Pam Developments Private Limited v. The State of West Bengal & Anr.

Case / Petition Number:
Civil Appeal Nos. 9781-9782 of 2024
Neutral Citation:[2024] 8 S.C.R. 615

Case Synopsis & Summary

Pam Developments Private Limited v. The State of West Bengal & Anr. arises from an arbitral award resolving a road-widening project dispute under the Arbitration and Conciliation Act, 1996. The contractor claimed multiple heads: loss of business, idle labour and machinery, labour charges for uneconomical stoppage of work, and interest on delayed payments and escalation; these were referred to arbitration. The Arbitral Award held the respondents liable for several heads and the District Judge upheld most of these, while the Calcutta High Court under ss. 34 and 37 partly set aside some heads and modified others. The appellant challenged the High Court’s order in a Civil Appeal before the Supreme Court. The Court scrutinised whether the High Court’s interference with the Arbitral Award was justified, focusing on the contract’s Special Terms and Conditions allegedly prohibiting idle labour and related costs, and the scope of Section 31(7) governing interest. The Supreme Court held that the contract clauses speak for themselves and the High Court’s reasoning on claim no. 3 (labour charges for idle stoppage) was sound, setting aside that head. It also restored the District Court’s upholding of claim no. 4 (interest on delayed payments) and allowed pre-reference interest for claim no. 6, clarifying the interplay between Section 31(7) and contractual terms. The decision underscores limited interference with arbitral awards and clarifies the grant of interest under the 1996 Act.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Pamidighantam Sri Narasimha
  • Pankaj Mithal
Judgment Date
2024-08-23
Court Decision / Holding
Civil Appeal arising out of SLP (C) No. 8128 of 2021 partly allowed. Civil Appeal arising out of SLP (C) No. 8129 of 2021 disposed of. Parties shall bear their own costs.
Final Disposition
Partly allowed; The Court allowed claims 4 and 6 and set aside certain High Court modifications; final disposition reflects partial allowance of appeals and restoration of portions of the Arbitral Award.

Parties to the Case

Appellants / Petitioners

  • Pam Developments Private Limited

Respondents

  • The State of West Bengal
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Saurav Agarwal
  • • Priyankar Saha
  • • Sarad Kumar Singhania
  • • Ms. Rashmi Singhania
  • • Anshuman Choudhry

Counsels for Respondents

  • • Ms. Madhumita Bhattacharjee
  • • Ms. Srija Choudhury
  • • Anant
  • • Ms. Sajal Bhrdwaj

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Sections 34, 37, 31(7)Arbitration Act, 1940Interest Act, 1978

Legal Doctrines & Maxims

  • Contract is the foundation of the legal relationship
  • Injured party is to be placed in the same financial position as if the contract had been performed
  • Public policy of India
  • Autonomy of contract and interplay with statutory provisions on interest

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court’s Section 37 interference was unwarranted for claims 3 and 6, arguing that contractual clauses do not bar consideration of pre-reference and pendente lite interest; they urge fidelity to the Arbitral Award where permissible and seek restoration or preservation of the award consistent with Section 31(7) and the contract terms.

Contentions of Respondents

The respondents urged that the High Court correctly read the Special Terms and Conditions of the contract to bar idle labour costs (claim 3) and that the arbitrator’s approach to interest required correction under Section 37; they contend that pre-reference interest is barred or limited by contract and that the Court should not disturb the High Court’s modifications unless clearly perverse.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (21)

