Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan

Case / Petition Number:
Civil Appeal No. 12238 of 2018
Neutral Citation:[2019] 5 S.C.R. 1169

Case Synopsis & Summary

The case concerns a Consumer Protection Act, 1986 complaint filed by Govindan Raghavan, a flat purchaser, against Pioneer Urban Land & Infrastructure Ltd. alleging deficiency of service for failure to obtain the Occupancy Certificate and hand over possession in a timely manner under the Apartment Buyer’s Agreement dated 08.05.2012 for a flat in Araya Complex, Gurugram. The agreement provided for occupancy certificate within 39 months from excavation with a 180-day grace; excavation commenced 04.06.2012. The builder failed to apply by the specified date. The National Consumer Disputes Redressal Commission passed an interim order restraining cancellation of allotment; during pendency, the builder obtained the Occupancy Certificate on 23.07.2018 and issued a possession letter on 28.08.2018. The Commission then held the last date for construction had expired about three years prior to the occupancy certificate and that the respondent could not be compelled to take possession; it refunded the entire amount deposited by the respondent with interest, plus compensation. The builder appealed under Section 23 CPA, arguing that terms in the Agreement—especially Clause 11.5 and Clause 20—were not unfair and that the complaint cannot operate as termination notice. The Supreme Court, however, held the terms wholly one-sided, unfair, and in violation of Section 2(r) of the CPA; it affirmed the NCDRC’s order and dismissed the appeals, while allowing the refund to be effected within three months.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Uday Umesh Lalit
  • Indu Malhotra
Judgment Date
2019-04-02
Court Decision / Holding
The Civil Appeals are dismissed. The Final Judgment and Order dated 23.10.2018 passed by the National Consumer Disputes Redressal Commission is affirmed. The appellant-builder is ordered to refund Rs. 4,48,43,026 deposited by the respondent along with interest at 10.7% simple interest per annum, calculated from the date of each installment until 05.02.2017 and from the date of the Commission’s final order until the date of refund. The period during which the interim stay of cancellation of the allotment operated is excluded from interest. The appellant is granted three months from today to effect the refund; all pending applications are disposed of.
Final Disposition
Appeals dismissed; NCDRC order affirmed; refund with interest and compensation as specified; three months to effect refund; pending applications disposed of.

Parties to the Case

Appellants / Petitioners

  • Pioneer Urban Land & Infrastructure Ltd.

Respondents

  • Govindan Raghavan

Legal Representation & Advocates

Counsels for Petitioners

  • • C.A. Sundaram
  • • Nikhil Nayyar
  • • T.V. S. Raghavendra C Sreyas

Counsels for Respondents

  • • Sushil Kasushik
  • • Manoj Yadav
  • • Himanshu Shekhar

Provisions of Law Cited

Consumer Protection Act, 1986 – Section 23Consumer Protection Act, 1986 – Section 2(r)Consumer Protection Act, 1986 – Section 2(o)Consumer Protection Act, 1986 – Section 12Haryana Real Estate (Regulation and Development) Rules, 2017 – Rule 15

Legal Doctrines & Maxims

  • Unconscionability / inequality of bargaining power in contracts
  • Standard form contracts are not binding if they are one-sided or unfair
  • Unfair trade practices under Section 2(r) of the CPA, 1986
  • Court will not enforce an unfair or unconscionable contract against a weaker party

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant-builder argued that the Apartment Buyer’s Agreement dated 08.05.2012 contains termination and refund provisions (Clause 11.5 and Clause 20). It contended that the respondent had not validly terminated the agreement by a written termination notice beneath Clause 11.5(ii); interim stay orders did not amount to termination and the refund was not legally required under the contract. It asserted that the occupancy certificate and possession were offered after a long delay but within the terms contemplated by the agreement, and that the National Commission’s determination of 10.7% interest was inconsistent with the contract terms; it relied on the specific contractual rates for delay and demanded reversal of the NC order on equity grounds.

