should not summarily uphold the order without considering potential evidence or objections.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Annakody v. State of Kerala2015 (4) KLT 757DistinguishedHeld that the requirement to take evidence arises only when a person shows cause against the conditional order; the Sessions Court misapplied this by demanding evidence in absence of any cause against the conditional order.
Union of India v. State of Gujarat and Others(2011) 14 SCC 62PositiveDirected that unauthorised constructions should not be permitted on public streets and that authorities must ensure compliance with this policy; supports removal of encroachments on public properties.
Shali v. State of Kerala(2019) 4 KLT 484PositiveHeld that no local authority shall permit unauthorised encroachments on public streets; reinforces obligation to remove encroachments to maintain public access.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Pokker A v. State of Kerala and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

# **IN THE HIGH COURT OF KERALA AT ERNAKULAM** # **PRESENT** **THE HONOURABLE MR. JUSTICE BECHU KURIAN THOMAS** **WEDNESDAY, THE 9[TH] DAY OF AUGUST 2023 / 18TH SRAVANA, 1945 CRL.REV.PET NO. 469 OF 2021** **AGAINST CRL.RP 9/2021 OF SESSIONS COURT, PALAKKAD** ## **REVISION PETITIONER/2ND RESPONDENT:** **POKKER A AGED 60 YEARS, S/O.ABDULLA, RESIDING AT AYINELLI, PUTTANIKKAD, KANDAMANGALAM P.O., KOTTOPPADAM, PALAKKAD DIST. 678 583** **BY ADVS. SRI.V.JOHN MANI SRI.S.JAYANT SRI.JACKSON JOHNY SRI.VARGHESE SABU SMT.K.K.SETHULAKSHMI SMT.GAYATHRI MENON** ## **RESPONDENTS/REVISION PETITIONER/STATE:** **1 STATE OF KERALA REPRESENTED BY THE SECRETARY, REVENUE AND HOUSING, SECRETARIAT, THIRUVANANTHAPURAM 695 001** **2 RAMAKRISHNAN KALLUVETTI HOUSE, KANDAMANGALAM POST, PRESIDENT MAMPATTA SIVA TEMPLE, PUTTANIKAD, PALAKKAD 678 583** **SRI.C.N PRABHAKARAN, PUBLIC PROSECUTOR** ## **THIS CRIMINAL REVISION PETITION HAVING COME UP FOR** **ADMISSION ON 09.08.2023, THE COURT ON THE SAME DAY PASSED THE FOLLOWING:** Crl.R.P No.469/21 ## **-:2:-** ## **BECHU KURIAN THOMAS, J.** **----------------------------------------Crl.R.P No.469 of 2021 ----------------------------------------** Dated this the 9[th] day of August, 2023 ## **ORDER** An arch was constructed by the Mambatta Shiva Temple on a public road. Alleging that the said construction on the public road is illegal and causes nuisance, an application was preferred before the Sub Divisional Magistrate, Palakkad. Pursuant to a conditional order, the learned Magistrate confirmed the order directing the removal of the arch. In a revision petition preferred by the president of the temple before the Sessions Court, the order of the Sub Divisional Magistrate was set aside and the case was remanded for fresh consideration. In this criminal revision petition preferred by the applicant (complainant) before the Sub Divisional Magistrate, the order of the learned Sessions Judge is impugned. 2. The revision petitioner alleges that immediately to the eastern side of his residence, a panchayat road is in existence which leads to the Mambatta Shiva Temple, having a width of 4.15 metres. It is alleged that the road was widened by the nearby residents including the revision petitioner, relinquishing their rights over a **-:3:-** Crl.R.P No.469/21 portion of their property. However, after the road was widened and concreted using the MLA Funds, the temple committee, under the leadership of its president, is alleged to have illegally constructed a semicircular arch at the beginning of the Panchayat road, thereby disturbing vehicular access. It was also alleged that the width of the road has been reduced to 3.65 metres and the arch even causes danger and trouble to the nearby residents. 3. Despite repeated complaints to the Panchayat, no action was initiated and finally a complaint was filed under section 133 of the Code of Criminal Procedure, 1973 (for short 'the Cr.P.C') before the Sub Divisional Magistrate seeking removal of the obstruction erected on the Panchayat road. The complaint was numbered as M.P. No.2 of 2021. The learned Sub Divisional Magistrate obtained reports from the Panchayat Secretary stating that the arch was constructed illegally without getting any permission and also that the road which was constructed by the Panchayat has been reduced in its width due to the construction of the arch. The report also mentions that the revision petitioner himself had relinquished rights over a portion of his property for the purpose of widening the road. 4. On being prima facie satisfied that an unlawful obstruction **-:4:-** Crl.R.P No.469/21 has been created on a public way, the learned Magistrate issued a conditional order on 06.01.2021 directing the first opposite party therein i.e., the secretary of the Mambatta Shiva Temple, to remove the obstruction within a period of seven days or to show cause on 20.01.2021 as to why the conditional order should not be made absolute. Thereafter the case was posted on several days, and by order dated 15.03.2021, after observing that the temple committee had failed to produce any evidence against the conditional order, the learned Sub Divisional Magistrate confirmed the conditional order and directed the illegal construction erected as an obstruction to the public way to be removed by making the conditional order absolute. 