Case NameCitationTreatmentExplanation
Secretary, Irrigation Department, Government of Orissa v. G.C. Roy[1991] Supp. 3 SCR 417 : (1992) 1 SCC 508PositiveCited as authority for placing the injured party in the financial position as if the contract had been performed.
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C. Budharaj[2001] 1 SCR 264 : (2001) 2 SCC 721PositiveCited in context of arbitration/intergovernmental decisions affecting relief and interest.
Union of India v. Krafters Engg. and Leasing (P) Ltd.[2011] 8 SCR 196 : (2011) 7 SCC 279PositiveUsed to illustrate principles relating to arbitral powers and contractual interpretations.
Board of Trustees for the Port of Calcutta v. Engineers-de-Space-Age[1995] Supp. 6 SCR 327 : (1996) 1 SCC 516PositiveCited for arbitration-related principles and public policy considerations.
Madnani Construction Corporation Private Limited v. Union of India[2009] 16 SCR 216 : (2010) 1 SCC 549PositiveCited in discussing arbitral power and contract-based limitations.
Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd.[2012] 8 SCR 813 : (2012) 12 SCC 10PositiveUsed to discuss pre-reference and pendente lite interest jurisprudence.
Union of India v. Ambica Construction[2016] 2 SCR 810 : (2016) 6 SCC 36PositiveCited for recent interpretations of pre-reference and pendente lite interest.
Ambica Construction v. Union of India(2017) 14 SCC 323PositiveCited as authority on arbitral powers and interest.
Raveechee and Company v. Union of India[2018] 5 SCR 138 : (2018) 7 SCC 664PositiveCited in context of arbitration and contractual interpretations.
Reliance Cellulose Products Ltd. v. ONGC Ltd.[2018] 6 SCR 618 : (2018) 9 SCC 266PositiveUsed to support principles on interest and award implications.
State of U.P. v. Harish Chandra and Co.[1999] 1 SCC 63PositiveCited for general principles guiding arbitral Awards and public policy.
Chandra and Co.[1998] Supp. 2 SCR 660 : (1999) 1 SCC 63PositiveCited as authority in related arbitration and contractual interpretations.
Sayeed Ahmed and Company v. State of Uttar Pradesh[2009] 10 SCR 841 : (2009) 12 SCC 26PositiveUsed to illustrate interest and contract-based provisions.
Union of India v. Saraswat Trading Agency[2009] 10 SCR 1063 : (2009) 16 SCC 504PositiveCited in context of arbitral powers and contract interpretation.
Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat[2010] 10 SCR 487 : (2010) 8 SCC 767PositiveCited regarding arbitral powers and interest terms.
Union of India v. Bright Power Projects (India) Pvt Ltd.[2015] 6 SCR 488 : (2015) 9 SCC 695PositiveCited for interest and award interpretation under 1996 Act.
Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited[2019] 2 SCR 41 : (2019) 17 SCC 786PositiveUsed to discuss jurisprudence on pre-reference and pendente lite interest.
Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation[2022] 3 SCR 716 : (2022) 9 SCC 286PositiveCited for contemporary interpretation of arbitral powers on interest.
Oriental Structural Engineers Private Limited v. State of Kerala[2021] 4 SCR 137 : (2021) 6 SCC 150PositiveApplied to arbitral powers and contract terms.
Central Bank of India v. Ravindra[2001] Supp. 4 SCR 323 : (2002) 1 SCC 367PositiveCited in discussing interest and award framework.
Secy./GM, Chennai, Central Coop. Bank Ltd. v. S. Kamalaveni Sundaram[2011] 1 SCR 66 : (2011) 1 SCC 790Mentioned OnlyReferred to but not central to the decision; acknowledged as authority.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,976 words•~28 min read

In The Court Record

Pam Developments Private Limited v. The State of West Bengal & Anr.