Contentions of Respondents

The respondent-flat purchaser argued that filing of the consumer complaint could be treated as a termination notice under Clause 11.5(ii), and that the builder’s delay in handing over possession was indefensible. He contended the agreement terms were one-sided and unfair, violating Section 2(r) CPA; he sought refund of the entire amount deposited plus interest and compensation, arguing that the stay-order period should be excluded from interest calculations. He also urged that the rate of interest under Rule 15 of the Haryana Rules was appropriate and that the builder’s financing costs justified the relief granted by the National Commission.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Lucknow Development Authority v. M.K. Gupta[1994] 1 SCC 243; [1993] 3 Suppl. SCR 615PositiveRelied on to establish the concept of service and the wider principle that courts will not enforce unfair or unconscionable contracts, especially where bargaining power is unequal.
Fortune Infrastructure & Anr. v. Trevor D’Lima & Ors.(2018) 5 SCC 442; [2018] 3 SCR 273PositiveRelied on to support the proposition that a purchaser cannot be made to wait indefinitely for possession and is entitled to refunds with compensation where delays are unreasonable.
Central Inland Water Transport Corporation Limited v. Brojo Nath Ganguly and Ors.(1986) 3 SCC 156; [1986] 2 SCR 278PositiveCited for principles of equality before the law and for striking down unfair or one-sided contracts where bargaining power is unequal.
Bharathi Knitting Company v. DHL Worldwide Express Courier Division of Airfreight Ltd.(1996) 4 SCC 704; [1996] 2 SCR 653Mentioned OnlyReferred to in para 6.6 as part of the discussion on unfair terms but not treated as binding authority for the decision.
Bangalore Development Authority v. Syndicate Bank(2007) 6 SCC 711; [2007] 7 SCR 47Mentioned OnlyReferred to in the discussion on refunds and interest but not directly applied as the controlling authority.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,503 words•~26 min read