5. Challenging the order of the Sub Divisional Magistrate, a revision petition was preferred by the president of the temple as Crl.R.P. No.9 of 2021 before the Sessions Court, Palakkad. By the impugned order dated 07.05.2021, the criminal revision petition was allowed by the Sessions Court after finding that the Sub Divisional Magistrate had committed an error in the procedure adopted before making the conditional order absolute. On the above findings, the criminal revision petition was allowed, and the matter was remanded to the Sub Divisional Magistrate for fresh consideration. One of the Crl.R.P No.469/21 **-:5:-** complainants before the Sub Divisional Magistrate has filed this criminal revision assailing the order of the learned Sessions Judge. 6. Even though notice to the second respondent was served, there is no appearance. The matter was heard on 04.07.2023 and was reserved for orders. However, on noticing that the lower court records had not been called for and since it was found essential, the case was reposted to 06.07.2023 and the records were called for. 7. I have perused the records meticulously. I have also called for the records of the Sub Divisional Magistrate and perused it. I have also heard the arguments of Sri. John Mani V., the learned counsel for the revision petitioner as well as Sri. C.N.Prabhakaran, the learned Public Prosecutor, on behalf of the first respondent. 8. In Annexure A3 order, the Sub Divisional Magistrate has observed that on 06.01.2021, he had issued a conditional order directing the unauthorised construction erected on a public road to be removed within seven days or to show cause on 20.01.2021 as to why the order should not be made absolute. However, it is seen from the records that even though the second respondent appeared before the Sub Divisional Magistrate pursuant to notice, no cause was shown by him against the order. The records do not reveal that Crl.R.P No.469/21 **-:6:-** any objection was filed by the second respondent against the conditional order, nor was any explanation submitted as to why the conditional order should not be made absolute. On 20.01.2021, on 10.02.2021, on 25.02.2021 and again on 01.03.2021 there were postings. There was not even denial of any public right in respect of the way. 9. In fact, it is evident from the reports that the road is a public road and at no point in time has any objection or explanation ever been submitted by the second respondent. On the other hand, the records reveal that the Sub Divisional Magistrate was satisfied that no permission was granted by the Panchayat for erecting the arch on a public road, and the Panchayat Secretary, as well as the Village Officer, were directed to visit the site and submit a report. Thus, it is evident that pursuant to the conditional order issued under section 133(1) of Cr.P.C, the second respondent failed to show any cause against the order or even deny the existence of a public right. 10. A perusal of the judgment of the learned Sessions Judge reveals that the court went on a wrong tangent by the observations on 01.03.2021, 'no sufficient legal evidence submitted'. The said observation could only mean that no sufficient legal evidence was Crl.R.P No.469/21 **-:7:-** submitted against the conditional order. This is evident from the subsequent endorsement 'to remove within 14 days'. It is thereafter that a detailed order was passed as Annexure A3, making the conditional order absolute. 11. In the decision in **Annakody v. State of Kerala** (2015 (4) KLT 757), a learned single Judge of this Court had held that before making the conditional order absolute, evidence must be adduced as in a summons case. The said decision was relied upon by the learned Sessions Judge to set aside the order of the Sub Divisional Magistrate on an assumption that the failure of the Magistrate to take evidence has resulted in the order being vitiated. However, the learned Sessions Judge failed to appreciate the dictum laid down in the said decision, which specifically mentions that the requirement to take evidence arises only when a person shows cause against the conditional order stipulated under section 138(1) of Cr.P.C. The impugned order fails to appreciate that the respondent had never shown cause against the conditional order. Therefore the Sub Divisional Magistrate was not bound to take evidence and could legally proceed to make the conditional order absolute. The need for adducing evidence arises only if a dispute is raised by the opposite Crl.R.P No.469/21 **-:8:-** party against the conditional order. In the absence of any cause being shown against the conditional order issued under section 133(1) of Cr.P.C, and in the absence of any denial of the public right, it is not essential for the Magistrate to proceed to take evidence. 