High Court of KeralaSingle JudgeDismissed

P. Thyagarajan v. The Executive Engineer, Central Public Works Department, Office of the Executive Engineer, C Wing, 1st Floor, CGO Complex, Poonkulam, Vellayani P.O., Thiruvananthapuram-695522

Case / Petition Number:WP(C).No.27862 OF 2020(G)

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • P.V. ASHA
Judgment Date
2021-01-21
Court Decision / Holding
Writ petition dismissed. The Court held there is no justification to interfere with Ext.P6 termination under Clause 3 of the agreement. The petitioner is urged to cooperate for joint measurement to facilitate re-tendering. Admitted payments, if any, shall be released after settlement. The decision emphasizes limited judicial review in contractual matters and permits re-tendering while preserving rights to legal remedies.
Final Disposition
Dismissed

Parties to the Case

Appellants / Petitioners

  • P. Thyagarajan

Respondents

  • The Executive Engineer, Central Public Works Department, Office of the Executive Engineer, C Wing, 1st Floor, CGO Complex, Poonkulam, Vellayani P.O., Thiruvananthapuram-695522

Legal Representation & Advocates

Counsels for Petitioners

  • • S. Sachithananda Pai

Counsels for Respondents

  • • P. Vijayakumar, ASG of India
  • • Girishkumar V., CGC
  • • Sri Krishna, CGC

Case Synopsis & Summary

P. Thyagarajan, an A-class civil works contractor, challenged Ext.P6, the termination of his contract for constructing a dormitory at Navodaya Vidyalaya, Vithura. After accepting the e-tender in 2018, he started in August 2018. Delays occurred due to the Covid-19 outbreak and a directive from the Navodaya Principal stopping work, arguing risk of spread. He submitted Ext.P2 on 4 June 2020, explaining and offering to complete by 30 September 2020, and later sought extension up to 30 January 2021. The respondent contends the contract required completion by 25 February 2019 under Ext.P1 and that delays were attributable to the contractor; several notices flagged lapses in progress and safety, with alleged extensions considered up to 31 August 2019; after further show-cause notices and responses, Ext.P6 terminated the contract under Clause 3 of the GCC 2014, forfeiting PBG and EMD. The petitioner argues stoppage at the Principal’s request and Covid-19 caused delays, implying an extension, and contends termination was mala fide. The High Court held the termination was in accordance with the contract, emphasized the limited scope of judicial review in contractual matters, and declined to interfere with the administrative decision, directing joint measurement and payment for already completed work while permitting re-tendering.

Provisions of Law Cited

General Conditions of Contract for Central PWD works 2014 (GCC 2014)Clause 3(a)(b) of GCC 2014Clause 2 of the contractArticle 14 of the Constitution of India (constitutional principle invoked)

Legal Doctrines & Maxims

  • Fair play in the joints (Tata Cellular: Union of India)
  • Mala fides
  • Judicial review in contractual matters is limited (doctrine)
  • Power of judicial review dependent on factual circumstances (case-law approach)
  • Arbitrary and unreasonable action should be avoided (constitutional principle)
  • Public interest considerations in contract termination and re-tendering

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that Ext.P6 Termination is unjust, relying on Covid-19 stoppages and principal's instruction to halt work, plus the lack of any granted extension beyond 30.01.2021. He argues an implied extension from the stoppage and public interest in avoiding costly re-tendering. He asserts the work was near completion and that payments for completed parts should not imply a denial of extension. He maintains the delays were largely caused by non-availability of drawings and labour, and that the termination without considering his explanations was mala fide and contrary to the public interest.