In The Court Record

Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan

1169 [2019] 5 S.C.R. 1169 PIONEER URBAN LAND & INFRASTRUCTURE LTD. A v. ## GOVINDAN RAGHAVAN (Civil Appeal No. 12238 of 2018) APRIL 02, 2019 B ## **[UDAY UMESH LALIT AND INDU MALHOTRA, JJ.]** _Consumer Protection Act, 1986 – s.23 – Deficiency of service – Appellant-Builder launched a residential project and respondentflat purchaser entered into an Apartment Buyer’s agreement to purchase an apartment in the said project for a total sale consideration of Rs.4,83,25,280/- – As per agreement, the appellant was to apply for the occupancy certificate within 39 months from the date of excavation with grace period of 180 days – However, Appellant-builder failed to apply for occupancy certificate as per agreement – Consumer complaint filed before the National Commission – During the pendency of the proceedings, the appellant obtained the occupancy certificate and pleaded National Commission to direct the respondent to take possession of the flat – However, the respondent refused to take possession as there was an inordinate delay of almost 3 years – National Commission allowed the consumer complaint and held that respondent could not be compelled to take possession at such belated stage – Further, appellant was directed to refund Rs.4,48,43,026 i.e. the amount deposited by the respondent along with interest @ 10.7% S.I. p.a. towards compensation – On appeal, held: The respondent-flat purchaser made out a clear case of deficiency of service on the part of the appellant-builder – Appellant failed to fulfill his contractual obligation of obtaining the occupancy certificate and offering possession of the flat to the respondent within the time stipulated in the agreement, or within a reasonable time thereafter – Respondent was justified in terminating the Apartment Buyer’s Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession whenever it is offered by the Builder – Respondent was legally entitled to seek refund of the money deposited by him along with appropriate compensation – Respondent had to also service a loan that he had obtained for_ C D E F G H 1169 1170 SUPREME COURT REPORTS [2019] 5 S.C.R. - A _purchasing the flat by paying interest @10% to the Bank – In the circumstances, no illegality in the impugned order passed by the National Commission – Haryana Real Estate (Regulation And Development) Rules, 2017 – r.15._ - _Consumer Protection Act, 1986 – s.2(r) – Unfair and_ - B _unreasonable apartment buyer’s agreement – Held: A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder – The contractual terms of the Buyer’s Agreement in the instant case was ex-facie one-sided, unfair and unreasonable – The incorporation of such one-sided clauses in an_ - C _agreement constitutes an unfair trade practice as per s.2(r) of the Consumer Protection Act since it adopts unfair methods or practices for the purpose of selling the flats by the Builder._ ## **Dismissing the appeals, the Court** - D **HELD: 1. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are** _**exfacie**_ **one-sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade** - E **practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder. This Court has no hesitation in holding that the terms of the Apartment Buyer’s Agreement dated 08.05.2012 were wholly one-sided and unfair to the** - F **Respondent-Flat Purchaser. The Appellant-Builder could not seek to bind the Respondent with such one-sided contractual terms. [Paras 6.7 and 7][1183-B-D]** **2. In the present case, the National Commission has passed an equitable Order. The Commission has not awarded any Interest** G **for the period during which the Order of stay of cancellation of the allotment was in operation on the request of the RespondentFlat Purchaser. The National Commission has rightly awarded Interest @10.7% S.I. p.a. by applying Rule 15 of the Haryana Real Estate (Regulation And Development) Rules, 2017 from** H PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. 1171 GOVINDAN RAGHAVAN **the date of each installment till 05.02.2017 i.e. till the date after** A **which the Order of stay of cancellation of the allotment was passed; and thereafter, from the date of the Commission’s final Order till the date on which the amount is refunded with Interest. [Para 8.1][1183-G-H; 1184-A-B]** **3. There is no illegality in the Impugned Order dated 23.10.2018 passed by the National Commission. The AppellantBuilder failed to fulfill his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to the Respondent-Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent-Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired. During this period, the Respondent-Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest @10% to the Bank. In the meanwhile, the Respondent-Flat Purchaser also located an alternate property in Gurugram. In these circumstances, the Respondent-Flat Purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with Interest. [Para 9][1184-B-E]** _Lucknow Development Authority v. M.K. Gupta_ _**(**_ **1994) 1 SCC 243 : [1993] 3 Suppl. SCR 615;** _Fortune Infrastructure & Anr. v. Trevor D’Lima & Ors._ **(2018) 5 SCC 442: [2018] 3 SCR 273 ;** _Central Inland Water Transport Corporation Limited and Ors. v. Brojo Nath Ganguly and Ors_ _**.