[2024] 8 S.C.R. 615 : 2024 INSC 628 ## **Pam Developments Private Limited** ## **v.** ## **The State of West Bengal & Anr.** (Civil Appeal Nos. 9781-9782 of 2024) 23 August 2024 ## **[Pamidighantam Sri Narasimha* and Pankaj Mithal, JJ.]** ## **Issue for Consideration** Matter pertains to the arbitral award in favour of the contractor as regards labour charges for uneconomical stoppage of work, interest on delayed payment, and interest, upheld by the District Judge but set aside/modified by the High Court. ## **Headnotes[†]** **Arbitration and Conciliation Act, 1996 – ss. 34 and 37 – Arbitral awards – Work contract – Claims raised by the contractor under different heads alleging delays on the part of the State, referred to the arbitrator – Arbitral award in favour of the contractor under heads-loss of business, uneconomic utilization of plant and machinery, labour charges for uneconomical stoppage of work, interest on delayed payment, escalation bill, interest and costs – Award challenged by the State, whereby the District Judge set aside few of the claims – High Court modified the award – Interference with:** **Held:** Decision of the High Court setting aside the award with respect to claim as regards labour charges for uneconomical stoppage of workup held since the arbitrator did not even refer to the contractual provisions which prohibited such claim – Judgment of the High Court setting aside claim of interest on delayed payment awarded by the Arbitrator, as upheld by the District Judge u/s. 34 is set aside since nothing perverse in the reasoning of the Arbitrator and nor such conclusion against public policy – Judgment of the High Court in so far as it modified claim as regards interest, to the extent of rejecting pre-reference interest awarded by the arbitrator, as upheld by the District Judge u/s. 34 is set aside since the High Court had no reason to interfere with the Arbitral Award with respect to grant of pre-reference interest, since the contract * Author [2024] 8 S.C.R. 616 ## **Digital Supreme Court Reports** between parties does not prohibit the same – Award as regards labour charges for uneconomical stoppage of work set aside and award as regards interest on delayed payment is upheld – As regards the claim of interest, the appellant entitled to claim prereference interest. [Para 10] ## **Arbitration and Conciliation Act, 1996 – Work contract – Arbitration proceedings – Contractual clauses – Interpretation of – Claim relating to loss caused due to idle labour, machinery – High Court held that the said claim is impermissible under the contractual provisions – Correctness:** **Held:** Contract clauses speak for themselves – High Court did what the Arbitrator should have done and examined what the contract provides – This is not even a matter of interpretation – It is the duty of every arbitral tribunal and court alike and without exception, for contract is the foundation of the legal relationship – High Court came to the conclusion that awarding any amount towards idle, machinery, etc. is prohibited under the ‘Special Terms and Conditions’ of the Contract – Arbitrator did not even refer to the contractual provisions and the District Court dismissed the objections u/s. 34 with a standard phrase – High Court exercising jurisdiction u/s 37 did its duty and the conclusions of the High Court are correct and cannot be interfered with. [Paras 7, 7.3-7.5] ## **Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Dispute relating to work contract – Arbitral award – Arbitrator awarded interest on delayed payment of running account bills – Upheld by the District Court – However, the High Court set aside the award – Challenge to:** **Held:** Conclusion of the High Court, that it appears that the bills were paid soon after they were prepared or that, in that case there could not have been any claim for interest cannot qualify as grounds for interference u/s 37 – Equally, the approach of the High Court in holding that the Arbitrator neither established nor discussed the questions posed by it, not a ground to set aside the Award – Reasoning of the Arbitrator is reflected in that portion of the Award and nothing perverse is seen in it – Nor such conclusion is against the public policy – Judgment of the High Court in relation to the said claim set aside and the Award is restored. [Paras 8.5, 8.6] [2024] 8 S.C.R.  617 **Pam Developments Private Limited v. The State of West Bengal & Anr.** **Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Dispute relating to work contract – Arbitral award – As regards claim relating to Interest, Arbitrator awarded interest @12% on sum awarded from the date when appellant claimed breach of contract, to the date of the Award, and further interest @ 9.25% p.a. from date of Award till actual payment – District Judge upheld the same – However, the High Court held that pre-reference interest could not have been granted for this period, and that as the Arbitrator could have granted interest only for pendent lite and post award, the Award was modified directing pendente lite interest along with post award interest – Correctness:** **Held:** s. 31(7) determines the grant of interest – Power of the Arbitrator to grant pre-reference interest, pendente lite interest, and post-award interest u/s 31(7) of the Act is fairly well-settled – High Court had no reason to interfere with the Arbitral Award with respect to grant of pre-reference interest, since the contract between parties does not prohibit the same. [Paras 9.4-9.6] **Arbitration and Conciliation Act, 1996 – s 37(1) – Power of the Arbitrator to grant pre-reference interest, pendente lite interest, and post-award interest under – Difference in the position of law under the Arbitration Act, 1940 – Encapsulated. [Para 9.5]** ## **Case Law Cited** _Secretary, Irrigation Department, Government of Orissa v. G.C. Roy_ **[1991] Supp. 3 SCR 417 : (1992) 1 SCC 508;** _Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C. Budharaj_ **[2001] 1 SCR 264 : (2001) 2 SCC 721;** _Union of India v. Krafters