Contentions of Respondents

The respondent contends the project had a fixed completion date under Ext.P1 (210 days, commencing 31.07.2018, due 25.02.2019). Delays were the contractor’s responsibility, with multiple notices for acceleration and lapses. After considering evidence, Chief Engineer’s assessments and show-cause notices, the department extended time only up to 31.08.2019, and after further review the termination was issued under Clause 3 of the contract. The pandemic did not justify delay, and a re-tendering decision was taken to protect public interest; termination complied with the contract terms and the law. Prior extensions and drawings delays were argued but did not warrant extension; the court should not compel continuation of a terminated contract where confidence has been lost.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
State of Kerala v. M.K. Jose(2015) 9 SCC 433PositiveApex Court held that a writ petition should not ordinarily be entertained when there is a breach of contract involving factual disputes, guiding judicial approach in this matter.
ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.(2004) 3 SCC 553PositiveJudicial review in contractual matters is not totally excluded; prerogative writs should be exercised when action is arbitrary or violative of Article 14.
Noble Resources Ltd. v. State of Orissa(2006) 10 SCC 236PositiveWhether to exercise judicial review depends on factual circumstances in each case.
Tata Cellular: Union of India(2004) 6 SCC 651PositiveCourt reviews the manner of decision-making in contracts and should not substitute administrative decisions where there is no arbitrariness; fair play is essential.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against P. Thyagarajan v. The Executive Engineer, Central Public Works Department, Office of the Executive Engineer, C Wing, 1st Floor, CGO Complex, Poonkulam, Vellayani P.O., Thiruvananthapuram-695522 and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