**_ **(1986) 3 SCC 156 : [1986] 2 SCR 278 – relied on.** _Bharathi Knitting Company v. DHL Worldwide Express Courier Division of Airfreight Ltd._ **(1996) 4 SCC 704 : [1996] 2 Suppl. SCR 653 ;** _Bangalore Development Authority v. Syndicate Bank_ **(2007) 6 SCC 711 : [2007] 7 SCR 47 – referred to.** B C D E F G ## **Case Law Reference** |**[1996]**|**2**|**Suppl. SCR**|**653**|**referred to**|**Para 8**| |---|---|---|---|---|---| |**[1993]**|**3**|**Suppl. SCR**|**615**|**relied on**<br>|**Para 6.6**| H 1172 [2019] 5 S.C.R. ## SUPREME COURT REPORTS |A|**[2018]**|**3**|**SCR**|**273**|**relied on**<br>|**Para 6.1**| |---|---|---|---|---|---|---| ||**[1986]**|**2**|**SCR**|**278**|**relied on**|**Para 6.1**| ||**[2007]**|**7**|**SCR**|**47**|**referred to**|**Para 4.3**| B CIVIL APPELLATE JURISDICTION: Civil Appeal No.12238 of 2018. From the Judgement and Order dated 23.10.2018 of the National Disputes Redressal Commission in Consumer Complaint No.239 of 2017. C.A. Sundram, Sr. Adv., Nikhil Nayyar, T.V. S. Raghavendra C Sreyas, Advs. For the Appellant. Sushil Kasushik, Manoj Yadav, Himanshu Shekhar, Advs. For the Respondents. The Judgment of the Court was delivered by D **INDU MALHOTRA, J.** 1. The present statutory Appeals have been filed under Section 23 of the Consumer Protection Act, 1986 to challenge the Final Judgment and Order dated 23.10.2018 passed in Consumer Case No. 238 of 2017 and Consumer Case No. 239 of 2017 by the National Consumer Disputes Redressal Commission (hereinafter E referred to as “the National Commission”). 2. Since a common issue arises in both the Civil Appeals, they are being disposed of by the present common Judgment and Order. 3. For the sake of brevity, the facts in C.A. No. 12238 of 2018 are being referred to, being the lead matter. F The factual matrix of the said Civil Appeal is as under : - 3.1. The Appellant – Builder launched a residential project by the name “Araya Complex” in Sector 62, Golf Course Extension Road, Gurugram. G The Respondent – Flat Purchaser entered into an Apartment Buyer’s Agreement dated 08.05.2012 with the Appellant – Builder to purchase an apartment in the said project for a total sale consideration of Rs. 4,83,25,280/-. H PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. 1173 GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] As per Clause 11.2 of the Agreement, the Appellant – Builder A was to make all efforts to apply for the Occupancy Certificate within 39 months from the date of excavation, with a grace period of 180 days. - 3.2. The excavation of the project commenced on 04.06.2012. As per Clause 11.2 of the Agreement, the Builder was required to B apply for the Occupancy Certificate by 04.09.2015, or within a further grace period of 6 months i.e. by 04.03.2016, and offer possession of the flat to the Respondent – Flat Purchaser. The Appellant – Builder however failed to apply for the Occupancy Certificate as per the stipulations in the Agreement. C - 3.3. The Respondent – Flat Purchaser filed a Consumer Complaint before the National Commission on 27.01.2017 alleging deficiency of service on the part of the Appellant – Builder for failure to obtain the Occupancy Certificate, and hand over possession of the flat. - D The Respondent prayed _inter-alia_ for :- - Refund of the entire amount deposited being Rs. 4,48,43,026/-, along with Interest @18% p.a.; and - Compensation of Rs. 10,00,000/- for mental agony, harassment, discomfort and undue hardship; and - E - Refund of the wrongfully charged taxes including Service Tax, and other charges along with Interest @18% p.a.; and Litigation Costs of Rs. 1,00,000/-. - 3.4. On 06.02.2017, the National Commission passed an _ex-parte_ Interim Order restraining the Appellant – Builder from cancelling the allotment made in favour of the Respondent – Flat Purchaser during the pendency of the Consumer Case. - 3.5. During the pendency of the proceedings before the National Commission, the Appellant – Builder obtained the Occupancy Certificate on 23.07.2018, and issued a Possession Letter to the Respondent – Flat Purchaser on 28.08.2018. - F - G H 1174 SUPREME COURT REPORTS [2019] 5 S.C.R. - A - B - 3.6. The Appellant – Builder submitted before the National Commission that since the construction of the apartment was complete, and the Occupancy Certificate had since been obtained, the Respondent – Flat Purchaser must be directed to take possession of the apartment, instead of directing refund of the amount deposited. - 3.7. The Respondent – Flat Purchaser however submitted that he was not interested in taking possession of the apartment on account of the inordinate delay of almost 3 years. The Respondent – Flat Purchaser stated that he had, in the meanwhile, taken an alternate property in Gurugram, and sought - C refund of the entire amount of Rs. 4,48,43,026/- deposited by him along with Interest @18% p.a. - 3.8 The National Commission _vide_ Final Judgment and Order dated 23.10.2018 allowed the Consumer Complaint filed by the