Engg. and Leasing (P) Ltd._ **[2011] 8 SCR 196 : (2011) 7 SCC 279;** _Board of Trustees for the Port of Calcutta v. Engineers-de-Space-Age_ **[1995] Supp. 6 SCR 327 : (1996) 1 SCC 516;** _Madnani Construction Corporation Private Limited v. Union of India_ **[2009] 16 SCR 216 : (2010) 1 SCC 549;** _Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd._ **[2012] 8 SCR 813 : (2012) 12 SCC 10;** _Union of India v. Ambica Construction_ **[2016] 2 SCR 810 : (2016) 6 SCC 36;** _Ambica Construction v. Union of India_ **(2017) 14 SCC 323;** _Raveechee and Company v. Union of India_ **[2018] 5 SCR 138 : (2018) 7 SCC 664;** _Reliance Cellulose Products Ltd. v. ONGC Ltd._ **[2018] 6 SCR 618 : (2018) 9 SCC 266;** _State of U.P. v. Harish_ [2024] 8 S.C.R. 618 ## **Digital Supreme Court Reports** _Chandra and Co._ **[1998] Supp. 2 SCR 660 : (1999) 1 SCC 63;** _Sayeed Ahmed and Company v. State of Uttar Pradesh_ **[2009] 10 SCR 841 : (2009) 12 SCC 26;** _Union of India v. Saraswat Trading Agency_ **[2009] 10 SCR 1063 : (2009) 16 SCC 504;** _Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat_ **[2010] 10 SCR 487 : (2010) 8 SCC 767;** _Union of India v. Bright Power Projects (India) Pvt Ltd._ **[2015] 6 SCR 488 : (2015) 9 SCC 695;** _Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited_ **[2019] 2 SCR 41 : (2019) 17 SCC 786;** _Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation_ **[2022] 3 SCR 716 : (2022) 9 SCC 286;** _Oriental Structural Engineers Private Limited v. State of Kerala_ **[2021] 4 SCR 137 : (2021) 6 SCC 150;** _Central Bank of India v. Ravindra_ **[2001] Supp. 4 SCR 323 : (2002) 1 SCC 367;** _Secy./GM, Chennai, Central Coop. Bank Ltd. v. S. Kamalaveni Sundaram_ **[2011] 1 SCR 66 : (2011) 1 SCC 790 – referred to.** ## **List of Acts** Arbitration and Conciliation Act, 1996; Arbitration Act, 1940; Interest Act, 1978. ## **List of Keywords** Arbitral award; Labour charges for uneconomical stoppage of work; Interest on delayed payment; Interest; Work contract; Loss of business; Uneconomic utilization of plant and machinery; Escalation bill; Costs; Contractual provisions; Pre-reference interest; Special Terms and Conditions of the Contract; Public policy; Pendente lite interest; Post award interest. ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 9781-9782 of 2024 From the Judgment and Order dated 03.06.2021 of the High Court at Calcutta in FMAT No.376 of 2019 and COT No. 54 of 2019 ## **Appearances for Parties** Saurav Agarwal, Priyankar Saha, Sarad Kumar Singhania, Ms. Rashmi Singhania, Anshuman Choudhry, Advs. for the Appellant. Ms. Madhumita Bhattacharjee, Ms. Srija Choudhury, Anant, Ms. Sajal Bhrdwaj, Advs. for the Respondents. [2024] 8 S.C.R.  619 **Pam Developments Private Limited v. The State of West Bengal & Anr.** ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Pamidighantam Sri Narasimha, J** . 1. Leave granted. 2. State of West Bengal, respondent herein, issued a notice inviting tenders on 08.09.2010, for the widening and strengthening of Egra Bajkul road under the Tamluk Highway Division in Purbo Medinipur District and accepted appellant’s offer, leading to grant of a Work Order for the project to be completed within 18 months from 23.12.2010. The project got delayed by about five months, but the work was completed by 09.11.2012. 3. The appellant raised a bill for Rs. 77,85,290 and that was in addition to seven other claims under different heads, owing to alleged delays on part of the Respondent. As the respondent denied any liability, the dispute was referred to Arbitration for resolution. 4. The Arbitrator gave his award on 30.01.2018, holding the respondents are liable to the tune of Rs.1,37,25,252, with interest. There were seven claims. Claim no. 1 related to _loss of business,_ with respect to which Rs. 3,87,530 was awarded; claim no. 2 related to _uneconomic utilization of plant and machinery,_ with respect to which Rs. 61,22,000 was awarded and claim no. 3 related to _labour charges for uneconomical stoppage of work,_ with respect to which Rs.5,80,500 was awarded; claim no. 4 related to _interest on delayed payment of running account bills and escalation bill_ for which the Arbitrator awarded Rs. 54,84,024; claim no. 5 related to _escalation_ with respect to which Rs.11,51,198 was granted; and claim 6 related to _interest on the sum awarded_ , with respect to which interest @12% p.a. was awarded from 12.04.2016 to 30.01.2018 and @ 9.25% p.a. post award interest till date of actual payment. Finally claim no.7 pertained to costs and the Arbitrator awarded 4 lakhs to the appellant, being the successful party. - 4.1 The Respondents challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996[1] and it was allowed 1 Hereinafter referred to as the ‘Act’. [2024] 8 S.C.R. 620 ## **Digital Supreme Court Reports** in part by the District Judge setting aside claim no. 1 for _loss of business_ , since the same had never been claimed by the appellant and was thus beyond the Arbitrator’s jurisdiction. Claim no. 2 for _uneconomic utilization of plant and machinery_ was also set aside because the Arbitrator didn’t account for the loss of 135 days at the behest of the appellant while determining the alleged 200 days of ‘wasted machine’. - 4.2 Aggrieved by the decision of the District Judge, the appellant filed an appeal under Section 37 of the Act against the order setting aside the award on claims 1 and 2. On the other hand, the Respondent filed a cross appeal seeking setting aside of the rest of the claims as well. By the order impugned before us, the Calcutta High Court exercising jurisdiction under Section 37 of the Act set aside claim no.1 as well as claim nos. 3 and 4, but restored the Award with respect to claim no.2. However, while retaining claim no. 5 as it is, the High Court slightly modified claim no. 6 relating to pre-reference interest. 5. A comprehensive table of the claims and the decision in the Award, Section 34 and Section 37 jurisdiction is as follows – |Claim no.