12. In this context, it is relevant to refer to the decision of the Supreme Court in **Union of India v. State of Gujarat and Others** [(2011) 14 SCC 62]. In the said decision, the Supreme Court had categorically directed that henceforth no unauthorised construction shall be carried out or permitted in the name of temple, church, mosque or Gurudwara etc., on public streets, public parks or other public places etc. A further direction was issued to all the District Collectors and Magistrates to ensure that there is total compliance of the order of the Supreme Court. Further, in the decision in **Shali v. State of Kerala** (2019 (4) KLT 484), a learned single Judge of this Court had specifically directed that no local authority shall permit any unauthorised constructions encroaching upon public streets, including footpaths and all such encroachments will have to be removed. It was also held that such unauthorised constructions encroaching into the public streets, including footpaths causing obstruction to the users of the street, including pedestrians, must be Crl.R.P No.469/21 **-:9:-** removed by the secretaries of the local authorities without even any notice to the person who made such unauthorised constructions. 13. The aforesaid binding principles of law make it a bounden obligation upon all Magistrates and the Secretaries of the local authorities to direct removal of all illegal encroachments irrespective of any presumed objections that may be raised against such removal. 14. Concededly, no permission has been obtained by the second respondent or the temple committee for constructing an arch. In fact, no permission can even be granted either by the Secretary of the local authority or by the Government for erecting any such construction on public property. The report of the Village Officer, as well as the Secretary of the local authority available before the Sub Divisional Magistrate, clearly indicated that the width of the road had been reduced from 4.15 metres to 3.65 metres due to the construction of the arch. It was also reported that due to the construction of the arch, there is a restriction on the height of the vehicular access, which is also an obstruction in a public way. Even if vehicles can pass through the road, despite the arch, still, construction on a public road, reducing its width or height, is an Crl.R.P No.469/21 **-:10:-** illegal construction. There is also no dispute that the road is a Panchayat road which was widened using the area surrendered by the revision petitioner/complainant himself. 15. On a perusal of the impugned order of the learned Sessions Judge, it is evident that the conclusions arrived at are irregular. The conclusion that the Magistrate was bound to take evidence in the circumstance of the case is also improper and irregular. The finding that the Sub Divisional Magistrate had prejudged the issue, is without any basis and is also incorrect and improper. 16. In view of the above discussion, this Court is satisfied that the impugned order is liable to be interfered with. Accordingly, the order of the learned Sessions Court, Palakkad in Crl.R.P. No.9 of 2021 is hereby set aside, and the order of the Sub Divisional Magistrate, Ottapalam, dated 15.03.2021 in M.P. No.2 of 2021 is upheld. ## This criminal revision petition is allowed as above. Sd/- ## **BECHU KURIAN THOMAS JUDGE** vps Crl.R.P No.469/21 ## **-:11:-** ## **APPENDIX** **ANN. A1 TRUE COPY OF THE MEMORANDUM OF WRIT PETITION AS WP(C) No.23569/2020 ALONG WITH ITS EXHIBITS ANN.A2 TRUE COPY OF THE ARGUMENT NOTE SUBMITTED BY THE PETITIONER BEFORE THE SUB COLLECTOR, OTTAPALAM ALONG WITH ITS ACKNOWLEDGEMENT ANN.A3 TRUE COPY OF THE ORDER PASSED BY THE SUB COLLECTOR/RDO OTTAPALAM DATED 15.03.2021 IN MP NO.02/2021 ANN.A4 TRUE COPY OF THE MEMORANDUM OF CRIMINAL REVISION PETITION AS CRL.RP NO.09/2021 FILED BY THE SECRETATY, MAMBATTA SHIVA TEMPLE BEFORE THE DISTRICT COURT, PALAKKAD ANN.A5 TRUE COPY OF THE JUDGMENT DATED 07.04.2021 IN WP(C) 23569 OF 2020 OF THIS HON'BLE COURT ANN.A6 TRUE COPY OF THE ORDER DATED 07.05.2021 IN CRL.R.P. NO.09/2021**