# **IN THE HIGH COURT OF KERALA AT ERNAKULAM** ## **PRESENT** **THE HONOURABLE SMT. JUSTICE P.V.ASHA** **THURSDAY, THE 21ST DAY OF JANUARY 2021 / 1ST MAGHA, 1942** ## **WP(C).No.27862 OF 2020(G)** ## **PETITIONER:** **P.THYAGARAJAN, AGED 60 YEARS, S/O.S.PANKAJAKSHAN, VRINDAVAN, PERINGAMALA, KALLIYOOR P.O., THIRUVANANTHAPURAM-695 742.** **BY ADV. SRI.S.SACHITHANANDA PAI** ## **RESPONDENT:** **THE EXECUTIVE ENGINEER, CENTRAL PUBLIC WORKS DEPARTMENT, OFFICE OF THE EXECUTIVE ENGINEER, C WING, 1ST FLOOR, CGO COMPLEX, POONKULAM, VELLAYANI P.O., THIRUVANANTHAPURAM-695 522.** **BY ADVS.SRI.P.VIJAYAKUMAR, ASG OF INDIA SRI.GIRISHKUMAR.V., CGC SRI.CGC.SMT.KRISHNA,** **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 21.01.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **WP(C).No.27862 OF 2020(G)** **-2-** ## **JUDGMENT** **Dated this the 21st day of January 2021** The petitioner, who is an A class civil works contractor, has filed this writ petition aggrieved by Ext.P6 order dated 8.12.2020 of termination of the contract. He seeks a direction to the respondent to permit him to complete the construction within a reasonable time. 2. As per Ext.P1 letter dated 16.7.2018 the respondent accepted the e-tender submitted by petitioner for the work of “ _construction of 0.75 unit dormitory (G+1) for girls at Navodaya Vidyalaya, Vithura, District Thiruvananthapuram, Kerala including water supply, sanitary installations, drainage and internal electrical installations, fans and fittings._ ” It is **WP(C).No.27862 OF 2020(G)** **-3-** stated that after furnishing performance guarantee on 25.7.2018, he started the work in August 2018; but he was unable to complete the work within the stipulated time because of the outbreak of Covid-19 pandemic. He has further stated that, in answer to a show cause notice from the respondent, he had submitted Ext P2 explanation on 4.6.2020, undertaking to complete the work by 30.9.2020. It is his further case that the Principal of the School, where the construction was going on, had requested him as per Ext.P3 letter, dated 29.07.2020, to stop the work due to the fear of spread of Covid-19, pointing out that the teachers were residing there with family. It is also submitted that he was constrained to stop the work on the basis of the said letter as well ## **WP(C).No.27862 OF 2020(G)** **-4-** as the oral direction of the respondent. While so, the petitioner was issued with Ext.P4 show cause notice on 30.10.2020 proposing termination of the contract invoking Clause 3(a)(b) of General Conditions of Contract for Central PWD works 2014. It is stated that though petitioner submitted Ext.P5 explanation on 10.11.2020 explaining the entire circumstances, the respondent issued Ext.P8 order on 8.12.2020, terminating the contract and forfeiting the performance guarantee as well as the earnest money deposit. Petitioner was directed to report before the respondent for joint measurement. It is stated that contract is terminated without appreciating the fact that the work had to be stopped at the request of the Principal; without taking note of the **WP(C).No.27862 OF 2020(G)** **-5-** scarcity of labourers after the Covid-19 outbreak and without considering any of the factual circumstances pointed out in his explanation. It is stated that he had already requested for extension of time up to 30.01.2021 and not to take any penal action against him. 3. According to the petitioner, he would be able to complete the work, in case he is given three months' time as he has made all arrangements for the same. The learned counsel for the petitioner submitted that a re-tender at this stage would only be contrary to public interest as it would involve more expenditure to the Government as the rate of work would be different. 4. The learned central Government Counsel has filed a statement on behalf of ## **WP(C).No.27862 OF 2020(G)** **-6-** the respondent refuting the contentions raised by the petitioner. It is stated that pursuant to Ext.P1 letter of acceptance, an agreement was entered into between the petitioner and the Executive Engineer, wherein it was stipulated that the period of completion of the work would be 210 days, specifying the date of commencement of the work as 31.07.2018 and due date of completion as 25.2.2019. It is therefore stated that the outbreak of Covid-19 pandemic which occurred after an year could not have been the reason for delay in completion of work. It is stated that the respondent had been asking the petitioner to accelerate the progress of work with due diligence issuing Annexure R1(b) to R1(p) letters issued between 25.01.2019 and 27.11.2019 and ## **WP(C).No.27862 OF 2020(G)** **-7-** thereafter, informing him the violation of contractual conditions and obligations from his part with warning that the department would be forced to take action under Clause 3 of the contract on failure to maintain desired progress of the work. It is stated that during inspections several defects in the work and lapses in