|Arbitral Award|Section 34|Section 37| |---|---|---|---| |1. Loss of<br>business|Awarded<br>Rs.3,87,530.|Award Set aside,<br>because it was<br>never claimed by<br>the appellant and<br>was the basis for<br>granting of-site<br>expenses.|Affirmed<br>the decision<br>of District<br>judge.| |2.<br>Uneconomic<br>utilization of<br>plant and<br>machinery|Awarded Rs.<br>61,22,000 for<br>deploying plant<br>and machinery<br>on all 200 wasted<br>days as required<br>under the<br>Contract.|<br>Award set aside, as<br>Arbitrator did not<br>account for wastage<br>of 135 days by the<br>appellant itself.|Awarded<br>claim no.<br>2, thereby<br>reversing<br>decision by<br>the District<br>Judge.| [2024] 8 S.C.R.  621 ## **Pam Developments Private Limited v. The State of West Bengal & Anr.** |3. Labour<br>Charges for<br>uneconomical<br>stoppage of<br>work|Arbitrator granted<br>3% of the<br>contract amount<br>Rs.5,80,500/- as<br>per the Hudson’s<br>formula.|Award upheld by the<br>District Court.|<br>Set aside,<br>because it is<br>contrary to<br>the Special<br>Terms and<br>Conditions<br>of the<br>Contract.| |---|---|---|---| |4. Interest<br>on delayed<br>payment<br>of Running<br>Account Bills<br>and Escalation<br>Bills|Awarded Rs.<br>54,84,024/- on<br>the ground<br>of interest on<br>blocked capital<br>(when amount<br>exceeded Rs.1<br>crore) @12% pa.|Award upheld by the<br>District Court.|<br>Set aside<br>because<br>monthly bills<br>raised by<br>appellants<br>were paid<br>without<br>delay. As per<br>clauses 7-9,<br>no claim<br>for interest<br>arises.| |5. Escalation<br>Bill|Awarded<br>Rs.11,51,198/- as<br>respondent has<br>already paid part<br>of such amount.<br>The claimant is<br>entitled to the<br>balance.|Award upheld by the<br>District Court.|<br>Affirmed the<br>Award and<br>decision of<br>the District<br>Judge.| |6. Interest|Arbitrator<br>awarded interest<br>@12% on<br>amount of claims<br>w.e.f 12.04.2016<br>to the date of<br>Award and further<br>interest @9.25%<br>p.a. from date of<br>award till actual<br>payment.|<br>Award upheld by<br>the District Judge.|Modified.<br>Only interest<br>pendent<br>lite and<br>post award<br>payable.<br>No interest<br>for pre-<br>reference<br>period.| [2024] 8 S.C.R. 622 ## **Digital Supreme Court Reports** |7. Cost|Awarded Rs.4<br>Lakhs towards<br>legal and<br>administrative<br>expenses.||| |---|---|---|---| 6. Mr. Saurav Agarwal, counsel for the appellant, confined his submissions to claim no. 3, 4 and 6 awarded by the Arbitrator and upheld by the District Judge but set aside/modified by the High Court. We will deal with each of these claims. 7. Re claim no. 3: This claim relating to loss caused due to idle labour, machinery, etc. - 7.1 On this count, the Arbitrator accepted the claim of loss on the ground of on-site establishment ‘as permissible’ to the extent of 3% of the contract amount by the Hudson’s formula for expenses of engineers, supervisors, etc. It was his considered view that the appellant maintained such an establishment to execute the work and the same has not been disputed by the Respondent. Therefore, he awarded claim no. 3 in favour of the appellant for Rs.5,80,500. - 7.2 The challenge to the Award made by the Respondent was dismissed by the District Judge under Section 34, holding that the findings of the Arbitrator cannot be held to be irrational, insensible or unrealistic and also that they are not in conflict with public policy. We may state at this very stage that this common reasoning of the District Court while upholding the Award for claim nos. 3, 4, 5 and 6. The standard reasoning of the District Court for these claims is as follows: - _“I have gone through the observation of the learned Arbitrator in respect of claim Nos. 3, 4, 5 and 6. On meticulous scrutiny of the award with reference to the documents produced by the parties to the ease, I find that the reasons and findings given by the learned Arbitrator cannot be said to be irrational, insensible or unrealistic. In fact, award in respect of claim Nos. 3, 4, 5 & 6 cannot be said_ [2024] 8 S.C.R.  623 ## **Pam Developments Private Limited v. The State of West Bengal & Anr.** _to be.in conflict with the public policy of India even by stretch of Imagination. On the other hand, it is apparent that cogent and acceptable reasons have been furnished by the learned Arbitrator in respect of these four heads of claims (claim Nos. 3 to 6). The award in respect of such four claims does not call for any interference.”_ - 7.3 While exercising jurisdiction under Section 37, the High Court examined the relevant clauses of the contract and held the claim is impermissible under the contractual provisions. They are extracted herein below for ready reference. ## _‘’SPECIAL TERMS AND CONDITIONS CONDITION IN EXTENDED PERIOD_ _As Clause 4 of W.B.F. 2908 or Clause 5 of W.B.F. No.2911 (ii) as the case may be when an extension of time for completion of work is authorised by the Engineer-In-Charge, it will be taken for granted that the validity of the contract is extended automatically upon the extended period with all terms and conditions rates, etc. remaining unaltered, i.e. the tender is revalidated upon the extended period. EXTENSION OF TIME_ _For cogent reasons over which the contractor will have no control and which will retard the· progress, extension of time for the period lost will be granted on receipt of application from the contractor before the expiry date of contract. No claim whatsoever for idle labour, additional establishment, cost of materials and labour and hire charges of tools & Plants etc. would be entertained under any circumstances. The contractor should consider the above factor while quoting this rate. Applications for such extension of time should be submitted by the contractor in the manner indicated in Clause 5 of the printed form of W.B.F. No. 2911 (ii)._ _IDLE LABOUR Whatever the reasons may be no claim or idle labour, enhancement of labour rate additional_ [2024] 8 S.C.R. 624 ## **Digital Supreme Court Reports** _establishment cost, cost of TOLL and hire and labour charges of tools and plants Railway freight etc. would be entertained under any circumstances.”