Respondent – Flat Purchaser, and held that since the last date - D stipulated for construction had expired about 3 years before the Occupancy Certificate was obtained, the Respondent – Flat Purchaser could not be compelled to take possession at such a belated stage. The grounds urged by the Appellant – Builder for delay in E handing over possession were not justified, so as to deny awarding compensation to the Respondent – Flat Purchaser. The clauses in the Agreement were held to be wholly one – sided, unfair, and not binding on the Respondent – Flat Purchaser. The Appellant – Builder was directed to refund Rs. 4,48,43,026/ F - i.e. the amount deposited by the Respondent – Flat Purchaser, along with Interest @10.7% S.I. p.a. towards compensation. The rate of Interest @10.7% S.I. p.a. was fixed in accordance with Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 which reads as follows : G _“15. An allottee shall be compensated by the promoter for loss or damage sustained due to incorrect or false statement in the notice, advertisement, prospectus or brochure in the terms of Section 12. In case, allottee wishes to withdraw from the project due to discontinuance of promoter’s business as_ H PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] 1175 _developers on account of suspension or revocation of the_ A _registration or any other reason(s) in terms of clause (b) subsection (I) of Section 18 or the promoter fails to give possession of the apartment/ plot in accordance with terms and conditions of agreement for sale in terms of sub-section (4) of section 19. The promoter shall return the entire amount_ B _with interest as well as the compensation payable. The rate of interest payable by the promoter to the allottee or by the allottee to the promoter, as the case may be, shall be the State Bank of India highest marginal cost of lending rate plus two percent._ _…”_ (emphasis supplied) However, for the period when the Interim Order dated 06.02.2017 was in operation, which restrained the Appellant – Builder from cancelling the Respondent’s allotment, no Interest was awarded. The National Commission ordered payment of Interest from the date of each installment till 05.02.2017; and from the date of the Order passed by the Commission till the date on which the amount would be refunded. - 3.9. Aggrieved by the Order dated 23.10.2018 passed by the National Commission, the Appellant – Builder preferred the present statutory Appeal under Section 23 of the Consumer Protection Act, 1986. 4. Mr. C.A. Sundaram, Senior Counsel appeared for the Appellant – Builder, and drew our attention to the following Clauses in the Apartment Buyer’s Agreement dated 08.05.2012 _viz._ Clause 11.5 (ii), (iv) and (v) along with Clause 20 which read as under : _“11.5. (ii) In the event of further delay by the Developer in handing over of the possession of the Unit even after 12 months from the end of grace period, then in such case, the intending Allottee shall have an additional option to terminate this Agreement by giving termination notice of 90 days to the Developer and refund of the actual installment paid by him against the Unit after adjusting the taxes paid / interest / penalty on delayed payments._ C D E F G _…_ H 1176 SUPREME COURT REPORTS [2019] 5 S.C.R. A B C _(iv) Developer shall, within ninety (90) days from the date of receipt of termination notice of said Unit, refund to the intending Allottee, all the monies received excluding the service tax collected on various remittances, till the date of the refund, from the Intending Allottee under this Agreement. In case the Developer fails to refund the Sale Price, the Developer shall pay interest to the Intending Allottee @ 9% per annum for any period beyond the said period of ninety (90) days. The Intending Allottee shall have no other claim against the Developer in respect of the said Unit along with the parking space. The Intending Allottee in this event shall have no right to seek any compensation apart from the interest as stipulated herein._ ## _…_ D E _(v) If the Intending Allottee fails to exercise his right of termination within the time limit as aforesaid, by delivery to the Developer of a written notice acknowledged by the Developer in this regard, then he shall not be entitled to terminate this Agreement thereafter and he shall continue to be bound by the provisions of this Agreement, provided that in such case, the Developer shall continue to pay the compensation provided herein._ ## _20. RIGHT OF CANCELLATION BY THE ALLOTTEE_ F G _Except to the extent specifically and expressly stated elsewhere in this Agreement, the Intending Allottee shall have the right to cancel this Agreement solely in the event of the clear and unambiguous failure of the warranties of the Developer that leads to frustration of the contract on that account. In such case, the Allottee shall be entitled to a refund of the installments actually paid by it along with interest thereon @ 6% per annum, within a period of 90 days from the date of communication to the Developer in this regard less any payments made towards taxes paid by the Developer or interest paid due or payable, any other amount of a non-refundable nature. No other claim, whatsoever, monetary or otherwise shall lie against the Developer nor shall be raised otherwise_ H 1177 ## PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] _or in any manner whatsoever by the Allottee. Save and except_ A _to this limited extent, the Allottee shall not have any right to cancel this Agreement on any ground whatsoever.”