safety were found. He was given several chances to improve the quality of work, speed etc. to abide by the programme of work, in each of the notices issued to him, where the lapses were explained. On expiry of the time schedule on 25.02.2019, extension was granted upto 31.08.2019 without prejudice to the right of Government to recover liquidated damages; the Chief Engineer had also examined the case and it was found that petitioner was responsible ## **WP(C).No.27862 OF 2020(G)** **-8-** for the delay. It is stated that despite the direction of the Chief Engineer in Annexure R1(e) letter dated 08.08.2019, while giving another opportunity to petitioner, even after finding the petitioner solely responsible for the delay, petitioner did not submit the application for rescheduling of milestone for completion of work on war footing, in a proper format, even after reminding him the same in Annexure R1(i) letter of the respondent or in Annexure R1(j) letter of the Superintending Engineer. In the absence of any proper application for ROM or for extension of time and taking note of the slow pace in the work the Chief Engineer issued Annexure R1(k) show cause notice on 27.11.2019 under Clause 2 of the agreement proposing action against the petitioner for **WP(C).No.27862 OF 2020(G)** **-9-** imposing compensation for the prolonged delay and the casual approach of the petitioner, stating that there was no likelihood of completion of work within 07.02.2020, as per the work schedule submitted by petitioner. It is stated that the respondent had issued another show cause notice Annexure R1(l) dated 03.05.2020 to petitioner for action under Clause 3 and after considering the explanation of the petitioner and taking note of the outbreak of Covid-19 and the lockdown measures the respondent had, in Ext.R1(m) letter dated 04.06.2020, recommended extension of time till 30.09.2020. But even thereafter petitioner did not take any pro- active steps. Therefore Ext.P4 show cause notice was issued for proceeding under clause 3. It is stated that Annexure R1(n)and R1(o) **WP(C).No.27862 OF 2020(G)** **-10-** letters would show that the explanation of petitioner was considered. While terminating the contract the reasons for the same are also stated in Ext.P6, which are sufficient for termination. It is stated that the Principal as well as the Chairman of the managing Committee had expressed serious concern over the delay in completion of the work in their letters Annexure R1(p) dated 27.11.2019, Annexure R1(r)letter dated 25.02.2020. It is stated that the Principal had as per Annexure R1(s) letter dated 06.10.2020 requested to hand over the building immediately, pointing out the inconvenience caused to them. It is stated that petitioner himself assumed that extension was given till 31.01.2021, even in the absence of any such orders. He used to ## **WP(C).No.27862 OF 2020(G)** **-11-** raise false allegations against the department. It is also pointed out the petitioner has already been found responsible for the delay in completion of construction of other two hostels also in Thiruvananthapuram. 5. The petitioner filed a reply affidavit stating that though the respondent never extended the period of contract fixed as on 25.02.2019, the request of petitioner for extension till 30.01.2021 was never objected. It is stated that he has satisfactorily completed several works like those covered by Exts.P6 and P7 produced along with the reply affidavit, under the respondent and that he had been carrying out the present work also with due diligence. According to him, the delay occurred because ## **WP(C).No.27862 OF 2020(G)** **-12-** of the inaction of the respondent in furnishing the drawings, non-finalisation of location lay out, etc. It is stated that the revised structural drawings for foundation details of the building were made available only on 08.11.2018; plinth level and foundation details were finalised only on 12.11.2018; architectural drawings were issued only on 16.04.2019, that too after a series of correspondence in Exts.P9 to P12 letters sent to the respondent between 03.09.2018 and 23.02.2019, in which he had explained the hindrances occurred in the execution of work. It is stated that the drawings of the part plan basement level and ground level of toilet block was issued only on 17.08.2019, as evident from Ext.P8 letter of the respondent, whereas the actual ## **WP(C).No.27862 OF 2020(G)** **-13-** completion of the work stipulated was 25.01.2019. It is also his case that his application for extension of period of contract was accepted by the respondent without any reservation. It is stated that the work which was stopped at the instance of the Principal of the School could be restarted only with the minimized structural resources in the absence of sufficient number of labourers. Pointing out Ext.P13 payment agreement as well as 7[th] RA bill approved in Ext.P15 by the respondent on 30.10.2020 and 5.12.2020 respectively and the payment effected as per