_ - 7.4 Mr. Saurav Agarwal submitted that the High Court under Section 37 ignored the plausible view of the Arbitrator, as upheld under Section 34, and substituted it with its own reasoning. - 7.5 This submission is persuasive, but the contract clauses speak for themselves. In fact, High Court did what the Arbitrator should have done. Examine what the contract provides. This is not even a matter of interpretation. It is the duty of every Arbitral Tribunal and Court alike and without exception, for contract is the foundation of the legal relationship. Having considered the above referred clauses in the Contract the High Court came to the conclusion that awarding any amount towards idle, machinery, etc. is prohibited under the ‘Special Terms and Conditions’ of the Contract. The Arbitrator did not even refer to the contractual provisions and the District Court dismissed the objections under Section 34 with a standard phrase as extracted hereinabove. High Court exercising jurisdiction under Section 37 did its duty and we are of the opinion that the conclusions of the High Court are correct and cannot be interfered with. 8. Re claim no. 4: This claim relates to interest on delayed payment of running account bills. - 8.1 The Arbitrator held that the Claimant is entitled to receive compensation for any loss and/or damage of capital which arose naturally from breach or which parties knew to be likely to arise from breach. Payments on running account bills is guided by clause 7 of the Contract and there is no prohibition in the contract regarding payment of interest on the ‘blocked capital’. Therefore, holding that the injured party ought to be placed in the same financial position he would have been but for the other party’s fault, the Arbitrator awarded interest on delayed payments at the rate of 12% p.a., which was quantified to Rs. 54,84,024. As indicated above, the District Court upheld the Award. [2024] 8 S.C.R.  625 ## **Pam Developments Private Limited v. The State of West Bengal & Anr.** ## 8.2 The relevant portion of the Award is as follows:- “ _23.1… As the claimant is entitled to payment of R/A bills when the amount is Rs. 1 crore and above, I accept the statements/calculation made by the claimant vide Statement submitted before the arbitral tribunal for Rs. 82,26,036/-. In compliance of direction issued by MOM no. 21 dated 24.7.2017, based on work value of Rs. one crore. Such statement giving all details covering the criteria of bill value of Rs. 1 crore was served to respondent and there was no comment on such statement whatsoever. Payment of R/A bills is guided only by the provision under clause 7 with amendment thereon. Claimant claimed interest @ 18% p.a. which is not allowed. I restrict rate of interest @ 12% p.a. only and thereby the admissible amount of the claim stands at Rs. 54,84,024/- [Rs. 82,26,036 ÷ 18 X 12]_ _23.2 The claimant notified loss of interest during the execution period under Interest Act (vide annexure-K, page 109, Annexure-m page-112, annexure-O, page 115, annex.-R1, page-119 & 122 with claimant’s document). Moreover, such payment is out of the written contract for executed quantities. There is no prohibition in the contract for payment of interest on blocked capital. The claimant is otherwise entitled to receive payment on account of interest on blocked capital. Such principle of law is laid down in the case of Secretary, Irrigation Department Government of Orissa Vs. G.C. Ray reported in (1992) 1 SCC 508. The claimant is entitled to receive compensation for any loss or damage and/or blockage of capital which arose naturally from the breach or which the parties knew to be likely to arrive from such breach. The injured party is to be placed in the same financial position, as he would have been in, if the other party had duly carried out the contract, i.e., to place the injured party in the same position if the contract has been performed. I award Rs. 54,84,024/- only.”_ - 8.3 Mr. Saurav Agarwal submitted that the payments became due when the gross amount of work done exceeded Rs.1 crore, therefore the delay was to be accounted for from this date. [2024] 8 S.C.R. 626 ## **Digital Supreme Court Reports** The error, he submits is because the High Court relied on chart submitted by the respondents, unlike the Arbitrator and the District judge who relied on appellant’s chart. - 8.4 High Court exercising jurisdiction under Section 37 merely recounted the dates on which the bills were raised, and the payments made. Thereafter High Court formulated certain questions, which it felt that the Arbitrator and the District Judge should have answered, but failed to hold any discussion on such questions. In this view of the matter, the High Court proceeded to set aside Award of claim no. 4. The relevant portion of the High Court Judgment is as follows:- “ _The learned Arbitrator proceeded on the basis of the statement submitted by the appellant that there was delay in the payment of these bills. The unpaid running account bills were described as “blocked capital”. He viewed the delay in receiving “this blocked capital” as “loss and damage” to the appellant and granted Rs. 54,84,024/- on that reasoning, as “interest”._ _The learned Judge upheld this award. It is challenged by the respondent. The respondent relies on Clauses 7, 8 and 9 of the contract by which monthly bills had to be raised by the appellant on the measurement made. These payments against the monthly running account bills were to be treated as advance under Clause 7. Payment could have been made only when the gross amount exceeded Rs. 1 crore. According to the respondent no bill was raised by the appellant. According to the statement of claim of the appellant, the first bill for Rs. 1,32,91,180/- was prepared on 29[th] August, 2011 and paid on or about 30[th] August 2011. Similarly, the second was prepared on 7[th] February, 2012 and paid on 9[th] February, 2012. The third and fourth bills for Rs. 1,28,23,488/- and Rs. 1,30,90,000/respectively were prepared on 5[th] March, 2012 and paid between 30[th] March, 2012 and 20[th] June, 2012. The fifth bill for Rs. 3,14,82,214/- was prepared on 6[th] July, 2012 and paid between 24[th] July, 2012 and 1[st]_ [2024] 8 S.C.R.  627 ## **Pam Developments Private Limited v. The State of West Bengal & Anr.