_ (emphasis supplied) - 4.1. It was submitted that the Respondent – Flat Purchaser was not entitled to refund of the amount deposited, since the Apartment Buyer’s Agreement was not terminated by the Respondent – Flat Purchaser in accordance with Clause 11.5 (ii) of the Agreement, which stipulates that the allottee has to terminate the Agreement by giving a Termination Notice of 90 days to the Developer. Since the Respondent – Flat Purchaser had not terminated the Agreement by a written notice as per Clause 11.5, the Builder could not sell the apartment, and refund the money to the Respondent – Flat Purchaser. On the contrary, the Respondent filed a Consumer Complaint and obtained an _ex-parte_ Interim Order dated 06.02.2017 restraining the Builder from cancelling the allotment made in favour of the Respondent. 4.2. It was further submitted that if the filing of the Consumer Complaint is considered as an act of termination of the Agreement, then the same was pre-mature. As per Clause 11.5 (ii), the Respondent – Flat Purchaser could have claimed refund only after the expiry of 12 months after the grace period came to an end i.e. after 04.03.2017. However, the Consumer Complaint was filed on 27.01.2017. In these circumstances, even if it is found that the Appellant – Builder is liable to refund the amount deposited with Interest, then the date of the Impugned Order i.e. 23.10.2018, must be treated as the date of serving the Termination Notice as per Clause 11.5 (ii) of the Agreement, and the Appellant – Builder should be held liable to pay Interest only after 90 days from the date of termination i.e. from 23.01.2019. B C D E F G - 4.3. With respect to rate of Interest awarded by the National Commission, it was submitted that the Commission erred in granting Interest @10.7% S.I. p.a. even though Clause 20 of H 1178 SUPREME COURT REPORTS [2019] 5 S.C.R. - A the Agreement provided Interest @6% p.a. in case of delay in handing over possession. Even under Clause 11.5 of the Agreement, the Builder was liable to pay Interest @9% p.a., but not @10.7% S.I. p.a. The learned Senior Counsel relied upon this Court’s Judgment in _Bharathi Knitting Company_ v. _DHL Worldwide Express Courier Division of Airfreight Ltd._ ,[1] - B and submitted that the National Commission could not have granted compensation in excess of the rate prescribed by the Agreement. 5. Mr. Sushil Kaushik, learned Counsel represented the Respondent – Flat Purchaser. C 5.1. It was submitted that the filing of the Consumer Complaint may be treated as his Termination Notice under Clause 11.5 (ii) of the Agreement. Under the Agreement, the Builder was obligated to apply for the Occupancy Certificate within 39 months from the date of excavation, with a grace period of further 6 months. D The period got over by 04.03.3016 after taking into account the grace period. - Admittedly, the Appellant – Builder offered possession after an inordinate delay of almost 3 years on 28.08.2018. On account of the inordinate delay, the Respondent – Flat Purchaser had - E no option but to arrange for alternate accommodation in Gurugram. Hence, he could not be compelled to take possession of the apartment after such a long delay. - It was in these circumstances that the Respondent – Flat Purchaser sought stay of the cancellation of the allotment as a - F collateral, till his claim for refund was adjudicated by the National Commission. - 5.2. It was further submitted that the Clauses of the Agreement were one-sided. As per Clause 6.4 (ii) of the Apartment Buyer’s Agreement, the Appellant Builder could charge Interest @18% - G p.a. for delayed payments. However, the Appellant – Builder was not required to pay equivalent Interest to the Respondent – Flat Purchaser for delay in handing over possession of the flat. - H 1(1996) 4 SCC 704. PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. 1179 GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] On the contrary, as per Clause 11.5 (iv) of the Agreement, in A case of delay on the part of the Appellant – Builder in handing over possession of the flat, the Respondent – Flat Purchaser was entitled to Interest @9% p.a. only. - 5.3. The Respondent further submitted that the National Commission had ordered payment of Interest as per the statutory Rules i.e. B Rule 15 of the Haryana Real Estate (Regulation and Development) Rules, 2017 @10.7% S.I. p.a. The Respondent – Flat Purchaser submitted that he had obtained a loan for Rs. 3,30,00,000/- from Standard Chartered Bank to purchase the flat in question, and had entered into a Tripartite Loan Agreement with the Bank and the Builder. The Respondent – Flat Purchaser had to pay Interest @10% p.a. for servicing the loan for the entire period. Hence, Interest @10.7% S.I. p.a. awarded by the National Commission was just and fair. It was pointed out that even though the National Commission had not granted Interest for the period during which the Order of stay of cancellation of the allotment was in operation, the Respondent – Flat Purchaser had to pay Interest to the Bank even for this period. - 5.4. The Respondent – Flat Purchaser submitted that the present Appeal be dismissed, and the Builder be directed to pay the amount awarded by the National Commission with Interest, within 1 week, so that the Respondent can discharge his loan liability. 