Ext.P16 memorandum on 21.12.2020, the petitioner claims that the respondent had impliedly granted extension based on his request in Ext P14 letter dated 07.09.2020. According to him payment could ## **WP(C).No.27862 OF 2020(G)** **-14-** not have been made to him in the absence of extension of time for completion of work or after termination of contract. It is stated that the work, which he had to stop in July 2020 at the instance of Principal, could be restarted only after permission was granted on 26.08.2020. The work could be restarted by 15.09.2020, after arranging sufficient labourers, and materials. According to petitioner, he had explained the reasons for the delay, in the explanation he had submitted and had assured to complete the work by 30.01.2021. After the respondent allowed the petitioner to continue with the work, the termination of contract by Ext.P6 order is _mala fide._ It is stated that the work awarded to him at 2016 schedule of rates would have to be re-arranged only at ## **WP(C).No.27862 OF 2020(G)** **-15-** escalated rate of 2018 which would incur more expenditure to Government. It is the case of the petitioner that he has not violated any of the conditions of contract and it would be in furtherance of public interest to permit him to complete the work. 6. I heard Sri.Sachithanada Pai the learned Counsel for the petitioner and the learned CGC appearing for the respondent. The learned counsel for the petitioner submits that petitioner requires only three more months' time to complete work. The learned Central Government Counsel on instructions submitted that the respondent as well as the Department has lost confidence in the petitioner. The learned Central Government Counsel also points out that when the respondents have arrived at the decision ## **WP(C).No.27862 OF 2020(G)** **-16-** to terminate the contract only after taking note of all the circumstances, the progress of work etc. this Court may not interfere with the same. It is also argued that nothing prevents the respondent from making payment for the work that have been already carried out and such payment cannot imply grant of extension of time for completion of work. 7. When the petitioner submits that he has completed major part of the work, it is disputed by the respondent. Similarly the reason for the delay caused in completion, according to petitioner, is on the respondent; whereas it is solely on petitioner, according to the respondent. Petitioner claims that there was implied extension of time for completion which is stoutly opposed by respondent. **WP(C).No.27862 OF 2020(G)** **-17-** 8. Admittedly there is no order granting extension of time to the petitioner for the period up to 30.01.2021. Petitioner claims only implied extension. 9. It is seen that the contract is terminated in accordance with the provisions contained in the agreement executed between the parties as well as the provisions contained in the General Conditions of Contract. There is serious dispute as to the reason for the delay apart from the plea of loss of confidence on the petitioner. In such circumstances, this Court will not be justified in interfering with the issue. Though the petitioner pointed out that he would complete the work within a period of three months or that there would be additional expenditure on account of ## **WP(C).No.27862 OF 2020(G)** **-18-** enhancement of rate in the event of a retender, when the respondents submit that they have lost confidence in a party, this Court cannot compel the respondents to permit the petitioner to work. It is seen that a number of notices were being issued to petitioner to accelerate the progress of work, though petitioner asserts that delay was caused at the instance of respondent. The termination is seen effected after a lot of correspondence between the parties and it is stated that the said termination is in accordance with clause 3 of the agreement. Therefore it is only appropriate for the petitioner to co-operate with the respondent to complete the joint measurement. 10. The scope of judicial review in contractual matters is very limited. In the **WP(C).No.27862 OF 2020(G)** **-19-** judgment in _**State of Kerala v. M.K. Jose: (2015) 9 SCC 433**_ the Apex Court held that Court should ordinarily not entertain a writ petition, if there is a breach of contract when factual disputes are involved. The Apex Court was considering an appeal against the judgment of this court which permitted the contractor to proceed with the work after setting aside the termination of contract based on the report filed by the Advocate Commissioner, regarding the quantum of work executed. In the judgment in _**ABL**_ _**International Ltd.**_ **v.