** _October, 2012. The sixth bill was raised on 5[th] July, 2012 and paid between 6[th] July, 2012 and 1[st] October, 2012. The work was completed on 9[th] November, 2012. What the learned Arbitrator did not determine were the following:_ - a) _Who was responsible for non-preparation of the RA bill within time?_ - b) _Which of the RA bill claims of the appellant were to be treated as advance under the above clause of the contract?_ - c) _Was any notice under the Interest Act, 1978 issued by the appellant and to what effect?_ - d) _For what amount and for which period the claim for interest was being entertained and granted by him?_ _From the above narration of facts it appears that the bills were paid soon after they were prepared. In that case there could not have been any claim for interest. If a claim for interest has been made for running account bill below one crore, under the said terms it is to be treated as a claim for interest for unpaid advance. No right to claim interest arose._ _Now, unless these facts were established by the appellant and discussed by the learned Arbitrator to show that there was delay in the preparation of the bills by the respondent, that those bills were over one crore and not be treated as advance and that the right to obtain payment thereof arose on their due submission and service of a notice under the Interest Act, 1978, the award of interest could not be justified. Total absence of discussion of these facts signifies that the learned Arbitrator completely failed to exercise its jurisdiction…._ ” - 8.5 The conclusion of the High Court, “ _that it appears that the bills were paid soon after they were prepared_ ” or that, “ _in that case there could not have been any claim for interest_ ” cannot qualify as grounds for interference under Section 37. Equally, the approach of the High Court in holding that the Arbitrator neither [2024] 8 S.C.R. 628 ## **Digital Supreme Court Reports** established nor discussed the questions posed by it is not a ground to set aside the Award. The reasoning of the Arbitrator is reflected in that portion of the Award extracted hereinabove and we see nothing perverse in it. Nor such conclusion is against our public policy. The scope of Section 37 is enunciated in many decisions of this Court, and we apply the principles laid down therein to the facts of the present case. - 8.6 For these reasons, we set aside the judgment of the High Court in relation to claim no. 4 and restore the Award and thereby the judgment of the District Court upholding the Award. 9. Re claim no. 6: This claim relates to Interest - 9.1 Arbitrator awarded interest @12% on sum awarded from 12.04.2016, which is the date when appellant claimed breach of contract, to 30.01.2018, which is the date of the Award, and further interest @ 9.25% p.a. from date of Award till actual payment. This was confirmed by the District Judge under Section 34. - 9.2 High Court held that the contract between the parties prohibits grant of pre-reference interest and therefore interest could not have been granted for this period. As per the High Court, as the Arbitrator could have granted interest only for pendent lite and post award, the Award was modified directing - pendente lite interest @12% p.a. from 03.08.2016 till date of award i.e. 30.01.2018, along with post award interest @ 9.25% p.a. - 9.3 The learned counsel for the appellants has submitted that the award for interest is within the domain of the Arbitrator under Section 31(7) and ought not to be substituted by courts under Section 34 or 37. - 9.4 Section 31(7) of the Act determines the grant of interest. The relevant provision is extracted hereunder for ready reference. ## “ _**31. Form and contents of arbitral award.—**_ _(7) (a) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate_ [2024] 8 S.C.R.  629 **Pam Developments Private Limited v. The State of West Bengal & Anr.** _as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made._ _(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of two per cent higher than the current rate of interest prevalent on the date of award, from the date of award to the date of payment._ _Explanation.—The expression “current rate of interest” shall have the same meaning as assigned to it under clause (b) of section 2 of the Interest Act, 1978 (14 of 1978).”_ - 9.5 The power of the Arbitrator to grant pre-reference interest, _pendente lite_ interest, and post-award interest under Section 31(7) of the Act is fairly well-settled. The judicial determinations also highlight the difference in the position of law under the Arbitration Act, 1940. The following propositions can be summarised from a survey of these cases: - I. Under the Arbitration Act, 1940, there was no specific provision that empowered an Arbitrator to grant interest. However, through judicial pronouncements, this Court has affirmed the power of the Arbitrator to grant prereference, _pendente lite_ , and post-award interest on the rationale that a person who has been deprived of the use of money to which he is legitimately entitled has a right to be compensated for the same.[2] When the agreement does not prohibit the grant of interest and a party claims interest, it is presumed that interest is an implied term of the agreement, and therefore, the Arbitrator has the power to decide the same.[3] - II. Under the 1940 Act, this Court has adopted a strict > 2 _Secretary, Irrigation Department, Government of Orissa v. G.C. Roy_ (1992) 1 SCC 508 _, para 43(i). Also see Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C. Budharaj,_ (2001) 2 SCC 721 _; Union of India v. Krafters Engg. and Leasing (P) Ltd._ (2011) 7 SCC 279 > 3 _G.C. Roy (supra), paras 43(iv) and 44._ [2024] 8 S.C.R. 630 ## **Digital Supreme Court Reports** construction of contractual clauses that prohibit the grant of interest and has held that the Arbitrator has the power to award interest unless there is an express, specific provision that excludes the jurisdiction of the Arbitrator[4] from awarding interest for the dispute in question.