6. We have heard the learned Counsel for both the parties, and perused the pleadings, and written submissions filed. - 6.1. In the present case, admittedly the Appellant – Builder obtained the Occupancy Certificate almost 2 years after the date stipulated in the Apartment Buyer’s Agreement. As a consequence, there was a failure to hand over possession of the flat to the Respondent – Flat Purchaser within a reasonable period. The Occupancy Certificate was obtained after a delay of more than 2 years on 28.08.2018 during the pendency of the proceedings before the National Commission. C D E F G H 1180 SUPREME COURT REPORTS [2019] 5 S.C.R. - A In _Lucknow Development Authority_ v. _M.K. Gupta_ ,[2] this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2 (o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to - B deficiency of service. - C In _Fortune Infrastructure & Anr._ v. _Trevor D’Lima & Ors._ ,[3] this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation. - 6.2. The Respondent – Flat Purchaser has made out a clear case of deficiency of service on the part of the Appellant – Builder. The Respondent – Flat Purchaser was justified in terminating the Apartment Buyer’s Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession - D whenever it is offered by the Builder. The Respondent – Purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation. - 6.3. The National Commission in the Impugned Order dated 23.10.2018 held that the Clauses relied upon by the Builder - E were wholly one-sided, unfair and unreasonable, and could not be relied upon. The Law Commission of India in its 199[th] Report, addressed the issue of ‘Unfair (Procedural & Substantive) Terms in Contract’. The Law Commission _inter-alia_ recommended that F a legislation be enacted to counter such unfair terms in contracts. In the draft legislation provided in the Report, it was stated that : _“A contract or a term thereof is substantively unfair if such contract or the term thereof is in itself harsh, oppressive_ G _or unconscionable to one of the parties.”_ - 6.4. A perusal of the Apartment Buyer’s Agreement dated 08.05.2012 reveals stark incongruities between the remedies available to both the parties. - 2 (1994) 1 SCC 243. - H 3 (2018) 5 SCC 442. ## PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. 1181 GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] For instance, Clause 6.4 (ii) of the Agreement entitles the Appellant – Builder to charge Interest @18% p.a. on account of any delay in payment of installments from the Respondent – Flat Purchaser. Clause 6.4 (iii) of the Agreement entitles the Appellant – Builder to cancel the allotment and terminate the Agreement, if any installment remains in arrears for more than 30 days. On the other hand, as per Clause 11.5 of the Agreement, if the Appellant – Builder fails to deliver possession of the apartment within the stipulated period, the Respondent – Flat Purchaser has to wait for a period of 12 months after the end of the grace period, before serving a Termination Notice of 90 days on the Appellant – Builder, and even thereafter, the Appellant – Builder gets 90 days to refund only the actual installment paid by the Respondent – Flat Purchaser, after adjusting the taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the Appellant – Builder is liable to pay Interest @9% p.a. only. 6.5. Another instance is Clause 23.4 of the Agreement which entitles the Appellant – Builder to serve a Termination Notice upon the Respondent – Flat Purchaser for breach of any contractual obligation. If the Respondent – Flat Purchaser fails to rectify the default within 30 days of the Termination Notice, then the Agreement automatically stands cancelled, and the Appellant – Builder has the right to forfeit the entire amount of Earnest Money towards liquidated damages. On the other hand, as Clause 11.5 (v) of the Agreement, if the Respondent – Flat Purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the Agreement thereafter, and shall be bound by the provisions of the Agreement. - 6.6. Section 2 (r) of the Consumer Protection Act, 1986 defines ‘unfair trade practices’ in the following words : A B C D E F G “ _‘unfair trade practice’ means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or_ H 1182 SUPREME COURT REPORTS [2019] 5 S.C.R. A _for the provision of any service, adopts any unfair method or unfair or deceptive practice …”_ ,and includes any of the practicesenumerated therein. The provision is illustrative, and not exhaustive. In _Central Inland Water Transport Corporation Limited and_ B _Ors._ v. _Brojo Nath Ganguly and Ors._ ,[4] this Court held that : _“89. … Our judges are bound by their oath to ‘uphold the Constitution and the laws’. The Constitution was enacted to secure to all the citizens of this country social and economic justice. Article 14 of the Constitution guarantees to all persons_ C _equality before the law and equal protection of the laws. This principle is that the courts will not enforce and will, when called upon to do so, strike down an unfair and unreasonable contract, or an unfair and unreasonable clause in a contract, entered into between parties who are not equal in bargaining power. It is difficult to give an exhaustive list of all bargains_ D _of this type. No court can visualize the different situations which can arise in the affairs of men. One can only attempt to give some illustrations. For instance, the above principle will apply where the inequality of bargaining power is the result of the great disparity in the economic strength of the_ E _contracting parties. It will apply where the inequality is the result of circumstances, whether of the creation of the parties or not. It will apply to situations in which the weaker party is in a position in which he can obtain goods or services or means of livelihood only upon the terms imposed by the stronger party or go without them. It will also apply where a_ F _man has no choice, or rather no meaningful choice, but to give his assent to a contract or to sign on the dotted line in a prescribed or standard form or to accept a set of rules as part of the contract, however unfair, unreasonable and unconscionable a clause in that contract or form or rules_ G _may be. This principle, however, will not apply where the bargaining power of the contracting parties is equal or almost equal. This principle may not apply where both parties are businessmen and the contract is a commercial transaction. …_ D _…_ H 4(1986) 3 SCC 156 ## PIONEER URBAN LAND & INFRASTRUCTURE LTD. v. 1183 GOVINDAN RAGHAVAN [UDAY UMESH LALIT, J.] _These cases can neither be enumerated nor fully illustrated._ A _The court must judge each case on its own facts and circumstances.”_ (emphasis supplied) - 6.7. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. - The contractual terms of the Agreement dated 08.05.2012 are _ex-facie_ one-sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder. 7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer’s Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent – Flat Purchaser. The Appellant – Builder could not seek to bind the Respondent with such one-sided contractual terms. 8. We also reject the submission made by the Appellant – Builder that the National Commission was not justified in awarding Interest @10.7% S.I. p.a. for the period commencing from the date of payment of each installment, till the date on which the amount was paid, excluding only the period during which the stay of cancellation of the allotment was in operation. B C D E In _Bangalore Development Authority_ v. _Syndicate Bank_ ,[5] a Coordinate Bench of this Court held that when possession of the allotted F plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable Interest thereon from the date of payment till the date of refund. - 8.1. In the present case, the National Commission has passed an equitable Order. The Commission has not awarded any Interest G for the period during which the Order of stay of cancellation of the allotment was in operation on the request of the Respondent – Flat Purchaser. 5(2007) 6 SCC 711. H 1184 SUPREME COURT REPORTS [2019] 5 S.C.R. - A The National Commission has rightly awarded Interest @10.7% S.I. p.a. by applying Rule 15 of the Haryana Real Estate (Regulation And Development) Rules, 2017 from the date of each installment till 05.02.2017 i.e. till the date after which the Order of stay of cancellation of the allotment was passed; and thereafter, from the date of the Commission’s final Order till - B the date on which the amount is refunded with Interest. 9. We see no illegality in the Impugned Order dated 23.10.2018 passed by the National Commission. The Appellant – Builder failed to fulfill his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to the Respondent – Purchaser within C the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent – Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired. During this period, the Respondent – Flat Purchaser had to service a loan that he had obtained D for purchasing the flat, by paying Interest @10% to the Bank. In the meanwhile, the Respondent – Flat Purchaser also located an alternate property in Gurugram. In these circumstances, the Respondent – Flat Purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with Interest. E 10. The Civil Appeals are accordingly dismissed, and the Final Judgment and Order dated 23.10.2018 passed by the National Consumer Disputes Redressal Commission is affirmed. The appellant is granted a period of three months from today to refund the amount to the respondent. All pending Applications, if any, are accordingly disposed of. F Ankit Gyan Appeals dismissed. G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.