** _**Export Credit Guarantee Corpn. of India Ltd.: (2004)3SCC 553,**_ the Apex Court, held that though judicial review in contractual matters is not totally excluded, the plenary right of the High Court to issue a prerogative writ will not **WP(C).No.27862 OF 2020(G)** **-20-** normally be exercised by the Court unless the action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the Court thinks it necessary to exercise the said jurisdiction. In **Noble** **Resources Ltd. v. State of Orissa:** **(2006)10SCC 236** it was held that the question whether power to exercise judicial review should be exercised, should be decided in the factual circumstances of each case. While considering the challenge against award of contract the Apex Court, in **Tata Cellular: Union of India: (2004)6 SCC 651,** held that the role of the court in matters involving contracts is only to review the manner in which the decision is taken and the Court ## **WP(C).No.27862 OF 2020(G)** **-21-** which does not have expertise in matters covered by the tender would not venture to correct the administrative decision and there should be a fair play in the joints for an administrative body and that the administrative decision must not only be tested by the application of principle of reasonableness while it should also be free from arbitrariness not affected by bias or actuated by _mala fides_ . Therefore, I am of the view that interference with the Ext.P6 order is not warranted under Article 226 of the constitution of India. The writ petition accordingly dismissed. In order to enable the respondents to re-tender the work, the petitioner shall co-operate with the respondents for the joint measurement without **WP(C).No.27862 OF 2020(G)** **==> picture [30 x 8] intentionally omitted <==** any delay. Admitted payment if any due to the petitioner shall also be made after the same. It is made clear that the dismissal of the writ petition will not stand in the way of the petitioner invoking the remedies available to him in accordance with law. **Sd/P.V.ASHA JUDGE** akv **WP(C).No.27862 OF 2020(G)** **-23-** ## **APPENDIX** ## **PETITIONER'S/S EXHIBITS:** **EXHIBIT P1 COPY OF THE ACCEPTANCE OF TENDER ISSUED BY THE RESPONDENT.** - **EXHIBIT P2 EXPLANATION DATED 04.06.2020 OF THE PETITIONER.** - **EXHIBIT P3 LETTER DATED 29.07.2020 OF THE PRINCIPAL, NAVODAYA VIDYALAYA.** - **EXHIBIT P4 SHOW CAUSE DATED 30.10.2020 OF THE RESPONDENT.** - **EXHIBIT P5 EXPLANATION DATED 10.11.2020 OF THE PETITIONER.** - **EXHIBIT P6 LETTER OF TERMINATION OF CONTRACT OF THE RESPONDENT DATED 08.12.2020.** - **EXHIBITS ALONG WITH REPLY AFFIDAVIT:** **EXHIBIT P6 COPY OF THE COMPLETION CERTIFICATE ISSUED BY THE RESPONDENT DATED 02.07.2016. EXHIBIT P7 COPY OF THE COMPLETION CERTIFICATE ISSUED BY THE RESPONDENT DATED 06/02/2020. EXHIBIT P8 COPY OF THE LETTER DATED 17/08/2020 OF THE RESPONDENT.** **EXHIBIT P9 COPY OF THE LETTER DATED 03/09/2018 OF THE PETITIONER.** **EXHIBIT P10 COPY OF THE LETTER DATED 30/10/2018 OF THE PETITIONER.** **EXHIBIT P11 COPY OF THE LETTER DATED 09/11/2018 OF THE PETITIONER. EXHIBIT P12 COPY OF THE LETTER DATED 23/02/2019 OF THE PETITIONER.** **EXHIBIT P13 COPY OF MEMORANDUM OF PAYMENT ON AGREEMENT DATED 30/10/2020.** **WP(C).No.27862 OF 2020(G)** **-24-** **EXHIBIT P14** **COPY OF THE LETTER DATED 07/09/2020 OF THE PETITIONER.** **EXHIBIT P15 COPY OF ABSTRACT BOOK OF RUNNING ACCOUNT DATED 05/12/2020.** **EXHIBIT P16 COPY OF MEMORANDUM OF PAYMENT ON AGREEMENT DATED 21/12/2020.** **RESPONDENT'S/S EXHIBITS:** **ANNEXURE R1(A) COPY OF LETTER FROM THE ASSISTANT ENGINEER DATED 26/08/2020.** - **ANNEXURE R1(B) COPY OF LETTER FROM THE RESPONDENT DATED 25/01/2019.** - **ANNEXURE R1(C) COPY OF LETTER FROM THE RESPONDENT DATED 18/07/2019.** **ANNEXURE R1(D) COPY OF LETTER FROM THE RESPONDENT DATED 03/08/2019.** - **ANNEXURE R1(E) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 08/08/2019.** **ANNEXURE R1(F) COPY OF LETTER FROM THE PETITIONER DATED 19/08/2019.** **ANNEXURE R1(G) COPY OF PROGRAM CHART SUBMITTED BY THE PETITIONER DATED 19/08/2019. ANNEXURE R1(H) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 22/08/2019.** **ANNEXURE R1(I) COPY OF LETTER FROM THE RESPONDENT DATED 27/08/2019. ANNEXURE R1(J) COPY OF THE LETTER FROM THE SUPERINTENDING ENGINEER DATED 27/09/2019. ANNEXURE R1(K) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 27/11/2019.** **WP(C).No.27862 OF 2020(G)** ## **-25-** **ANNEXURE R1(L) COPY OF LETTER FROM THE RESPONDENT DATED 13/05/2020.** **ANNEXURE R1(M) COPY OF LETTER FROM THE RESPONDENT DATED 10/06/2020.** **ANNEXURE R1(N) COPY OF LETTER FROM THE RESPONDENT DATED 19/11/2020.** - **ANNEXURE R1(O) COPY OF LETTER FROM THE CHIEF ENGINEER DATED 01/12/2020.** - **ANNEXURE R1(P) COPY OF LETTER FROM THE PRINCIPAL, JNV DATED 27/11/2019.** - **ANNEXURE R1(Q) COPY OF THE LETTER FROM THE RESPONDENT DATED 06/12/2019.** - **ANNEXURE R1(R) COPY OF LETTER FROM THE ASSISTANT COLLECTOR, THIRUVANANTHAPURAM DATED 25/02/2020.** - **ANNEXURE R1(S) COPY OF LETTER FROM THE PRINCIPAL, JNV, VITHURA DATED 06/10/2020.** **ANNEXURE R1(T) COPY OF LETTER FROM THE RESPONDENT DATED 20/02/2020.** **ANNEXURE R1(U) COPY OF LETTER FROM THE ASSISTANT ENGINEER DATED 03/09/2019.** - **ANNEXURE R1(V) COPY OF LETTER FROM THE RESPONDENT DATED 05/09/2019.** //TRUE COPY// PA TO JUDGE