[5] - III. Under the 1996 Act, the power of the Arbitrator to grant interest is governed by the statutory provision in Section 31(7). This provision has two parts. Under sub-section (a), the Arbitrator can award interest for the period between the date of cause of action to the date of the award, _unless otherwise agreed by the parties_ . Sub-section (b) provides that unless the award directs otherwise, the sum directed to be paid by an arbitral award shall carry interest at the rate of 2% higher than the current rate of interest, from the date of the award to the date of payment. - IV. The wording of Section 31(7)(a) marks a departure from Arbitration Act, 1940 in two ways: _first_ , it does not make an explicit distinction between pre-reference and _pendente lite_ interest as both of them are provided for under this subsection; _second_ , it sanctifies party autonomy and restricts the power to grant pre-reference and _pendente lite_ interest the moment the agreement bars payment of interest, even if it is not a specific bar against the Arbitrator.[6] - V. The power of the Arbitrator to award pre-reference and _pendente lite_ interest is not restricted when the agreement > 4 _Board of Trustees for the Port of Calcutta v. Engineers-de-Space-Age_ (1996) 1 SCC 516 _, paras 4 and 5; Madnani Construction Corporation Private Limited v. Union of India_ (2010) 1 SCC 549 _; Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd._ (2012) 12 SCC 10 _, paras 18-20; Union of India v. Ambica Construction_ (2016) 6 SCC 36 _(First Ambica Construction Case); Ambica Construction v. Union of India_ (2017) 14 SCC 323 _(Second Ambica Construction Case); Raveechee and Company v. Union of India_ (2018) 7 SCC 664 _; Reliance Cellulose Products Ltd. v. ONGC Ltd._ (2018) 9 SCC 266 - 5 _State of U.P. v. Harish Chandra and Co._ (1999) 1 SCC 63 > 6 _Sayeed Ahmed and Company v. State of Uttar Pradesh_ (2009) 12 SCC 26 _, paras 14, 23, 24; Union of India v. Saraswat Trading Agency_ (2009) 16 SCC 504 _; Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat_ (2010) 8 SCC 767 _, para 19; Union of India v. Bright Power Projects (India) Pvt Ltd._ (2015) 9 SCC 695 _, para 13; Reliance Cellulose Products Ltd (supra), para 24; Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited_ (2019) 17 SCC 786 _, paras 13-15; Delhi Airport Metro Express Private Limited v. Delhi Metro Rail Corporation_ (2022) 9 SCC 286 _, paras 16-20, 24_ [2024] 8 S.C.R.  631 ## **Pam Developments Private Limited v. The State of West Bengal & Anr.** is silent on whether interest can be awarded[7] or does not contain a specific term that prohibits the same.[8] - VI. While _pendente lite_ interest is a matter of procedural law, pre-reference interest is governed by substantive law.[9] Therefore, the grant of pre-reference interest cannot be sourced solely in Section 31(7)(a) (which is a procedural law), but must be based on an agreement between the parties (express or implied), statutory provision (such as Section 3 of the Interest Act, 1978), or proof of mercantile usage.[10] - 9.6 In view of the above, the High Court had no reason to interfere with the Arbitral Award with respect to grant of pre-reference interest, since the Contract between parties does not prohibit the same. 10. Having analysed the reasoning in the Award and the judgment of the District Judge under Section 34 of the Act and of the High Court under Section 37 with respect to claim nos. 3, 4 and 6, we; - (a) Uphold the decision of the High Court in setting aside the Award with respect to claim no. 3 and dismiss the Civil Appeal to this extent. - (b) Allow the appeal and set aside the judgment of the High Court in so far as it rejected and set aside claim no. 4 awarded by the Arbitrator, as upheld by the District Judge under Section 34. - (c) Allow the appeal and set aside the judgment of the High Court in so far as it modified claim no. 6, to the extent of rejecting pre-reference interest awarded by the Arbitrator, as upheld by the District Judge under Section 34. - (d) In conclusion, Award of claim no. 3 is set aside and Award of claim no. 4 is upheld. Under claim no.6, the appellant will also be entitled to claim pre-reference interest. > 7 _Jaiprakash Associates Limited v. Tehri Hydro Development Corporation India Limited_ (2019) 17 SCC 786 _, para 13.2_ > 8 _Oriental Structural Engineers Private Limited v. State of Kerala_ (2021) 6 SCC 150 _, paras 15-18_ > 9 _Central Bank of India v. Ravindra_ (2002) 1 SCC 367, para 39 following _G.C. Roy_ (supra), para 43(v) 10 _Central Bank of India_ (supra), para 39; _Secy./GM, Chennai, Central Coop. Bank Ltd. v. S. Kamalaveni Sundaram_ (2011) 1 SCC 790, para 13 [2024] 8 S.C.R. 632 ## **Digital Supreme Court Reports** 11. The Civil Appeal arising out of SLP (C) No. 8128 of 2021 is allowed in part as indicated hereinabove and Civil Appeal arising out of SLP (C) No. 8129/2021 stands disposed of accordingly. Parties shall bear their own costs. _Result of the case: _ Civil Appeal arising out of SLP (C) No. 8128 of 2021 partly allowed. Civil Appeal arising out of SLP (C) No. 8129 of 2021 disposed of. - _†Headnotes prepared by:_ Nidhi Jain
End of Judgment Record
Browse All Supreme Court of India (2024) Decisions
2024-04-09

Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors

This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.

2024-10-04

Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others

Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.

2024-03-21

Union of India v. M/s Indian Oil Corporation Ltd.

This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.

2024-07-23

Gene Campaign & Anr. v. Union of India & Ors.

This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.